CN211330750U - Controlled cooling device for multi-line slitting rolling of bar - Google Patents

Controlled cooling device for multi-line slitting rolling of bar Download PDF

Info

Publication number
CN211330750U
CN211330750U CN201921458939.7U CN201921458939U CN211330750U CN 211330750 U CN211330750 U CN 211330750U CN 201921458939 U CN201921458939 U CN 201921458939U CN 211330750 U CN211330750 U CN 211330750U
Authority
CN
China
Prior art keywords
cooling
water
bar
unit
assembly seat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921458939.7U
Other languages
Chinese (zh)
Inventor
王长生
肖立军
张忠峰
张红雁
郭其江
袁成玺
孟丽军
曹文强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Shiheng Special Steel Group Co Ltd
Original Assignee
Shandong Shiheng Special Steel Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Shiheng Special Steel Group Co Ltd filed Critical Shandong Shiheng Special Steel Group Co Ltd
Priority to CN201921458939.7U priority Critical patent/CN211330750U/en
Application granted granted Critical
Publication of CN211330750U publication Critical patent/CN211330750U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Heat Treatments In General, Especially Conveying And Cooling (AREA)

Abstract

The utility model relates to a multi-wire rod segmentation rolling control cooling device, this multi-wire rod segmentation rolling control cooling device, including many single line cooling device that set up side by side, many single line cooling device locate on same fixed water beam, show the centering precision that has improved the rod operation central line, reduce the rod and pile the steel risk, every single line cooling device includes transition guide slot, cooling structure and the collection guide slot that sets gradually along the rod direction of production, the cooling structure includes water cooling unit, counter-blow water unit and air passing unit; from the structure setting of water-cooling unit and air passing unit, can realize that cooling nozzle and air passing pipe fix a position the installation fast, set up cooling nozzle's first assembly seat and air passing pipe's second assembly seat into the same structure, adopt the same mounting means, can realize that cooling nozzle and air passing pipe different distributions on fixed water beam to comparatively quick adjustment production technology and production error, for example by continuous cooling to intermittent type cooling technology, line difference in temperature etc..

