CN211215984U - Water-storage power station construction is with spraying dust fall system - Google Patents

Water-storage power station construction is with spraying dust fall system Download PDF

Info

Publication number
CN211215984U
CN211215984U CN201922214795.7U CN201922214795U CN211215984U CN 211215984 U CN211215984 U CN 211215984U CN 201922214795 U CN201922214795 U CN 201922214795U CN 211215984 U CN211215984 U CN 211215984U
Authority
CN
China
Prior art keywords
water
water supply
storage tank
spraying
water storage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922214795.7U
Other languages
Chinese (zh)
Inventor
钱志强
丛中方
苗忠艳
吕恰旭
刘玉
原红红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Wendeng Pumped Storage Co ltd
State Grid Corp of China SGCC
State Grid Xinyuan Co Ltd
Original Assignee
Shandong Wendeng Pumped Storage Co ltd
State Grid Corp of China SGCC
State Grid Xinyuan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Wendeng Pumped Storage Co ltd, State Grid Corp of China SGCC, State Grid Xinyuan Co Ltd filed Critical Shandong Wendeng Pumped Storage Co ltd
Priority to CN201922214795.7U priority Critical patent/CN211215984U/en
Application granted granted Critical
Publication of CN211215984U publication Critical patent/CN211215984U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Machines (AREA)

Abstract

The utility model relates to a spray dust fall system for construction of a pumped storage power station, which solves the technical problem of poor effect of a spray system of the construction site of the existing pumped storage power station and comprises a water storage tank, a water storage tank water supply pump, a water storage tank water supply pipeline, a spray control electromagnetic valve, a spray water supply pump, an end plug, a spray gun and a spray automatic controller, wherein the water storage tank water supply pipeline is connected with the water storage tank, and the water storage tank water supply pump is connected with the water storage tank water supply pipeline; the water supply pipeline is connected with the bottom of the water storage tank, the end plug is connected with the tail end of the water supply pipeline, the spraying control electromagnetic valve is connected with the water supply pipeline, the spraying control electromagnetic valve is close to a water outlet of the water storage tank, the spraying water supply pump is connected with the water supply pipeline, the water supply pipeline is connected with a plurality of tee joints, and the tee joints are connected with a water spraying spray gun; the water storage tank water supply pump, the spraying control electromagnetic valve and the spraying water supply pump are respectively and electrically connected with the spraying automatic controller. The utility model discloses can be used to the pumped storage power station job site.

