CN211338645U - Building engineering material lifting device - Google Patents

Building engineering material lifting device Download PDF

Info

Publication number
CN211338645U
CN211338645U CN201922247298.7U CN201922247298U CN211338645U CN 211338645 U CN211338645 U CN 211338645U CN 201922247298 U CN201922247298 U CN 201922247298U CN 211338645 U CN211338645 U CN 211338645U
Authority
CN
China
Prior art keywords
fixed plate
lifting device
fixedly connected
shaped frame
material lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922247298.7U
Other languages
Chinese (zh)
Inventor
刘冬余
郭亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201922247298.7U priority Critical patent/CN211338645U/en
Application granted granted Critical
Publication of CN211338645U publication Critical patent/CN211338645U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a building engineering material lifting device, including first fixed plate, the upper end left part of first fixed plate is provided with slip hoisting device, the upper end right part of first fixed plate is provided with stop device, the board is placed to slip hoisting device and stop device's the common fixedly connected with in opposite face lower part, place the upper end middle part of board and placed the material section of thick bamboo, the arc of the equal fixedly connected with in both ends right part around the both ends left part and the front and back both ends right part around the first fixed plate, two the opposite face middle part of arc all is provided with a rotation strutting arrangement, both sides have a gyro wheel through the equal swing joint of pivot around the lower extreme left part of first fixed plate both sides and lower extreme right part. A building engineering material lifting device, drive the material section of thick bamboo up-movement through placing the board to make the building engineering material promote to high-rise building in, operation process is simple, thereby has improved work efficiency.