Description

Controlled cooling device for multi-line slitting rolling of bar
Technical Field
The utility model relates to a rod production field especially relates to a multi-thread segmentation rolling control cooling device of rod.
Background
In the multi-line cutting rolling production of the bar, a control cooling device is needed, is generally arranged between a K1 finishing mill group and a flying shear, and mainly comprises a transition guide groove, a water penetration cooling device and a collection guide groove which are sequentially arranged along the production direction of the bar. During actual production, the bar rolled by the K1 finishing mill set is transferred from the transition guide groove to the water cooling device for water cooling, and after cooling, the bar is gathered to flying shear operation through the collection guide groove.
The water cooling device comprises two sets of replaceable water cooling devices, wherein each set of water cooling device is provided with 7 sets of water penetrating pipes in the rolling direction, all the water penetrating pipes are arranged in one water penetrating box through circular pipe clamps, the water penetrating boxes are arranged on 2 moving trolleys, the moving trolleys are connected together through bolts, and one set of water penetrating pipes is driven to move to a working position through a hydraulic cylinder according to the process requirements when the water cooling device is used. Although the water penetration and cooling device can achieve the cooling effect, the following defects exist: firstly, 2 moving trolley structures are adopted, so that the water cooling device has poor front and back centering performance, steel piling accidents are easily caused, and the steel rolling production process is influenced; and the circular pipe clamp is easy to loosen after frequent movement, and the water penetrating pipe under high-pressure water supply is easy to deviate, so that centering is influenced, and the risk of steel piling is increased. Secondly, the cooling effect of the existing water cooling device is poor, when the multi-line bar is cooled, in order to facilitate cooling, the cooling water of the multi-line bar is controlled by a unified switch, so that all lines can supply water synchronously, but in actual cooling, because the rolling processes are different, for example, the error existing in the rolled center line bar and the rolled side line bar is about 5-6 ℃, the difference in temperature between all lines can occur due to manual centering installation error at the beginning of rolling, and the defects of inconsistent quality of the produced bar, high rejection rate and the like can be caused. Thirdly, when the existing water cooling device is worn to cool the bar, the water is brought seriously along with the operation of the bar, so that the surface of the bar is cooled unevenly, wave bends are generated, the quality of finished products is seriously influenced, and steel piling accidents are easily caused. Fourthly, the cooling effect is single, and the process requirements of sectional cooling according to different lengths cannot be met.
The existing transition guide groove adopts a fixed base structure, but the centering precision is poor due to the fact that the water tank penetrates through the guide groove to move back and forth, and the guide groove belongs to a long-term steel piling accident point.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a remedy prior art not enough, provide a high rod multi-thread segmentation rolling control cooling device of centering precision, can prevent the rod through the phenomenon of taking water after the cooling device cooling, and can pass through the distribution of unit and water-cooling unit on fixed water beam through the sky, realize the adjustment of the line-to-line difference in temperature and realize rod intermittent type or continuous cooling, solved the difficult problem that exists among the prior art.
The utility model discloses a solve the technical means that above-mentioned technical problem adopted and do:
a controlled cooling device for multi-wire splitting rolling of a bar comprises a plurality of single-wire cooling devices which are arranged in parallel, wherein the single-wire cooling devices are arranged on the same fixed water beam, each single-wire cooling device comprises a transition guide groove, a cooling structure and a collecting guide groove which are sequentially arranged along the production direction of the bar, and the cooling structure comprises a water cooling unit, a water counter-pumping unit and an air passing unit;
the water cooling unit comprises a first assembly seat arranged on the fixed water beam, a cooling nozzle is arranged on the first assembly seat, the cooling nozzle is provided with a water inlet and a first clamping table along the production direction of the bar, an annular convex part is connected outside the water inlet, the annular convex part is connected with a water inlet hole arranged on the first assembly seat in an embedded manner, the first clamping table is clamped with a clamping groove arranged on the first assembly seat, a pressing part for fastening the cooling nozzle on the first assembly seat is arranged on the first assembly seat, and the water cooling units of adjacent single lines share the first assembly seat;
the air passing unit comprises a second assembly seat installed on the fixed water beam, the second assembly seat is the same as the first assembly seat, an air passing pipe is installed on the second assembly seat, a plugging portion for plugging the water inlet hole and a second clamping table matched with the clamping groove are arranged on the air passing pipe, and the air passing units of adjacent single lines share the second assembly seat.
By last knowing, this application adopts transition guide slot, cooling structure and collects the guide slot and installs on same fixed water beam, can improve each other to neutrality, reduces the rod and piles the steel risk, and from the structure setting of water cooling unit and air passing unit, can realize cooling nozzle and the quick location installation of air passing pipe. And set up the first assembly seat with cooling nozzle and the second assembly seat that empty pipe was managed to the same structure, adopt the same mounting means, can realize that cooling nozzle and empty pipe are in the different distributions on fixed water beam to comparatively quick adjustment production technology and production error, for example by continuous cooling to intermittent type cooling technology, line difference in temperature etc..
When the cooling structure is composed of at least 1 water cooling unit, at least 1 counter-water-beating unit, at least 1 air-passing unit, at least 1 water cooling unit and at least 1 counter-water-beating unit, and the cooling structure of the adjacent single lines is the same, the intermittent production of the bar can be realized, when the bar is produced, the bar is initially cooled by the water cooling unit, then is cooled again by the air-passing unit, wherein the counter-water-beating unit is used for preventing the bar cooled by the water cooling unit from carrying water backwards, the phenomenon of uneven cooling can be avoided, the phenomena of wave bending and the like caused by uneven cooling of the bar are further reduced, and the risk of steel piling is finally reduced. The number of the water cooling units is related to the bar process, and the lower the temperature of the cooling bed is at the later stage of the bar, the more the water cooling units are arranged along the production direction of the bar.
When the cooling structure is composed of at least 1 minimum unit formed by at least 1 water cooling unit, at least 1 water counterattack unit and at least 1 air passing unit, the cooling structure of adjacent single lines is the same, the continuous cooling production of the bar can be realized, wherein the water cooling unit is used for cooling the bar in a penetrating way, the water counterattack unit is used for preventing the bar from moving backwards and carrying water, and the air passing unit is used for guiding the bar to the collecting guide groove.
When the cooling structure comprises at least 1 minimum unit that 1 at least empty unit-1 at least water cooling unit-1 at least counter water unit formed, the cooling structure of adjacent single line is the same, can realize the continuous cooling production of rod, wherein the water cooling unit is used for the rod to wear the water-cooling, counter water unit is used for preventing the rod to move backward and take water, empty unit is used for the rod to lead to water cooling unit from the transition guide slot to can prevent to a certain extent that the water of water cooling unit from spraying to the temperature measuring device at transition guide slot end, influence its use.
When an empty pipe is arranged between adjacent cooling nozzles of one single line, and the cooling nozzles are arranged on the rest single lines parallel to the empty pipe, the adjustment of large temperature difference between the lines can be realized, for example, when a certain production process produces bars, the cooling temperature of one single line cooling device is lower than that of other single lines and is 15-20 ℃, the machine needs to be stopped, one cooling nozzle of the line is rapidly replaced by the empty pipe, and the temperature difference adjustment range of the single empty pipe is about 15-20 ℃, so that the temperature difference between the lines can be compensated, the uniform temperature production of each line is realized, and the quality of finished products is ensured.
