CN206753085U - A kind of sliding platform for being used to install high-altitude wire frame steel construction - Google Patents
A kind of sliding platform for being used to install high-altitude wire frame steel construction Download PDFInfo
- Publication number
- CN206753085U CN206753085U CN201720416244.7U CN201720416244U CN206753085U CN 206753085 U CN206753085 U CN 206753085U CN 201720416244 U CN201720416244 U CN 201720416244U CN 206753085 U CN206753085 U CN 206753085U
- Authority
- CN
- China
- Prior art keywords
- truss
- altitude
- wire frame
- sliding platform
- steel construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 40
- 239000010959 steel Substances 0.000 title claims abstract description 40
- 238000010276 construction Methods 0.000 title claims abstract description 17
- 230000007246 mechanism Effects 0.000 claims description 10
- 230000005540 biological transmission Effects 0.000 claims 1
- 230000005571 horizontal transmission Effects 0.000 claims 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims 1
- 238000000034 method Methods 0.000 abstract description 14
- 238000009434 installation Methods 0.000 abstract description 9
- 230000008569 process Effects 0.000 description 8
- 238000010586 diagram Methods 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 2
- 230000007547 defect Effects 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000003032 molecular docking Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Landscapes
- Movable Scaffolding (AREA)
Abstract
本实用新型涉及一种用于安装高空网架钢结构的滑移平台,具有若干互相平行的桁架,桁架具有上下两根互相平行的方钢管,桁架两端的下方设置有滑轮机构;相邻桁架的间距等于高空网架钢结构的球节点纵向间隔;前后两侧的桁架与相邻桁架之间通过端部和中部的剪刀撑结构进行加固;桁架通过设置于两端的水平传力杆和水平连接杆固定为一体,水平传力杆与桁架的下方钢管固定,水平连接杆与桁架的上方钢管固定。使用本滑移平台进行安装高空网架钢结构安装,可以有效地解决网架跨度大,现场大型吊装设备难以进入安装的困难;滑移拼装平台的支架费用比满堂红脚手架高空散装法节省40%以上;且占用建筑物周边场地少,只需一侧施工通道场地即可。
The utility model relates to a sliding platform for installing a high-altitude grid steel structure, which has several parallel trusses. The spacing is equal to the longitudinal spacing of the ball joints of the high-altitude grid steel structure; the trusses on the front and rear sides and the adjacent trusses are reinforced by the scissors brace structure at the end and the middle; It is fixed as a whole, the horizontal dowel bar is fixed to the lower steel pipe of the truss, and the horizontal connecting rod is fixed to the upper steel pipe of the truss. Using this sliding platform to install high-altitude grid steel structure installation can effectively solve the difficulty of large grid span and large-scale hoisting equipment on site; the support cost of the sliding assembly platform can save more than 40% compared with the high-altitude bulk method of full house scaffolding ; and occupy less space around the building, only one side of the construction passage site is sufficient.
Description
技术领域technical field
本实用新型涉及一种用于安装高空网架钢结构的滑移平台,属于高空钢结构安装技术领域。The utility model relates to a sliding platform for installing high-altitude grid steel structures, which belongs to the technical field of high-altitude steel structure installation.
背景技术Background technique
20 世纪开始,世界许多国家和地区建造了成千上万的各类型的钢网架结构,为人类的生产生活提供了更加便捷的、更加健康的空间场所,例如体育运动场、飞机库、各类戏剧院、各种会展中心等。网架结构是大跨度空间结构的一种形式之一,具有良好的受力性能,较大的刚度和较好的整体性,从某种意义上优于平面结构,能有效承受各种荷载作用,结构制作安装也相对比较方便。我国在网架安装施工中,创造了许多简便有效的安装方法。Since the beginning of the 20th century, thousands of various types of steel grid structures have been built in many countries and regions of the world, providing more convenient and healthier spaces for human production and life, such as sports fields, hangars, various Theaters, various convention centers, etc. Grid structure is one of the forms of long-span space structure, which has good mechanical performance, greater rigidity and better integrity. In a sense, it is superior to plane structure and can effectively withstand various loads. , The structure is relatively convenient to manufacture and install. my country has created many simple and effective installation methods in the installation and construction of grid frames.