Description

Building engineering material lifting device
Technical Field
The utility model relates to a building engineering technical field specifically is a building engineering material hoisting device.
Background
The building engineering refers to an engineering entity formed by the construction of various building constructions and their auxiliary facilities and the installation of lines, pipelines and equipment matched with them. Wherein "housing construction" indicates there is the top cap, the beam column, the wall, the basis and can form the inner space, satisfy the engineering that people produced, live in, study, public activity needs, current building engineering need promote the material to high-rise building usually in the work progress on, present material hoisting device is complicated in the operation in the use, and is high to people's technical requirement degree, thereby work efficiency has been reduced, secondly take place the skew easily in the use and cause empting of material, lifting cost has been improved.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building engineering material hoisting device to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a building engineering material lifting device, includes first fixed plate, the upper end left part of first fixed plate is provided with slip hoisting device, the upper end right part of first fixed plate is provided with stop device, the board is placed to slip hoisting device and the common fixedly connected with in stop device's opposite face lower part, place the upper end middle part of board and placed the material section of thick bamboo, the equal fixedly connected with arc in both ends left part around and both ends right part around the first fixed plate, two the opposite face middle part of arc all is provided with a rotation strutting arrangement, both sides are through the equal swing joint of pivot gyro wheel around both sides and the lower extreme right part around the lower extreme left part of first fixed plate.
Preferably, the sliding lifting device comprises a first U-shaped frame, the top of an inner cavity of the first U-shaped frame is connected with a threaded rod in an alternating mode, the threaded rod penetrates through the top of the inner cavity of the first U-shaped frame and is fixedly connected with a positive and negative motor, the lower portion of the outer surface of the threaded rod is connected with a first sliding block in a threaded mode, and the first U-shaped frame is fixedly connected with the sliding lifting device and a first fixing plate in the left portion of the upper end of a first fixing plate.
Preferably, the limiting device comprises a second U-shaped frame, a limiting rod is fixedly connected to the top of the inner cavity of the second U-shaped frame, a second sliding block is movably connected to the lower portion of the outer surface of the limiting rod, and the limiting device and the first fixing plate are fixedly connected together through the second U-shaped frame and fixedly connected to the right portion of the upper end of the first fixing plate.
Preferably, the rotation supporting device comprises a first rotating rod, a supporting plate is fixedly mounted at the left part of the outer surface of the first rotating rod, a gear is fixedly connected to the right part of the outer surface of the first rotating rod, the first rotating rod penetrates through the middle part of the right end of the left arc plate and is fixedly connected with a second positive and negative motor, and the first rotating rod penetrates through the middle part of the opposite surface of the two sets of arc plates and is connected with the rotation supporting device and the arc plates in a movable mode.
Preferably, the sliding lifting device and the limiting device are on the same horizontal line.
Preferably, the supporting plate and the first fixing plate are on the same horizontal line.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the plate is placed through first slider drive and up-moving, sets up the limiting rod and plays limiting displacement to placing the plate, has improved the stability of placing the plate when up-sliding, prevents that the material in the material section of thick bamboo from spraying out, then drives the material section of thick bamboo up-moving to make the building engineering material promote to high-rise building in, operation process is simple, and is low to people's technical requirement degree, thereby has improved work efficiency.
2. Drive first bull stick through the positive and negative motor of second and rotate to contact ground when driving the backup pad and rotating, push first fixed plate up-motion with ground mutual extrusion, and then drive the gyro wheel and up-move and break away from ground, prevent that the gyro wheel from taking place to remove, ensure the operating steadily of material section of thick bamboo, reduced the lifting cost.
Drawings
Fig. 1 is a schematic view of the overall structure of a building engineering material lifting device of the present invention;
fig. 2 is a schematic structural view of a rotary supporting device of the building engineering material lifting device of the present invention;
FIG. 3 is a schematic structural view of a position limiter of the construction material lifting device of the present invention;
fig. 4 is the utility model relates to a building engineering material hoisting device's slip hoisting device schematic structure.
In the figure: 1. a first fixing plate; 2. a sliding lift device; 3. a limiting device; 4. placing the plate; 5. a material cylinder; 6. an arc-shaped plate; 7. a rotation support device; 8. a roller; 21. a first U-shaped frame; 22. a threaded rod; 23. a first positive and negative motor; 24. a first slider; 31. a second U-shaped frame; 32. a limiting rod; 33. a second slider; 71. a first rotating lever; 72. a support plate; 73. a gear; 74. and a second positive and negative motor.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "both ends", "one end", "the other end" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element to which the reference is made must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "disposed," "connected," and the like are to be construed broadly, and for example, "connected" may be either fixedly connected or detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Referring to fig. 1-4, the present invention provides a technical solution: the utility model provides a building engineering material lifting device, including first fixed plate 1, the upper end left part of first fixed plate 1 is provided with slip hoisting device 2, the upper end right part of first fixed plate 1 is provided with stop device 3, the common fixedly connected with in opposite face lower part of slip hoisting device 2 and stop device 3 places board 4, place the upper end middle part of board 4 and placed material section of thick bamboo 5, arc 6 of the equal fixedly connected with in both ends left part and front and back both ends right part around first fixed plate 1, the opposite face middle part of two arc 6 all is provided with one and rotates strutting arrangement 7, both sides have a gyro wheel 8 through the equal swing joint of pivot around both sides and the lower extreme right part around the lower extreme left part of first fixed plate 1.
The sliding lifting device 2 comprises a first U-shaped frame 21, the top of an inner cavity of the first U-shaped frame 21 is connected with a threaded rod 22 in an inserting mode, the threaded rod 22 penetrates through the top of the inner cavity of the first U-shaped frame 21 and is fixedly connected with a first positive and negative motor 23, the lower portion of the outer surface of the threaded rod 22 is connected with a first sliding block 24 in a threaded mode, the first sliding block 24 drives the material barrel 5 to be lifted from bottom to top, conveying of materials is facilitated, and the first U-shaped frame 21 is fixedly connected to the left portion of the upper end of the first fixing plate 1 to fixedly connect the sliding lifting device 2 with the first fixing plate 1; the limiting device 3 comprises a second U-shaped frame 31, a limiting rod 32 is fixedly connected to the top of an inner cavity of the second U-shaped frame 31, the limiting rod 32 has a limiting effect on the placing plate 4, the stability of the placing plate 4 during lifting is improved, the material barrel 5 is prevented from toppling over, a second sliding block 33 is movably connected to the lower portion of the outer surface of the limiting rod 32, and the second U-shaped frame 31 is fixedly connected to the right portion of the upper end of the first fixing plate 1 to fixedly connect the limiting device 3 and the first fixing plate 1 together; the rotating support device 7 comprises a first rotating rod 71, a support plate 72 is fixedly installed at the left part of the outer surface of the first rotating rod 71, the support plate 72 is contacted with the ground when rotating, and the roller 8 is enabled to move upwards when the first fixing plate 1 is pushed to move upwards by extrusion, so that the roller 8 is prevented from rolling, a gear 73 is fixedly connected at the right part of the outer surface of the first rotating rod 71, the first rotating rod 71 penetrates through the middle part of the right end of the left arc-shaped plate 6 and is fixedly connected with a second positive and negative motor 74, and the first rotating rod 71 is inserted and connected in the middle parts of opposite surfaces of the two groups of arc-shaped plates 6 to movably connect the rotating support; the sliding lifting device 2 and the limiting device 3 are positioned on the same horizontal line; the supporting plate 72 and the first fixing plate 1 are on the same horizontal line.
It should be noted that the utility model relates to a building engineering material lifting device, the material is placed in the material cylinder 5, the threaded rod 22 is driven to rotate by the first positive and negative motor 23, thereby driving the first slider 24 to slide upwards along the direction of the threaded rod 22, further driving the placing plate 4 to synchronously move upwards along the first slider 24, at the same time, the second slider 33 moves upwards along the direction of the limiting rod 32, the limiting rod 32 is arranged to limit the placing plate 4, the stability of the placing plate 4 when sliding upwards is improved, the material in the material cylinder 5 is prevented from being sprayed out, the material cylinder 5 is moved upwards when the placing plate 4 moves upwards, thereby the building engineering material is lifted into the high-rise building, the operation process is simple, the technical requirement for people is low, thereby the work efficiency is improved, the first rotating rod 71 is driven to rotate by the second positive and negative motor 74, thereby contact ground when driving backup pad 72 and rotating, gear 73 in the first fixed plate 1 the place ahead drives the gear 73 rotation in first fixed plate 1 rear simultaneously to both sides backup pad 72 pushes away first fixed plate 1 upward movement with ground extrusion each other around the drive, and then drives gyro wheel 8 upward movement and breaks away from ground, prevents that gyro wheel 8 from taking place to remove, ensures the steady operation of material section of thick bamboo 5, has reduced the cost of promotion.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. A building engineering material lifting device comprises a first fixing plate (1), and is characterized in that: the utility model discloses a material cylinder, including first fixed plate (1), the upper end left part of first fixed plate (1) is provided with slip hoisting device (2), the upper end right part of first fixed plate (1) is provided with stop device (3), the common fixedly connected with in opposite face lower part of slip hoisting device (2) and stop device (3) places board (4), place the upper end middle part of board (4) and placed material section of thick bamboo (5), arc (6) of the equal fixedly connected with in both ends right part around the front and back both ends left part of first fixed plate (1) two the opposite face middle part of arc (6) all is provided with one and rotates strutting arrangement (7), both sides have gyro wheel (8) through the equal swing joint of pivot around both sides and the lower extreme right part around the lower extreme left part of first fixed plate (1).
2. A construction work material lifting device according to claim 1, characterised in that: slide lifting device (2) include first U-shaped frame (21), the inner chamber top of first U-shaped frame (21) alternates and is connected with threaded rod (22), threaded rod (22) run through the inner chamber top of first U-shaped frame (21) and the first positive and negative motor of fixedly connected with (23), the surface lower part threaded connection of threaded rod (22) has first slider (24), first U-shaped frame (21) fixed connection will slide lifting device (2) and first fixed plate (1) fixed connection in the upper end left part of first fixed plate (1).
3. A construction work material lifting device according to claim 1, characterised in that: stop device (3) include second U-shaped frame (31), the inner chamber top fixedly connected with gag lever post (32) of second U-shaped frame (31), the surface lower part swing joint of gag lever post (32) has second slider (33), stop device (3) and first fixed plate (1) fixed connection are in the same place in the upper end right part of first fixed plate (1) for second U-shaped frame (31) fixed connection.
4. A construction work material lifting device according to claim 1, characterised in that: rotate strutting arrangement (7) and include first bull stick (71), the surface left part fixed mounting of first bull stick (71) has backup pad (72), the surface right part fixedly connected with gear (73) of first bull stick (71), right-hand member middle part and the positive and negative motor of fixedly connected with second (74) that left side arc (6) were run through in first bull stick (71), first bull stick (71) are alternated to be connected and will rotate strutting arrangement (7) and arc (6) swing joint in the opposite face of two sets of arcs (6).
5. A construction work material lifting device according to claim 1, characterised in that: the sliding lifting device (2) and the limiting device (3) are positioned on the same horizontal line.
6. A construction work material lifting device according to claim 4, characterised in that: the supporting plate (72) and the first fixing plate (1) are positioned on the same horizontal line.
CN201922247298.7U 2019-12-16 2019-12-16 Building engineering material lifting device Expired - Fee Related CN211338645U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922247298.7U CN211338645U (en) 2019-12-16 2019-12-16 Building engineering material lifting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922247298.7U CN211338645U (en) 2019-12-16 2019-12-16 Building engineering material lifting device

Publications (1)

Publication Number Publication Date
CN211338645U true CN211338645U (en) 2020-08-25

Family

ID=72104375

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922247298.7U Expired - Fee Related CN211338645U (en) 2019-12-16 2019-12-16 Building engineering material lifting device

Country Status (1)

Country Link
CN (1) CN211338645U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112460442A (en) * 2020-11-23 2021-03-09 李耀坤 Outdoor LED electronic display screen
CN112718946A (en) * 2020-12-18 2021-04-30 南京斯伯克数控装备有限公司 High-flexibility bending machine convenient for angle adjustment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112460442A (en) * 2020-11-23 2021-03-09 李耀坤 Outdoor LED electronic display screen
CN112718946A (en) * 2020-12-18 2021-04-30 南京斯伯克数控装备有限公司 High-flexibility bending machine convenient for angle adjustment

Similar Documents

Publication Publication Date Title
CN211338645U (en) Building engineering material lifting device
CN106284952A (en) A kind of intelligence ceramic tile stickers machine people
CN218397524U (en) Steel bar rust cleaning device for water conservancy building construction
CN212503512U (en) Elevator cab overhauls safety arrangement
CN210973592U (en) Different-caliber corrugated pipe mixed hoisting and transporting device
CN214527795U (en) Detachable tower crane steel structure platform
CN212198351U (en) Elevating gear for construction
CN110228528B (en) Variable wheel base frame and have jack-up vehicle of variable wheel base frame
CN212954028U (en) Crane for civil engineering construction
CN214409306U (en) Slope displacement monitoring device for open-air coal mine based on Beidou positioning technology
CN211195335U (en) Wine box positioner is used in wine box printing
CN207608831U (en) A kind of New operation device of bridge construction
CN219672164U (en) Movable concrete conveying pump
CN210716756U (en) Base is used in electromechanical device installation of urban construction
CN111622115A (en) Efficient bridge engineering construction platform
CN214194975U (en) Steel house convenient to remove
CN218879290U (en) Balance adjustment structure of pneumatic hoist
CN210238503U (en) Piling device for building construction
CN212642176U (en) Outer facade curtain wall construction erection equipment
CN112777532B (en) Electric power construction aerial working lift platform
CN217020066U (en) Safe type die carrier processing is with roll-over table
CN218715819U (en) Building engineering construction protector
CN218492305U (en) Construction equipment for bridge anti-collision wall
CN216553179U (en) Concrete breaking device with adjustable curve breaking and length
CN216955561U (en) Multi-functional hardness testing device of building material

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200825

Termination date: 20201216