CN211286549U - Civil engineering is with construction support - Google Patents

Civil engineering is with construction support Download PDF

Info

Publication number
CN211286549U
CN211286549U CN201922041480.7U CN201922041480U CN211286549U CN 211286549 U CN211286549 U CN 211286549U CN 201922041480 U CN201922041480 U CN 201922041480U CN 211286549 U CN211286549 U CN 211286549U
Authority
CN
China
Prior art keywords
civil engineering
fixed base
fixed
maintenance door
microcontroller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922041480.7U
Other languages
Chinese (zh)
Inventor
庞传山
白玉琴
景宏君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Science and Technology
Original Assignee
Xian University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Science and Technology filed Critical Xian University of Science and Technology
Priority to CN201922041480.7U priority Critical patent/CN211286549U/en
Application granted granted Critical
Publication of CN211286549U publication Critical patent/CN211286549U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a construction support for civil engineering, which comprises a fixed base and a working platform, wherein the fixed base is provided with a maintenance door, the middle part of the maintenance door is fixed with an operation box, the side of the fixed base is provided with a rotary rod, the rotary rod is in transmission connection with a ground drilling fixed rod below the fixed base through a transmission bevel gear inside the fixed base, a pneumatic lifting column is arranged inside the maintenance door, the upper part of the pneumatic lifting column is connected with a connecting cube through a supporting upright post, the working platform is arranged on the connecting cube, and the construction support for civil engineering improves the adaptability to the terrain by a ground drilling stable mode, has better stability and lower fixed cost compared with the traditional support frame fixed at the side part and is convenient and fast to adjust the height, the automatic alarm device has an automatic alarm function, can give an alarm to people, and avoids construction accidents.

Description

Civil engineering is with construction support
Technical Field
The utility model relates to a civil engineering equipment field specifically is a civil engineering is with construction support.
Background
Civil engineering is a general term of scientific technology for building various land engineering facilities, and in addition to house buildings, various technical works such as investigation, planning, design, construction, installation and maintenance and the like for newly building, reconstructing or expanding buildings, structures, related supporting facilities and the like of various projects and completed engineering entities thereof, in the civil engineering construction process, a construction support is indispensable as equipment for providing support for constructors and materials.
However, the support used in the civil engineering construction process in the market generally only has the function of a simple fixed support, is difficult to adjust in height, is inconvenient to use, and is unstable in gravity center and easy to topple over when the bearing weight is too large, so that construction accidents are caused.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a civil engineering is with construction support to current civil engineering construction support that proposes in solving above-mentioned background art highly is difficult to adjust in the use, comparatively inconvenient problem during the use, and this kind of support is when bearing capacity is too big moreover, and the focus is unstable, emptys easily, leads to the construction accident.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a construction support for civil engineering, includes unable adjustment base and work platform, unable adjustment base's side is provided with the maintenance door, the middle part of maintenance door is fixed with the operation box, the rotary rod is installed to unable adjustment base's side, the rotary rod passes through unable adjustment base inside transmission bevel gear with the brill ground dead lever transmission of unable adjustment base below is connected, maintain the inside pneumatic lift post that is provided with of door, pneumatic lift post top is connected with connecting the cube through the support post, work platform installs connect on the cube, the both sides of support post respectively are provided with an anti-tilt supporting spring, pressure sensor is installed on anti-tilt supporting spring's well upper portion.
For the convenience of the utility model discloses a routine maintenance, unable adjustment base with it installs together through the hinge to maintain the door, maintain the door with the operation box passes through bolt fastening and twists and connect.
For the convenience of control the utility model discloses, improve the utility model discloses an easy operability, be provided with microcontroller in the operation box, pressure sensor is connected with microcontroller's input, microcontroller's input has still met altitude mixture control button, altitude mixture control button is including rising button and decline button, microcontroller's output termination has bee calling organ, be provided with the solenoid valve that admits air on the admission line of pneumatic lift post, be provided with exhaust solenoid valve on the exhaust duct of pneumatic lift post, solenoid valve and exhaust solenoid valve all are connected with microcontroller's output.
In order to improve the utility model discloses a stability, the rotary rod bore the ground dead lever transmission bevel gear's quantity is four, sets up respectively unable adjustment base's below four corners department.
In order to improve the utility model discloses adaptability to the topography, the rotary rod stretch into the inside one end of unable adjustment base with transmission bevel gear connects, bore ground dead lever stretch into the inside one end of unable adjustment base with transmission bevel gear connects.
In order to facilitate lifting and reduce the utility model discloses a support height, pneumatic lift post with the support post pneumatic drive is connected, the support post with it can dismantle the connection to connect the cube, connect the cube with work platform can dismantle the connection, work platform with prevent inclining supporting spring fixed connection.
In order to improve the stability and the accuracy of connecting cube and work platform installation, it includes the base block to connect the cube, the centre of base block is provided with main installation shaft hole, the array has the assistance all around of main installation shaft hole connect the supplementary mounting hole of cube installation location.
Compared with the prior art, the beneficial effects of the utility model are that:
this civil engineering is with construction support through boring stable mode, has improved the adaptability to the topography, compares traditional side fixed support frame, and stability is better, and fixed cost is also lower, simultaneously the utility model discloses altitude mixture control is convenient, when empting, has the automatic alarm function, can send out the police dispatch newspaper to people, avoids the construction accident.
Drawings
Fig. 1 is a front view of the civil engineering construction bracket of the present invention;
fig. 2 is a schematic view of the internal structure of the civil engineering construction bracket of the present invention;
fig. 3 is a schematic view showing the connection relationship between the microcontroller and other units of the construction bracket for civil engineering of the present invention;
fig. 4 is the utility model discloses civil engineering is with construction support's connection cube's three-dimensional view.
In the figure: 1. a fixed base; 2. maintaining the door; 3. an operation box; 4. rotating the rod; 5. drilling a ground fixing rod; 6. supporting the upright post; 7. a pressure sensor; 8. an anti-tilt support spring; 9. a working platform; 10. a connecting cube; 11. a pneumatic lifting column; 12. a drive bevel gear; 301. a microcontroller; 302. a height adjustment button; 303. a buzzer; 1001. a base block; 1002. a main mounting shaft hole; 1003. an auxiliary mounting hole; 1101. an air inlet solenoid valve; 1102. an exhaust solenoid valve.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the utility model discloses a construction support for civil engineering, including unable adjustment base 1 and work platform 9, unable adjustment base 1's side is provided with maintenance door 2, the middle part of maintaining door 2 is fixed with operation box 3, rotary rod 4 is installed to unable adjustment base 1's side, rotary rod 4 is connected with the transmission of the ground dead lever 5 of unable adjustment base 1 below through unable adjustment base 1 inside transmission bevel gear 12, maintain 2 inside pneumatic lift post 11 that are provided with of door, pneumatic lift post 11 top is connected with connection cube 10 through support post 6, work platform 9 installs on connecting cube 10, support post 6's both sides respectively are provided with an anti-tilt supporting spring 8, pressure sensor 7 is installed on anti-tilt supporting spring 8's well upper portion.
The fixed base 1 and the maintenance door 2 are installed together through a hinge, the maintenance door 2 and the operation box 3 are fixedly screwed through bolts, and the maintenance door 2 can be used for daily maintenance of the pneumatic lifting column 11.
The operation box 3 is internally provided with a microcontroller 301, the pressure sensor 7 is connected with the input end of the microcontroller 301, the input end of the microcontroller 301 is also connected with a height adjusting button 302, the height adjusting button 302 comprises an ascending button and a descending button, the output end of the microcontroller 301 is connected with a buzzer 303, an air inlet electromagnetic valve 1101 is arranged on an air inlet pipeline of the pneumatic lifting column 11, an air outlet electromagnetic valve 1102 is arranged on an air outlet pipeline of the pneumatic lifting column 11, and the air inlet electromagnetic valve 1101 and the air outlet electromagnetic valve 1102 are both connected with the output end of the microcontroller 301. When the lifting button is pressed, the microcontroller 301 controls the air inlet solenoid valve 1101 to enable the pneumatic lifting column 11 to be air-inlet, and the pneumatic lifting column 11 is lifted; when the down button is pressed, the microcontroller 301 controls the exhaust solenoid valve 1102 to exhaust the pneumatic lifting column 11 and lower the pneumatic lifting column 11; when the working platform 9 inclines to enable the pressure detected by the pressure sensor 7 to be increased and exceed a preset pressure alarm value, the microcontroller 301 controls the buzzer 303 to give an alarm to a user, and the user is prompted to pay attention to safety.
The quantity of rotary rod 4, brill ground dead lever 5, transmission bevel gear 12 is four, sets up respectively in unable adjustment base 1's below four corners departments, sets up like this and can provide steady support for unable adjustment base 1 through the combination of four sets of rotary rod 4, brill ground dead lever 5, transmission bevel gear 12.
One end of the rotating rod 4 extending into the fixed base 1 is connected with the transmission bevel gear 12, and one end of the ground drilling fixed rod 5 extending into the fixed base 1 is connected with the transmission bevel gear 12. Rotary rod 4 drives through transmission bevel gear 12 and bores ground dead lever 5 rotatory to feed downwards, bore into earth, improved the utility model discloses adaptability to the topography.
Pneumatic lift post 11 is connected with the pneumatic transmission of support post 6, and support post 6 can be dismantled with connection cube 10 and be connected, and connection cube 10 can be dismantled with work platform 9 and be connected, and work platform 9 and the supporting spring 8 fixed connection that prevents inclining, and pneumatic lift post 11 can drive work platform 9 lifting and decline through support post 6 to provide height-adjustable's support function for the user.
Connect cube 10 and include base block 1001, the centre of base block 1001 is provided with main installation shaft hole 1002, and the array has the supplementary mounting hole 1003 of connecting cube 10 erection site all around of main installation shaft hole 1002, and supplementary mounting hole 1003 can provide the effect of location for the erection joint of main installation shaft hole 1002 and work platform 9, improves the utility model discloses the packaging efficiency. In specific implementation, a main mounting shaft for inserting into the main mounting shaft hole 1002 and an auxiliary mounting shaft for inserting into the auxiliary mounting hole 1003 can be arranged on the working platform 9, so that the working platform 9 and the connecting cube 10 can be stably connected.
The working principle is as follows: the connecting cube 10 comprises a base block 1001, a main mounting shaft hole 1002 is arranged in the middle of the base block 1001, auxiliary mounting holes 1003 for mounting and positioning the auxiliary connecting cube 10 are arrayed around the main mounting shaft hole 1002, a working platform 9 with a required size is mounted on the connecting cube 10 through the main mounting shaft hole 1002 under the positioning of the auxiliary mounting holes 1003, the utility model is placed at a required position, then a rotating rod 4 is rotated, the rotating rod 4 is meshed with a transmission bevel gear 12, the transmission bevel gear 12 is meshed with a ground drilling fixing rod 5, the ground drilling fixing rod 5 is connected with a transmission bevel gear 12 in a transmission feeding way, the rotating rod 4 drives the ground drilling fixing rod 5 to rotate through the transmission bevel gear 12 and feed downwards to drill into the soil, the number of the rotating rod 4, the ground drilling fixing rod 5 and the transmission bevel gear 12 is four, the four rotating rods are respectively arranged at four corners below the fixing base 1, and four sets of ground drilling stabilizing devices are used for providing a, be used for construction staff work and place construction material in work platform 9, the user can pass through operation box 3 input work order, drive support post 6 variation height by operation box 3 control pneumatic lift post 11, when 9 focus changes of work platform, work platform 9's slope can be exerted pressure on pressure sensor 7, pressure sensor 7 will receive pressure feedback to microcontroller 301, when the pressure grow that pressure sensor 7 detected and exceed preset's pressure alarm value, microcontroller 301 control bee calling organ 303 sends the police dispatch newspaper to the user, the suggestion user notices safety.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. The utility model provides a construction support for civil engineering which characterized in that: comprises a fixed base (1) and a working platform (9), a maintenance door (2) is arranged on the side surface of the fixed base (1), an operation box (3) is fixed in the middle of the maintenance door (2), a rotating rod (4) is installed on the side edge of the fixed base (1), the rotating rod (4) is in transmission connection with a ground drilling fixing rod (5) below the fixed base (1) through a transmission bevel gear (12) in the fixed base (1), a pneumatic lifting column (11) is arranged inside the maintenance door (2), the upper part of the pneumatic lifting column (11) is connected with a connecting cube (10) through a supporting upright post (6), the working platform (9) is arranged on the connecting cube (10), two sides of the supporting upright post (6) are respectively provided with an anti-inclination supporting spring (8), and a pressure sensor (7) is arranged at the middle upper part of the anti-inclination supporting spring (8).
2. The construction bracket for civil engineering as claimed in claim 1, wherein: the fixed base (1) and the maintenance door (2) are installed together through hinges, and the maintenance door (2) and the operation box (3) are fixedly screwed through bolts.
3. The construction bracket for civil engineering as claimed in claim 1, wherein: be provided with microcontroller (301) in operation box (3), pressure sensor (7) are connected with the input of microcontroller (301), the input of microcontroller (301) has still been connect high adjustment button (302), high adjustment button (302) are including rising button and decline button, the output termination of microcontroller (301) has bee calling organ (303), be provided with air inlet solenoid valve (1101) on the admission line of pneumatic lift post (11), be provided with exhaust solenoid valve (1102) on the exhaust duct of pneumatic lift post (11), air inlet solenoid valve (1101) and exhaust solenoid valve (1102) all are connected with the output of microcontroller (301).
4. The construction bracket for civil engineering as claimed in claim 1, wherein: the number of the rotating rods (4), the ground drilling fixing rods (5) and the number of the transmission bevel gears (12) are four, and the four rotating rods are respectively arranged at four corners below the fixing base (1).
5. The construction bracket for civil engineering as claimed in claim 1, wherein: one end of the rotating rod (4) extending into the fixed base (1) is connected with the transmission bevel gear (12), and one end of the ground drilling fixed rod (5) extending into the fixed base (1) is connected with the transmission bevel gear (12).
6. The construction bracket for civil engineering as claimed in claim 1, wherein: the pneumatic lifting column (11) is connected with the supporting upright column (6) in a pneumatic transmission mode, the supporting upright column (6) is detachably connected with the connecting cube (10), the connecting cube (10) is detachably connected with the working platform (9), and the working platform (9) is fixedly connected with the anti-inclination supporting spring (8).
7. The construction bracket for civil engineering as claimed in claim 1, wherein: the connecting cube (10) comprises a base block (1001), a main mounting shaft hole (1002) is formed in the middle of the base block (1001), and auxiliary mounting holes (1003) for assisting the connecting cube (10) in mounting and positioning are arrayed on the periphery of the main mounting shaft hole (1002).
CN201922041480.7U 2019-11-24 2019-11-24 Civil engineering is with construction support Expired - Fee Related CN211286549U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922041480.7U CN211286549U (en) 2019-11-24 2019-11-24 Civil engineering is with construction support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922041480.7U CN211286549U (en) 2019-11-24 2019-11-24 Civil engineering is with construction support

Publications (1)

Publication Number Publication Date
CN211286549U true CN211286549U (en) 2020-08-18

Family

ID=72031970

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922041480.7U Expired - Fee Related CN211286549U (en) 2019-11-24 2019-11-24 Civil engineering is with construction support

Country Status (1)

Country Link
CN (1) CN211286549U (en)

Similar Documents

Publication Publication Date Title
CN209211941U (en) A kind of civil engineering work construction bracket
CN207269213U (en) A kind of supporting mechanism of solar panels
CN211286549U (en) Civil engineering is with construction support
CN210223002U (en) Novel geological environment monitoring and early warning device
CN210918144U (en) Constructional engineering construction support
CN214430045U (en) Novel afforestation punches device
CN213460978U (en) Metal pipeline bridge
CN212388946U (en) Portable operation bench for building engineering
CN213897521U (en) Support column for prefabricated building
CN205617771U (en) Construction operation platform and pipe -line transportation integrated device in high residential building elevartor shaft
CN213837824U (en) Deep foundation pit safety arrangement that construction used
CN210419106U (en) Dedicated track regulation formula elevating gear of municipal construction
CN221074110U (en) Drilling tower
CN207022698U (en) Dragon fruit post
CN207513230U (en) A kind of building-supporting supporting structure
CN217924732U (en) Scaffold frame with adjustable construction is used for housing construction
CN205141488U (en) Distribution transformer platform district patrols and examines operation platform
CN213927649U (en) Beam support for civil engineering construction
CN217420417U (en) Building decoration operation platform convenient to build
CN217130807U (en) Portable land mapping device
CN212295572U (en) Scaffold structure for building
CN212642061U (en) Scaffold frame that engineering construction operation was used is built in room
CN216196871U (en) Strutting arrangement for civil engineering
CN205382564U (en) Modular strengthen profiled steel structure factory building
CN215564990U (en) A safety protection structure for water conservancy construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200818