国内成熟的比较简单的网架安装工艺有以下几种:The mature and relatively simple grid installation techniques in China are as follows:
1、满堂红脚手架屋面组对工艺:此工艺是从地面搭脚手架一直到屋面下檐,使屋面形成一个大平台,屋面网架就在平台上进行组装。1. Mantanghong scaffolding roof assembly process: This process is to build scaffolding from the ground to the lower eaves of the roof, so that the roof forms a large platform, and the roof grid is assembled on the platform.
此工艺的优点:安全、大型吊装机械使用少、组对速度快、质量有保证。缺点是脚手架搭设工作量大,脚手架用量大,不适合上下交叉施工。The advantages of this process: safety, less use of large hoisting machinery, fast assembly speed, and guaranteed quality. The disadvantage is that the workload of scaffolding is large, and the amount of scaffolding is large, which is not suitable for up and down cross construction.
2、地面分布组对,空中对接工艺:此工艺是在地面将网架组对呈一段一段的网架,由两台抬吊到空中进行分块组对,网架从一头往另一头逐步推进。2. Ground distribution pairing and aerial docking process: This process is to assemble the grids on the ground into a section of grids, and lift them into the air by two sets to carry out block pairing, and the grids are gradually advanced from one end to the other. .
此工艺的有点:节省脚手架的使用,占用馆内施工场地少,无需大吨位起吊设备。能有效解决屋面施工脚手架与地面看台土建施工的矛盾。缺点是:占用两步吊车时间长,高空作业多,空中组对难度大,危险性大。The advantages of this process: save the use of scaffolding, occupy less construction space in the pavilion, and do not need large-tonnage lifting equipment. It can effectively solve the contradiction between roof construction scaffolding and ground stand civil construction. The disadvantages are: it takes a long time to occupy the two-step crane, and there are many high-altitude operations, which makes it difficult and dangerous to assemble in the air.
3、地面小单元组对,空中组对工艺:此方法就是在地面只组对一球三杆,吊到空中进行组装,需要临时支柱配合安装。3. Small unit pairing on the ground, pairing process in the air: This method is to assemble only one ball and three rods on the ground, and then hang them in the air for assembly, which requires temporary pillars to cooperate with the installation.
此工艺优点:速度快,无需大吨位吊车配合,占用场地少,能有效解决屋面作业与看土建同时施工的矛盾。缺点是:高空作业,危险性高。The advantages of this process are: fast speed, no need for large-tonnage cranes, less space occupation, and can effectively solve the contradiction between roofing work and civil engineering construction at the same time. The disadvantage is: high-altitude operation, high risk.
发明内容Contents of the invention
本实用新型的目的在于:克服上述现有技术的缺陷,提出一种用于安装高空网架钢结构的滑移平台,借助该平台进行高空网架钢结构的安装,降低高空作业的危险性。The purpose of this utility model is: to overcome the defects of the prior art mentioned above, to propose a sliding platform for installing the steel structure of the high-altitude grid, and to use the platform to install the steel structure of the high-altitude grid to reduce the danger of high-altitude operations.