Preferably, detain on the fixed water beam that is equipped with cooling structure and be equipped with a plurality of protection casings, cooling structure locates between fixed water beam and a plurality of protection casings, and the protection casing can play the guard action when piling the steel to can prevent that the waste water after the cooling nozzle cooling is used from splashing, and then improve the cooling water utilization ratio. Specifically, in order to facilitate the hoisting of the protective cover, a plurality of hoisting rings are arranged at the top of the protective cover; in order to accurately position the water beam with the fixed water beam, a buckling convex part is arranged on the fixed water beam, and a buckling cap which is matched with the buckling convex part and embedded is arranged on the protective cover.
In order to increase the sealing performance of the connection part of the water inlet hole, sealing rings are respectively arranged between the water inlet hole and the annular convex part and between the water inlet hole and the plugging part. For an empty pipe, the plugging effect is better, and the influence on the stability of water inlet pressure difference of other lines is avoided; for the cooling nozzle, the water supply effect is better, avoids extravagant and guarantees the pressure difference stability of intaking. Specifically, the plugging portion comprises a positioning block fixedly sleeved with the empty pipe, and a plugging clamping table is fixedly connected to the bottom of the positioning block.
Preferably, in order to reduce the number of installation units, two adjacent water cooling units along the running direction of the bar material can share the first assembly seat, and two adjacent empty units along the running direction of the bar material can share the second assembly seat.
Preferably, the cooling nozzle includes along entry pipe A, box body A, export pipe A and the export guide pin bushing that rod production direction connected gradually, be formed with cooling channel in entry pipe A, export pipe A and the export guide pin bushing respectively, be formed with the water cavity A with the cooling channel intercommunication in the box body A, entry pipe A's end and export pipe A's top stretch into in the water cavity A to form the water inlet seam A with rod production direction acutangular angle, the box body bottom is located to water inlet and annular convex part, first ka tai is located on the export guide pin bushing, water inlet seam A communicates cooling channel and water inlet, install a plurality of gaskets between entry pipe A and the box body A to adjust water inlet seam A size through increasing and decreasing gaskets. So set up, compare traditional screw thread regulation mode, can guarantee the uniformity of different cooling nozzle inflow or the quantitative inflow adjustment that realizes different cooling nozzles.
Because the rolled sidelines are contacted with air during rolling, the temperature of the bar of the sidelines is slightly lower than that of the bar of the central line, and the temperature difference is 5-6 ℃, therefore, when the bar is cooled, the central line water inflow needs to be increased. Because of the line differential temperature of the slitting rolling process itself, the shim adjustment is done here when the cooling nozzles are installed.
Wherein, in order to strengthen the intensity that export guide pin bushing and export pipe A are connected, export guide pin bushing can set up to following structure, and is specific, the guide pin bushing that exports includes the guide pin bushing body, guide pin bushing body top periphery side body coupling has the fixed plate, the fixed plate with export pipe A rigid coupling. And the starting end of the guide sleeve body penetrates through the fixing plate to form an embedded convex part, and the embedded convex part is matched and connected with an embedded groove formed in the outlet guide pipe.
In order to reduce the steel piling accident of the bars, the initial end of the cooling channel of the outlet guide sleeve, the initial end of the cooling channel of the outlet guide pipe A and the initial end of the cooling channel of the inlet guide pipe A are all annular bell mouths; for the sealing property of the connection of each part, sealing rings are respectively arranged between the outlet conduit A and the box body A, between the inlet conduit A and the box body A, and between the annular convex part and the water inlet hole.
Preferably, the water-flapping-units comprise a third assembly seat arranged on the fixed water beam, a plurality of centering reverse nozzles and guide pipes are arranged on the third assembly seat along the production direction of the bar material, the reverse nozzles are used for preventing the bar material from moving backwards and carrying water, the water-flapping-units on adjacent single lines share the third assembly seat, and each reverse nozzle comprises an inlet guide pipe B, a box body B and an outlet guide pipe B which are fixedly connected in sequence along the running direction of the bar material; the inlet guide pipe B and the outlet guide pipe B are respectively internally provided with a water blocking channel, the opposite ends of the inlet guide pipe B and the outlet guide pipe B are in shaft hole clearance fit to form a water inlet seam B communicated with the water blocking channel, and the water inlet direction of the water inlet seam B and the running direction of the bar material form an obtuse angle; the box body B, the inlet guide pipe B and the outlet guide pipe B are enclosed together to form a water cavity B communicated with the water inlet seam B, a water inlet B communicated with the water cavity B is formed in the box body B, and the water inlet B is communicated with a water inlet hole formed in the third assembling seat. Wherein the size of the water inlet gap B is adjusted in the same way as the water inlet gap A of the cooling nozzle.
The third assembling seat and the first assembling seat are different in the number of water inlet holes and the number of the pressing parts.
Preferably, a plurality of water inlet pipes are arranged on the side portion of the fixed water beam, a plurality of water inlet channels connected with the water inlet pipes are arranged at the top of the fixed water beam, and the water inlet channels are communicated with water inlet holes in the first assembly base, the second assembly base and the third assembly base to supply water.
Preferably, the transition guide groove comprises a transition plate and a cover plate, a first guide groove is formed in the top of the transition plate along the running direction of the bar, and the first guide grooves of adjacent single lines share one transition plate; the cover plate is arranged on the transition plate at the top of the first guide groove, the cover plates of adjacent single lines are shared and form a transition channel for the bar to run with the first guide groove, the running tail end of the cover plate is fixedly connected with the transition plate, and the running starting end of the cover plate is movably covered with the transition plate; wherein, for the angle that opens and shuts of restriction apron, the end of apron is equipped with spacing portion, is equipped with on the cab apron with spacing portion complex butt portion, spacing portion with butt portion laminating is in order to restrict the angle that opens and shuts of apron, so set up, can prevent that the apron from transitionally overturning and striking other equipment. And when the opening and closing angle of the cover plate is set to be larger than 90 degrees to 180 degrees, the carding bar is not influenced by the cover plate when the steel rolling accident happens. For the convenience of operation, a handle can be arranged at the top of the cover plate. In order to facilitate hoisting, a lifting hook can be arranged on the transition plate; in order to fix the transition plate, a fixed plate is fixedly connected to the bottom of the transition plate, and the fixed plate is connected with the fixed water beam through a bolt.
The collecting guide groove comprises a collecting base, a collecting plate and a second protective cover, and the collecting base is arranged on the fixed water beam; the collecting plate is fixedly arranged on the collecting base, a second guide groove is formed in the top of the collecting plate, the second guide grooves of adjacent single lines share one collecting plate, and the second guide grooves on the single lines are gathered from the starting end of the second guide groove to the tail end of the second guide groove along the running direction of the bar; the second protective cover is buckled on the collecting plate at the top of the second guide groove, and the second protective covers of the adjacent single lines share the second protective cover and form a channel for the bar to run with the second guide groove. Wherein, for the installation of the second protection casing of convenience, the top of second protection casing has set firmly the handle, and second protection casing lateral part is equipped with the second draw-in groove, be equipped with on the collecting plate with the spacing post of second draw-in groove complex. When the second draw-in groove to rod traffic direction slope setting, can make between the two be connected more firm along with the rod operation between second protection casing and the collecting plate. In order to reduce the steel piling probability, the initial end of the collecting channel is an annular horn mouth; for the installation of the entire collecting channel, a lifting ring is provided on the collecting channel. In practical use, the number of the collecting guide grooves can be set according to requirements, and the common conditions of steel rolling are generally 2 or 4.
Preferably, the pressing portion comprises support columns symmetrically and fixedly connected to two sides of the assembling seat, a cross beam is fixedly connected to the tops of the two support columns, a plurality of adjusting bolts are connected to the cross beam in a threaded mode, and the bottoms of the adjusting bolts penetrate through the cross beam and then abut against the tops of the cooling nozzles and the tops of the empty tubes. The one end of crossbeam is articulated with one of them support column, the other end of crossbeam and wherein another support column can be dismantled fixedly, the expansion end of crossbeam is equipped with the handle, so sets up, makes things convenient for empty piece and cooling nozzle replacement installation.
First assembly seat has set firmly a plurality of installation departments respectively with the bottom of collecting the base, and every installation department tip extends the lateral part setting of first assembly seat and collection base, be equipped with on the fixed water beam with installation department complex mounting groove, the installation department is restricted in the mounting groove through the stopper, stopper demountable installation is in the mounting groove. Wherein, because first assembly seat is heavier with collection base weight, for the ease of installation, set firmly rings on first assembly seat and collection base, when assembling it with fixed water beam, the installation after squatting is squat in the hoist and mount can.
In the above text, the various starting ends and the ending ends mentioned are opposite, the starting end is the bar entering end, and the ending end is the bar exiting end.
The utility model adopts the above structure, the advantage that has is:
1. the centering precision of the running center line of the bar is obviously improved by improving the structure of the control cooling device, and the cooling nozzle and the hollow pipe can be quickly positioned and installed by the structural arrangement of the water cooling unit and the hollow unit; and set up the first assembly seat with cooling nozzle and the second assembly seat that empty pipe was managed to the same structure, adopt the same mounting means, can realize that cooling nozzle and empty pipe are in the different distributions on fixed water beam to comparatively quick adjustment production technology and production error, for example by continuous cooling to intermittent type cooling technology, line difference in temperature etc..
2. The problem of water after the rod is cooled can be solved, and the wave bending phenomenon caused by uneven cooling of the surface of the rod is avoided, so that the steel piling accident caused by the uneven cooling of the surface of the rod is avoided, and the quality of finished products is improved.
3. The small-range temperature difference adjustment of each line can be realized through the adjustment of the water inlet seam of the cooling nozzle.
4. The centering precision of transition guide slot, collection guide slot respectively with cooling structure has been improved, the reduction piles steel risk.
Drawings
Fig. 1 is a schematic side view of embodiment 1 of the present invention;
FIG. 2 is a schematic top view of the portion of FIG. 1;
FIG. 3 is a left side view of the first mounting block and the cooling nozzle of FIG. 2;
FIG. 4 is a right side view of the first mounting block and the cooling nozzle of FIG. 2;
FIG. 5 is a schematic cross-sectional view of the cooling nozzle of FIG. 2;
FIG. 6 is a schematic view of the hollow tube of FIG. 3;
FIG. 7 is a schematic cross-sectional view of the reversing nozzle of FIG. 3;
FIG. 8 is a schematic top view of a portion of the transition channel of FIG. 1;
FIG. 9 is an enlarged view of part A of FIG. 1;
FIG. 10 is an enlarged view of the portion B in FIG. 1;
FIG. 11 is a schematic top view showing the structure of embodiment 2;
FIG. 12 is a schematic top view showing the structure of embodiment 3;
FIG. 13 is a schematic top view showing the structure of embodiment 4;
fig. 14 is a partial structural view of fig. 13.
In the figure, 1, a fixed water beam, 2, a transition guide groove, 3, a cooling structure, 4 and a collection guide groove;
11. buckling a convex part 12, a water inlet pipe 13 and a water inlet channel;
21. a transition plate 211, a first guide groove 212, a contact part 213 and a fixing plate;
22. a cover plate 221, a limiting part 222 and a handle;
31. the water cooling unit 311, the first assembling seat 3111, the water inlet hole 3112, the clamping groove 3113 and the pressing part; 312. the cooling nozzle, 3121, water inlet, 3122, first clamping table, 3123, annular projection, 3124, inlet conduit a, 3125, box body a, 3126, outlet conduit a, 3127, outlet guide sleeve, 3128, water cavity a, 3129, water inlet seam a;
32. the water counterattack unit 321, the third assembling seat 322, the reverse nozzle 3221, the inlet conduits B and 3222, the box bodies B and 3223, the outlet conduits B and 3224, the water inlet seams B and 3225, the water cavities B and 3226 and the water inlet B;
33. an empty passing unit 331, an empty passing pipe 3311, a blocking part 3312 and a second clamping platform; 332. a second mounting seat;
34. a protective cover 341 is buckled with a cap;
41. collect base, 42, collection board, 421, second guide slot, 422, spacing post, 43, second protection casing, 431, second draw-in groove.
Detailed Description
In order to clearly illustrate the technical features of the present invention, the present invention is explained in detail by the following embodiments in combination with the accompanying drawings.
In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present application, however, the present application may be practiced in other ways than those described herein, and therefore the scope of the present application is not limited by the specific embodiments disclosed below.
In addition, in the description of the present application, it is to be understood that the terms "center", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "axial", "radial", "circumferential", and the like, indicate orientations and positional relationships based on those shown in the drawings, are only for convenience of description and simplicity of description, and do not indicate or imply that the referenced devices or elements must have a particular orientation, be constructed and operated in a particular orientation, and thus, are not to be construed as limiting the present application. Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of the present application, "a plurality" means two or more unless specifically limited otherwise.
In this application, unless expressly stated or limited otherwise, the terms "mounted," "connected," "secured," and the like are to be construed broadly and can include, for example, fixed connections, removable connections, or integral parts; the connection can be mechanical connection, electrical connection or communication; either directly or indirectly through intervening media, either internally or in any other relationship. The specific meaning of the above terms in the present application can be understood by those of ordinary skill in the art as appropriate.
In this application, unless expressly stated or limited otherwise, the first feature "on" or "under" the second feature may be directly contacting the first and second features or indirectly contacting the first and second features through intervening media. In the description herein, reference to the description of the term "one embodiment," "some embodiments," "an example," "a specific example," or "some examples," etc., means that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the application. In this specification, the schematic representations of the terms used above are not necessarily intended to refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
It should be noted that, in fig. 2, for convenience of understanding the present solution, the protective cover is not drawn on the cooling structure along the production direction of the bar, and a partial top view of the cooling structure can be directly seen when a part of the fixed water beam is exposed; the collection channel does not depict the second guard formation. In fig. 8, two transition channels are shown in succession for the sake of easy understanding of the transition channel structure, wherein the cover structure of one transition channel is not shown.
