CN210922601U - Construction project completion environmental protection inspection device for acceptance - Google Patents

Construction project completion environmental protection inspection device for acceptance Download PDF

Info

Publication number
CN210922601U
CN210922601U CN201922076454.8U CN201922076454U CN210922601U CN 210922601 U CN210922601 U CN 210922601U CN 201922076454 U CN201922076454 U CN 201922076454U CN 210922601 U CN210922601 U CN 210922601U
Authority
CN
China
Prior art keywords
pipe
welded
partition plate
fixedly connected
liquid storage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922076454.8U
Other languages
Chinese (zh)
Inventor
陈达君
黎公铭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hainan Lvyu Environmental Technology Co ltd
Original Assignee
Hainan Lvyu Environmental Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hainan Lvyu Environmental Technology Co ltd filed Critical Hainan Lvyu Environmental Technology Co ltd
Priority to CN201922076454.8U priority Critical patent/CN210922601U/en
Application granted granted Critical
Publication of CN210922601U publication Critical patent/CN210922601U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Testing Resistance To Weather, Investigating Materials By Mechanical Methods (AREA)

Abstract

The utility model discloses a construction project completion environmental protection inspection is accepted and is used verifying attachment relates to building acceptance technical field, when accepting the project in to current building construction, relies on the problem that there is the error easily of manually operation check-out set, the following scheme is proposed now, including placing the board, place board top fixedly connected with install bin, the inner wall welding of install bin has the baffle, the top left side of baffle is equipped with the air pump, fixedly connected with runs through the fixed pipe of baffle on the air pump, the below of baffle is equipped with the stock solution pipe with the bottom inner wall fixed connection of install bin, the inside cover of stock solution pipe is equipped with the left side inner wall welded gag lever post with the install bin, the right side of gag lever post is equipped with the inside sealing plug that is located the stock solution pipe, and the right-hand member top of stock solution pipe is equipped with the passage with baffle welded. The utility model discloses do not need manual debugging equipment to detect, reduce the error that the people was for leading to, withdraw liquid when out of work moreover, make things convenient for the transport of equipment.

Description

Construction project completion environmental protection inspection device for acceptance
Technical Field
The utility model relates to a construction acceptance technical field especially relates to a construction project completes environmental protection and accepts and uses verifying attachment.
Background
In the building construction, the project of construction needs to be inspected, and the project that needs the inspection when inspecting has a lot, for example needs the plane or the roughness of inspection building, and traditional inspection mode is more crude, and need manual laying equipment to detect when the operation, so not only the efficiency is lower, and there is the error in the result of detection, for this reason we propose a construction project and mend environmental protection inspection device for acceptance.
SUMMERY OF THE UTILITY MODEL
The utility model provides a pair of construction project completion environmental protection is tested and is received and use verifying attachment has solved when receiving the project among the current building construction, relies on the problem that there is the error easily in manually operation check out test set.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
a testing device for environment-friendly acceptance check of construction project completion comprises a placing plate, wherein an installation box is fixedly connected to the top of the placing plate, a partition plate is welded to the inner wall of the installation box, an air pump is arranged on the left side of the top of the partition plate, a fixing pipe penetrating through the partition plate is fixedly connected to the air pump, a liquid storage pipe fixedly connected with the inner wall of the bottom of the installation box is arranged below the partition plate, a limiting rod welded to the inner wall of the left side of the installation box is sleeved inside the liquid storage pipe, a sealing plug located inside the liquid storage pipe is arranged on the right side of the limiting rod, a guide pipe welded to the partition plate is arranged above the right end of the liquid storage pipe, one end, away from the partition plate, of the guide pipe is welded to the inner wall of the installation box, an installation pipe is welded to the outer wall of the right side of the installation box, a piston is, the top fixedly connected with laser lamp of bracing piece, the top welding of installation pipe has two layer boards.
Preferably, a first through hole and a second through hole are formed in one side, close to each other, of the installation box and the installation pipe, the second through hole is located above the first through hole, and the second through hole is communicated with the material guide pipe.
Preferably, the partition plate is provided with a mounting hole, and the right end of the liquid storage pipe is fixedly sleeved in the mounting hole.
Preferably, two supporting blocks welded with the placing plate are arranged below the piston, an arc-shaped groove is formed in the top of the supporting plate along the length direction of the supporting plate, and a sponge pad is bonded inside the arc-shaped groove.
Preferably, an air inlet is formed in the left side of the wall of the top box of the installation box, the bottom of the air pump is connected with a fixed seat through a bolt, and the bottom of the fixed seat is welded with the partition plate.
Preferably, the right side of air pump is equipped with the battery with baffle fixed connection, the bottom welding of liquid storage pipe has the connecting block.
Preferably, the bottom of the placing plate is connected with four universal wheels through bolts, and two push rods are welded on the left side of the top of the placing plate.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses an installation air pump, install bin, baffle, liquid storage pipe, sealing plug, gag lever post, installation pipe, piston, floating ball, bracing piece and laser lamp isotructure, wherein the air pump increases the decompression to the baffle below, conveniently changes like this that the sealing plug moves back and forth in the liquid storage pipe, thereby can control the liquid in the liquid storage pipe and flow into in the installation pipe, the piston can shift up simultaneously, and live the second through-hole is sealed, can make like this liquid float the ball, thereby make the laser lamp keep the level to detect;
2. the utility model can control the discharge and the collection of the liquid by installing the structures of the liquid storage pipe, the sealing plug, the piston and the like and adjusting the movement of the piston and the sealing plug, thereby being convenient for carrying and moving the equipment;
to sum up, the device is novel in design, and easy operation does not need manual debugging equipment to detect, reduces the error that artificially leads to, withdraws liquid when out of work moreover, makes things convenient for the transport of equipment.
Drawings
Fig. 1 is a schematic view of a piston of the testing device for environment protection acceptance of construction project completion in a rear elevation structure, provided by the utility model;
fig. 2 is a schematic view of the piston of the testing device for environment protection acceptance of construction project completion in front elevation structure provided by the utility model;
fig. 3 is the utility model provides a construction project completes environmental protection and accepts and uses verifying attachment's layer board side view structure schematic.
In the figure: the device comprises a placing plate 1, an installing box 2, a partition plate 3, an air pump 4, a storage battery 5, a material guide pipe 6, a fixing pipe 7, a liquid storage pipe 8, a limiting rod 9, a piston 10, a supporting plate 11, a supporting rod 12, a floating ball 13, a laser lamp 14, a push rod 15, a sealing plug 16, a supporting block 17 and an installing pipe 18.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-3, a testing device for environment-friendly acceptance check of construction project completion comprises a placing plate 1, an installation box 2 is fixedly connected to the top of the placing plate 1, a partition plate 3 is welded to the inner wall of the installation box 2, an air pump 4 is arranged on the left side of the top of the partition plate 3, a fixing pipe 7 penetrating through the partition plate 3 is fixedly connected to the air pump 4, a liquid storage pipe 8 fixedly connected to the inner wall of the bottom of the installation box 2 is arranged below the partition plate 3, a limiting rod 9 welded to the inner wall of the left side of the installation box 2 is sleeved inside the liquid storage pipe 8, a sealing plug 16 positioned inside the liquid storage pipe 8 is arranged on the right side of the limiting rod 9, a material guide pipe 6 welded to the partition plate 3 is arranged above the right end of the liquid storage pipe 8, one end, away from the partition plate 3, of the material guide pipe 6 is welded to the inner wall of, a floating ball 13 is arranged above the piston 10, a supporting rod 12 is fixedly connected to the top of the floating ball 13, a laser lamp 14 is fixedly connected to the top end of the supporting rod 12, and two supporting plates 11 are welded to the top of the installation tube 18.
In this embodiment, a first through hole and a second through hole are formed on the side, close to each other, of the mounting box 2 and the mounting tube 18, the second through hole is located above the first through hole, and the second through hole is communicated with the material guiding tube 6.
In this embodiment, the partition plate 3 is provided with a mounting hole, and the right end of the liquid storage pipe 8 is fixedly sleeved in the mounting hole.
In this embodiment, the lower side of the piston 10 is provided with two supporting blocks 17 welded to the placing plate 1, the top of the supporting plate 11 is provided with an arc-shaped groove along the length direction thereof, and the sponge pad is bonded inside the arc-shaped groove.
In this embodiment, the inlet port has been seted up in the left side of the top tank wall of install bin 2, and there is the fixing base bottom of air pump 4 through bolted connection, and the bottom and the 3 welding of baffle of fixing base.
In this embodiment, the right side of air pump 4 is equipped with the battery 5 with 3 fixed connection of baffle, and the bottom welding of liquid storage pipe 8 has the connecting block.
In this embodiment, the bottom of the placing plate 1 is connected with four universal wheels through bolts, and the left side of the top of the placing plate 1 is welded with two push rods 15.
The working principle is that firstly, clear water is stored in the liquid storage pipe 8, when the horizontal condition of a building needs to be detected, the air pump 4 is started, the air pump 4 increases and decreases the lower part of the partition plate 3, the air pressure increase below the partition plate 3 can push the sealing plug 16 to move in the fixed pipe 8, the sealing plug 16 can push the clear water to move, the clear water enters the installation pipe 18 from the second through hole, the air pressure increase below the partition plate 3 also drives the air pressure increase below the piston 10, so that the piston 10 also moves upwards, when the second through hole is completely blocked by the piston 10, most of the clear water enters the installation pipe 18, the floating ball 13 in the installation pipe 18 floats, so that the support rod 12 drives the laser lamp 14 to move upwards, the floating ball 13 can ensure that the laser lamp 14 is always kept horizontal, errors caused by manual operation are worried about, and similarly, when the air pump 4 pumps air, the air pressure in the space below the partition plate 3 can be, can make piston 10 move down like this, piston 10 moves down and makes the second through-hole open to make the clear water flow the liquid storage pipe 8 again in deposit, whole device is through the removal of adjusting piston 10 and sealing plug 16, can control the discharge of liquid like this and pack up, thereby conveniently remove equipment transport, do not need manual debugging equipment to detect, reduce the error that artificially leads to, withdraw liquid when out of work moreover, make things convenient for the transport of equipment.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (7)

1. The inspection device for construction project completion environment-friendly acceptance inspection comprises a placement plate (1) and is characterized in that an installation box (2) is fixedly connected to the top of the placement plate (1), a partition plate (3) is welded to the inner wall of the installation box (2), an air pump (4) is arranged on the left side of the top of the partition plate (3), a fixed pipe (7) penetrating through the partition plate (3) is fixedly connected to the air pump (4), a liquid storage pipe (8) fixedly connected with the inner wall of the bottom of the installation box (2) is arranged below the partition plate (3), a limiting rod (9) welded to the inner wall of the left side of the installation box (2) is sleeved inside the liquid storage pipe (8), a sealing plug (16) located inside the liquid storage pipe (8) is arranged on the right side of the limiting rod (9), a guide pipe (6) welded to the partition plate (3) is arranged above the right end of the liquid storage pipe, and baffle (3) was kept away from in passage (6) one end and the inner wall welding of install bin (2), the right side outer wall welding of install bin (2) has installation pipe (18), the inside movable sleeve of installation pipe (18) is equipped with piston (10), the top of piston (10) is equipped with floats ball (13), the top fixedly connected with bracing piece (12) of floating ball (13), the top fixedly connected with laser lamp (14) of bracing piece (12), the top welding of installation pipe (18) has two layer boards (11).
2. The testing device for as-built environmental acceptance inspection of construction projects as claimed in claim 1, wherein the mounting box (2) and the mounting tube (18) are provided with a first through hole and a second through hole at the side close to each other, the second through hole is positioned above the first through hole, and the second through hole is communicated with the material guide tube (6).
3. The testing device for environment-friendly acceptance check as claimed in claim 1, wherein the partition plate (3) is provided with mounting holes, and the right end of the liquid storage pipe (8) is fixedly sleeved in the mounting holes.
4. The testing device for environment-friendly acceptance of construction project completion according to claim 1, characterized in that two supporting blocks (17) welded with the placing plate (1) are arranged below the piston (10), the top of the supporting plate (11) is provided with an arc-shaped groove along the length direction, and a sponge pad is bonded inside the arc-shaped groove.
5. The testing device for environment-friendly acceptance of construction project completion as claimed in claim 1, wherein an air inlet hole is formed in the left side of the top box wall of the installation box (2), a fixed seat is connected to the bottom of the air pump (4) through a bolt, and the bottom of the fixed seat is welded with the partition plate (3).
6. The testing device for environment protection acceptance during construction project completion according to claim 1, wherein the right side of the air pump (4) is provided with a storage battery (5) fixedly connected with the partition plate (3), and the bottom of the liquid storage pipe (8) is welded with a connecting block.
7. The testing device for as-built environmental acceptance of construction projects as claimed in claim 1, wherein four universal wheels are connected to the bottom of the placing plate (1) through bolts, and two push rods (15) are welded to the left side of the top of the placing plate (1).
CN201922076454.8U 2019-11-27 2019-11-27 Construction project completion environmental protection inspection device for acceptance Active CN210922601U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922076454.8U CN210922601U (en) 2019-11-27 2019-11-27 Construction project completion environmental protection inspection device for acceptance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922076454.8U CN210922601U (en) 2019-11-27 2019-11-27 Construction project completion environmental protection inspection device for acceptance

Publications (1)

Publication Number Publication Date
CN210922601U true CN210922601U (en) 2020-07-03

Family

ID=71348575

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922076454.8U Active CN210922601U (en) 2019-11-27 2019-11-27 Construction project completion environmental protection inspection device for acceptance

Country Status (1)

Country Link
CN (1) CN210922601U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117268353A (en) * 2023-11-22 2023-12-22 山西六建集团有限公司 Engineering perpendicularity detection equipment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117268353A (en) * 2023-11-22 2023-12-22 山西六建集团有限公司 Engineering perpendicularity detection equipment
CN117268353B (en) * 2023-11-22 2024-02-09 山西六建集团有限公司 Engineering perpendicularity detection equipment

Similar Documents

Publication Publication Date Title
WO2021174449A1 (en) Water quality sampling device for environmental protection technology development
CN201553157U (en) Storage tank plate-type propellant management device
JPH0255928A (en) Leak inspector
CN210922601U (en) Construction project completion environmental protection inspection device for acceptance
CN201247130Y (en) Case type tightness checkout tank for ship
CN205594018U (en) Sewage automatic checkout device
CN213336367U (en) Floating island type water level monitoring system
CN104330472A (en) Pipeline traction testing device and pipeline traction testing method
CN213180586U (en) Pipeline is suppressed and is leaked hunting device
CN107237309B (en) Truss pile leg
CN205783666U (en) Air-conditioner
CN214408226U (en) Water nuclear pollution detection device
CN213209602U (en) Underground water undisturbed well washing sampling device for environment detection
CN212483004U (en) Water quality sampling equipment for underground water environment detection
CN110118864B (en) High-efficient environmental protection unmanned on duty surface water environmental quality monitoring station
CN210240746U (en) Exhaust valve for pressure pipeline
CN209131915U (en) A kind of water purification fore filter air tightness detection machine
CN219863255U (en) Floating oil detection and collection device
CN218035172U (en) Special test system for water supply equipment
CN214471180U (en) Novel inspection and test equipment for dirt box of railway vehicle
CN202013268U (en) Leakage detection device for oil tank of excavating machine
CN213274482U (en) Water level testing device for pipeline water closing test
CN213432743U (en) Underground hidden balance beam
CN214096999U (en) Auxiliary device for fatigue testing machine
CN208705223U (en) Water pollution detection device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant