CN211080808U - Parapet steel cable platform - Google Patents
Parapet steel cable platform Download PDFInfo
- Publication number
- CN211080808U CN211080808U CN201921391102.5U CN201921391102U CN211080808U CN 211080808 U CN211080808 U CN 211080808U CN 201921391102 U CN201921391102 U CN 201921391102U CN 211080808 U CN211080808 U CN 211080808U
- Authority
- CN
- China
- Prior art keywords
- parapet
- cable
- platform
- vertical
- horizontal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 33
- 239000010959 steel Substances 0.000 title claims abstract description 33
- 238000010276 construction Methods 0.000 abstract description 16
- 238000009434 installation Methods 0.000 abstract description 6
- 230000009286 beneficial effect Effects 0.000 abstract description 2
- 230000001681 protective effect Effects 0.000 description 12
- 238000009432 framing Methods 0.000 description 4
- 239000011120 plywood Substances 0.000 description 4
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 238000011161 development Methods 0.000 description 2
- 239000011521 glass Substances 0.000 description 2
- 239000002023 wood Substances 0.000 description 2
- 230000003111 delayed effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000011148 porous material Substances 0.000 description 1
- 230000002035 prolonged effect Effects 0.000 description 1
- 238000012216 screening Methods 0.000 description 1
Images
Landscapes
- Fencing (AREA)
Abstract
The utility model provides a parapet steel cable platform mainly relates to the building field. The utility model provides a parapet steel cable platform, includes parapet, horizontal cable, vertical cable, the parapet is closed shape, equal linear a plurality of pairs of through-holes that set up on the parapet four sides, horizontal cable passes two pairs of horizontal relative through-hole rear end tensioning and connects, vertical cable passes two pairs of vertical relative through-hole rear end tensioning and connects, the multiunit horizontal cable and multiunit the netted operation panel is constituteed to vertical cable, netted operation panel top sets up the protection network, the protection network top sets up the flat board. The beneficial effects of the utility model reside in that: the utility model discloses utilize the parapet to build the steel cable operation platform of daylighting top installation, the construction cost of platform is lower, and can not produce the construction operation on ground and disturb, has shortened the time limit for a project greatly.
Description
Technical Field
The utility model relates to the field of building, specifically a parapet steel cable platform.
Background
Along with the development of economy, landmark markets and office buildings in various regions are gradually increased, and in order to achieve the purpose of energy saving and lighting, a glass lighting roof is more selectively designed above an indoor hollow lobby of the building. However, many daylighting roofs are installed at a high height, which causes a problem of difficulty in construction. The existing conventional means is solved by adopting a mode of erecting a full framing scaffold and arranging an operation platform, but once the full framing scaffold is assembled, the full framing scaffold cannot be detached before the construction of the daylighting roof is finished, and the development of ground operation below the full framing scaffold is often delayed, so that the ground operation and the installation of the glass daylighting roof cannot be synchronously carried out, the construction period is prolonged, and the cost is increased.
SUMMERY OF THE UTILITY MODEL
For solving prior art's not enough, the utility model provides a parapet steel cable platform, it can utilize the parapet to build the steel cable operation platform of daylighting top installation, and the construction cost of platform is lower, and can not disturb the construction operation on ground, has shortened the time limit for a project greatly.
The utility model discloses a realize above-mentioned purpose, realize through following technical scheme:
The utility model provides a parapet steel cable platform, includes parapet, horizontal cable, vertical cable, the parapet is closed shape, equal linearity sets up a plurality of pairs of through-holes on the parapet four sides, and the through-hole is corresponding on the relative two sides parapet, horizontal cable passes two pairs of horizontal relative through-hole rear end tensionings and connects, vertical cable passes two pairs of vertical relative through-hole rear end tensionings and connects, the multiunit horizontal cable and multiunit the netted operation panel is constituteed to vertical cable, the nodical position mountable a certain amount of hasp of netted operation panel prevents mutual slip. The top of the net-shaped operating platform is provided with a protective net, and the top of the protective net is provided with a flat plate.
The through holes which are transversely opposite are arranged at the same horizontal height, and the through holes which are vertically opposite are arranged at the same height.
The through hole is formed at a position with a height of 200-300mm at the bottom of the parapet wall.
And the contact positions of the transverse guy cable and the vertical guy cable with the parapet wall are inserted into battens.
And a safety steel cable is arranged on the outer side of the parapet wall.
Contrast prior art, the beneficial effects of the utility model are that:
The utility model discloses a parapet carries on, utilizes the steel cable to build the installation operation panel on daylighting top, makes workman can work on the operation panel, accomplishes the installation on daylighting top. The construction cost of the whole operation platform is lower than that of a full scaffold, the construction and dismantling speed is high, the construction operation on the ground cannot be interfered, and the construction period is greatly shortened.
Drawings
FIG. 1 is a schematic top view of the present invention;
Fig. 2 is a schematic top view of embodiment 2 of the present invention;
Fig. 3 is a schematic view of a partially enlarged structure of part a of the present invention.
Reference numerals shown in the drawings: 1. a parapet wall; 2. a transverse stay cable; 3. a vertical stay cable; 4. a protective net; 5. a flat plate; 6. wood block; 7. a safety steel cord; 8. and (4) a column.
Detailed Description
The present invention will be further described with reference to the accompanying drawings and specific embodiments. It should be understood that these examples are for illustrative purposes only and are not intended to limit the scope of the present invention. Furthermore, it should be understood that various changes or modifications of the present invention may be made by those skilled in the art after reading the teachings of the present invention, and these equivalents also fall within the scope defined in the present application.
As shown in figures 1-3, the utility model relates to a parapet steel cable platform, including parapet 1, horizontal cable 2, vertical cable 3, parapet 1 is closed shape, and closed form parapet is the indispensable structure of many markets, office building top surface. A plurality of pairs of through-holes are seted up to equal linearity on 1 four sides of parapet, and the through-hole is corresponding on 1 parapet of relative two sides, both ends tensioning is connected after horizontal cable 2 passes two pairs of horizontal relative through-holes, vertical cable 3 passes two pairs of vertical relative through-holes rear ends tensioning and connects, the multiunit horizontal cable 2 and multiunit vertical cable 3 component network form operation panel, and at the in-process that the through-hole was seted up, the trompil elevation of two directions can be unanimously also crisscross under can be seted up. The top of the net-shaped operation platform is provided with a protective net 4, large pores between the net-shaped operation platforms are filled by the protective net, and the boundary of the protective net is fixed on a concrete parapet or a floor slab to protect operators. The top of the protective net 4 is provided with a flat plate 5, and the flat plate is laid to clean obstacles for operation and walking of operators on the flat plate. Meanwhile, the laying of the protective net can play a role in increasing friction force, so that the flat plate can be placed on the mesh-shaped operating platform more stably. This device makes workman can work on the operation panel through the construction of steel cable on the parapet, accomplishes the installation of daylighting top. The construction cost of the whole operation platform is lower than that of a full scaffold, the construction and dismantling speed is high, the construction operation on the ground cannot be interfered, and the construction period is greatly shortened.
Specifically, the through holes which are transversely opposite are arranged at the same horizontal height, and the through holes which are vertically opposite are arranged at the same height. Through the consistency that the through-hole was seted up, what make horizontal cable and vertical cable builds more evenly, the effect of building of platform is more stable.
Specifically, the through hole is formed at a position with a height of 200-300mm at the bottom of the parapet wall 1.
Specifically, the contact positions of the transverse stay cables 2 and the vertical stay cables 3 and the parapet wall 1 are inserted into battens 6. Through the insertion of flitch, protect parapet through-hole position, avoid steel cable direct contact through-hole to cause the wall body to drop.
Specifically, a safety steel cable 7 is arranged on the outer side of the parapet wall 1. The safety cable serves as a secondary protection for the worker. The safety steel cable can be fixed on a parapet wall and can also be fixed on a roof surface, and the safety steel cable is used for pulling the safety rope to the waist of a worker to protect the worker.
Example 1:
The utility model provides a parapet steel cable platform, includes parapet 1, horizontal cable 2, vertical cable 3, parapet 1 is closed shape, equal linearity is seted up a plurality of to the through-hole on 1 four sides of parapet, and the through-hole is corresponding on 1 of relative two-sided parapet. The through holes are arranged at the positions 200-300mm higher than the bottom of the parapet wall 1, the horizontal heights of the transversely opposite through holes are consistent, and the heights of the vertically opposite through holes are consistent. The transverse stay cable and the vertical stay cable are steel wire ropes with the diameter of 18mm, the transverse stay cable 2 penetrates through the two pairs of transverse opposite through holes and then is connected with two ends in a tensioning mode, the vertical stay cable 3 penetrates through the two pairs of vertical opposite through holes and then is connected with two ends in a tensioning mode, and the two ends of each steel wire rope are connected through steel wire rope connecting pieces. And the contact positions of the transverse guy cable 2 and the vertical guy cable 3 with the parapet wall 1 are inserted into battens 6. The net-shaped operation platform is formed by the multiple groups of the transverse guys 2 and the multiple groups of the vertical guys 3, the top of the net-shaped operation platform is paved with a protective net 4, the protective net is bound with the edge guys of the transverse guys and the vertical guys in the embodiment, and the protective net can be arranged in multiple layers for ensuring safety. The flat plate 5 is laid on the top of the protective screening 4, the flat plate can be made of wood boards, plywood and the like, and plywood is adopted in the embodiment. Can punch on the plywood, utilize the iron wire to tie up the plywood and tie up on the cable. In this embodiment, a safety steel cable 7 is arranged outside the parapet wall 1, and two ends of the safety steel cable are respectively fixed at the corners of the parapet wall by using steel cable connecting pieces.
After the lighting ceiling is installed, the net-shaped operating platform needs to be detached, and the through holes in the parapet wall are permanently sealed.
It should be noted that the specific project is designed specifically according to the actual situation to satisfy the stress requirement of the mesh console.
Example 2:
Aiming at the embodiment 1, the parapet outer side in this embodiment is provided with a plurality of parapet stand columns, when the parapet is punched, a pair of through holes are formed in two sides of the stand columns, and the steel cable bypasses the parapet stand columns, so that the supporting strength of the net-shaped operating platform can be increased. It should be noted that battens are inserted between the steel cables passing around the columns and the columns to protect the columns.
Claims (5)
1. The utility model provides a parapet steel cable platform, includes parapet (1), horizontal cable (2), vertical cable (3), its characterized in that: parapet (1) is closed shape, equal linear a plurality of pairs of through-holes that set up on parapet (1) four sides, the through-hole is corresponding on relative two sides parapet (1), horizontal cable (2) pass two pairs of horizontal relative through-hole rear end tensioning and connect, vertical cable (3) pass two pairs of vertical relative through-hole rear end tensioning and connect, the multiunit horizontal cable (2) and multiunit net form operation panel is constituteed in vertical cable (3), net form operation panel top sets up protection network (4), protection network (4) top sets up flat board (5).
2. A parapet steel cable platform as claimed in claim 1, wherein: the through holes which are transversely opposite are arranged at the same horizontal height, and the through holes which are vertically opposite are arranged at the same height.
3. A parapet steel cable platform as claimed in claim 1, wherein: the through hole is arranged at a position with a height of 200-300mm at the bottom of the parapet wall (1).
4. A parapet steel cable platform as claimed in claim 1, wherein: and the contact positions of the transverse guy cable (2) and the vertical guy cable (3) with the parapet wall (1) are inserted into battens (6).
5. A parapet steel cable platform as claimed in claim 1, wherein: and a safety steel cable (7) is arranged on the outer side of the parapet wall (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921391102.5U CN211080808U (en) | 2019-08-26 | 2019-08-26 | Parapet steel cable platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921391102.5U CN211080808U (en) | 2019-08-26 | 2019-08-26 | Parapet steel cable platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN211080808U true CN211080808U (en) | 2020-07-24 |
Family
ID=71625585
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921391102.5U Expired - Fee Related CN211080808U (en) | 2019-08-26 | 2019-08-26 | Parapet steel cable platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN211080808U (en) |
-
2019
- 2019-08-26 CN CN201921391102.5U patent/CN211080808U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208430687U (en) | Self-anchored type suspended-cable structure support construction and system | |
CN106760529A (en) | Roof system steel truss slipping and assembling operation platform and installation method | |
CN105298099A (en) | Modular suspension type steel tube fastener scaffold operating platform and erecting method thereof | |
CN110562868B (en) | Hoisting construction method for unit type glass curtain wall of super high-rise building | |
CN106760561B (en) | Assembling method of sectional sliding roof steel truss | |
CN111155756B (en) | Arc-shaped elevation large-angle variable slope hydraulic protection structure and construction method thereof | |
CN206319610U (en) | Roof system steel truss slipping and assembling construction platform structure | |
CN211080808U (en) | Parapet steel cable platform | |
CN206753085U (en) | A kind of sliding platform for being used to install high-altitude wire frame steel construction | |
CN103321438B (en) | A kind of modular protection marguise of large cantilever being applicable to high-building construction | |
CN209780190U (en) | Hanging platform for large-span beam string beam daylighting roof construction | |
CN110778094A (en) | High-altitude large-span dragline net operating platform and construction method | |
CN107299766B (en) | Prefabricated sloping roof plate supporting system and construction method thereof | |
CN111945561B (en) | Special-shaped cable tower decorative plate installation device and construction method | |
CN211974268U (en) | Arc-shaped vertical face large-angle variable slope hydraulic protection structure | |
CN109736503B (en) | Sound-absorbing suspended ceiling device under grid structure and construction method thereof | |
CN113047594A (en) | Movable climbing frame for elevator shaft and erection method thereof | |
CN210563326U (en) | Overhead unit type overhead sliding splicing operation platform | |
CN108316633B (en) | Daylighting roof operation platform and construction method | |
CN107035037A (en) | High building top layer curtain wall frame and its installation method | |
CN203440913U (en) | Supporting structure for reinforced concrete corridor construction | |
CN210263834U (en) | Pier stud safety protection construction platform | |
CN208604911U (en) | A kind of novel suspention beam bracket | |
CN203878966U (en) | Ascending and descending protecting screen of spine structure | |
CN206091253U (en) | Be suitable for irregular space's simple and easy steel bracket platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200724 |