CN211143181U - Sludge discharge device for long-distance pressure pipeline - Google Patents

Sludge discharge device for long-distance pressure pipeline Download PDF

Info

Publication number
CN211143181U
CN211143181U CN201921157252.XU CN201921157252U CN211143181U CN 211143181 U CN211143181 U CN 211143181U CN 201921157252 U CN201921157252 U CN 201921157252U CN 211143181 U CN211143181 U CN 211143181U
Authority
CN
China
Prior art keywords
mud
well
row
wet well
sludge discharge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921157252.XU
Other languages
Chinese (zh)
Inventor
龙程理
齐鸣
陈燕波
李璐
杨墨
田俊
张辛平
吴迪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central and Southern China Municipal Engineering Design and Research Institute Co Ltd
Original Assignee
Central and Southern China Municipal Engineering Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central and Southern China Municipal Engineering Design and Research Institute Co Ltd filed Critical Central and Southern China Municipal Engineering Design and Research Institute Co Ltd
Priority to CN201921157252.XU priority Critical patent/CN211143181U/en
Application granted granted Critical
Publication of CN211143181U publication Critical patent/CN211143181U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model provides a arrange mud device for long distance pipeline under pressure, the purpose is solved because of the too dark row's mud valve well and the wet well construction difficulty of row's mud and the inconvenient problem of maintenance that leads to of conduit burial depth. The concrete technical scheme comprises a sludge discharge eccentric tee joint, a sludge discharge valve well and a sludge discharge wet well which are connected together through a sludge discharge pipe, and a steel pipe structure is adopted as the sludge discharge wet well, so that the construction is more convenient and efficient; only need open the mud valve when the maintenance, use interim vacuum pump to form the siphon through the evacuation interface as required, discharge muddy water in the pipeline, reuse interim stealthily dirty pump to fix and utilize hand-drive block to stealthily dirty pump temporarily to send to the mud wet well bottom of row on the guide rail platform, can be clean with the inside muddy water pump drainage of wet well for maintenance operation is very convenient.

Description

Sludge discharge device for long-distance pressure pipeline
Technical Field
The utility model relates to a plumbing technical field, in particular to a row's mud device for long distance pipeline under pressure
Background
Long distance pressure water pipelines require maintenance and sludge removal, and therefore sludge removal is essential for long distance pressure water pipelines. Generally, the long-distance water delivery pressure pipeline sludge discharge is realized by adopting an eccentric sludge discharge tee joint, a sludge discharge valve well and a sludge discharge wet well at a lower position of the pipeline height, and the sludge discharge valve well and the sludge discharge wet well can be built together according to requirements. Therefore, the mud discharging water or the pipeline emptying water is controlled by the mud discharging valve, and the mud discharging water or the emptying water overflows to a municipal drainage pipe network in the wet well. However, in practical engineering, the arrangement of the mud drainage wells has certain limitations, the long-distance water transmission pipeline passes through the underground and underground obstacles, and usually adopts a form of a top pipe, and the buried depth of the top pipe can reach 10m, so that the traditional mud drainage valve well and the mud drainage wet well are not beneficial to construction, and construction is difficult; and the mud valve well is deeper, and the maintenance is inconvenient.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a arrange mud device for long distance pipeline under pressure to solve because of the too dark row's mud valve well and the wet well construction difficulty of row's mud and the inconvenient problem of maintenance that leads to of conduit burial depth.
In order to solve the technical problem, the utility model discloses a following technical scheme realizes:
the utility model provides a arrange mud device for long distance pipeline under pressure, includes through the eccentric tee bend of row's mud that the mud pipe coupling is in the same place, arrange mud valve well and arrange the mud wet well, arrange the mud wet well be steel tube structure, just arrange the bottom of a well setting of mud wet well in the eccentric tee bend below of row's mud, the bottom of a well setting of arranging mud valve well is in the below of row's mud pipe is located be equipped with row's mud gate valve and evacuation interface on arranging the mud pipe in the mud valve well, connect a temporary vacuum pump on the evacuation interface, when the temporary vacuum pump overhauls for the maintenance, take certainly on the maintenance car.
Preferably, set up a plurality of guide rail brackets on the inside lateral wall of steel tubular construction of row's mud wet well, guide rail bracket's top is equipped with hand-drive block, guide rail bracket's bottom is equipped with water pump guide rail platform.
Preferably, a temporary submersible sewage pump used for maintenance is arranged on the water pump guide rail platform.
Preferably, a mud discharging tee joint is arranged on a mud discharging pipe inside a steel pipe structure of the mud discharging wet well, and the pipeline flange blind plate is connected with the mud discharging pipe through the mud discharging tee joint.
Preferably, the well depth of the sludge discharge valve well is 2.5-3.5 meters, and the well depth of the sludge discharge wet well is 8-15 meters.
Preferably, the structural specification of the steel pipe of the sludge discharge wet well is DN 800-DN 1400 mm.
Compared with the prior art, the beneficial effects of the utility model are that:
the utility model provides a mud discharging device for long-distance pressure pipelines, which adopts a steel pipe structure as a mud discharging wet well, so that the construction is more convenient and efficient; only need open row mud valve well during the maintenance, use interim vacuum pump as required to form the siphon through evacuation interface evacuation, discharge muddy water in the pipeline, reuse interim stealthily dirty pump to fix and utilize hand-drive block to stealthily dirty the pump with interim stealthily on the guide rail platform and send to row mud wet well bottom, can be clean with the inside muddy water pump drainage of wet well for the maintenance operation is very convenient. In a word, the utility model provides a pair of a row's mud device for long distance pipeline under pressure can facilitate the construction and the maintenance of row's mud valve well and row's mud wet well, plays the propulsive effect and provides convenience for the maintenance in later stage to whole engineering construction progress.
Drawings
Fig. 1 is a schematic view of the overall structure of the present invention.
Shown in the figure: 1-a sludge discharge eccentric tee joint, 2-a sludge discharge valve well, 3-a sludge discharge wet well, 4-a sludge discharge gate valve, 5-a vacuum pumping interface, 6-a temporary vacuum pump, 7-a guide rail bracket, 8-a manual hoist, 9-a water pump guide rail platform, 10-a temporary submersible sewage pump, 11-a sludge discharge tee joint, 12-a pipeline flange blind plate and 13-a sludge discharge pipe.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention will be further described in detail with reference to the accompanying drawings and specific embodiments. It is to be understood that the specific embodiments described herein are for purposes of illustration only and are not to be construed as limiting the invention.
The embodiment relates to a mud discharging device for a long-distance pressure pipeline, which is structurally shown in figure 1 and comprises a mud discharging eccentric tee joint 1, a mud discharging valve well 2, a mud discharging wet well 3, a mud discharging gate valve 4, a vacuumizing interface 5, a temporary vacuum pump 6, a guide rail support 7, a manual hoist 8, a water pump guide rail platform 9, a temporary submersible sewage pump 10, a mud discharging tee joint 11, a pipeline flange blind plate 12 and a mud discharging pipe 13.
Specifically, the mud discharging eccentric tee joint 1 is connected with a mud discharging pipe 13, and the other end of the mud discharging pipe 13 extends into a mud discharging valve well 2 and a mud discharging wet well 3.
Specifically, the mud discharging valve well 2 is dug to the position below the mud discharging pipe 13 from the ground, and the well depth of the mud discharging valve well 2 is 2.5-3.5 meters.
Specifically, will arrange row's mud gate valve 4 and evacuation interface 5 arrange the inside of row's mud valve well 2 to set gradually on mud pipe 13 connect a temporary vacuum pump 6 on the evacuation interface 5, temporary vacuum pump 6 when overhauing for the maintenance, take on the maintenance car certainly.
Specifically, arrange mud wetting well 3 be steel tubular construction, just arrange mud wetting well 3's shaft bottom setting in the below of arranging mud eccentric tee bend 1, adopt DN800 ~ DN1400 m's steel pipe to bury 8 ~ 15 meters underground from ground and constitute a closed area, pipeline flange blind flange 12, arrange mud tee bend 11, arrange mud pipe 13, water pump guide rail platform 9, guide rail bracket 7, hand block 8 and arrange within this closed area.
Concretely, a plurality of rail brackets 7 set up arrange on the inside lateral wall of steel tubular construction of mud wet well 3, rail brackets 7's top is equipped with hand-drive block 8, rail brackets 7's bottom is equipped with water pump guide rail platform 9, set up the interim stealthily dirty pump 10 of usefulness when the maintenance was overhauld on the water pump guide rail platform 9, interim stealthily dirty pump 10 is when the maintenance is overhauld, and the maintenance car is gone up from the area.
Specifically, be located be equipped with a row's mud tee bend 11 on the inside mud pipe 13 of the steel tubular construction of row's mud wet well 3 sets up on mud pipe 13, pipeline flange blind plate 12 passes through row's mud tee bend 11 is connected with the mud pipe 13 at both ends.
The utility model provides a mud discharging device for long-distance pressure pipelines, which adopts a steel pipe structure to replace a mud discharging wet well, thereby omitting civil construction such as brick concrete and the like, and leading the construction to be more convenient and efficient; only need open row mud valve well 2 when the maintenance, use interim vacuum pump 6 to form the siphon through evacuation interface 5 evacuation as required, discharge muddy water in the pipeline, reuse interim stealthily dirty pump 10 to fix on water pump guide rail platform 9 and utilize hand-operated block 8 to send interim stealthily dirty pump 10 to row mud wet well 3 bottom, can be clean with the inside muddy water pump drainage of row mud wet well 3 for maintenance operation is comparatively convenient.
The parts not described in the specification are prior art or common general knowledge. The present embodiment is only used for illustrating the present invention, and is not used to limit the scope of the present invention, and modifications such as equivalent replacement made by those skilled in the art to the present invention are all considered to fall within the protection scope of the claims of the present invention.

Claims (6)

1. The utility model provides a arrange mud device for long distance pipeline under pressure, includes row's mud eccentric tee bend (1), row's mud valve well (2) and row's mud wet well (3) that link together through mud pipe (13), its characterized in that: arrange mud wet well (3) be steel tubular construction, just the shaft bottom of arranging mud wet well (3) sets up in the below of arranging mud eccentric tee bend (1), the shaft bottom of arranging mud valve well (2) sets up the below of mud pipe (13) is located be equipped with row mud gate valve (4) and evacuation interface (5) on arranging mud pipe (13) in mud valve well (2), connect a temporary vacuum pump (6) on evacuation interface (5).
2. A mud discharge device for long distance pressure pipes according to claim 1, wherein: arrange and set up a plurality of guide rail bracket (7) on the inside lateral wall of steel tubular construction of mud wet well (3), the top of guide rail bracket (7) is equipped with hand-drive block (8), the bottom of guide rail bracket (7) is equipped with water pump guide rail platform (9).
3. A mud discharge device for long distance pressure pipes according to claim 2, wherein: and a temporary submersible sewage pump (10) used for maintenance is arranged on the water pump guide rail platform (9).
4. A mud discharge device for long distance pressure pipes according to claim 3, wherein: be located be equipped with a row of mud tee bend (11) on mud pipe (13) inside the steel tubular construction of row mud wet well (3), pipeline flange blind plate (12) pass through mud pipe (13) are connected with mud pipe (11).
5. A mud discharge device for long distance pressure pipes according to claim 1, wherein: the well depth of the mud discharging valve well (2) is 2.5-3.5 meters, and the well depth of the mud discharging wet well (3) is 8-15 meters.
6. A mud discharge device for long distance pressure pipes according to claim 1, wherein: the structural specification of the steel pipe of the sludge discharge wet well (3) is DN 800-DN 1400 mm.
CN201921157252.XU 2019-07-23 2019-07-23 Sludge discharge device for long-distance pressure pipeline Active CN211143181U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921157252.XU CN211143181U (en) 2019-07-23 2019-07-23 Sludge discharge device for long-distance pressure pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921157252.XU CN211143181U (en) 2019-07-23 2019-07-23 Sludge discharge device for long-distance pressure pipeline

Publications (1)

Publication Number Publication Date
CN211143181U true CN211143181U (en) 2020-07-31

Family

ID=71744403

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921157252.XU Active CN211143181U (en) 2019-07-23 2019-07-23 Sludge discharge device for long-distance pressure pipeline

Country Status (1)

Country Link
CN (1) CN211143181U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112412738A (en) * 2020-11-19 2021-02-26 佛山市顺德区水利水电勘测设计院有限公司 Hump siphon type water outlet flow passage of small and medium-sized pump station and use method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112412738A (en) * 2020-11-19 2021-02-26 佛山市顺德区水利水电勘测设计院有限公司 Hump siphon type water outlet flow passage of small and medium-sized pump station and use method thereof

Similar Documents

Publication Publication Date Title
CN103883796B (en) Silt particle mud district hand pick formula jacking construction device and method
CN206346209U (en) A kind of quick solution dewatering well piping plugging structure
CN102535519A (en) I-shaped steel joint structure for underground continuous wall and construction method for I-shaped steel joint structure
CN211143181U (en) Sludge discharge device for long-distance pressure pipeline
CN204343330U (en) A kind of plastic drain-pipe and manhole sealing and connecting device
CN102605803A (en) Inspection well
CN104878771A (en) Construction method for vacuum tube well dewatering system
US4285359A (en) Interface unit for vacuum sewers
CN204080839U (en) A kind of Yield rainfall relation device
CN209854813U (en) Deep basal pit precipitation well dredging device
CN205224063U (en) High -efficient precipitation device of hypotonicity clay
CN203757177U (en) Mud sand sludge area manual pipe jacking construction device
CN206956917U (en) A kind of automatically cleaning pumping plant base for collecting sludge certainly
CN205663006U (en) Sewage sewage pipes is used in municipal administration
CN211200626U (en) U-shaped communication pipeline for drainage of adverse slope in construction site
CN210887513U (en) Plastic inspection well
CN202530553U (en) Inspection well
CN107700471B (en) Low-level drainage body suitable for ultra-low-level vacuum preloading method
CN215829459U (en) Underground water discharge device around working well
CN105887902B (en) Well point plastic strip vacuum pre-pressed joint precipitating, pre-pressing dynamic consolidation method
CN212316962U (en) Basement drainage device that falls
CN104963383B (en) A kind of pressure conduit inverted siphon hydraulic automatism erosion and deposition device
CN105862713B (en) Soft soil foundation integral type well point plastic strip vacuum system
CN205716060U (en) Municipal wastewater abnormity concrete pipe
CN216839362U (en) Reinforced CFG pile composite foundation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant