Prior art keywords
guide rail
backup pad
rotation axis
plastering
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921368809.4U
Other languages
Chinese (zh)
Inventor
李耀闯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Xianjing Landscape Engineering Co ltd
Original Assignee
Zhuji Yitong Network Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuji Yitong Network Technology Co Ltd filed Critical Zhuji Yitong Network Technology Co Ltd
Priority to CN201921368809.4U priority Critical patent/CN211257709U/en
Application granted granted Critical
Publication of CN211257709U publication Critical patent/CN211257709U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model provides a wall body plastering unit for building relates to the building field. This wall body plastering device for building, including the backup pad, the last surface center fixed mounting of backup pad has step motor, and step motor's output fixed mounting has the rotation axis, and the bottom of rotation axis runs through the backup pad and extends to the below of backup pad, and the fixed cover in bottom of rotation axis has connect running gear, running gear includes drive mechanism and center pin, drive mechanism and rotation axis fixed connection. This wall body plastering device for building can drive the rotation axis rotation through step motor is rotatory, can pass through the cooperation of driving gear and driven gear, realize the rotation of walking wheel, through the removal of walking wheel at the guide rail inslot, whole device can be supported to cooperation and bracing piece and connecting rod, can reach and scrape the ash bin and become fixed distance's effect with the outer wall all the time, the inhomogeneous problem of the thickness of plastering that wall body soil ash device leads to because walking part's defect among the prior art has been solved.

