CN211312764U - Underground pipe gallery construction tool - Google Patents

Underground pipe gallery construction tool Download PDF

Info

Publication number
CN211312764U
CN211312764U CN201921834485.9U CN201921834485U CN211312764U CN 211312764 U CN211312764 U CN 211312764U CN 201921834485 U CN201921834485 U CN 201921834485U CN 211312764 U CN211312764 U CN 211312764U
Authority
CN
China
Prior art keywords
pipe gallery
underground pipe
rod
montant
support frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921834485.9U
Other languages
Chinese (zh)
Inventor
李景卓
李平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Construction Engineering Group Co Ltd
Original Assignee
Xinjiang Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang Construction Engineering Group Co Ltd filed Critical Xinjiang Construction Engineering Group Co Ltd
Priority to CN201921834485.9U priority Critical patent/CN211312764U/en
Application granted granted Critical
Publication of CN211312764U publication Critical patent/CN211312764U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses an underground pipe gallery construction frock, including bottom plate main part, worm wheel and worm, first montant is installed to the middle inside bearing of bottom plate main part, and the inside threaded connection of first montant has the second montant to the support frame is installed in the top outside of second montant, the bottom mounting of support frame has the bottom plate main part, and the outside bearing of support frame installs the bull stick, and the outside winding of bull stick has the connection rope, the backup pad is installed on the top of second montant, and the front and back both sides face of backup pad all is fixed with the auxiliary frame. This underground pipe gallery construction frock is provided with the backup pad, is convenient for place the pipeline at the both ends of backup pad, consequently as long as the universal wheel through bottom plate main part bottom moves about the backup pad, just can be convenient for support and carry out supplementary installation work to the pipeline of the inside both sides face of underground pipe gallery, and the whole frock of being convenient for uses in less region, has improved the application range of whole frock.