为了达到上述目的,本实用新型提出的用于安装高空网架钢结构的滑移平台,其特征在于:具有若干互相平行的桁架,所述桁架具有上下两根互相平行的方钢管,两方钢管之间焊接有立杆和斜杆,桁架两端的下方设置有滑轮机构;相邻桁架的间距等于高空网架钢结构的球节点纵向间隔;前后两侧的桁架与相邻桁架之间通过端部和中部的剪刀撑结构进行加固;桁架通过设置于两端的水平传力杆和水平连接杆固定为一体,所述水平传力杆与桁架的下方钢管固定,水平连接杆与桁架的上方钢管固定。In order to achieve the above object, the utility model proposes a sliding platform for installing a high-altitude grid steel structure, which is characterized in that it has a number of parallel trusses, and the trusses have two parallel square steel pipes up and down, two square steel pipes There are vertical rods and diagonal rods welded between them, and a pulley mechanism is set under the two ends of the truss; the distance between adjacent trusses is equal to the longitudinal distance between the ball joints of the high-altitude grid steel structure; the trusses on the front and rear sides and the adjacent trusses pass through It is reinforced with the scissor brace structure in the middle; the truss is fixed as a whole by the horizontal dowel bars and horizontal connecting rods arranged at both ends, the horizontal dowel bars are fixed to the lower steel pipe of the truss, and the horizontal connecting rods are fixed to the upper steel pipe of the truss.
本实用新型用于安装高空网架钢结构的滑移平台,进一步的改进在于:The utility model is used to install the sliding platform of the high-altitude grid steel structure, and the further improvement lies in:
1、滑移平台还具有设置于结构框架柱内侧的桁车梁,桁车梁上设置有滑移轨道,所述滑轮机构与滑移轨道相配合。1. The sliding platform also has a truss girder arranged on the inside of the structural frame column. A sliding track is arranged on the trussing girder, and the pulley mechanism cooperates with the sliding track.
2、所述滑轮机构具有固定在桁架端部下方的开口朝下的半工字型滚轮架,所述滚轮架横向开孔,孔内插入有滚轮轴,滚轮轴落在滑移轨道上,所述滚轮架两侧设置有两对调节定位螺栓,用于分别从两侧抵住滑移轨道,实现桁架与滑移轨道之间角度的调节和桁架在滑移轨道上的定位。2. The pulley mechanism has a semi-I-shaped roller frame fixed below the end of the truss with the opening facing downward. The roller frame has a horizontal hole, and a roller shaft is inserted into the hole, and the roller shaft falls on the sliding track. Two pairs of adjustment positioning bolts are arranged on both sides of the roller frame, which are used to respectively bear against the sliding track from both sides to realize the adjustment of the angle between the truss and the sliding track and the positioning of the truss on the sliding track.
3、桁架的上方沿桁架纵向方向布置有与高空网架球节点对应的支撑架安装座。3. Above the truss, there is a supporting frame mounting seat corresponding to the ball node of the high-altitude grid along the longitudinal direction of the truss.
4、所述桁架上方铺设有踏板。4. A pedal is laid above the truss.
本实用新型用于安装高空网架钢结构的滑移平台,结构巧妙,力学性能满足实际需要,降低高空作业的危险性。使用本滑移平台进行安装高空网架钢结构安装,可以有效地解决网架跨度大,现场大型吊装设备难以进入安装的困难;在屋面网架施工期间,下部土建作业可交错进行;滑移拼装平台的支架费用比满堂红脚手架高空散装法节省40%以上;且占用建筑物周边场地少,只需一侧施工通道场地即可。The utility model is used for installing a sliding platform of a high-altitude grid steel structure, which has an ingenious structure, mechanical properties that meet actual needs, and reduces the risk of high-altitude operations. Using this sliding platform to install the high-altitude grid steel structure installation can effectively solve the difficulty that the grid span is large and the large-scale hoisting equipment on site is difficult to enter and install; during the construction of the roof grid, the lower civil work can be staggered; sliding assembly The support cost of the platform saves more than 40% compared with the high-altitude bulk method of full-house scaffolding; and it occupies less space around the building, only one side of the construction passage site is sufficient.
附图说明Description of drawings
下面结合附图对本实用新型作进一步的说明。Below in conjunction with accompanying drawing, the utility model is further described.
图1是滑移平台结构示意图。Figure 1 is a schematic diagram of the structure of the sliding platform.
图2是滑移平台的侧视图。Figure 2 is a side view of the skid platform.
图3是滑移轨道和滑轮机构示意图。Fig. 3 is a schematic diagram of the sliding track and the pulley mechanism.
图中标号示意图下:Under the schematic diagram of the labels in the figure:
1-上球节点;1'-下球节点;4-滑轮机构;41-滚轮架;42-滚轮轴;43-调节定位螺栓;5-滑移轨道;51-滑移轨道固定件;6-桁架;7-桁车梁;8-结构框架柱;61-水平传力杆;62-剪刀撑结构;63-水平连接杆; 64-上方钢管;65-下方钢管;66-立杆;67-斜杆。1-upper ball node; 1'-lower ball node; 4-pulley mechanism; 41-roller frame; 42-roller shaft; 43-adjusting positioning bolt; 5-sliding track; 51-sliding track fixing piece; 6- Truss; 7-truss beam; 8-structural frame column; 61-horizontal dowel; 62-scissors brace structure; 63-horizontal connecting rod; 64-upper steel pipe; Diagonal bar.
具体实施方式detailed description
下面结合附图和具体实施例对本实用新型做进一步说明。Below in conjunction with accompanying drawing and specific embodiment the utility model is described further.
如图1、图2所示,高空网架钢结构由上球节点1、下球节点1'和将球节点连接在一起的连接杆构成。本实施例用于安装高空网架钢结构的滑移平台,组成包括:设置于结构框架柱8内侧的桁车梁7、设置于桁车梁7上的滑移轨道8、和由若干互相平行的通过水平传力杆连接在一起桁架6。桁架6具有上下两根互相平行的方钢管(上方钢管64和下方钢管65),两方钢管之间焊接有立杆66和斜杆67,桁架6两端的下方设置有与滑移轨道相配合的滑轮机构4。相邻桁架的间距等于高空网架钢结构的球节点纵向间隔;桁架的上方沿桁架纵向方向布置有与高空网架球节点对应的支撑架安装座(图中为标出),为用于安装球节点的支撑装置提供定位点。借助本滑移平台,在施工完一个区段高空网架安装后,滑移至下个工位再进行下一区段高空网架的安装。如图2所示,前后两侧的桁架与相邻桁架之间通过端部和中部的剪刀撑结构62进行加固;桁架6通过设置于两端的水平传力杆61和水平连接杆63固定为一体,水平传力杆62与桁架6的下方钢管固定,水平连接杆63与桁架6的上方钢管固定。一方面,水平传力杆61和水平连接杆63将多榀桁架6连接为一个整体,另一方面水平传力杆61为滑移平台的移动传递牵引力(可利用拉力装置——比如手拉葫芦进行牵引)。为了提高安全性,在桁架上方铺设有踏板,供施工人员踩踏。As shown in Figure 1 and Figure 2, the high-altitude grid steel structure is composed of upper spherical nodes 1, lower spherical nodes 1' and connecting rods connecting the spherical nodes together. This embodiment is used to install the sliding platform of the high-altitude grid steel structure, which consists of: the truss girder 7 arranged on the inside of the structural frame column 8, the sliding track 8 arranged on the truss girder 7, and several parallel to each other The trusses 6 are connected together by horizontal dowel bars. The truss 6 has two upper and lower square steel pipes (upper steel pipe 64 and lower steel pipe 65 ) parallel to each other. Vertical rods 66 and oblique rods 67 are welded between the two steel pipes. Pulley mechanism 4. The distance between adjacent trusses is equal to the longitudinal spacing of the ball joints of the high-altitude grid steel structure; above the trusses, there are support frame mounting seats (marked in the figure) corresponding to the ball joints of the high-altitude grid structure along the longitudinal direction of the trusses, which are used for installation The support device of the ball joint provides the anchor point. With the help of this sliding platform, after the installation of the high-altitude grid in one section is completed, it can slide to the next station and then install the high-altitude grid in the next section. As shown in Figure 2, the trusses on the front and rear sides and the adjacent trusses are reinforced by scissor brace structures 62 at the ends and in the middle; , the horizontal dowel bar 62 is fixed to the steel pipe below the truss 6 , and the horizontal connecting rod 63 is fixed to the steel pipe above the truss 6 . On the one hand, the horizontal dowel bar 61 and the horizontal connecting bar 63 connect the multiple trusses 6 as a whole; to tow). In order to improve safety, there are pedals laid above the truss for construction personnel to step on.
如图3所示,滑轮机构具有固定在桁架端部下方的开口朝下的半工字型滚轮架41,滚轮架41横向开孔,孔内插入有滚轮轴42,滚轮轴42落在滑移轨道5上,滚轮架41两侧设置有两对调节定位螺栓43,用于分别从两侧抵住滑移轨道5,实现桁架与滑移轨道之间角度的调节和桁架在滑移轨道上的定位。As shown in Figure 3, the pulley mechanism has a semi-I-shaped roller frame 41 fixed on the bottom of the truss end with the opening facing downward. On the track 5, two pairs of adjustment positioning bolts 43 are arranged on both sides of the roller frame 41, which are used to resist the sliding track 5 from both sides, so as to realize the adjustment of the angle between the truss and the sliding track and the adjustment of the truss on the sliding track. position.
除上述实施例外,本实用新型还可以有其他实施方式。凡采用等同替换或等效变换形成的技术方案,均落在本实用新型要求的保护范围。In addition to the above embodiments, the utility model can also have other implementations. All technical solutions formed by equivalent replacement or equivalent transformation fall within the scope of protection required by the utility model.
Claims (5)
- A kind of 1. sliding platform for being used to install high-altitude wire frame steel construction, it is characterised in that:With some truss parallel to each other, The truss has upper and lower two square steel tubes parallel to each other, and vertical rod and brace are welded between two square steel tubes, truss both ends Lower section is provided with pulley mechanism;The ball node that the spacing of adjacent truss is equal to high-altitude wire frame steel construction is longitudinally spaced;Front and rear sides Truss and adjacent truss between reinforced by the scissors support structure at end and middle part;Truss is by being arranged at the water at both ends Flat transmission rod and horizontal brace rod are fixed as one, and the lower square steel tube of the horizontal transmission rod and truss is fixed, horizontal brace rod Fixed with the upper square steel tube of truss.
- 2. the sliding platform according to claim 1 for being used to install high-altitude wire frame steel construction, it is characterised in that:Also have and set The purlin bicycle beam being placed on the inside of structural frames trestle, sliding rail is provided with the bicycle beam of purlin, and the pulley mechanism matches with sliding rail Close.
- 3. the sliding platform according to claim 2 for being used to install high-altitude wire frame steel construction, it is characterised in that:The pulley Mechanism, which has, is fixed on downward opening semi-shaped turning rolls below truss end, the turning rolls lateral opening, in hole Inserted with roller shaft, roller shaft falls on sliding rail, and the turning rolls both sides are provided with two pairs of regulation bolts, for dividing Sliding rail is not propped up from both sides, realizes that the regulation of angle and truss are determined on sliding rail between truss and sliding rail Position.
- 4. the sliding platform according to claim 1 for being used to install high-altitude wire frame steel construction, it is characterised in that:Truss it is upper Side is disposed with support frame mounting seat corresponding with high-altitude wire frame ball node along truss longitudinal direction.
- 5. the sliding platform according to claim 1 for being used to install high-altitude wire frame steel construction, it is characterised in that:The truss Top is equipped with pedal.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720416244.7U CN206753085U (en) | 2017-04-20 | 2017-04-20 | A kind of sliding platform for being used to install high-altitude wire frame steel construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720416244.7U CN206753085U (en) | 2017-04-20 | 2017-04-20 | A kind of sliding platform for being used to install high-altitude wire frame steel construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206753085U true CN206753085U (en) | 2017-12-15 |
Family
ID=60614341
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720416244.7U Expired - Fee Related CN206753085U (en) | 2017-04-20 | 2017-04-20 | A kind of sliding platform for being used to install high-altitude wire frame steel construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206753085U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110306676A (en) * | 2019-07-04 | 2019-10-08 | 广西天正钢结构有限公司 | A kind of steel truss arch stand and its construction method |
CN113882643A (en) * | 2021-09-28 | 2022-01-04 | 中建八局第一建设有限公司 | Mounting device for welded ball steel net rack |
CN114737774A (en) * | 2022-04-11 | 2022-07-12 | 中国二十冶集团有限公司 | Synchronous sliding method for steel structure roof jig frame |
CN116378432A (en) * | 2023-05-23 | 2023-07-04 | 北京城建集团有限责任公司 | A high-position sliding construction and track setting method of a flat grid frame |
-
2017
- 2017-04-20 CN CN201720416244.7U patent/CN206753085U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110306676A (en) * | 2019-07-04 | 2019-10-08 | 广西天正钢结构有限公司 | A kind of steel truss arch stand and its construction method |
CN113882643A (en) * | 2021-09-28 | 2022-01-04 | 中建八局第一建设有限公司 | Mounting device for welded ball steel net rack |
CN114737774A (en) * | 2022-04-11 | 2022-07-12 | 中国二十冶集团有限公司 | Synchronous sliding method for steel structure roof jig frame |
CN116378432A (en) * | 2023-05-23 | 2023-07-04 | 北京城建集团有限责任公司 | A high-position sliding construction and track setting method of a flat grid frame |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208430687U (en) | Self-anchored type suspended-cable structure support construction and system | |
CN104929373B (en) | Large span Square Steel Tubes Truss and its accumulation slippage construction method | |
CN203188589U (en) | Rigid-frame continuous beam zero block construction bracket supporting system | |
CN206753085U (en) | A kind of sliding platform for being used to install high-altitude wire frame steel construction | |
CN107816223B (en) | Safe and stable type station canopy station house and installation method thereof | |
CN103866986B (en) | Long span variable cross-section bolted spherical node net shell mounting method | |
CN107060098A (en) | A kind of high-altitude wire frame Steel Structure Installation method based on sliding platform | |
CN109057365A (en) | A kind of Node In Large-span Pipe Truss roof truss air translation installation method | |
CN106760529A (en) | Roof system steel truss slipping and assembling operation platform and installation method | |
CN101775896B (en) | Rigid hanging scaffolding for installation of steel roof equipment piping | |
CN204551891U (en) | A kind of Spatial beam string structure and truss combining structure | |
CN206513004U (en) | A kind of movable hanger for being easy to roof inner slab to install | |
CN108412187B (en) | Construction device and construction method for outer frame structure of ultra-high conjoined group tower | |
CN104790644B (en) | Extending and contracting sliding support frame for roof decorative bottom boards | |
CN206319610U (en) | Roof system steel truss slipping and assembling construction platform structure | |
CN203238948U (en) | Hollow ultrahigh formwork profile steel platform | |
CN201635377U (en) | Rigid hanging scaffolding for installation of long-span steel roof equipment piping | |
CN104818675B (en) | Assembling method for steel bar segments | |
CN209538639U (en) | Make track movable Scaffold by oneself | |
CN105625732B (en) | Superelevation overhanging steel structure truss support free construction method | |
CN204418372U (en) | The steel beam column venue be made up of arch component space tubular truss | |
CN204325940U (en) | A kind of large span arch bridge non-support cable crane system construction pylon | |
CN204435675U (en) | A kind of lattice salomonica structure | |
CN111379227A (en) | Variable-width platform device for hydraulic creeping formwork for quickly constructing double-limb cable tower and construction method | |
CN202559727U (en) | Load-bearing support structure of template of overhead long-span floor slab of building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |