CN210975806U - High stability road bridge construction is with vibration pile driver - Google Patents
High stability road bridge construction is with vibration pile driver Download PDFInfo
- Publication number
- CN210975806U CN210975806U CN201921524578.1U CN201921524578U CN210975806U CN 210975806 U CN210975806 U CN 210975806U CN 201921524578 U CN201921524578 U CN 201921524578U CN 210975806 U CN210975806 U CN 210975806U
- Authority
- CN
- China
- Prior art keywords
- plate
- displacement
- welding
- welded
- groove
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims description 13
- 238000006073 displacement reaction Methods 0.000 claims abstract description 58
- 238000003466 welding Methods 0.000 claims abstract description 18
- 238000009435 building construction Methods 0.000 abstract description 3
- 238000001125 extrusion Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model belongs to the pile driver field, especially, high stability is vibration pile driver for road bridge building construction, the structure to current pile driver is complicated, complex operation to the efficiency of pile is lower, can not satisfy people's needs problem, now proposes following scheme, and it includes the movable plate, the welding of top one side of movable plate has the riser, and the displacement groove has been seted up to one side of riser, and slidable mounting has the displacement board in the displacement groove, and the welding of the bottom of displacement board has first spring, and the bottom of first spring welds on the bottom inner wall of displacement groove, and the welding of the bottom of displacement board has two contact plates, and bolt fixedly connected with driving motor is passed through to one side of displacement board, and the welding has the pivot on driving motor's the output shaft, and the kerve has been seted up to the bottom of displacement board, has seted up the commentaries on classics hole on the inner wall. The utility model discloses the practicality is good, and the effectual efficiency that improves the pile satisfies people's needs.
Description
Technical Field
The utility model relates to a pile driver technical field especially relates to a high stability road bridge is vibratory pile driver for construction.
Background
The pile driver is often used in road and bridge construction, and the pile driver on the construction site consists of a pile hammer, a pile frame and accessory equipment, and utilizes impact force to drive a pile into underground piling machinery.
The structure of present pile driver is complicated, complex operation to the efficiency of pile is lower, can not satisfy people's needs.
Disclosure of Invention
The utility model aims at solving the structure complicacy that has the pile driver among the prior art, complex operation to the efficiency of pile is lower, can not satisfy people's needs shortcoming, and the high stability road bridge vibration pile driver for construction that proposes.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
A high-stability vibration pile driver for road and bridge building construction comprises a movable plate, wherein a vertical plate is welded on one side of the top of the movable plate, a displacement groove is formed in one side of the vertical plate, a displacement plate is arranged in the displacement groove in a sliding mode, a first spring is welded at the bottom of the displacement plate, the bottom end of the first spring is welded on the inner wall of the bottom of the displacement groove, two contact plates are welded at the bottom of the displacement plate, a driving motor is fixedly connected to one side of the displacement plate through a bolt, a rotating shaft is welded on an output shaft of the driving motor, a bottom groove is formed in the bottom of the displacement plate, a rotating hole is formed in the inner wall of one side of the bottom groove, the rotating shaft is rotatably installed in the rotating hole, a cam is fixedly sleeved on the outer side of the rotating shaft, a sliding groove is formed in the inner wall of the other side of, the cam contacts with the top of clamp plate, and the opposite side welding of displacement board has a plurality of first set squares, and slidable mounting has the connecting plate in the displacement groove, and the one side welding that the connecting plate is close to the displacement board has a plurality of second set squares, and the second set square contacts with the inclined plane of first set square, and the welding has a plurality of second springs between one side inner wall of connecting plate and displacement groove.
Preferably, one side of the connecting plate is welded with a pulling plate, the inner wall of one side of the displacement groove is provided with a pulling hole, the pulling plate is slidably installed in the pulling hole, one side of the pulling plate is welded with an operating plate, and the operating plate is in contact with the vertical plate.
Preferably, the bottom of the moving plate is fixedly connected with four universal wheels through bolts, so that the moving plate can move conveniently.
Preferably, a pile body is arranged on one side of the moving plate, the bottom of the contact plate is in contact with the top of the pile body, and the bottom of the pressing plate is in contact with the top of the pile body.
Preferably, the same inclined plate is welded between the moving plate and the vertical plate, so that the strength is improved.
Preferably, the number of the second springs is six, so that the connecting plate can be restored to the original position.
In the utility model, a high stability road bridge vibration pile driver for building construction, place the pile body in the position of waiting to pile, pulling the operation panel, remove the fixed to the displacement board, then pull the displacement board, make the bottom of contact plate and clamp plate all contact with the pile body, start driving motor, the pivot drives the cam and rotates, the cam drives the clamp plate and moves, the clamp plate drives the slide plate and moves, under the continuous rotation of cam, make the clamp plate move back and forth in the vertical direction, make the pile body move down, at this moment, the first spring drives the displacement board to move because of self elasticity, the displacement board drives the first set square to move, the first set square drives the second set square to move, until the first set square contacts with the inclined plane of the adjacent second set square, make the displacement board move down, at this moment, the displacement board can not move upwards, so operate, until accomplishing the pile, easy operation, the efficient of pile.
The utility model discloses the practicality is good, and the effectual efficiency that improves the pile satisfies people's needs.
Drawings
Fig. 1 is a schematic structural view of a vibration pile driver for high-stability road and bridge construction provided by the utility model;
Fig. 2 is a schematic structural view of a part a of the vibration pile driver for high-stability road and bridge construction according to the present invention;
Fig. 3 is the utility model provides a high stability road bridge construction is with part B's schematic structure diagram of vibratory pile driver.
In the figure: 1. moving the plate; 2. a vertical plate; 3. a sloping plate; 4. a displacement plate; 5. a first spring; 6. a contact plate; 7. a drive motor; 8. pressing a plate; 9. a rotating shaft; 10. a cam; 11. a first set square; 12. a connecting plate; 13. a second set square; 14. a second spring.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-3, a high stability road bridge construction vibration pile driver, including a movable plate 1, a vertical plate 2 welded on one side of the top of the movable plate 1, a displacement slot formed on one side of the vertical plate 2, a displacement plate 4 slidably mounted in the displacement slot, a first spring 5 welded on the bottom of the displacement plate 4, the bottom end of the first spring 5 welded on the inner wall of the bottom of the displacement slot, two contact plates 6 welded on the bottom of the displacement plate 4, a driving motor 7 fixedly connected to one side of the displacement plate 4 through a bolt, a rotating shaft 9 welded on the output shaft of the driving motor 7, a bottom slot formed on the bottom of the displacement plate 4, a rotating hole formed on the inner wall of one side of the bottom slot, the rotating shaft 9 rotatably mounted in the rotating hole, a cam 10 fixedly sleeved on the outer side of the rotating shaft 9, a sliding slot formed on the inner wall of the other, the bottom welding of slide has the third spring, the bottom of third spring welds on the bottom inner wall of spout, cam 10 contacts with the top of clamp plate 8, the opposite side welding of displacement board 4 has a plurality of first set squares 11, sliding mounting has connecting plate 12 in the displacement groove, one side welding that connecting plate 12 is close to displacement board 4 has a plurality of second set squares 13, second set square 13 contacts with the inclined plane of first set square 11, the welding has a plurality of second springs 14 between one side inner wall of connecting plate 12 and displacement groove.
In this embodiment, one side welding of connecting plate 12 has the arm-tie, has seted up the trompil on one side inner wall of displacement groove, and arm-tie slidable mounting has the operation panel in the trompil, and the operation panel contacts with riser 2 in one side welding of arm-tie.
In this embodiment, four universal wheels are fixedly connected to the bottom of the moving plate 1 through bolts, so that the moving plate 1 can move conveniently.
In this embodiment, a pile is disposed on one side of the moving plate 1, the bottom of the contact plate 6 contacts with the top of the pile, and the bottom of the pressing plate 8 contacts with the top of the pile.
In this embodiment, the same inclined plate 3 is welded between the moving plate 1 and the vertical plate 2, so that the strength is improved.
In this embodiment, the number of the second springs 14 is six, which enables the connecting plate 12 to return to the original position.
In the utility model, when in use, the pile body is placed at the position to be piled, the operation board is pulled to remove the fixation of the displacement board 4, then the displacement board 4 is pulled to ensure that the contact board 6 and the bottom of the pressure board 8 are both contacted with the pile body, the operation board is loosened to ensure that the first triangle board 11 is contacted with the inclined plane of the second triangle board 13, the driving motor 7 is started, the driving motor 7 is controlled by the control switch, the driving motor 7 is powered by the storage battery, the output shaft of the driving motor 7 drives the rotating shaft 9 to rotate, the rotating shaft 9 drives the cam 10 to rotate, the cam 10 extrudes the pressure board 8 to drive the pressure board 8 to move, the pressure board 8 drives the sliding board to move, the sliding board extrudes the third spring, the pressure board 8 moves back and forth in the vertical direction under the continuous rotation of the cam 10, so that the pile body moves down, at the moment, the first spring 5 drives, the elasticity of first spring 5 is greater than the elasticity of second spring 14, displacement plate 4 drives first set square 11 and removes, first set square 11 extrusion second set square 13 drives second set square 13 and removes, second set square 13 extrusion second spring 14, until first set square 11 contacts with the inclined plane of adjacent second set square 13, make displacement plate 4 when moving down, displacement plate 4 can not upwards remove this moment, so operate, until accomplishing the pile, and easy operation, the efficiency of pile is high.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.
Claims (3)
1. The utility model provides a high stability road bridge vibration pile driver for construction, including movable plate (1), a serial communication port, the welding of top one side of movable plate (1) has riser (2), the displacement groove has been seted up to one side of riser (2), sliding mounting has displacement board (4) in the displacement groove, the welding of the bottom of displacement board (4) has first spring (5), the bottom of first spring (5) welds on the bottom inner wall of displacement groove, the welding of the bottom of displacement board (4) has two contact plates (6), one side of displacement board (4) is through bolt fixedly connected with driving motor (7), the welding has pivot (9) on the output shaft of driving motor (7), the kerve has been seted up to the bottom of displacement board (4), seted up the trompil on the inner wall of one side of kerve, pivot (9) rotate and install in the trompil, the outside fixed cover of pivot (9) is equipped with cam (10, a sliding groove is formed in the inner wall of the other side of the bottom groove, a sliding plate is arranged in the sliding groove in a sliding mode, a pressing plate (8) is welded on one side of the sliding plate, a third spring is welded at the bottom of the sliding plate, the bottom end of the third spring is welded on the inner wall of the bottom of the sliding groove, a cam (10) is in contact with the top of the pressing plate (8), a plurality of first triangular plates (11) are welded on the other side of the displacement plate (4), a connecting plate (12) is arranged in the displacement groove in a sliding mode, a plurality of second triangular plates (13) are welded on one side, close to the displacement plate (4), of the connecting plate (12), the second triangular plates (13) are in contact with the inclined surfaces of the first triangular plates (11), a plurality of second springs (14) are welded between the connecting plate (12) and the inner wall of one side of the displacement groove, one side welding of arm-tie has the operation panel, and the operation panel contacts with riser (2), four universal wheels of bolt fixedly connected with are passed through to the bottom of movable plate (1), one side of movable plate (1) is equipped with the pile body, and the bottom of contact plate (6) contacts with the top of pile body, and the bottom of clamp plate (8) contacts with the top of pile body.
2. The vibrating pile driver for high-stability road and bridge construction according to claim 1, wherein the same inclined plate (3) is welded between the moving plate (1) and the vertical plate (2).
3. A high stability road and bridge construction vibration pile driver as claimed in claim 1, characterized in that the number of the second spring (14) is six.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921524578.1U CN210975806U (en) | 2019-09-15 | 2019-09-15 | High stability road bridge construction is with vibration pile driver |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921524578.1U CN210975806U (en) | 2019-09-15 | 2019-09-15 | High stability road bridge construction is with vibration pile driver |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210975806U true CN210975806U (en) | 2020-07-10 |
Family
ID=71447141
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921524578.1U Expired - Fee Related CN210975806U (en) | 2019-09-15 | 2019-09-15 | High stability road bridge construction is with vibration pile driver |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210975806U (en) |
-
2019
- 2019-09-15 CN CN201921524578.1U patent/CN210975806U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN200978525Y (en) | Hydraulic striking hammer | |
CN202170659U (en) | Double layer parking rack | |
CN205615385U (en) | Construction is with small -size short distance heavy object loading and transporting device | |
CN210975806U (en) | High stability road bridge construction is with vibration pile driver | |
CN109208573A (en) | A kind of movable type double end compacting of subsoil pendulum | |
CN115142414A (en) | Hydraulic pile driver | |
CN202880251U (en) | Mechanical barrel-embracing device | |
CN215441854U (en) | Foundation engineering tamping equipment | |
CN211522976U (en) | Highway construction warning sign with snow protection function | |
CN202073097U (en) | Portable internal combustion type piling machine | |
CN210858595U (en) | Coal mine drilling machine supporting device | |
CN115288133A (en) | Municipal administration hydraulic engineering is with surface of water pile device | |
CN211710839U (en) | Mine field slope is gone and is prevented falling vehicle connection auxiliary device on way | |
CN211006624U (en) | Foundation engineering tamping equipment | |
CN211438859U (en) | Rock drill feed beam upset frock and feed beam assembly system | |
CN102910402B (en) | Mechanical bin holding device | |
CN207360500U (en) | A kind of bicycle power-assisted device wireless remote control handle | |
CN214993823U (en) | Small-size pile driver is used in highway construction | |
CN217629821U (en) | Rammer for civil engineering | |
CN206091448U (en) | Three -dimensional parking device in ground | |
CN213709477U (en) | Simple structure conveniently removes building rammer compactor | |
CN213199927U (en) | Crawler crane traveling mechanism | |
CN216489110U (en) | High-low voltage integrated prefabricated substation | |
CN110565620A (en) | Foundation engineering tamping equipment | |
CN212154642U (en) | Swift pile device of construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200710 |
|
CF01 | Termination of patent right due to non-payment of annual fee |