CN211312861U - Railing and eave connection structure of ancient building - Google Patents
Railing and eave connection structure of ancient building Download PDFInfo
- Publication number
- CN211312861U CN211312861U CN201922047226.8U CN201922047226U CN211312861U CN 211312861 U CN211312861 U CN 211312861U CN 201922047226 U CN201922047226 U CN 201922047226U CN 211312861 U CN211312861 U CN 211312861U
- Authority
- CN
- China
- Prior art keywords
- railing
- eave
- upper portion
- ancient building
- horizontal pole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000007493 shaping process Methods 0.000 claims abstract description 6
- 239000004540 pour-on Substances 0.000 claims 1
- 239000002023 wood Substances 0.000 description 6
- 238000009434 installation Methods 0.000 description 5
- 238000005266 casting Methods 0.000 description 4
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 241000121612 Lepechinia calycina Species 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 210000001503 joint Anatomy 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
Images
Landscapes
- Steps, Ramps, And Handrails (AREA)
Abstract
The utility model discloses a railing and eave connection structure of ancient building relates to ancient building technical field, and it has the standing groove including installing the stand on basic unit upper portion, and the shaping of basic unit upper portion has pour the shaping on the interior bottom surface of standing groove and has placed the board, places the fixed frame of upper portion fixedly connected with of board, and the stand is placed and is located the upper portion of placing the board in fixed frame inside, and the lateral wall level of fixed frame is pegged graft there is the first bolt of threaded connection inside the stand. The utility model discloses it is comparatively stable to have to be connected between stand and the basic unit, uses comparatively convenient effect.
Description
Technical Field
The utility model belongs to the technical field of ancient building technique and specifically relates to a railing and eave connection structure of ancient building is related to.
Background
At present, ancient architecture in China is a structural mode mainly comprising a wooden framework, and in the current stage, due to the development of concrete structures, except that the repair work of some ancient architectures still adopts a wooden structure system, other newly-built antique architecture structures mostly adopt concrete structures to replace partial wooden structures, form the main structure of the antique architecture combined with concrete and big wooden structures, and also completely use the main structure of the antique architecture of the concrete structure.
The prior Chinese utility model with the publication number of CN204919817U discloses a connecting structure of a floor rail and an eave of an antique building, which comprises a rail body, wherein the rail body is arranged on a wood purlin, the wood purlin is arranged on a steel structure column, and one side of the wood purlin is provided with a corridor; the steel structure column is welded with reinforcing steel bars, and the reinforcing steel bars are inserted into the wood balms.
The above prior art solutions have the following drawbacks: the wood purlin can move upwards relative to the reinforcing steel bars, so that the connection between the railing body and the wood purlin is unstable.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a railing and eave connection structure of ancient building is connected comparatively stably between railing body and the wood purlin.
The above technical purpose of the present invention can be achieved by the following technical solutions: the utility model provides a railing and eave connection structure of ancient building, is including installing the stand on basic unit upper portion, basic unit upper portion shaping has the standing groove, the shaping has placed the board on the interior bottom surface of standing groove, the fixed frame of upper portion fixedly connected with of placing the board, the stand is placed at fixed frame inside and is located the upper portion of placing the board, the lateral wall level of fixed frame is pegged graft there is the first bolt of threaded connection at the stand inside.
Through adopting above-mentioned technical scheme, the basic unit is when pouring, and the preforming has the standing groove, places the board and pours in the inside of standing groove, and fixed frame this moment is located the upper portion of placing the board, places the stand on the upper portion of placing the board and is located the inside of fixed frame, then passes fixed frame threaded connection with first bolt level inside the stand. The stand is comparatively stable with being connected between the basic unit, and it is comparatively convenient to use.
The utility model discloses further set up to, place the up end of board and install the threaded rod of vertical setting, threaded rod threaded connection is inside the stand.
Through adopting above-mentioned technical scheme, during the installation, place the stand on the upper portion of threaded rod, then rotate the stand for the stand is placed inside the standing groove, thereby makes to place and is connected comparatively stably between board and the stand.
The utility model discloses further set up to, place two pieces of pouring of bottom fixedly connected with of board, pour the piece and pour in basic unit inside.
Through adopting above-mentioned technical scheme, pour the piece and pour inside the basic unit for it is comparatively stable to pour the piece relative basic unit, owing to place the board and pour the piece rigid coupling moreover, makes to place the comparatively stable installation of board on the basic unit, thereby makes the comparatively stable installation of stand place the board.
The utility model discloses further set up to, two first horizontal pole and the second horizontal pole that is located first horizontal pole bottom are all installed to the relative one side of stand, and it has a plurality of montants to peg graft between first horizontal pole and the second horizontal pole.
By adopting the technical scheme, during installation, the plurality of vertical rods are firstly inserted on the upper part of the second transverse rod, then the first transverse rod is installed on the upper part of the vertical rods, and finally the first transverse rod and the second transverse rod are inserted inside the upright post.
The utility model discloses further set up to, first horizontal pole is vertical along its extending direction has seted up a plurality of first grooves along its extending direction is vertical on a plurality of first holes, the second horizontal pole of having seted up, and the montant passes first hole and places at first inslot portion.
Through adopting above-mentioned technical scheme, install first horizontal pole and second horizontal pole between two stands earlier, then pass first hole with the montant and peg graft inside first groove. Mode this moment of adoption avoids need with the riser whole pegs graft on the second horizontal pole, then installs the upper portion at a plurality of montants with first horizontal pole, and the installation is comparatively simple.
The utility model discloses further set up to, the upper portion of first horizontal pole is provided with the arc apron, the upper portion in first hole is established to arc apron lid, the third bolted connection through vertical setting between arc apron and the first horizontal pole.
Through adopting above-mentioned technical scheme, when the montant because unexpected the emergence is damaged, take out the third bolt, then shift up the arc apron, peg graft at first inslot portion with new montant from first hole can.
The utility model discloses further set up to, be provided with a plurality of second bolts on the lateral wall of fixed frame, the second bolt is inside the stand for slope threaded connection.
Through adopting above-mentioned technical scheme, second bolt slope threaded connection increases the compactness of being connected between stand and the fixed frame inside the stand for the stand is comparatively stable places inside the standing groove.
The utility model discloses further set up to, cup jointed the slip ring that is located the standing groove inside on the stand.
Through adopting above-mentioned technical scheme, be provided with the slip ring, reduce debris and enter into the inside condition of standing groove for the leakproofness of standing groove is better.
To sum up, the utility model discloses following beneficial effect has:
1. the upright post is arranged in the fixing frame and is locked through the first bolt, so that the upright post cannot move relative to the fixing frame, and the upright post is stably connected relative to the base layer;
2. the threaded rod is arranged, the upright post is stably placed on the upper part of the placing plate, and the contact area between the upright post and the placing plate is further increased;
3. the montant passes first hole grafting inside first groove, and follow-up if the montant takes place to damage, can be quick separate the montant from between first horizontal pole and the second horizontal pole.
Drawings
FIG. 1 is a schematic view of the overall structure of the embodiment;
FIG. 2 is a schematic vertical sectional view of a column in the embodiment;
FIG. 3 is an enlarged schematic view of portion A of FIG. 2;
FIG. 4 is a schematic structural diagram illustrating an arc-shaped cover plate according to an embodiment.
Reference numerals: 1. a base layer; 11. a placement groove; 12. casting the sheet; 13. placing the plate; 131. a threaded rod; 14. a fixing frame; 15. a first bolt; 151. a second bolt; 152. a slip ring; 2. a column; 21. a circular hole; 3. a first cross bar; 31. a first hole; 32. an arc-shaped cover plate; 321. a first plate; 322. a second plate; 33. a third bolt; 34. a first butt joint plate; 35. mounting grooves; 4. a second cross bar; 41. a first groove; 5. a vertical rod.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Referring to fig. 1-2, for the utility model discloses a railing and eave connection structure of ancient building, the railing is installed on 1 upper portion of basic unit on two layers, and 1 upper portion of basic unit is pour and is formed with a plurality of standing grooves 11, and standing groove 11 internally mounted has stand 2, installs first horizontal pole 3 and second horizontal pole 4 between two stands 2.
Referring to fig. 3, the inside casting molding of base layer 1 at the bottom of placing groove 11 has two casting pieces 12 with L-shaped vertical cross sections, upper end face integrated into one piece of two casting pieces 12 has placing plate 13, the upper end face welded connection who places plate 13 has fixed frame 14, upright 2 is vertically placed inside fixed frame 14 and is located the up end of placing plate 13, horizontal peg graft on the lateral wall of fixed frame 14 has threaded connection at the inside first bolt 15 of upright 2, peg graft on the lateral wall of fixed frame 14 has threaded connection at the inside second bolt 151 of upright 2, second bolt 151 is located the upper portion of first bolt 15, second bolt 151 inclines upwards to extend. The second bolt 151 is disposed obliquely, so that the connection between the pillar 2 and the fixing frame 14 is tight.
Referring to fig. 3, in order to stabilize the connection between the column 2 and the placing plate 13, a threaded rod 131 is welded to the upper end surface of the placing plate 13, and the threaded rod 131 is vertically screwed inside the column 2.
Referring to fig. 3, in order to reduce the entry of dirt into the standing groove 11, a sliding ring 152 placed inside the standing groove 11 is provided vertically on the column 2.
Referring to fig. 2, two round holes 21 have been all seted up to two relative one sides of stand 2, and round hole 21 is vertical arranges and the interval sets up, and it has first horizontal pole 3 to peg graft between two higher round holes 21 of horizontal position, and it has second horizontal pole 4 to peg graft between two lower round holes 21 of horizontal position. First horizontal pole 3 has vertically seted up a plurality of first holes 31 along its extending direction, has vertically seted up a plurality of first grooves 41 along its extending direction on second horizontal pole 4, is provided with a plurality of montants 5 between first horizontal pole 3 and the second horizontal pole 4, and montant 5 all passes first hole 31 and pegs graft inside first groove 41.
Referring to fig. 2 and 4, in order to lock the vertical rod 5, an arc-shaped cover plate 32 is covered on the upper part of the first cross rod 3, and the arc-shaped cover plate 32 is in threaded connection with the first cross rod 3 through a third bolt 33 which is vertically arranged. The arc-shaped cover plate 32 is divided into a first plate 321 and a second plate 322, the first plate 321 is fixedly connected with the first abutting plate 34 at one end close to the second plate 322, and the mounting groove 35 for placing the first abutting plate 34 is arranged at one end of the second plate 322 close to the first plate 321.
In the use of the embodiment, 1, during the pouring of the base layer 1, the pouring sheet 12 is poured at the bottom of the placing groove 11, the placing groove 11 is poured and formed at the upper part of the base layer 1, the placing plate 13 is positioned at the upper part of the inner bottom surface of the placing groove 11, and the fixing frame 14 is welded and connected at the upper end part of the placing plate 13. 2. Placing the upright post 2 on the upper part of the threaded rod 131, rotating the upright post 2 to enable the threaded rod 131 to be in threaded connection with the upright post 2, enabling the upright post 2 to be located on the upper end face of the placing plate 13, and then enabling the first bolt 15 and the second bolt 151 to penetrate through the fixing frame 14 to be in threaded connection with the inside of the upright post 2; 3. the cross bar is inserted between the two upright posts 2, and the vertical bar 5 is inserted into the first groove 41 through the first hole 31. And finally, covering the arc-shaped cover plate 32 on the upper part of the first cross rod 3, and finally, threading a third bolt 33 through the arc-shaped cover plate 32 and connecting the third bolt inside the first cross rod 3 in a threaded manner.
The embodiment of this specific implementation mode is the preferred embodiment of the present invention, not limit according to this the utility model discloses a protection scope, so: all equivalent changes made according to the structure, shape and principle of the utility model are covered within the protection scope of the utility model.
Claims (8)
1. The utility model provides a railing and eave connection structure of ancient building, is including installing stand (2) on basic unit (1) upper portion, its characterized in that: basic unit (1) upper portion shaping has standing groove (11), the shaping is pour on the interior bottom surface of standing groove (11) and is placed board (13), the fixed frame (14) of upper portion fixedly connected with of placing board (13), stand (2) are placed inside fixed frame (14) and are located the upper portion of placing board (13), the lateral wall level of fixed frame (14) is pegged graft and is had first bolt (15) of threaded connection in stand (2) inside.
2. The connecting structure of the railing and the eave of the ancient building according to claim 1, characterized in that: the upper end face of the placing plate (13) is provided with a vertically arranged threaded rod (131), and the threaded rod (131) is in threaded connection with the inside of the upright post (2).
3. The connecting structure of the railing and the eave of the ancient building according to claim 1, characterized in that: the bottom of the placing plate (13) is fixedly connected with two pouring sheets (12), and the pouring sheets (12) are poured inside the base layer (1).
4. The connecting structure of the railing and the eave of the ancient building according to claim 1, characterized in that: two first horizontal pole (3) and second horizontal pole (4) that are located first horizontal pole (3) bottom are all installed to the relative one side of stand (2), and it has a plurality of montants (5) to peg graft between first horizontal pole (3) and second horizontal pole (4).
5. The connecting structure of the railing and the eave of the ancient building according to claim 4, wherein: a plurality of first holes (31) are vertically formed in the first cross rod (3) along the extending direction of the first cross rod, a plurality of first grooves (41) are vertically formed in the second cross rod (4) along the extending direction of the second cross rod, and the vertical rod (5) penetrates through the first holes (31) and is placed inside the first grooves (41).
6. The connecting structure of the railing and the eave of the ancient building according to claim 5, wherein: the upper portion of first horizontal pole (3) is provided with arc apron (32), arc apron (32) lid is established on the upper portion of first hole (31), arc apron (32) are connected through vertical third bolt (33) that sets up between first horizontal pole (3).
7. The connecting structure of the railing and the eave of the ancient building according to claim 1, characterized in that: a plurality of second bolts (151) are arranged on the outer side wall of the fixing frame (14), and the second bolts (151) are connected in the upright columns (2) in an inclined threaded mode.
8. The connecting structure of the railing and the eave of the ancient building according to claim 1, characterized in that: and a sliding ring (152) positioned in the placing groove (11) is sleeved on the upright post (2).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201922047226.8U CN211312861U (en) | 2019-11-22 | 2019-11-22 | Railing and eave connection structure of ancient building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201922047226.8U CN211312861U (en) | 2019-11-22 | 2019-11-22 | Railing and eave connection structure of ancient building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211312861U true CN211312861U (en) | 2020-08-21 |
Family
ID=72080488
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201922047226.8U Expired - Fee Related CN211312861U (en) | 2019-11-22 | 2019-11-22 | Railing and eave connection structure of ancient building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211312861U (en) |
-
2019
- 2019-11-22 CN CN201922047226.8U patent/CN211312861U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110439270B (en) | Construction method of post-cast strip disassembly-free support system | |
CN112482434B (en) | Shaped large formwork vertical thin-wall side wall and construction method | |
CN111206768B (en) | Light beam plate structure platform and construction method thereof | |
CN109024676A (en) | A kind of formwork bracing system and its construction method of cast-in-place pipe gallery | |
CN211312861U (en) | Railing and eave connection structure of ancient building | |
CN210947477U (en) | High strength guardrail modelled after an antique | |
CN110573683B (en) | Roof structure and construction method thereof | |
US20090188034A1 (en) | Integrated Hot Tub, Spa, or Pool and Frame and Method of Inground Installation | |
CN109441031A (en) | The open spiral stairs structure of the concealed overhanging type of structural beams and its construction method | |
CN213038845U (en) | Support system | |
CN107642241A (en) | The stress supporting construction and construction method of a kind of prefabricated balcony | |
CN205591450U (en) | Suspension type stair | |
CN211776075U (en) | Steel construction building stair | |
CN212478795U (en) | Reinforcing structure behind large-span protection railing | |
CN217299928U (en) | Outer frame faces limit protective structure | |
CN215858711U (en) | Wood railing and bottom plate fixing structure | |
CN211691819U (en) | Color steel plate enclosure capable of being circulated in whole system | |
CN212836357U (en) | Light steel structure stair | |
CN213174769U (en) | Beam plate post-cast strip formwork structure | |
CN219710931U (en) | Flower frame beam construction operation platform | |
CN110965773B (en) | Support arrangement for steel house building | |
CN217537288U (en) | Corridor structure of old building additional elevator | |
CN219431321U (en) | Adjustable operation platform for elevator well construction | |
JPS5812990Y2 (en) | Building loading platform | |
CN220451395U (en) | Structural climbing frame attaching supporting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200821 |
|
CF01 | Termination of patent right due to non-payment of annual fee |