Description

Wall plastering device for building
Technical Field
The utility model relates to a building technical field specifically is a wall body plastering unit for building.
Background
In the construction of the outer wall, the outer wall needs to be connected with a heat-insulating material or a beautifying material due to the requirements of heat insulation and beautification, so that cement ash is used as a connecting agent, the cement ash is uniformly coated on the surface of the outer wall, and then the decorative or heat-insulating material is pasted on the surface of the outer wall coated with the cement ash.
Current outer wall plastering unit passes through the motor and drives haulage rope and pull whole device and remove to the realization is according to the effect of certain direction application cement ash, but the structure setting of current device has walking speed inhomogeneous, and the problem that changes takes place easily with the distance between the outer wall can lead to cement ash to apply the thickness difference, outer wall cement pothole in the process of applying.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a wall body plastering unit for building has solved the not good problem of effect is paintd to the cement ash among the prior art.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: a wall plastering device for buildings comprises a supporting plate, wherein a stepping motor is fixedly arranged at the center of the upper surface of the supporting plate, a rotating shaft is fixedly arranged at the output end of the stepping motor, the bottom end of the rotating shaft penetrates through the supporting plate and extends to the lower part of the supporting plate, a walking mechanism is fixedly sleeved at the bottom end of the rotating shaft and comprises a transmission mechanism and a central shaft, the transmission mechanism is fixedly connected with the rotating shaft, the central shaft is sleeved in the transmission mechanism, the transmission mechanism comprises a driving gear, a driven gear and a smooth wheel, the driving gear is fixedly connected to the bottom of the rotating shaft, the driven gear is meshed below the left side of the driving gear, the smooth wheel is arranged below the right side of the driving gear, the driven gear and the smooth wheel are fixedly sleeved on the outer surface of the central shaft, walking wheels are fixedly, the surface of center pin has cup jointed the bracing piece in drive mechanism's the left and right sides, and bracing piece bottom end fixedly connected with connecting rod, both ends fixedly connected with slider about the connecting rod, slider sliding connection is in the inside of supporting the groove. The upper surface of backup pad is located step motor's left end fixed mounting has the mud pump, and the upper surface of backup pad is located step motor's right side fixed mounting has the plastering case, and the plastering case is connected and link up with the mud pump, and the left surface of plastering case has seted up the spraying mouth, and backup pad below left and right sides sliding connection has the guide rail board, the stopper of the lower fixed surface that spacing groove backup pad and spacing groove adaptation is seted up to the upper surface of guide rail board, and connecting plate fixed connection is passed through to the bottom of two guide rail boards, and the guide rail groove has been seted up in the front of guide rail board, link up the guide rail board around the guide rail groove, and the front of guide rail board is located guide rail groove below and has seted up the support groove, and support the groove is parallel with the guide rail groove, the slot has been seted up to the front end of guide rail board, and the rear end.
Preferably, the bearing is fixedly sleeved on the outer surface of the connecting part of the central shaft and the guide rail plate, and the arrangement of the bearing can ensure that the central shaft does not directly contact with the guide rail plate, so that friction is reduced.
Preferably, the bottom fixed mounting of connecting rod has the piece of cleaning, and the cross sectional shape of cleaning the piece is trapezoidal, can clean away the cement ash that falls into between the guide rail board through the setting of cleaning the piece, avoids the motion of the dead device of card.
Preferably, the walking wheel is annular, and the upper and lower both ends of walking wheel and the inner wall meshing of guide rail groove can guarantee like this that the removal of walking wheel is stable does not produce the deviation.
Preferably, the one end that the spraying ash case was seted up the spraying ash mouth carries out the chamfer, and the quantity of spraying ash mouth is thirteen, forms the difference in height through the chamfer, can utilize not to set up the chamfer part and trowel cement ash, can evenly spray the cement ash to the outer wall through thirteen spraying ash mouths.
Advantageous effects
The utility model provides a wall body plastering unit for building. The method has the following beneficial effects:
1. this wall body plastering device for building can drive the rotation axis rotation through step motor is rotatory, can pass through the cooperation of driving gear and driven gear, realize the rotation of walking wheel, through the removal of walking wheel at the guide rail inslot, whole device can be supported to cooperation and bracing piece and connecting rod, can reach and scrape the ash bin and become fixed distance's effect with the outer wall all the time, the inhomogeneous problem of the thickness of plastering that wall body soil ash device leads to because walking part's defect among the prior art has been solved.
2. This wall body plastering unit for building through setting up the marl pump, absorbs the marl and then supplies with the plastering case, and the cement ash can spray on the outer wall through spouting the ash mouth, can paint evenly through the cement ash that the plastering case will spray, has solved among the prior art and has plastered need the manual work to plaster.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the traveling mechanism of the present invention;
FIG. 3 is a schematic view of the connection of the upper surface of the support plate according to the present invention;
fig. 4 is a schematic front view of the guide rail plate of the present invention.
The automatic plastering machine comprises a supporting plate-1, a stepping motor-2, a rotating shaft-3, a travelling mechanism-4, a plaster pump-5, a plastering box-6, a plaster spraying opening-7, a guide rail plate-8, a limiting groove-9, a limiting block-10, a connecting plate-11, a guide rail groove-12, a supporting groove-13, a transmission mechanism-14, a central shaft-15, a travelling wheel-16, a supporting rod-17, a connecting rod-18, a sliding block-19, a driven gear-20, a smooth wheel-21, a slot-22 and a driving gear-23.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The embodiment of the utility model provides a wall body plastering unit for building:
in the first embodiment, as shown in fig. 1, the cement plastering device comprises a supporting plate 1, a stepping motor 2 is fixedly installed at the center of the upper surface of the supporting plate 1, a rotating shaft 3 is fixedly installed at the output end of the stepping motor 2, the bottom end of the rotating shaft 3 penetrates through the supporting plate 1 and extends to the lower part of the supporting plate 1, a traveling mechanism 4 is fixedly sleeved at the bottom end of the rotating shaft 3, the traveling mechanism 4 can drive the whole device to move, a plaster pump 5 is fixedly installed at the left end of the stepping motor 2 on the upper surface of the supporting plate 1, a plaster box 6 is fixedly installed at the right side of the stepping motor 2 on the upper surface of the supporting plate 1, the plaster box 6 is connected and communicated with the plaster pump 5, a plaster spraying port 7 is formed on the left side surface of the plaster box 6, one end of the plaster box 6 provided with the spraying port 7 is chamfered, the quantity of the plaster ports 7 is thirteen, a, can evenly spray the cement ash to the outer wall through thirteen dust spouts 7, the left and right sides sliding connection in backup pad 1 below has guide rail plate 8.
Embodiment two, as shown in fig. 4 and fig. 1, spacing groove 9 has been seted up to the upper surface of guide rail plate 8, the lower fixed surface of backup pad 1 is connected with the stopper 10 with spacing groove 9 adaptation, connecting plate 11 fixed connection is passed through to the bottom of two guide rail plates 8, guide rail groove 12 has been seted up on the front of guide rail plate 8, run through guide rail plate 8 around guide rail groove 12, guide rail plate 8's front is located guide rail groove 12 below and has been seted up and support groove 13, support groove 13 can hold up whole device, support groove 13 and guide rail groove 12 parallel guide rail plate 8's front end has been seted up slot 22, guide rail plate 8's rear end is chamfered, two adjacent guide rail plates insert the slot 22 of front end in proper order, how long outer wall only needs to splice guide rail plate 8.
In the third embodiment, as shown in fig. 2, the traveling mechanism 4 includes a transmission mechanism 14 and a central shaft 15, the transmission mechanism 14 is fixedly connected with the rotating shaft 3, the central shaft 15 is sleeved inside the transmission mechanism 14, a bearing is sleeved on the outer surface of the connection portion of the central shaft 15 and the guide rail plate 8, the central shaft 15 is ensured not to be in direct contact with the guide rail plate 8 by the arrangement of the bearing, so as to reduce friction, traveling wheels 16 are fixedly installed at the left and right ends of the central shaft 15, the traveling wheels 16 are annular, the upper and lower ends of the traveling wheels 16 are engaged with the inner wall of the guide rail groove 12, so as to ensure that the traveling wheels 16 are stable in movement and do not generate deviation, the traveling wheels 16 are rotatably connected inside the guide rail groove 12, support rods 17 are sleeved on the outer surface of the central shaft 15 at the left and right sides of, the cross-sectional shape of cleaning the piece is trapezoidal, can clean away the cement ash that falls into between the guide rail board 8 through the setting of cleaning the piece, avoids the motion of card dead device, and both ends fixedly connected with slider 19 about connecting rod 18, slider 19 sliding connection are in the inside of supporting groove 13.
In the fourth embodiment, as shown in fig. 2, the transmission mechanism 14 includes a driving gear 23, a driven gear 20 and a photo wheel 21, the driving gear 23 is fixedly connected to the bottom of the rotating shaft 3, the driven gear 20 is engaged below the left side of the driving gear 23, the photo wheel 21 is disposed below the right side of the driving gear 23, both the driven gear 20 and the photo wheel 21 are fixedly sleeved on the outer surface of the central shaft 15, and the transmission mechanism 14 can distribute power.
When using, can drive rotation axis 3 through step motor 2 rotation rotatory, can realize walking wheel 16's rotation through driving gear 23 and driven gear 20's cooperation, through the removal of walking wheel 16 in guide rail groove 12, whole device can be supported to cooperation and bracing piece 17 and connecting rod 18, can reach and scrape ash bin 6 and become fixed distance's effect with the outer wall all the time.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. A wall plastering device for buildings comprises a supporting plate (1), and is characterized in that: the utility model discloses a plastering machine, including backup pad (1), upper surface center fixed mounting has step motor (2), the output fixed mounting of step motor (2) has rotation axis (3), the bottom of rotation axis (3) runs through backup pad (1) and extends to the below of backup pad (1), the fixed cover in bottom of rotation axis (3) has running gear (4), the left end fixed mounting that the upper surface of backup pad (1) is located step motor (2) has mud ash pump (5), the right side fixed mounting that the upper surface of backup pad (1) is located step motor (2) has plastering case (6), plastering case (6) are connected and link up with mud ash pump (5), the left surface of plastering case (6) has been seted up and has been spouted grey mouth (7), backup pad (1) below left and right sides sliding connection has guide rail board (8).
2. A wall plastering apparatus for construction according to claim 1, wherein: spacing groove (9) have been seted up to the upper surface of guide rail plate (8), stopper (10) of the lower fixed surface of backup pad (1) be connected with spacing groove (9) adaptation, connecting plate (11) fixed connection is passed through to the bottom of two guide rail plates (8), guide rail groove (12) have been seted up in the front of guide rail plate (8), link up guide rail plate (8) around guide rail groove (12), the front of guide rail plate (8) is located guide rail groove (12) below and has been seted up and support groove (13), support groove (13) and guide rail groove (12) are parallel.
3. A wall plastering apparatus for construction according to claim 1, wherein: running gear (4) include drive mechanism (14) and center pin (15), drive mechanism (14) and rotation axis (3) fixed connection, the inside at drive mechanism (14) is cup jointed in center pin (15), both ends fixed mounting has walking wheel (16) about center pin (15), walking wheel (16) rotate to be connected in the inside of guide rail groove (12), bracing piece (17) have been cup jointed to the left and right sides that the surface of center pin (15) is located drive mechanism (14), bracing piece (17) bottom fixedly connected with connecting rod (18), both ends fixedly connected with slider (19) about connecting rod (18), slider (19) sliding connection is in the inside of supporting groove (13).
4. A wall plastering apparatus for construction according to claim 3, wherein: drive mechanism (14) include driving gear (23), driven gear (20) and aureola (21), and driving gear (23) fixed connection is in the bottom of rotation axis (3), and driven gear (20) meshing is in the left side below of driving gear (23), and aureola (21) set up in the right side below of driving gear (23), and driven gear (20) and aureola (21) are all fixed cup joint at the surface of center pin (15).
5. A wall plastering apparatus for construction as claimed in claim 2, wherein: the slot (22) has been seted up to the front end of guide rail board (8), and the rear end of guide rail board (8) carries out the chamfer, and two adjacent guide rail boards insert in the slot (22) of front end in proper order.
CN201921368809.4U 2019-08-21 2019-08-21 Wall plastering device for building Expired - Fee Related CN211257709U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921368809.4U CN211257709U (en) 2019-08-21 2019-08-21 Wall plastering device for building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921368809.4U CN211257709U (en) 2019-08-21 2019-08-21 Wall plastering device for building

Publications (1)

Publication Number Publication Date
CN211257709U true CN211257709U (en) 2020-08-14

Family

ID=71959214

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921368809.4U Expired - Fee Related CN211257709U (en) 2019-08-21 2019-08-21 Wall plastering device for building

Country Status (1)

Country Link
CN (1) CN211257709U (en)

Similar Documents

Publication Publication Date Title
CN104472282B (en) A kind of trees mechanical float automatically
CN109779217B (en) Interior decoration is with ground tiling auxiliary device
CN111604212B (en) Cement pipeline paint device on river course
CN111877708B (en) Wall cement for building plasters leveling device
CN112392186B (en) A special equipment of gluing for point-type glass curtain wall
CN204899164U (en) Hand -held type leatheroid brick jointing machine
CN211472056U (en) Automatic sliding form system for side ditch
CN211257709U (en) Wall plastering device for building
CN111719827A (en) Automatic wall coating device for building construction
CN208602744U (en) A kind of overlay film packing device for the production of PE water supplying pipe
CN210858041U (en) Civil engineering floating equipment
CN114769056B (en) Method and device for improving permeability of high inorganic filler glue solution formula
CN101575905A (en) Automated screeding and compaction polishing device
CN212984521U (en) Wall plastering equipment for architectural decoration
CN214917698U (en) Compound rubber coating device of double-sided tape
CN202611206U (en) Rail type millstone troweling machine
CN213436112U (en) Clean pipe device of hydraulic engineering
CN111701789B (en) Brushing equipment and brushing method for nano-silicon-fluorine polymer coating
CN209286933U (en) A kind of construction site dust-extraction unit
CN206934060U (en) A kind of high-rise horizontal glass roof cleaning equipment of automation
CN113863694A (en) Device for adjustable and rapid mortar spreading for wall building and use method
CN203296352U (en) Wall blade coating machine
CN208039757U (en) A kind of buildings decoration metope mopping device
CN201195938Y (en) Automated toweling ramming and polishing apparatus
CN217871650U (en) Plastering device for cement mortar in constructional engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201105

Address after: No.602, building 1, laoxianzhong, Fuying street, Xianju County, Taizhou City, Zhejiang Province, 317300

Patentee after: ZHEJIANG XIANJING LANDSCAPE ENGINEERING Co.,Ltd.

Address before: 311800 Datang Town Industrial Zone, Zhuji City, Shaoxing City, Zhejiang Province

Patentee before: ZHUJI YITONG NETWORK TECHNOLOGY Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200814

Termination date: 20210821