Description

Water-storage power station construction is with spraying dust fall system
Technical Field
The utility model relates to a, particularly, relate to a pumped storage power station construction is with spraying dust fall system.
Background
In recent years, national advocates and the increasing awareness of environmental protection make ecological construction and environmental protection focus, especially on construction sites, dust pollution becomes the first problem affecting people's life due to the large-area removal of vegetation, and dust control becomes an important task for air pollution prevention and control work. All construction sites also actively act, and particularly, the spraying dust suppression system is applied to the construction sites of house buildings, so that a good dust suppression effect is achieved. However, the construction site of the pumped storage power station has the characteristics of multiple points, wide range and the like, and the existing spraying system has an unsatisfactory effect and cannot achieve the optimal effect of 'no dust and no mud'.
Disclosure of Invention
The utility model discloses be exactly for solve the poor technical problem of current pumped storage power station job site's spraying system effect, provide an improvement press down dirt, dust removal effect's pumped storage power station construction is with spraying dust fall system.
The technical scheme of the utility model is that a spray dust fall system for pumped storage power station construction is provided, which comprises a water storage tank, a water storage tank water supply pump, a water storage tank water supply pipeline, a spray control electromagnetic valve, a spray water supply pump, an end plug, a spray gun and a spray automatic controller, wherein the water storage tank water supply pipeline is connected with the water storage tank, and the water storage tank water supply pump is connected with the water storage tank water supply pipeline; the water supply pipeline is connected with the bottom of the water storage tank, the end plug is connected with the tail end of the water supply pipeline, the spraying control electromagnetic valve is connected with the water supply pipeline, the spraying control electromagnetic valve is close to a water outlet of the water storage tank, the spraying water supply pump is connected with the water supply pipeline, the water supply pipeline is connected with a plurality of tee joints, and the tee joints are connected with a water spraying spray gun; the water storage tank water supply pump, the spraying control electromagnetic valve and the spraying water supply pump are respectively and electrically connected with the spraying automatic controller;
the water supply pipeline is a fabric rubber hose, and the water storage tank is a plastic cylindrical water storage tank;
the distance between two adjacent water spraying spray guns is 14m, a square concrete pier is poured at the bottom of each water spraying spray gun, and black and yellow reflective paint is coated on the square concrete pier; and covering the water supply pipeline with soft soil to form a soil ridge with the thickness of about 15 cm.
Preferably, a water level controller is arranged in the water storage tank and is electrically connected with the automatic spraying controller.
The beneficial effects of the utility model are that, adjust the spray time according to weather characteristics, reached the best effect of "not dusting, not muddy", in the construction of pumped storage power station, effectively controlled the dust harm of construction road. When the system operates, the rain and fog are uniform and automatically rotate, the angle is adjustable, the blind areas are avoided due to reasonable arrangement, and the dust prevention and suppression effects are obvious. Effective installation of the spraying system is implemented, so that the dust fall effect is greatly improved, sprinkling personnel and sprinkling vehicles are liberated, and the cost is reduced.
Further features of the invention will be made apparent in the following description of embodiments with reference to the accompanying drawings.
Drawings
FIG. 1 is a schematic structural diagram of a spraying dust-settling system for pumped storage power station construction;
FIG. 2 is a schematic view of a plurality of water spray guns installed at the edge of a construction temporary road.
The symbols in the drawings illustrate that:
1. the spraying device comprises a water storage tank, 2 water sources, 3 a water storage tank water supply pump, 4 a water level controller, 5 a water storage tank water supply pipeline, 6 a water supply pipeline, 7 a spraying control electromagnetic valve, 8 a spraying water supply pump, 9 an end plug, 10 a tee joint and 11 a spraying spray gun. 12. And constructing a temporary road.
Detailed Description
As shown in fig. 1, the spray dust-settling system for the construction of the pumped storage power station comprises a water storage tank 1, a water storage tank water supply pump 3, a water level controller 4, a water storage tank water supply pipeline 5, a water supply pipeline 6, a spray control electromagnetic valve 7, a spray water supply pump 8, an end plug 9, a tee joint 10, a spray gun 11, a spray automatic controller, the water storage tank 1 is connected with a water source 2 through the water storage tank water supply pipeline 5, the water storage tank water supply pump 3 is connected with the water storage tank water supply pipeline 5, and the water storage tank water supply pump 3 can input required water from the water source 2 to the water storage tank 1. The water level controller 4 is arranged in the water storage tank 1, and the water level controller 4 is electrically connected with the automatic spraying controller. The water supply pipeline 6 is connected with the bottom of retaining jar 1, and end shutoff 9 and the end connection of water supply pipeline 6 spray control solenoid valve 7 and are connected with water supply pipeline 6, spray control solenoid valve 7 and are close to the delivery port of retaining jar 1, spray the working shaft 8 and are connected with water supply pipeline 6, are connected with a plurality of tee bend 10 on the water supply pipeline 6, and tee bend 10 is connected with watering spray gun 11. The automatic spraying controller is used for controlling the whole system to work, and the water storage tank water supply pump 3, the spraying control electromagnetic valve 7 and the spraying water supply pump 8 are respectively and electrically connected with the automatic spraying controller.
The pipe material of the water supply pipeline 6 is a fabric rubber hose with the specification of phi 50 and the working pressure of 1.0 MPA. As the temporary roads on the construction site are all earth and stone pavements and are not paved by concrete, the running vehicles are easy to roll the pipelines, and the soft rubber pipes are adopted, and the pipelines are easy to damage if steel pipes or PPR pipes are adopted.
The water storage tank 1 adopts 10m3The plastic cylindrical water storage tank. Considering that the temporary road position of a construction site mostly has no fixed water source,and considering the construction cost, a water storage tank is adopted for storing water, and a spraying control electromagnetic valve 7 is arranged at the water outlet of the water storage tank to control the water outlet. A water level controller 4 is installed in the water storage tank, and when the water level in the water storage tank is insufficient, a water supply pump 3 of the water storage tank automatically opens a water supply source.
The spray water supply pump 8 adopts a 4.0kw booster pump, the water inlet end of the pump is connected with the inlet at the bottom of the water storage tank, and the outlet is connected with the spray system.
The sprinkling spray gun 11 adopts a zinc alloy controllable rocker arm spray head, the size is DN25, the spraying pressure is 2.5-4 kg, the connection mode is external thread connection, and the spraying spray gun adopts threads to be connected with a round galvanized steel pipe with the same diameter DN25 and the length of 1.0 meter. The spray gun is not suitable for spraying, and the water outlet of the spray gun is too thin, so that blockage is easy to occur.
As shown in FIG. 2, each construction temporary road 12 is generally 5-7 m wide, so when the spraying system is installed, the distance between two adjacent spraying guns 11 is controlled to be 14m, and the distance between the spraying heads of the spraying guns is controlled to be 7 m. A plurality of water spraying spray guns are arranged on one side of a temporary construction road 12, a square concrete pier 14 with the length, width and height of 20cm is poured at the bottom of each water spraying spray gun 11 for fixing, and black and yellow reflective paint is coated on the square concrete pier to achieve the warning effect. And covering the water supply pipeline 6 by soft soil after the laying is finished to form a soil ridge with the thickness of about 15cm, thereby playing a role in protection.
Control modules such as the automatic spraying controller are installed in the control box, and the control box is installed on the concrete base to prevent rainwater influence.
The water storage tank 1 is arranged on the outer side of a construction road, the vehicle passing cannot be influenced, meanwhile, the water storage tank is arranged at a position close to a water source point, a water level controller arranged in the water storage tank controls the starting of a water supply pump of the water storage tank, and when the water level in the water tank is insufficient, a switch is automatically switched on to supplement the water source. When the spraying system is far away from the water source point, a well can be drilled to fetch water or a watering cart is adopted to store water regularly. In the area (such as the opening of a traffic tunnel) near the sewage treatment station, the treated water can be directly used as a spraying water source.
The rotation angle of the sprinkling spray gun is controlled to be 180 degrees, and the influence of the terrain is eliminated in order to control the water outlet distance of 7m according to the power of the water supply pump of the set of sprinkling system. When the whole set of system has 11 spray guns, the length of a water supply pipeline between every two spray guns is 14 meters, and the total length of the pipeline is about 145 meters (the length of the water pipe between the outlet of the water containing pump and the first spray gun is about 5 meters).
The pumped storage power station has multiple construction points, the main construction working surfaces comprise upper and lower reservoirs, underground plants, water delivery and power generation systems, upper and lower reservoir dams and the like, and the dust is easily raised because slag transport vehicles pass through. Therefore, the installation place of the spraying system is preferably selected from a traffic tunnel portal (the slag car frequently enters and exits an underground workshop), a main hardened pavement with large traffic flow and one side of each temporary construction road.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not intended to limit the present invention, which may be modified and varied by those skilled in the art.

Claims (2)

1. A spray dust-settling system for construction of a pumped storage power station is characterized by comprising a water storage tank, a water storage tank water supply pump, a water storage tank water supply pipeline, a spray control electromagnetic valve, a spray water supply pump, an end plug, a spray gun and a spray automatic controller, wherein the water storage tank water supply pipeline is connected with the water storage tank, and the water storage tank water supply pump is connected with the water storage tank water supply pipeline; the spraying water supply system comprises a water storage tank, a water supply pipeline, a spraying control electromagnetic valve, a spraying water supply pump, a spraying spray gun and a spraying control electromagnetic valve, wherein the water supply pipeline is connected with the bottom of the water storage tank, the end plug is connected with the tail end of the water supply pipeline, the spraying control electromagnetic valve is connected with the water supply pipeline, the spraying control electromagnetic valve is close to a water outlet of the water storage tank, the spraying water supply pump is connected with the water supply pipeline, the; the water storage tank water supply pump, the spraying control electromagnetic valve and the spraying water supply pump are respectively and electrically connected with the spraying automatic controller;
the water supply pipeline is a fabric rubber hose, and the water storage tank is a plastic cylindrical water storage tank;
the distance between two adjacent water spraying spray guns is 14m, a square concrete pier is poured at the bottom of each water spraying spray gun, and black and yellow reflective paint is coated on the square concrete pier; and covering the water supply pipeline with soft soil to form a soil ridge with the thickness of about 15 cm.
2. The spray dust suppression system for pumped storage power station construction according to claim 1, wherein a water level controller is arranged in the water storage tank, and the water level controller is electrically connected with the spray automatic controller.
CN201922214795.7U 2019-12-11 2019-12-11 Water-storage power station construction is with spraying dust fall system Active CN211215984U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922214795.7U CN211215984U (en) 2019-12-11 2019-12-11 Water-storage power station construction is with spraying dust fall system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922214795.7U CN211215984U (en) 2019-12-11 2019-12-11 Water-storage power station construction is with spraying dust fall system

Publications (1)

Publication Number Publication Date
CN211215984U true CN211215984U (en) 2020-08-11

Family

ID=71914480

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922214795.7U Active CN211215984U (en) 2019-12-11 2019-12-11 Water-storage power station construction is with spraying dust fall system

Country Status (1)

Country Link
CN (1) CN211215984U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116905418A (en) * 2023-07-17 2023-10-20 辽宁工程技术大学 Intelligent maintenance system and method for open-pit mine road

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116905418A (en) * 2023-07-17 2023-10-20 辽宁工程技术大学 Intelligent maintenance system and method for open-pit mine road

Similar Documents

Publication Publication Date Title
CN205461539U (en) Tower crane high altitude sprays dust fall system
CN204244843U (en) A kind of solar energy automatic spraying arrangement utilizing rainwater
KR102069229B1 (en) Smart type automatic spray device for four seasons
CN211215984U (en) Water-storage power station construction is with spraying dust fall system
CN105638389A (en) Multifunctional self-walking urban road green belt irrigation vehicle
CN205389802U (en) It is multi -functional from walking urban road greenbelt irrigator
CN211020348U (en) Irrigation equipment for landscaping maintenance
CN216108560U (en) Slope reinforcing apparatus for building municipal works
CN205598830U (en) Industrial area ground dust collector is executed to building
CN208533301U (en) Road guard-rail and rain recycling system
KR102049198B1 (en) Smart clean road system and construction method thereof
US20230046121A1 (en) Farmland irrigation and drainage system
CN103774872A (en) Parking lot and rainwater utilization project which are constructed by utilizing space under elevated road
CN204579351U (en) Irrigation facilities in sands and system
CN105123368A (en) Multifunctional highway administration greening cover
CN214961645U (en) Afforestation engineering water-saving irrigation device
CN214853292U (en) Environment-friendly irrigation and maintenance device
CN210786673U (en) Automatic watering and dust falling system for construction site
CN212270806U (en) Efficient dust fall maintenance system special for large-area yard behind wharf
CN211566328U (en) Automatic maintenance device for highway engineering concrete member
CN210194522U (en) Multipurpose water spraying system for annular foundation pit
CN212942063U (en) Spraying and dust removing system for building construction
CN203082360U (en) A paying out machine for long distance pipeline engineering
CN201778300U (en) Automatic dustproof device that sprays of construction road
CN205954550U (en) A spraying dedusting device for improving underground cavern air quality