Example 1:
as shown in fig. 1 to 10, in this embodiment, the bar multi-line splitting rolling control cooling device includes a plurality of single-line cooling devices arranged in parallel, and the plurality of single-line cooling devices are arranged on the same fixed water beam 1, so that single-line centering performance can be improved, and steel piling risk of the bar can be reduced, each single-line cooling device includes a transition guide slot 2, a cooling structure 3 and a collection guide slot 4 which are sequentially arranged along a bar production direction, and the cooling structure 3 includes a water cooling unit 31, a counter water unit 32 and an air passing unit 33;
the water cooling unit 31 comprises a first assembling seat 311 arranged on a fixed water beam 1, a cooling nozzle 312 is arranged on the first assembling seat 311, the cooling nozzle 312 is provided with a water inlet 3121 and a first clamping table 3122 along the bar production direction, the water inlet 3121 is externally connected with an annular convex portion 3123, the annular convex portion 3123 is connected with a water inlet 3111 arranged on the first assembling seat 311 in an embedded manner, the first clamping table 3122 is clamped with a clamping groove 3112 arranged on the first assembling seat 311, the first assembling seat 311 is provided with a pressing portion 3113 for fastening the cooling nozzle 312 thereon, and the water cooling units 31 of adjacent single lines share the first assembling seat 311; the air passing unit 33 comprises a second assembly seat installed on the fixed water beam 1, the second assembly seat is the same as the first assembly seat, an air passing pipe 331 is installed on the second assembly seat, a blocking portion 3311 for blocking the water inlet hole 3111 and a second clamping table 3312 matched with the clamping groove 3112 are arranged on the air passing pipe 331, and the air passing unit 33 of the adjacent single line shares the second assembly seat. From the structural arrangement of the water cooling unit and the air passing unit, the cooling nozzle 312 and the air passing pipe 331 can be quickly positioned, installed and replaced with each other.
Cooling structure 3 comprises the minimum unit that 1 at least water-cooling unit-1 at least anti-water unit of pounding out-1 at least unit of crossing the unit-1 at least water-cooling unit of at least-1 at least water-cooling unit forms, and the cooling structure 3 of adjacent single line is the same, so set up, can realize the intermittent production of rod, when rod production, carry out the bar primary cooling through water-cooling unit 31 earlier, again through the empty unit 33 rewarming of crossing, next cool off through water-cooling unit 31 once more, wherein the anti-water unit 32 that pounces out is used for preventing the water-cooling unit 31 refrigerated rod to take water backward, can avoid the emergence of the inhomogeneous phenomenon of cooling, and then reduce the rod and produce phenomenons such as wave is curved because of the cooling inequality, the steel risk has finally been reduced to pile. The number of the water cooling units 31 is related to the bar process, and the lower the temperature of the cooling bed in the later period of the bar is, the more the number of the water cooling units 31 is arranged along the production direction of the bar.
Understandably, a plurality of protective covers 34 are buckled on the fixed water beam 1 provided with the cooling structure 3, the cooling structure 3 is arranged between the fixed water beam 1 and the plurality of protective covers 34, the protective covers 34 can play a protective role in steel piling, and can prevent the cooling nozzle 312 from splashing the waste water after being cooled and used, so that the utilization rate of the cooling water is improved. Specifically, in order to facilitate the hoisting of the protective cover 34, a plurality of hoisting rings are arranged at the top of the protective cover 34; in order to accurately position the fixed water beam 1, the buckling convex part 11 is arranged on the fixed water beam 1, and the buckling cap 341 which is matched with the buckling convex part 11 and embedded is arranged on the protective cover 34.
It is understood that, in order to increase the sealing performance at the connection of the water inlet 3111, sealing rings are respectively provided between the water inlet 3111 and the annular convex portion 3123, and between the water inlet 3111 and the blocking portion 3311. For the empty pipe 331, the plugging effect is better, and the stability of water inlet pressure difference of other lines is prevented from being influenced; for the cooling nozzle 312, the water supply effect is better, waste is avoided and the stability of the water inlet pressure difference is ensured. Specifically, the plugging portion 3311 includes a positioning block fixedly sleeved with the hollow pipe 331, and a plugging block platform embedded in cooperation with the water inlet hole is fixedly connected to the bottom of the positioning block.
Understandably, the portion 3113 compresses tightly including the support column of symmetry rigid coupling in assembly seat both sides, has the crossbeam at the top rigid coupling of two support columns, threaded connection has a plurality of adjusting bolt on the crossbeam, and adjusting bolt's bottom runs through behind the crossbeam with cooling nozzle 312 top and empty top of passing through pipe 331 butt. One end of the cross beam is hinged to one of the support columns, the other end of the cross beam is detachably fixed to the other support column, and the movable end of the cross beam is provided with a handle, so that the air passing pipe 331 and the cooling nozzle 312 can be conveniently replaced and installed.
Understandably, in order to reduce the number of installation units and facilitate the installation, the first assembly seat 311 can be shared by two adjacent water cooling units 31 along the running direction of the bar, and the second assembly seat can be shared by two adjacent idle units 33 along the running direction of the bar.
It can be understood that the cooling nozzle 312 includes an inlet conduit a3124, a box a3125, an outlet conduit a3126 and an outlet guide 3127, which are sequentially connected along the rod production direction, cooling channels are respectively formed in the inlet conduit a3124, the outlet conduit a3126 and the outlet guide 3127, a water cavity a3128 communicated with the cooling channels is formed in the box a3125, a distal end of the inlet conduit a3124 and a leading end of the outlet conduit a3126 extend into the water cavity a3128, and a water inlet slit a3129 forming an acute angle with the rod production direction is formed, the water inlet port 3121 and the annular protrusion 3123 are provided at the bottom of the box 3125, the first clamping platform 3122 is provided on the outlet guide 3127, the water inlet slit a3129 communicates the cooling channels with the water inlet port 3121, a plurality of gaskets are installed between the inlet conduit a3124 and the box a3125, and the size of the water inlet slit a3129 is adjusted by increasing or decreasing the gaskets. So set up, compare traditional screw thread regulation mode, can guarantee the uniformity of different cooling nozzle 312 inflow or the quantitative inflow adjustment that realizes different cooling nozzle.
Specifically, because during rolling, the rolled sideline has contacted the air, leads to the rod temperature of sideline to be slightly less than the rod temperature of central line, and the error is 5-6 degrees centigrade, consequently, when the rod cools off, needs to increase the central line inflow, because the error temperature is lower, this moment, the accessible increases the packing ring number of a plurality of cooling nozzle 312 on the central line, realizes that the inflow increases, and then adjusts each line difference in temperature, guarantees finished product quality. Because of the tolerances inherent in the rolling, the adjustment of the washer is done here when the cooling nozzle is installed.
In order to enhance the connection strength between the outlet guide 3127 and the outlet guide a3126, the outlet guide 3127 may be configured as follows, specifically, the outlet guide 3127 includes a guide body, a fixing plate is integrally connected to an outer circumferential side of a starting end of the guide body, and the fixing plate is fixedly connected to the outlet guide a 3126. The starting end of the guide sleeve body penetrates through the fixing plate to form an embedded convex part, and the embedded convex part is matched and connected with an embedded groove formed in the outlet guide pipe; in order to reduce the steel piling accident of the bars, the starting ends of the cooling channels of the outlet guide sleeves, the outlet guide pipe A3126 and the inlet guide pipe A3124 are all annular bell mouths; for the sealing property of the connection of each part, sealing rings are respectively arranged between the outlet conduit A3126 and the box body A3125, between the inlet conduit A3124 and the box body A3125, and between the annular convex portion 3123 and the water inlet 3111.
Understandably, the water rebounding units 32 comprise a third assembling seat 321 arranged on the fixed water beam 1, a plurality of centering reverse nozzles 322 and guide pipes 323 are arranged on the third assembling seat 321 along the production direction of the bar, the reverse nozzles 322 are used for preventing the bar from moving backwards and carrying water, the water rebounding units 32 of adjacent single lines share the third assembling seat 321, and the reverse nozzles 322 comprise an inlet guide pipe B3221, a box body B3222 and an outlet guide pipe B3223 which are fixedly connected in sequence along the running direction of the bar; a water blocking channel is respectively arranged in the inlet conduit B3221 and the outlet conduit B3223, the opposite ends of the inlet conduit B3221 and the outlet conduit B3223 form shaft holes in clearance fit to form a water inlet slit B3224 communicated with the water blocking channel, and the water inlet direction of the water inlet slit B3224 is arranged at an obtuse angle with the bar material running direction; a water cavity B3225 communicated with the water inlet gap B3224 is defined by the box body B3222, the inlet conduit B3221 and the outlet conduit B3223, a water inlet B3226 communicated with the water cavity B3225 is arranged on the box body B3222, and the water inlet B3226 is communicated with a water inlet hole formed in the third assembling seat 321. Wherein the size of the water inlet gap B is adjusted in the same way as the water inlet gap A of the cooling nozzle. The third assembling seat 321 is different from the first assembling seat in the number of the water inlet holes and the number of the pressing portions.
Understandably, a plurality of water inlet pipes 12 are arranged on the side portions of the fixed water beams 1, a plurality of water inlet channels 13 connected with the water inlet pipes are arranged on the top portions of the fixed water beams 1, and the water inlet channels 13 are communicated with water inlet holes in the first assembly base, the second assembly base and the third assembly base to supply water.
The transition guide groove 2 comprises a transition plate 21 and a cover plate 22, the top of the transition plate 21 is provided with a first guide groove 211 along the running direction of the bar material, and the first guide grooves of adjacent single lines share one transition plate 21; the cover plate 22 is arranged on the transition plate 21 at the top of the first guide groove 211, the cover plates of adjacent single lines are shared, and a transition channel for the bar material to run is enclosed by the cover plates and the first guide groove 211, the running tail end of the cover plate 22 is fixedly connected with the transition plate 21, and the running starting end of the cover plate 22 is movably covered with the transition plate 21; in order to limit the opening and closing angle of the cover plate 22, the end of the cover plate 22 is provided with a limiting portion 221, the transition plate 21 is provided with an abutting portion 212 matched with the limiting portion 221, the limiting portion 221 is attached to the abutting portion 212 to limit the opening and closing angle of the cover plate 22, and thus the cover plate 22 can be prevented from being overturned in a transition mode to impact other equipment. And when the opening and closing angle of the cover plate 22 is set to be more than 90 degrees to 180 degrees, the carding bars are not influenced by the cover plate when steel rolling accidents happen. A handle 222 may also be provided on the top of the cover 22 for ease of handling. For the convenience of hoisting, a lifting hook can be arranged on the transition plate 21; for fixing the transition plate 21, a fixing plate 213 is fixedly connected to the bottom thereof, and the fixing plate is connected to the fixed water beam 1 by bolts.
The collecting channel 4 comprises a collecting base 41, a collecting plate 42 and a second protective cover 43, wherein the collecting base 41 is installed on the fixed water beam 1; the collecting plate 42 is fixedly arranged on the collecting base 41, the top of the collecting plate 42 is provided with a second guide groove 421, the second guide grooves of adjacent single lines share one collecting plate, and the second guide grooves 421 on the multiple single lines gather together from the starting ends of the second guide grooves to the tail ends of the second guide grooves along the running direction of the bars; the second protective cover 43 is fastened on the collecting plate 42 at the top of the second guide groove 421, and the second protective covers of adjacent single lines are shared to form a channel for the bar to run with the second guide groove 421. In order to facilitate the installation of the second protection cover 43, a handle is fixedly arranged at the top of the second protection cover 42, a second clamping groove 431 is arranged at the side of the second protection cover 43, and a limiting column 422 matched with the second clamping groove 431 is arranged on the collecting plate 42. When the second locking groove 431 is disposed to be inclined toward the direction of the bar, the connection between the second protection cover 43 and the collecting plate 42 is more stable as the bar moves. In order to reduce the steel piling probability, the initial end of the collecting channel is an annular horn mouth; for the installation of the entire collecting channel, a lifting ring is provided on the collecting channel. In practical use, the number of the collecting guide grooves can be set according to requirements, and the common conditions of steel rolling are generally 2 or 4.
First assembly seat 311 and the bottom of collecting base 41 have set firmly a plurality of installation portions 3114 respectively, and every installation portion 3114 tip extends the lateral part setting of first assembly seat and collection base, be equipped with on the fixed water beam 1 with installation portion complex mounting groove, the installation portion is restricted through the stopper and is installed in the mounting groove, stopper demountable installation is in the mounting groove. Wherein, because first assembly seat is heavier with collection base weight, for the ease of installation, set firmly rings on first assembly seat and collection base, when assembling it with fixed water beam, the installation after squatting is squat in the hoist and mount can.
Example 2:
as shown in fig. 11, on the basis of embodiment 1, the cooling structure is arranged in a manner different from that of embodiment 1, specifically, the cooling structure is composed of a minimum unit formed by at least 1 water cooling unit, at least 1 water reflaxing unit and at least 1 air passing unit, and the cooling structure of the adjacent single lines is the same, so that the continuous cooling production of the bar can be realized, wherein the water cooling unit 31 is used for cooling the bar through water, the water reflaxing unit 32 is used for preventing the bar from moving backwards with water, and the air passing unit 33 is used for guiding the bar to the collecting guide groove.
Example 3:
as shown in fig. 12, in embodiment 1 or embodiment 2, at least one air passage unit 33 is provided at the starting end of the cooling structure, and the cooling structures 3 of the adjacent single lines are the same. At this time, the empty passage unit 33 is used for guiding the bar material from the transition guide groove to the water cooling unit 31, and can prevent the water of the water cooling unit 31 from being sprayed reversely to the temperature measuring device at the tail end of the transition guide groove to a certain extent, so that the use of the temperature measuring device is influenced.
Example 4:
as shown in fig. 13-14, on the basis of embodiment 3, when the empty pipe 331 is disposed between adjacent cooling nozzles 312 of one of the single lines, and the cooling nozzles 312 are disposed on the remaining single lines parallel to the empty pipe 311, the adjustment of the temperature difference between the lines can be achieved, for example, when a certain production process produces a bar, the cooling temperature of one of the single line cooling devices is 15-20 degrees celsius lower than that of the other single lines, the production needs to be stopped, and one cooling nozzle of the line is rapidly replaced by the empty pipe, and the temperature difference adjustment range of the single empty pipe is about 15-20 degrees celsius, so that the temperature difference between the lines can be compensated, and the uniform temperature production of each line can be achieved, thereby ensuring the quality of the finished product.
In the above text, the various starting ends and the ending ends mentioned are opposite, the starting end is the bar entering end, and the ending end is the bar exiting end.
The above-mentioned embodiments can not be regarded as the limitation to the protection scope of the present invention, and to those skilled in the art, it is right that any alternative improvement or transformation made by the embodiments of the present invention all fall within the protection scope of the present invention. The parts of the present invention not described in detail are the known techniques of those skilled in the art.

Claims (10)

1. A controlled cooling device for multi-wire splitting rolling of a bar is characterized by comprising a plurality of single-wire cooling devices arranged in parallel, wherein the single-wire cooling devices are arranged on the same fixed water beam, each single-wire cooling device comprises a transition guide groove, a cooling structure and a collection guide groove which are sequentially arranged along the production direction of the bar, and the cooling structure comprises a water cooling unit, a water flapping unit and an air passing unit;
the water cooling unit comprises a first assembly seat arranged on the fixed water beam, a cooling nozzle is arranged on the first assembly seat, the cooling nozzle is provided with a water inlet and a first clamping table along the production direction of the bar, an annular convex part is connected outside the water inlet, the annular convex part is connected with a water inlet hole arranged on the first assembly seat in an embedded manner, the first clamping table is clamped with a clamping groove arranged on the first assembly seat, a pressing part for fastening the cooling nozzle on the first assembly seat is arranged on the first assembly seat, and the water cooling units of adjacent single lines share the first assembly seat;
the air passing unit comprises a second assembly seat installed on the fixed water beam, the second assembly seat is the same as the first assembly seat, an air passing pipe is installed on the second assembly seat, a plugging portion for plugging the water inlet hole and a second clamping table matched with the clamping groove are arranged on the air passing pipe, and the air passing units of adjacent single lines share the second assembly seat.
2. The controlled cooling device for multi-wire cutting and rolling of bar according to claim 1, wherein the cooling structure is composed of at least 1 minimum unit formed by at least 1 water cooling unit, at least 1 water counterattack unit, at least 1 air passing unit, at least 1 water cooling unit and at least 1 water counterattack unit, and the cooling structures of the adjacent single wires are the same.
3. The controlled cooling device for multi-wire cutting rolling of bar according to claim 1, wherein the cooling structure is composed of at least 1 minimum unit formed by at least 1 water cooling unit, at least 1 counter water unit and at least 1 empty unit, and the cooling structures of the adjacent single wires are the same.
4. The controlled cooling device for multi-wire cutting rolling of bar according to claim 1, wherein the cooling structure is composed of at least 1 minimum unit formed by at least 1 empty passing unit, at least 1 water cooling unit and at least 1 counter water unit, and the cooling structures of the adjacent single wires are the same.
5. The controlled cooling device for the multi-wire cutting and rolling of bars according to any one of claims 1 to 4, characterized in that between adjacent cooling nozzles of one of the single wires there are empty tubes and on the remaining single wires juxtaposed to said empty tubes there are cooling nozzles.
6. The controlled cooling device for multi-wire cutting and rolling of bars according to claim 1, wherein a plurality of protective covers are fastened to the fixed water beam along the bar production direction, and the cooling structure is disposed between the protective covers and the fixed water beam.
7. The controlled cooling device for multi-wire slicing rolling of bar according to claim 1, wherein two adjacent water cooling units along the bar running direction share a first assembly seat, and two adjacent empty units along the bar running direction share a second assembly seat.
8. The device for controlling and cooling the bar through multi-wire cutting according to claim 1, wherein the cooling nozzle comprises an inlet guide pipe A, a box body A, an outlet guide pipe A and an outlet guide sleeve which are sequentially connected along the bar production direction, the tail end of the inlet guide pipe A and the initial end of the outlet guide pipe A extend into the box body A and form a water inlet seam A forming an acute angle with the bar production direction, a water inlet and an annular convex part are arranged at the bottom of the box body, a first clamping table is arranged on the outlet guide sleeve, the water inlet seam A is communicated with the water inlet, a plurality of gaskets are arranged between the inlet guide pipe A or/and the outlet guide pipe A and the box body A, and the size of the water inlet seam A is adjusted by increasing or decreasing the gaskets.
9. The controlled cooling device for the multi-wire cutting rolling of the bar according to claim 1, wherein the water-repelling units comprise a third assembling seat arranged on the fixed water beam, a plurality of aligned reverse nozzles and guide pipes are arranged on the third assembling seat along the production direction of the bar, the reverse nozzles are used for preventing the bar from moving backwards and carrying water, and the water-repelling units on adjacent single wires share the third assembling seat.
10. The device for controlling the cooling of the bar through the multi-wire cutting and rolling according to claim 1, wherein the transition guide slot comprises a transition plate and a cover plate, the top of the transition plate is provided with a first guide slot along the bar moving direction, the first guide slots of the adjacent single wires share the transition plate, the cover plate is arranged on the transition plate at the top of the first guide slot and forms a transition channel for the bar to move with the first guide slot, the cover plates of the adjacent single wires share, the moving end of the cover plate is fixedly connected with the transition plate, and the moving start end of the cover plate is movably covered with the transition plate.
CN201921458939.7U 2019-09-03 2019-09-03 Controlled cooling device for multi-line slitting rolling of bar Active CN211330750U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921458939.7U CN211330750U (en) 2019-09-03 2019-09-03 Controlled cooling device for multi-line slitting rolling of bar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921458939.7U CN211330750U (en) 2019-09-03 2019-09-03 Controlled cooling device for multi-line slitting rolling of bar

Publications (1)

Publication Number Publication Date
CN211330750U true CN211330750U (en) 2020-08-25

Family

ID=72100967

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921458939.7U Active CN211330750U (en) 2019-09-03 2019-09-03 Controlled cooling device for multi-line slitting rolling of bar

Country Status (1)

Country Link
CN (1) CN211330750U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110586669A (en) * 2019-09-03 2019-12-20 石横特钢集团有限公司 Controlled cooling device for multi-line slitting rolling of bar

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110586669A (en) * 2019-09-03 2019-12-20 石横特钢集团有限公司 Controlled cooling device for multi-line slitting rolling of bar
CN110586669B (en) * 2019-09-03 2024-04-09 石横特钢集团有限公司 Multi-line cutting rolling control cooling device for bar

Similar Documents

Publication Publication Date Title
CN110586669A (en) Controlled cooling device for multi-line slitting rolling of bar
CN211330750U (en) Controlled cooling device for multi-line slitting rolling of bar
CN212821769U (en) Roller cooling device
CN110586662B (en) Full-flow program-controlled rolling and cooling production line for bars
CN212092830U (en) Long high-efficient nozzle
CN203140459U (en) Fore water blowing device of hot rolled strip finishing mill
CN116493423A (en) Wire rod rough middle rolling quick groove changing guide and guard device
CN202894257U (en) Improved structure of zero-section spray of tubular crystallizer for rectangular blank and cogged ingot
CN107971352B (en) Inner cooling device and method for cooling steel pipe on line
CN202224619U (en) Gas-water spraying device for continuous casting
CN212525464U (en) Water cooling air seal device
CN209850485U (en) Cutting fluid sprinkler for digit control machine tool
CN102950267A (en) Spraying device for continuous casting
CN113146813A (en) Cutter mold fixing support device for aerated brick production
CN212761022U (en) Cooling device for continuous casting production of medium plate
IT9047898A1 (en) DEVICE FOR PARTIAL COOLING, FOR THE PURPOSE OF THERMAL STRAIGHTENING, OF SPECIAL LAMINATED PROFILES.
CN218798977U (en) Secondary cold spraying pipe support for zero sector section of slab continuous casting machine
CN215879234U (en) Connecting device for 650-mill cooling water pipe
CN213495656U (en) Flushing device for rolling groove
CN218026297U (en) High-strength stable roller scraper
CN218423604U (en) Fluid liquid agent spraying device
CN219112523U (en) Multi-line module quick water cooling device
CN214348228U (en) Aluminum die cleaning mechanism
CN215657052U (en) But quick replacement import and export pipe's card is cut absolutely
CN213469098U (en) Novel four-segmentation through-water cooling device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant