CN211201204U - High pier column reinforcement bed-jig device - Google Patents

High pier column reinforcement bed-jig device Download PDF

Info

Publication number
CN211201204U
CN211201204U CN201921744689.3U CN201921744689U CN211201204U CN 211201204 U CN211201204 U CN 211201204U CN 201921744689 U CN201921744689 U CN 201921744689U CN 211201204 U CN211201204 U CN 211201204U
Authority
CN
China
Prior art keywords
block
limiting block
rod
stopper
backup pad
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921744689.3U
Other languages
Chinese (zh)
Inventor
袁霈龙
刘平
孙登科
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHEC Dong Meng Engineering Co Ltd
Original Assignee
CCCC SHEC Dong Meng Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHEC Dong Meng Engineering Co Ltd filed Critical CCCC SHEC Dong Meng Engineering Co Ltd
Priority to CN201921744689.3U priority Critical patent/CN211201204U/en
Application granted granted Critical
Publication of CN211201204U publication Critical patent/CN211201204U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a high pier stud reinforcement bed-jig device, including steady frame, a supporting table and surrounding rod, the outside of surrounding rod is provided with the placement mechanism, the placement mechanism includes fixed plate, backup pad, place the box, mobile structure and first fixed block, three parallel backup pads arranged from top to bottom are located the surface of fixed plate, four first fixed blocks are two-by-two symmetrically distributed and are kept away from the position that the fixed plate side bottom is close to the corner at the backup pad of upside position, downside position, the mobile structure is located the bottom of the backup pad of upside position, downside position, the mobile structure includes steady block, carriage release lever, spring and first stopper, first stopper is relative with first fixed block, the side of first stopper is provided with the holding rod; the enclosing rod is located and leaves the standing groove of rectangle between first stopper, first fixed block, the backup pad three in, and the fixed plate is in stable state with the backup pad, is convenient for arrange the construction tool in place the box in and takes the use.

Description

High pier column reinforcement bed-jig device
Technical Field
The utility model belongs to the technical field of the bed-jig, concretely relates to high pier stud reinforcement bed-jig device.
Background
Civil engineering construction is because reinforcing bar length is longer, the reinforcing bar is circumstances such as intensive, often for satisfying the protective layer qualification rate requirement input a large amount of manpower and materials in the work progress, it is numerous and diverse to cause the technology, use reinforcing bar location bed-jig, facilitate the site operation, high pier stud reinforcement bed-jig device sets up three construction platform according to the pier stud shape, the platform annular is continuous integratively around the pier body, set up interim reinforced point on the cushion cap, the platform outside sets up the protection rail, thereby guarantee that the operating personnel increase of factor of safety when the operation, effectively guarantee the reinforcing bar of high pier and arrange and satisfy the standard requirement, three working face simultaneous working increases work efficiency, it is difficult to have effectively compensatied the high pier construction, the reinforcing bar is arranged and is unsatisfied the current defect.
The existing steel bar jig frame has the problem that tools falling off easily roll off from a construction platform when in use, the tools are picked up back and forth and are troublesome and time-consuming, steel bar materials and the like need to be placed during construction, the materials are hung on a surrounding rod and are inclined, and workers touch the materials accidentally and can be damaged, so that the high pier column steel bar binding jig frame device is provided.
Disclosure of Invention
An object of the utility model is to provide high pier stud reinforcement bed-jig device to there is the instrument that drops easily to roll from construction platform in the reinforcing bar bed-jig that provides when using in solving above-mentioned background art, makes a round trip to pick up the instrument troublesome and time-consuming, has during the construction in addition that reinforcing bar material etc. need place, and the material hangs on the surrounding rod crooked, bumps the problem that the material can receive the damage under the workman's accident.
In order to achieve the above object, the utility model provides a following technical scheme: high pier stud reinforcement bed-jig device, including steady frame, brace table and surrounding rod, the outside of surrounding rod is provided with placement mechanism, placement mechanism includes fixed plate, backup pad, places box, moving structure and first fixed block, and the backup pad of the three parallel of arranging from top to bottom is located the fixed plate on the surface, and the position that fixed plate one side bottom is close to the corner is kept away from to the two bisymmetry of four first fixed blocks in the backup pad that lies in upside position, downside position, moving structure lies in the bottom of the backup pad of upside position, downside position, moving structure includes steady block, carriage release lever, spring and first stopper, first stopper is relative with first fixed block, the side of first stopper is provided with the holding rod, and the side symmetry of the backup pad that lies in the intermediate position is provided with the peg.
Preferably, the stabilizing block is located at the bottom of the supporting plate, the first limiting block is located between the stabilizing block and the first fixing block, the moving rod is of a T-shaped structure, the moving rod sequentially penetrates through the stabilizing block and the spring and is connected with the first limiting block, and the first limiting block slides along the length direction of the moving rod.
Preferably, the holding rod is arranged to be of a T-shaped structure, the holding rod is connected with the side face of the first limiting block, the first limiting block is arranged to be of an L-shaped structure, and rectangular placing grooves are reserved among the first limiting block, the first fixing block and the supporting plate.
Preferably, the surface of the first fixing block opposite to the first limiting block is provided with a rectangular limiting groove, the first limiting block comprises a vertical part and a horizontal part, the moving rod is connected with the vertical part of the first limiting block, and when the first limiting block is connected with the first fixing block in a clamping manner, the horizontal part of the first limiting block is embedded into the limiting groove.
Preferably, the peg is "(+" type structure, just the peg includes vertical portion and lower horizontal portion, the tip of horizontal portion is connected with the side of backup pad under the peg.
Preferably, the outside symmetry of enclosing the pole is provided with stop gear, stop gear is located the position that is close to the brace table, stop gear includes fastening block and second stopper, fastening block and brace table are provided with between the two and shelter from the mechanism, it includes baffle and second fixed block to shelter from the mechanism.
Preferably, the fastening block includes short vertical portion, well horizontal portion and long vertical portion, the second stopper sets to "⊥" type structure, the second stopper is located the tip of the long vertical portion of fastening block, the short vertical portion of fastening block is located the surrounding rod, second fixed block symmetry is located the surface of baffle, the rectangular channel has been seted up to the bottom of baffle, the second stopper is connected with second fixed block, and second stopper embedding rectangular channel, the position that the baffle is located between two second fixed blocks is provided with the handle.
Compared with the prior art, the beneficial effects of the utility model are that: when construction is carried out on the pier stud steel bar jig frame, the supporting plate is lapped on the enclosing rod, the first limiting block is clamped with the first fixing block, the enclosing rod is positioned in a rectangular placing groove reserved among the first limiting block, the first fixing block and the supporting plate, and the fixing plate and the supporting plate are in a stable state, so that a construction tool can be conveniently placed in the placing box and taken for use;
the hanging rod is positioned on the side surface of the supporting plate and is of a 'Ji' type structure, so that a U-shaped steel bar can be conveniently placed on the hanging rod, the steel bar is prevented from being placed on the surrounding rod, and the condition that workers touch and are injured when the steel bar is inclined is avoided;
in addition, the baffle is attached to the supporting table by holding the handle, the second fixing block is connected with the second limiting block in a sliding and clamping mode, the baffle is in a stable state, the construction tools are prevented from falling off from the supporting table and rolling out when a worker walks on the supporting table, the time for picking up the falling tools back and forth is shortened, and the working efficiency is improved.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic side view of the fixing plate of the present invention;
FIG. 3 is a schematic top view of the storage box of the present invention;
FIG. 4 is a schematic front view of the fastening block of the present invention;
in the figure: 1. a stabilizing frame; 2. a support table; 3. a surrounding rod; 4. a placement mechanism; 5. a limiting mechanism; 6. a shielding mechanism; 7. a fixing plate; 8. a support plate; 9. placing the box; 10. a moving structure; 11. a first fixed block; 12. a hanging rod; 13. a stabilizing block; 14. a travel bar; 15. a spring; 16. a first stopper; 17. a holding rod; 18. a fastening block; 19. a second limiting block; 20. a baffle plate; 21. and a second fixed block.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Examples
Referring to fig. 1 to 4, the present invention provides a technical solution: a high pier column reinforcement jig device comprises a stabilizing frame 1, a supporting table 2 and a surrounding rod 3, wherein a placing mechanism 4 is arranged on the outer side of the surrounding rod 3, the placing mechanism 4 comprises a fixed plate 7, supporting plates 8, a placing box 9, a moving structure 10 and first fixed blocks 11, three parallel supporting plates 8 which are arranged from top to bottom are positioned on the surface of the fixed plate 7, the four first fixed blocks 11 are symmetrically distributed in pairs at positions, close to corners, of the bottom of one side, far away from the fixed plate 7, of the supporting plate 8 at the upper side position and the lower side position, the moving structure 10 is positioned at the bottom of the supporting plate 8 at the upper side position and the lower side position, the moving structure 10 comprises a stabilizing block 13, a moving rod 14, a spring 15 and a first limiting block 16, the first limiting block 16 is opposite to the first fixed block 11, a holding rod 17 is arranged on the side surface of the first limiting block 16, hanging rods 12, the outside symmetry of enclosing pole 3 is provided with stop gear 5, and stop gear 5 is located the position that is close to brace table 2, and stop gear 5 includes fastening block 18 and second stopper 19, and fastening block 18 and brace table 2 are provided with between the two and shelter from mechanism 6, shelter from mechanism 6 and include baffle 20 and second fixed block 21.
In this embodiment, firm piece 13 is located the bottom of backup pad 8, first stopper 16 is located between firm piece 13 and the first fixed block 11 both, carriage release lever 14 sets to "T" type structure, carriage release lever 14 passes firm piece 13 in proper order, spring 15 and is connected with first stopper 16, first stopper 16 slides along carriage release lever 14's length direction, spring 15's one end is connected with firm piece 13 and the other end is connected with first fixed block 11, be convenient for first stopper 16's removal.
In this embodiment, the holding rod 17 is set to "T" type structure, and the holding rod 17 is connected with the side of first stopper 16, and first stopper 16 sets to "L" type structure, leaves the standing groove of rectangle between first stopper 16, first fixed block 11, the backup pad 8 three, encloses the pole 3 and arranges the standing groove in, and the first stopper 16 of being convenient for, first fixed block 11, backup pad 8 are installed on enclosing the pole 3.
In this embodiment, a rectangular limiting groove is formed in the surface of the first fixing block 11 opposite to the first limiting block 16, the first limiting block 16 includes a vertical portion and a horizontal portion, the moving rod 14 is connected with the vertical portion of the first limiting block 16, and when the first limiting block 16 is connected with the first fixing block 11 in a clamping manner, the horizontal portion of the first limiting block 16 is embedded into the limiting groove, so that the first limiting block 16 is stably connected with the first fixing block 11.
In this embodiment, peg 12 is "+" type structure, and peg 12 includes vertical portion and lower horizontal portion, and the tip of horizontal portion is connected with the side of backup pad 8 under 12 pegs, is convenient for hang reinforced bar material.
In this embodiment, the fastening block 18 includes short vertical portion, well horizontal portion and long vertical portion, second stopper 19 sets to "⊥" type structure, second stopper 19 is located the tip of the long vertical portion of fastening block 18, fastening block 18 short vertical portion is located on enclosing rod 3, second fixed block 21 symmetry is located the surface of baffle 20, the rectangular channel has been seted up to the bottom of baffle 20, second stopper 19 is connected with the 21 block of second fixed block, and second stopper 19 embedding rectangular channel, the position that baffle 20 is located between two second fixed blocks 21 is provided with the handle, be convenient for grip and remove baffle 20.
The utility model discloses a theory of operation and use flow: when construction is carried out on the pier stud steel bar jig frame, the holding rod 17 is held and moved, the first limiting block 16 moves, the spring 15 is in a contraction state, the supporting plate 8 is put on the surrounding rod 3, the holding rod 17 is loosened, the spring 15 extends from the contraction state, the first limiting block 16 resets and is clamped with the first fixing block 11, at the moment, the surrounding rod 3 is positioned in the placing groove, the fixing plate 7 and the supporting plate 8 are in a stable state, and a construction tool is conveniently placed in the placing box 9 and is convenient to take and use;
the hanging rod 12 is positioned on the side surface of the supporting plate 8, and the hanging rod 12 is of a 'Ji' type structure, so that a U-shaped reinforcing steel bar can be conveniently placed on the hanging rod 12, and the reinforcing steel bar is prevented from being placed on the surrounding rod 3 and being accidentally touched by workers to be injured when the reinforcing steel bar is inclined;
in addition, the baffle 20 is attached to the support platform 2 by holding the handle, the baffle 20 slides along the length direction, the second fixing block 21 is connected with the second limiting block 19 in a sliding and clamping mode, the baffle 20 is in a stable state, the construction tools are prevented from falling off from the support platform 2 and rolling out when workers walk on the support platform 2, the time for picking up the falling tools back and forth is shortened, and the working efficiency is improved.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. High pier stud reinforcement bed-jig device, including steady frame (1), brace table (2) and surrounding rod (3), its characterized in that: the outside of enclosing rod (3) is provided with placement mechanism (4), placement mechanism (4) includes fixed plate (7), backup pad (8), places box (9), removes structure (10) and first fixed block (11), and three parallel backup pad (8) of arranging from top to bottom are located the surface of fixed plate (7), and two bisymmetry distributions of four first fixed block (11) are kept away from the position that fixed plate (7) one side bottom is close to the corner in backup pad (8) that are located upside position, downside position, remove structure (10) and are located the bottom of backup pad (8) of upside position, downside position, remove structure (10) including stabilizing block (13), removal pole (14), spring (15) and first stopper (16), first stopper (16) are relative with first fixed block (11), the side of first stopper (16) is provided with holding rod (17), hanging rods (12) are symmetrically arranged on the side surface of the supporting plate (8) positioned in the middle.
2. The high pier column reinforcement jig frame device according to claim 1, characterized in that: the fixing device is characterized in that the fixing block (13) is located at the bottom of the supporting plate (8), the first limiting block (16) is located between the fixing block (13) and the first fixing block (11), the moving rod (14) is arranged to be of a T-shaped structure, the moving rod (14) sequentially penetrates through the fixing block (13) and the spring (15) and is connected with the first limiting block (16), and the first limiting block (16) slides along the length direction of the moving rod (14).
3. The high pier column reinforcement jig frame device according to claim 1, characterized in that the holding rod (17) is arranged in a T-shaped structure, the holding rod (17) is connected with the side surface of the first limiting block (16), the first limiting block (16) is arranged in an L-shaped structure, and rectangular placing grooves are reserved among the first limiting block (16), the first fixing block (11) and the supporting plate (8).
4. The high pier column reinforcement jig frame device according to claim 1, characterized in that: the surface of the first fixing block (11) opposite to the first limiting block (16) is provided with a rectangular limiting groove, the first limiting block (16) comprises a vertical part and a horizontal part, the moving rod (14) is connected with the vertical part of the first limiting block (16), and when the first limiting block (16) is connected with the first fixing block (11) in a clamping mode, the horizontal part of the first limiting block (16) is embedded into the limiting groove.
5. The high pier column reinforcement jig frame device according to claim 1, characterized in that: the hanging rod (12) is of a 'Brix' type structure, the hanging rod (12) comprises an upper vertical portion and a lower horizontal portion, and the end portion of the lower horizontal portion of the hanging rod (12) is connected with the side face of the supporting plate (8).
6. The high pier column reinforcement jig frame device according to claim 1, characterized in that: the outside symmetry of enclosing pole (3) is provided with stop gear (5), stop gear (5) are located the position that is close to brace table (2), stop gear (5) are including fastening block (18) and second stopper (19), be provided with between fastening block (18) and brace table (2) and shelter from mechanism (6), shelter from mechanism (6) including baffle (20) and second fixed block (21).
7. The high pier column reinforcement jig frame device according to claim 6, wherein the fastening block (18) comprises a short vertical part, a middle horizontal part and a long vertical part, the second limiting block (19) is arranged in an ⊥ -shaped structure, the second limiting block (19) is located at the end part of the long vertical part of the fastening block (18), the short vertical part of the fastening block (18) is located on the surrounding rod (3), the second fixing blocks (21) are symmetrically located on the surface of the baffle (20), a rectangular groove is formed in the bottom of the baffle (20), the second limiting block (19) is connected with the second fixing blocks (21) in a clamping mode, the second limiting block (19) is embedded into the rectangular groove, and a handle is arranged at the position, located between the two second fixing blocks (21), of the baffle (20).
CN201921744689.3U 2019-10-17 2019-10-17 High pier column reinforcement bed-jig device Active CN211201204U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921744689.3U CN211201204U (en) 2019-10-17 2019-10-17 High pier column reinforcement bed-jig device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921744689.3U CN211201204U (en) 2019-10-17 2019-10-17 High pier column reinforcement bed-jig device

Publications (1)

Publication Number Publication Date
CN211201204U true CN211201204U (en) 2020-08-07

Family

ID=71850629

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921744689.3U Active CN211201204U (en) 2019-10-17 2019-10-17 High pier column reinforcement bed-jig device

Country Status (1)

Country Link
CN (1) CN211201204U (en)

Similar Documents

Publication Publication Date Title
CN204212064U (en) A kind of bridge construction Handy movable operation platform
CN103243922A (en) Floor concrete thickness control device
CN211201204U (en) High pier column reinforcement bed-jig device
CN105460853A (en) Lift for building
CN205036096U (en) Be used for accessible device that passes through of three -dimensional support of reinforcing bar
CN213268812U (en) Safety platform that building engineering construction was used
CN108792924B (en) Reinforcing steel bar positioning frame
CN210029948U (en) Safety device is used in hoisting equipment maintenance
CN206607504U (en) A kind of support platform for building
JP4644181B2 (en) Reactor structure cutting equipment
CN209904800U (en) Temporary enclosing and blocking foundation block transferring trolley
CN205152805U (en) Portable precast beam stretch -draw protector
CN215329379U (en) Be used for construction can gliding operation platform outside bridge railing
CN211548666U (en) Scaffold with protective device for plastering wall top
CN209682156U (en) Hydraulic pressure system production hose discharging frame under the overall leadership
CN210307730U (en) Suit insulating bench
CN214602448U (en) Shield segment steel reinforcement framework welding rack
CN209835562U (en) Trolley for tunnel construction
CN203392657U (en) Machine maintenance platform
CN106078655A (en) A kind of engine link laying rack
CN210941860U (en) Foundation ditch support or for slope support conveyer
CN210289046U (en) Operation platform capable of movably lifting
CN206468014U (en) A kind of concreting workbench
CN204139125U (en) Slope light transhipment precast plate device
CN213509545U (en) Safety device for scaffold

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant