CN211313299U - Support frame for construction - Google Patents

Support frame for construction Download PDF

Info

Publication number
CN211313299U
CN211313299U CN201921413471.XU CN201921413471U CN211313299U CN 211313299 U CN211313299 U CN 211313299U CN 201921413471 U CN201921413471 U CN 201921413471U CN 211313299 U CN211313299 U CN 211313299U
Authority
CN
China
Prior art keywords
steel pipe
base
support frame
threaded rod
weight box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921413471.XU
Other languages
Chinese (zh)
Inventor
方春旺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wu Jun
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201921413471.XU priority Critical patent/CN211313299U/en
Application granted granted Critical
Publication of CN211313299U publication Critical patent/CN211313299U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a support frame for construction relates to construction safety field. This support frame for construction, including the steel pipe, the middle part fixed connection chuck of steel pipe, the one end of steel pipe is seted up threaded hole, the other end of steel pipe is provided with the threaded rod, threaded connection has the base through threaded connection the one end of threaded rod, the top of base is provided with the equidistance bolt. This support frame for construction, the operator uses the threaded rod butt joint of steel pipe to the threaded hole of base, rotate the threaded rod and adjust the upper and lower distance of steel pipe, thereby make the height of backup pad can reach anticipated required height, through the chuck on the steel pipe, pothook on the public female steel pipe, accomplish horizontal butt joint and fixed, make the distance between two montants of it stable, the universal wheel that can raise the price is installed to the weight box bottom, increase the bottom weight of steel pipe, stability is improved, work efficiency is improved, safety is improved, time is saved, and cost is reduced.

Description

Support frame for construction
Technical Field
The utility model relates to a construction safety technical field specifically is a support frame for construction.
Background
Present building support is mostly buckle joint together, the installation is wasted time and energy, waste a large amount of manpower resources, whole list book, the limited buckle of holding power is not hard up or connect unstablely, the support atress inequality of jacking inclines or the off tracking easily, will seriously influence the quality of building, the building collapses even and brings danger, simultaneously probably need finely tune in the use when rotating the backup pad, current support can only wholly rotate or dismantle the back rotation of getting off and adorn again, it is very troublesome to adjust still can not transfer the exact angle by the support probably, hard, adjust also inaccurate target in place, need the repetitive operation.
However, the existing support frame for building construction is not simple enough in structure, inconvenient to use and install, and not simple to operate, which results in wasting a large amount of time and manpower, and increases the cost, so how to provide a support frame for building construction, which is simple in structure, convenient to use and install, and simple to operate becomes one of the problems that researchers in the field need to solve.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a support frame for construction has solved the inconvenient problem of a support frame structure installation operation for construction that proposes among the above-mentioned background art.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: a support frame for building construction comprises a steel pipe, wherein a clamping hole is formed in the surface of a chuck, a threaded hole is formed in one end of the steel pipe, a threaded rod is arranged at the other end of the steel pipe, one end of the threaded rod is connected with a base through threads, a base threaded hole is formed in the top of the base, an equidistant bolt is arranged at the top of the base, a counterweight box body is fixedly arranged at the bottom of the base, an upper support arm is fixedly arranged at the top of the inner wall of the counterweight box body, a long threaded rod is fixedly arranged at one end of the upper support arm, a lower support arm is fixedly arranged on the surface of the long threaded rod, a counterweight box base is fixedly arranged at one end of the lower support arm, a universal wheel is fixedly arranged at the bottom of the counterweight box body, equidistant threaded holes are formed in the upper surface of the counterweight box body, the one end of long threaded rod is provided with the chuck, the surface in card hole runs through and installs the pothook, the public steel pipe of one end fixedly connected with of pothook, the one end of public steel pipe has female steel pipe through threaded connection, the one end fixed mounting of steel pipe has the backup pad, the lower fixed surface of backup pad is connected with the floor, set screw is installed to the bottom of backup pad.
Preferably, the number of the bolts is eight, and the eight bolts are divided into two groups.
Preferably, the upper supporting arm is fixedly connected with the lower supporting arm through a rivet, and the number of the upper supporting arm and the number of the lower supporting arm are respectively two.
Preferably, the number of the springs is four, and the springs are fixedly connected to four corners of the weight box base.
Preferably, the base passes through equidistance bolt and counter weight box fixed connection, and the equidistance bolt has four.
Preferably, the upper supporting arm is fixedly connected with the counterweight box body through a bolt, and the top of the inner wall of the counterweight box body is provided with threads.
Preferably, the lower supporting arm is fixedly connected with the weight box base through a bolt, and the top of the weight box base is provided with threads.
Preferably, the surface of the chuck is provided with eight through-going chucking holes, and the angle of every two chucking holes is 45 degrees.
Preferably, the support plate is fixedly connected with the steel pipe through a fixing screw, and two rib plates are arranged on the lower surface of the support plate.
(III) advantageous effects
The utility model provides a support frame for construction. Has the following beneficial effects:
1. this support frame for construction, fix on ground through the base, the operator uses the threaded rod butt joint of steel pipe to the threaded hole of base, make it screw up, the operator rotates the threaded rod simultaneously and adjusts the upper and lower distance of steel pipe, thereby make the height of backup pad can reach anticipated required height, through the chuck on the steel pipe, pothook on the public female steel pipe, accomplish horizontal butt joint and fixed, and simultaneously, the threaded rod through public female steel pipe realizes butt joint and fine setting with the threaded hole, make the distance between its two montants stable, do not produce and rock, consequently, the stability of support frame to supporting the roof has been promoted, safety is improved, time saving, and cost is reduced.
2. This support frame for construction through the combination of base with the weight box, can realize removing, and the universal wheel that can raise the price is installed to the weight box bottom, uses spanner or electric drill to rotate its chuck, realizes going up and down, reduces to make the weight box can not remove and sit on the ground completely, increases the bottom weight of steel pipe, improves stability, improves work efficiency, saves the time cost.
Drawings
FIG. 1 is an overall structure diagram of the present invention;
FIG. 2 is a top view of the chuck of the present invention;
FIG. 3 is a cross-sectional structural view of the weight box of the present invention;
fig. 4 is the cross-sectional structure view of the threaded hole of the present invention.
In the figure: 1 threaded hole, 2 chucks, 3 steel pipes, 4 threaded rods, 5 base threaded holes, 6 bases, 7 equidistant bolts, 8 counterweight box bodies, 9 universal wheels, 10 hooks, 11 male steel pipes, 12 female steel pipes, 13 clamping holes, 14 counterweight box bases, 15 long threaded rods, 16 lower supporting arms, 17 upper supporting arms, 18 bolts, 19 rivets, 20 springs, 21 equidistant threaded holes, 22 through holes, 23 chucks, 24 fixing screws, 25 ribbed plates and 26 supporting plates.
Detailed Description
The invention is explained in more detail below with reference to the figures and examples.
Referring to fig. 1-4, embodiments of the present invention provide the following technical solutions: a support frame for building construction comprises a steel pipe 3, a chuck 2 is fixedly connected to the middle of the steel pipe 3, a clamping hole 13 is formed in the surface of the chuck 2, a threaded hole 1 is formed in one end of the steel pipe 3, a threaded rod 4 is arranged at the other end of the steel pipe 3, one end of the threaded rod 4 is connected with a base 6 through threads, a base threaded hole 5 is formed in the top of the base 6, equidistant bolts 7 are arranged at the top of the base 6, a counterweight box body 8 is fixedly arranged at the bottom of the base 6, an upper support arm 17 is fixedly arranged at the top of the inner wall of the counterweight box body 8, a long threaded rod 15 is fixedly arranged at one end of the upper support arm 17, a lower support arm 16 is fixedly arranged on the surface of the long threaded rod 15, a counterweight box base 14 is fixedly arranged at one end of the lower support arm, through-hole 22 has been seted up to the side of counter weight box 8, the top fixed mounting of the inner wall of counter weight box 8 has spring 20, the one end of long threaded rod 15 is provided with chuck 23, the surface of card hole 13 runs through and installs pothook 10, the public steel pipe 11 of the one end fixedly connected with of pothook 10, there is female steel pipe 12 public steel pipe 11's one end through threaded connection, the one end fixed mounting of steel pipe 3 has backup pad 26, the lower fixed surface of backup pad 26 is connected with floor 25, set screw 24 is installed to the bottom of backup pad 26.
In this embodiment: still include and fix on ground through base 6, the operator uses the threaded rod 4 butt joint of steel pipe 3 in the base screw hole 5 of base, make it screw up, the operator rotates threaded rod 4 and adjusts the upper and lower distance of steel pipe 3 simultaneously, thereby make the height of backup pad 26 can reach anticipated required height, through chuck 2 on the steel pipe, the pothook on the 11 female steel pipes 12 of public steel pipe, accomplish horizontal butt joint and fixed, simultaneously, the threaded rod and the screw hole through 11 female steel pipes 12 of public steel pipe 11 of public steel pipe realize butt joint and fine setting, make the distance between its two montants stable, do not produce and rock, consequently, the stability of support frame to supporting the roof has been promoted, safety is improved, time saving, and cost is reduced.
In this embodiment: through the combination of base 6 and weight box 8, can realize removing, weight box bottom 14 is installed and is raised the universal wheel 9 of price, uses spanner or electric drill to rotate its chuck, realizes going up and down, reduces to make weight box 8 can not remove and sit on the ground completely, increases the bottom weight of steel pipe 3, improves stability, improves work efficiency, saves the time cost.
Specifically, the method comprises the following steps: the bolts 18 have eight in total, and the eight bolts 18 are divided into two groups; thus, one set is fixedly connected to the upper support arm 17 and the weight box 8, and the other set is fixedly connected to the lower support arm 16 and the weight box base 14.
Specifically, the method comprises the following steps: the upper support arm 17 is fixedly connected with the lower support arm 16 through a rivet 19, and two upper support arms 17 and two lower support arms 16 are arranged respectively; therefore, the upper support arm 15 and the lower support arm 16 are opened and closed up and down by a rivet 19, and a screw hole passing through the long screw 15 is formed in the middle of the rivet 19.
Specifically, the method comprises the following steps: the number of the springs 20 is four, and the springs 20 are fixedly connected to four corners of the weight box base 14; therefore, the stability of the weight base is increased by the spring 20.
Specifically, the method comprises the following steps: the base 6 is fixedly connected with a counterweight box body 8 through equidistant bolts 7, and the number of the equidistant bolts 7 is four; therefore, the bolt 7 is screwed into the screw hole 21 in the upper surface of the counterweight housing 8, and the bolt is tightened to fix the counterweight housing.
Specifically, the method comprises the following steps: the surface of the chuck 2 is provided with eight through clamping holes 13, and the angle of every two clamping holes 13 is 45 degrees; therefore, the locking hole 13 is locked with the hook 10 of the female steel tube 12 of the male steel tube 11 to play a role in fixing.
Specifically, the method comprises the following steps: the support plate 26 is fixedly connected with the steel pipe 3 through a fixing screw 24, and two ribbed plates 25 are arranged on the lower surface of the support plate 26; therefore, the two ribs 25 serve to fix the support plate 26 against tilting.
The working principle is as follows: when the device is used, the base 6 is fixed on the ground, the threaded rod 4 of the steel pipe 3 is butted into the threaded hole 5 of the base to be screwed, meanwhile, an operator rotates the threaded rod 4 to adjust the vertical distance of the steel pipe 3, so that the height of the supporting plate 26 can reach the expected required height, the transverse butt joint and fixation are completed through the chuck 2 on the steel pipe and the clamping hook on the male steel pipe 11 and the female steel pipe 12, meanwhile, the butt joint and fine adjustment are realized through the threaded rod and the threaded hole of the male steel pipe 11 and the female steel pipe 12 on the steel pipe, therefore, the stability of the supporting frame for supporting the roof is improved, the movement can be realized through the combination of the base 6 and the weight box 8, the universal wheels 9 which can raise price are installed at the bottom 14 of the weight box, the lifting is realized through rotating the clamping heads of the universal wheels by using a spanner or an electric drill, the lifting is, the stability is improved.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (9)

1. The utility model provides a support frame for construction, includes steel pipe (3), middle part fixed connection chuck (2) of steel pipe (3), its characterized in that: the steel pipe support is characterized in that a clamping hole (13) is formed in the surface of the chuck (2), a threaded hole (1) is formed in one end of the steel pipe (3), a threaded rod (4) is arranged at the other end of the steel pipe (3), a base (6) is connected to one end of the threaded rod (4) through threads, a base threaded hole (5) is formed in the top of the base (6), equidistant bolts (7) are arranged at the top of the base (6), a counterweight box body (8) is fixedly arranged at the bottom of the base (6), an upper supporting arm (17) is fixedly arranged at the top of the inner wall of the counterweight box body (8), a long threaded rod (15) is fixedly arranged at one end of the upper supporting arm (17), a lower supporting arm (16) is fixedly arranged on the surface of the long threaded rod (15), a counterweight box base (14) is fixedly arranged at one end of the lower supporting arm (16, equidistant screw hole (21) has been seted up to the upper surface of counter weight box (8), through-hole (22) have been seted up to the side of counter weight box (8), the top fixed mounting of the inner wall of counter weight box (8) has spring (20), the one end of long threaded rod (15) is provided with chuck (23), the surface of card hole (13) is run through and is installed pothook (10), the public steel pipe of one end fixedly connected with (11) of pothook (10), there is female steel pipe (12) one end of public steel pipe (11) through threaded connection, the one end fixed mounting of steel pipe (3) has backup pad (26), the lower fixed surface of backup pad (26) is connected with floor (25), set screw (24) are installed to the bottom of backup pad (26).
2. The support frame for building construction according to claim 1, characterized in that: the bolts (18) have a total of eight, and the eight bolts (18) are divided into two groups.
3. The support frame for building construction according to claim 1, characterized in that: go up support arm (17) through rivet (19) and lower support arm (16) fixed connection, and go up support arm (17) and lower support arm (16) respectively have two.
4. The support frame for building construction according to claim 1, characterized in that: the springs (20) are four in total, and the springs (20) are fixedly connected to four corners of the weight box base (14).
5. The support frame for building construction according to claim 1, characterized in that: the base (6) is fixedly connected with the counterweight box body (8) through equidistant bolts (7), and the number of the equidistant bolts (7) is four.
6. The support frame for building construction according to claim 1, characterized in that: go up support arm (17) through bolt (18) and counter weight box (8) fixed connection, and the inner wall top of counter weight box (8) is seted up threadedly.
7. The support frame for building construction according to claim 1, characterized in that: the lower supporting arm (16) is fixedly connected with the weight box base (14) through a bolt (18), and the top of the weight box base (14) is provided with threads.
8. The support frame for building construction according to claim 1, characterized in that: the surface of the chuck (2) is provided with eight through clamping holes (13), and the angle of every two clamping holes (13) is 45 degrees.
9. The support frame for building construction according to claim 1, characterized in that: the support plate (26) is fixedly connected with the steel pipe (3) through a fixing screw (24), and two rib plates (25) are arranged on the lower surface of the support plate (26).
CN201921413471.XU 2019-08-29 2019-08-29 Support frame for construction Active CN211313299U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921413471.XU CN211313299U (en) 2019-08-29 2019-08-29 Support frame for construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921413471.XU CN211313299U (en) 2019-08-29 2019-08-29 Support frame for construction

Publications (1)

Publication Number Publication Date
CN211313299U true CN211313299U (en) 2020-08-21

Family

ID=72057217

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921413471.XU Active CN211313299U (en) 2019-08-29 2019-08-29 Support frame for construction

Country Status (1)

Country Link
CN (1) CN211313299U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114401166A (en) * 2021-12-31 2022-04-26 江苏德联达智能科技有限公司 Height-adjustable intelligent gateway

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114401166A (en) * 2021-12-31 2022-04-26 江苏德联达智能科技有限公司 Height-adjustable intelligent gateway

Similar Documents

Publication Publication Date Title
CN211313299U (en) Support frame for construction
CN212002599U (en) Electric power iron tower consolidates support with diversified fixed base
CN215564477U (en) Building construction formwork support
CN209831566U (en) Water heating pipeline erection bracing frame for building
CN110778109A (en) Angle-adjustable support fitting
CN117146160A (en) Portable mobile mounting frame for electromechanical equipment
CN214119160U (en) Interim fixing device of municipal administration pipeline installation
CN212743384U (en) High and large formwork supporting structure for building
CN212683504U (en) Steel bar rust removal device
CN210086066U (en) Bridge expansion joint installation adjustment tool
CN218061535U (en) Steel construction lift angle adjusting device for management integrates based on building site
CN212163232U (en) Double-shaft intermodulation solar photovoltaic power generation support system
CN220848969U (en) Adjustable steel diagonal column supporting device
CN215293878U (en) Support positioner that municipal administration plumbing construction was used
CN217824395U (en) Car body of solar light tower
CN217925068U (en) Construction formwork supporting construction
CN220522137U (en) Detachable stage of pin-connected panel
CN217678842U (en) Fastening device for water conservancy and hydropower building construction
CN205476444U (en) Light -duty support post based on low level jacking die carrier system
CN219296986U (en) Hoisting mechanism for installing electromechanical equipment
CN210921825U (en) Installation system of circulating hot water device
CN217537806U (en) Adjustable bracketing is used to girder steel scaffold frame
CN219825746U (en) Mounting structure
CN219599423U (en) Clamping device for steel structure machining
CN212002455U (en) Auxiliary support for building construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20230320

Address after: 611300 Group 5, Shude Village, Caichang Town, Dayi County, Chengdu, Sichuan

Patentee after: Wu Jun

Address before: No. 25, Changfang, Daigang Village, Shanyao, Quangang District, Quanzhou City, Fujian Province, 362114

Patentee before: Zhuang Jingjiang

TR01 Transfer of patent right