Description

Underground pipe gallery construction tool
Technical Field
The utility model relates to an underground pipe gallery technical field specifically is an underground pipe gallery construction frock.
Background
The underground pipe gallery is characterized in that an underground space is dug underground, various engineering pipelines such as electric power, communication, gas, heat supply, water supply and drainage and the like in a city are installed and placed in a centralized mode so as to be convenient for later-stage maintenance and monitoring, a pipeline construction tool is needed in the construction process of the underground pipe gallery, and the pipeline is convenient to install and lay well, but the underground pipe gallery construction tool still has some defects;
at present, when the pipeline in the underground pipe gallery is constructed in the market, the tool such as a scaffold, a lifting device or a hoisting device is required to be used in a matched mode, and due to the limitation of the underground internal space, when the pipeline on two side faces is required to be installed, the scaffold, the lifting device or the hoisting device cannot be conveniently rotated, turned around and moved, and therefore the pipeline is inconvenient to use;
therefore, the problem that the underground pipe gallery construction tool can well solve is solved.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an underground pipe gallery construction frock to solve the problem that traditional underground pipe gallery construction frock is inconvenient to carry out the installation of both sides face in the less region in inner space on the existing market that above-mentioned background art provided.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides an underground pipe gallery construction frock, includes bottom plate main part, worm wheel and worm, first montant is installed to the middle inner bearing of bottom plate main part, and the inside threaded connection of first montant has the second montant to the support frame is installed in the top outside of second montant, the bottom mounting of support frame has the bottom plate main part, and the outside bearing of support frame installs the bull stick, and the outside winding of bull stick has the connection rope, the backup pad is installed on the top of second montant, and the front and back both sides face of backup pad all is fixed with the auxiliary frame, and the inner bearing of backup pad is connected with two-way lead screw, the top winding of connecting the rope has two-way lead screw, the bottom outside key connection of first montant has the worm wheel, and the outside meshing of worm wheel is connected with the worm to the front end of.
Preferably, the left side surface and the right side surface of the second vertical rod are both provided with clamping grooves, the highest point of the second vertical rod is higher than that of the first vertical rod, and the first vertical rod is of a hollow structure.
Preferably, the support frame is an inverted U-shaped structure, a bump is arranged inside the support frame, and the bump is in concave-convex fit connection with the clamping groove.
Preferably, a first winding and containing disc is fixed on the outer side of the rotating rod and is of an H-shaped structure.
Preferably, the auxiliary frame is in an E-shaped structure, and the upper surface of the auxiliary frame and the upper surface of the support plate are on the same plane.
Preferably, a second winding disc is fixed on the outer side of the inner end of the bidirectional screw rod, a connecting rod is in threaded connection with the outer surface of the bidirectional screw rod, an extrusion plate is fixed at the top end of the connecting rod, a rubber pad is fixed on the outer side face of the extrusion plate, a limiting block is fixed at the bottom end of the connecting rod, and the inner end of the bidirectional screw rod is connected with the supporting plate through a torsion spring.
Compared with the prior art, the beneficial effects of the utility model are that: the underground pipe gallery construction tool is used;
(1) the supporting plate is arranged, and pipelines can be conveniently placed at two ends of the supporting plate through the arrangement of the supporting plate, so that the supporting plate can be conveniently supported to perform auxiliary installation work on the pipelines at two side surfaces in the underground pipe gallery only by moving the supporting plate leftwards and rightwards through the universal wheel at the bottom end of the bottom plate main body, the whole tool does not need to be rotated and turned around, the whole tool can be conveniently used in a small area, and the use range of the whole tool is improved;
(2) the internally mounted of backup pad has two-way lead screws, in order to drive connecting rod and stripper plate together to remove when the rotation through two-way lead screw, the pipeline of the stripper plate in with the backup pad of being convenient for promotes and installs on the mounting bracket in the underground pipe gallery, simultaneously, through the setting of the stripper plate that is the arc form, the stripper plate of being convenient for is fine promotes the pipeline.
Drawings
FIG. 1 is a schematic view of the main sectional structure of the present invention;
FIG. 2 is an enlarged schematic view of the structure at A of FIG. 1 according to the present invention;
FIG. 3 is a schematic top view of the present invention;
FIG. 4 is an enlarged schematic view of the structure of FIG. 1 at B according to the present invention;
FIG. 5 is a schematic view of the top view structure of the support frame of the present invention connected to the second vertical rod;
fig. 6 is a schematic view of the structure of the torsion spring according to the present invention.
In the figure: 1. a base plate main body; 2. a first vertical bar; 3. a second vertical bar; 31. a card slot; 4. a support frame; 41. a bump; 5. a rotating rod; 51. a first winding tray; 6. connecting ropes; 7. a worm gear; 8. a worm; 9. an auxiliary frame; 10. a support plate; 11. a bidirectional screw rod; 111. a second winding tray; 112. a connecting rod; 113. a pressing plate; 114. a rubber pad; 115. a limiting block; 116. a torsion spring.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-6, the present invention provides a technical solution: a construction tool for an underground pipe gallery comprises a bottom plate main body 1, a first vertical rod 2, a second vertical rod 3, a support frame 4, a rotating rod 5, a connecting rope 6, a worm wheel 7, a worm 8, an auxiliary frame 9, a support plate 10 and a bidirectional screw rod 11, wherein the first vertical rod 2 is installed in the middle of the bottom plate main body 1 through a bearing, the second vertical rod 3 is connected with the first vertical rod 2 through internal threads, the support frame 4 is installed on the outer side above the second vertical rod 3, the bottom end of the support frame 4 is fixedly provided with the bottom plate main body 1, the rotating rod 5 is installed on the outer side of the support frame 4 through a bearing, the connecting rope 6 is wound on the outer side of the rotating rod 5, the support plate 10 is installed on the top end of the second vertical rod 3, the auxiliary frame 9 is fixed on the front side surface and the rear side surface of the support plate 10, the bidirectional screw rod 11 is connected with the internal bearing of the support plate, the outer side of the worm wheel 7 is engaged with a worm 8, and the front end of the worm 8 penetrates through the bottom plate main body 1;
the left outer side surface and the right outer side surface of the second vertical rod 3 are both provided with clamping grooves 31, the highest point of the second vertical rod 3 is higher than that of the first vertical rod 2, and the inside of the first vertical rod 2 is of a hollow structure, so that the second vertical rod 3 can be kept to vertically ascend through the clamping grooves 31, and the second vertical rod 3 is prevented from rotating;
the supporting frame 4 is of an inverted U-shaped structure, the bump 41 is arranged inside the supporting frame 4, and the bump 41 is in concave-convex fit connection with the clamping groove 31, so that the second vertical rod 3 is limited through the bump 41 and the clamping groove 31, and the second vertical rod 3 is prevented from rotating;
a first winding and containing disc 51 is fixed on the outer side of the rotating rod 5, and the first winding and containing disc 51 is in an H-shaped structure, so that the rotating rod 5 can well drive the first winding and containing disc 51 to rotate together to take up or pay off the connecting rope 6 on the outer side when rotating;
the auxiliary frame 9 is of an E-shaped structure, and the upper surface of the auxiliary frame 9 and the upper surface of the supporting plate 10 are on the same plane, so that the auxiliary frame 9 of the E-shaped structure is matched with the supporting plate 10 to improve the stability of pipeline placement;
the second winding containing disc 111 is fixed on the outer side of the inner end of the bidirectional screw rod 11, the connecting rod 112 is in threaded connection with the outer surface of the bidirectional screw rod 11, the extrusion plate 113 is fixed at the top end of the connecting rod 112, the rubber pad 114 is fixed on the outer side face of the extrusion plate 113, the limiting block 115 is fixed at the bottom end of the connecting rod 112, the inner end of the bidirectional screw rod 11 is connected with the supporting plate 10 through the torsion spring 116, and therefore the second winding containing disc 111 is well driven to rotate by the bidirectional screw rod 11.
The working principle is as follows: when the underground pipe gallery construction tool is used, firstly, the whole tool is moved to a construction area in an underground pipe gallery, then, as shown in attached drawings 1 and 4, a pipeline to be installed is placed on the left side of the upper surface of a supporting plate 10, the pipeline is supported by an auxiliary frame 9, the placing stability of the pipeline is improved, then, the top end of a rotating rod 5 on the left side below the supporting plate 10 is connected with an external servo motor through a coupler, as shown in attached drawings 2, the rotating rod 5 starts to rotate, the rotating rod 5 drives a first winding containing disc 51 on the outer side to wind and wind a connecting rope 6 when rotating, further, the upper end of the connecting rope 6 drives a second winding containing disc 111 to rotate, so that the second winding containing disc 111 drives a bidirectional screw rod 11 of an internal integrated structure to rotate, at the moment, the bidirectional screw rod 11 stores force on a torsion spring 116, as shown in attached drawings 6, the later-stage torsion spring 116 drives the bidirectional screw rod 11 to rotate reversely, the bidirectional screw rod 11 drives the connecting rod 112 in threaded connection at the outer side to move outwards when rotating, the limiting block 115 at the bottom end of the connecting rod 112 slides in the sliding groove in the limiting block 115, and the moving stability of the connecting rod 112 is ensured, so that the extruding plate 113 and the rubber pad 114 fixed at the top end of the connecting rod 112 push the pipeline on the bidirectional screw rod 11, and the pipeline well enters the mounting frame at the side edge in the underground pipe gallery to be mounted;
if the pipeline at the right side inside the underground pipe gallery needs to be installed, then, the whole tool only needs to be horizontally moved rightwards through the universal wheel at the bottom of the bottom plate main body 1, then, as mentioned above, the pipeline installation work is carried out in the same way, when the pipelines with different heights need to be installed, at this time, as shown in figure 1, the front end of the worm 8 penetrates through the bottom plate main body 1 to be connected with an external servo motor, the servo motor drives the worm 8 to rotate, the worm 8 drives the outer worm wheel 7 to rotate when rotating, so that the first vertical rod 2 connected with the internal key of the worm wheel 7 rotates in the bearing inside the bottom plate main body 1, and meanwhile, as shown in figures 1 and 5, the clamping groove 31 inside the second vertical rod 3 is clamped and connected through the convex block 41 inside the supporting frame 4, so that the first vertical rod 2 drives the second vertical rod 3 connected with internal threads to ascend when rotating, so that the second vertical rod 3 adjusts the height position of the supporting plate 10, and simultaneously, the staff manually rotates the rotating rod 5, so that the first rotating rod 5 outside carries out the paying-off work around the containing disc 51, and after the height position is adjusted, the work of the servo motor is stopped, and then, as shown in the above, in the same way, the extrusion plate 113 pushes the pipeline on the supporting plate 10 to place the installation work, and the content not described in detail in the present specification belongs to the prior art known by the professional in the field.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.

Claims (6)

1. The utility model provides an underground pipe gallery construction frock, includes bottom plate main part (1), worm wheel (7) and worm (8), its characterized in that: the middle inner bearing of the bottom plate main body (1) is provided with a first vertical rod (2), the inner thread of the first vertical rod (2) is connected with a second vertical rod (3), the outer side of the upper part of the second vertical rod (3) is provided with a support frame (4), the bottom end of the support frame (4) is fixed with the bottom plate main body (1), the outer bearing of the support frame (4) is provided with a rotating rod (5), the outer side of the rotating rod (5) is wound with a connecting rope (6), the top end of the second vertical rod (3) is provided with a support plate (10), the front side surface and the rear side surface of the support plate (10) are both fixed with auxiliary frames (9), the inner bearing of the support plate (10) is connected with a bidirectional screw rod (11), the top end of the connecting rope (6) is wound with a bidirectional screw rod (11), the bottom end outer side key of the first vertical rod (2) is connected with a worm wheel (, and the front end of the worm (8) penetrates through the bottom plate main body (1).
2. The underground pipe gallery construction tool according to claim 1, characterized in that: draw-in groove (31) have all been seted up to the lateral surface about second montant (3), and the peak of second montant (3) is higher than the peak of first montant (2) to the inside of first montant (2) is hollow column structure.
3. The underground pipe gallery construction tool according to claim 2, characterized in that: the support frame (4) is an inverted U-shaped structure, a convex block (41) is arranged inside the support frame (4), and the convex block (41) is connected with the clamping groove (31) in a concave-convex matching mode.
4. The underground pipe gallery construction tool according to claim 1, characterized in that: a first winding and containing disc (51) is fixed on the outer side of the rotating rod (5), and the first winding and containing disc (51) is in an H-shaped structure.
5. The underground pipe gallery construction tool according to claim 1, characterized in that: the auxiliary frame (9) is of an E-shaped structure, and the upper surface of the auxiliary frame (9) and the upper surface of the support plate (10) are on the same plane.
6. The underground pipe gallery construction tool according to claim 1, characterized in that: the outer side of the inner end of the bidirectional screw rod (11) is fixed with a second winding disc (111), the outer surface of the bidirectional screw rod (11) is in threaded connection with a connecting rod (112), the top end of the connecting rod (112) is fixed with an extrusion plate (113), meanwhile, the outer side face of the extrusion plate (113) is fixed with a rubber pad (114), the bottom end of the connecting rod (112) is fixed with a limiting block (115), and meanwhile, the inner end of the bidirectional screw rod (11) is connected with the supporting plate (10) through a torsion spring (116).
CN201921834485.9U 2019-10-29 2019-10-29 Underground pipe gallery construction tool Expired - Fee Related CN211312764U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921834485.9U CN211312764U (en) 2019-10-29 2019-10-29 Underground pipe gallery construction tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921834485.9U CN211312764U (en) 2019-10-29 2019-10-29 Underground pipe gallery construction tool

Publications (1)

Publication Number Publication Date
CN211312764U true CN211312764U (en) 2020-08-21

Family

ID=72065010

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921834485.9U Expired - Fee Related CN211312764U (en) 2019-10-29 2019-10-29 Underground pipe gallery construction tool

Country Status (1)

Country Link
CN (1) CN211312764U (en)

Similar Documents

Publication Publication Date Title
CN211312764U (en) Underground pipe gallery construction tool
CN214243546U (en) Hoisting accessory is used in building engineering construction
CN219689130U (en) Lifting device for curtain wall installation
CN210534589U (en) Intelligent monitoring equipment
CN209161231U (en) Cable auxiliary positioning frame for the information transmission system
CN213584967U (en) Cable supporting device for power equipment
CN211396742U (en) Building engineering strutting arrangement
CN212427265U (en) Foundation pit construction monitoring device
CN213923894U (en) Lifting device for control engineering is convenient for fix different objects
CN211310401U (en) Automatic wire arranging device suitable for cable production
CN217236806U (en) Building engineering is with supplementary alignment device
CN220115815U (en) Glass fiber cloth winding device
CN214989820U (en) High-stability beam lifting machine
CN218261340U (en) Winding device for hose manufacturing
CN213387621U (en) Jacking device for air conditioner installation
CN216971886U (en) Suspension device for electric power erection
CN217263638U (en) Self-adhesion waterproofing membrane processing equipment
CN214466560U (en) Pipeline energy-saving non-excavation directional drilling machine
CN219316479U (en) A safe suspended structure for building build high altitude construction
CN211964020U (en) Fixing mechanism of chemical material dissolving tank
CN219349964U (en) Mounting structure for transformer framework
CN214527847U (en) Energy-saving construction device for fire engineering pipeline
CN218863649U (en) Steel case roof beam elevation adjusting device
CN218324205U (en) Electric pole correcting device for power engineering
CN214220671U (en) Safety device is used in hydraulic engineering construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee