CN210916822U - Shield constructs uses novel sleeper - Google Patents
Shield constructs uses novel sleeper Download PDFInfo
- Publication number
- CN210916822U CN210916822U CN201921129308.0U CN201921129308U CN210916822U CN 210916822 U CN210916822 U CN 210916822U CN 201921129308 U CN201921129308 U CN 201921129308U CN 210916822 U CN210916822 U CN 210916822U
- Authority
- CN
- China
- Prior art keywords
- trolley
- supporting platform
- shield
- supporting
- supporting surface
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 241001669679 Eleotris Species 0.000 title claims abstract description 28
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 24
- 239000010959 steel Substances 0.000 claims abstract description 24
- 238000003466 welding Methods 0.000 claims abstract description 12
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims abstract description 4
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 4
- 230000005641 tunneling Effects 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 8
- 238000000034 method Methods 0.000 abstract description 8
- 238000009434 installation Methods 0.000 abstract description 2
- 238000005516 engineering process Methods 0.000 description 2
- 125000004122 cyclic group Chemical group 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Landscapes
- Shielding Devices Or Components To Electric Or Magnetic Fields (AREA)
Abstract
The utility model relates to a supporting platform truck track sleeper technical field behind shield tunnel construction storage battery car, the shield constructs the machine specifically is a novel sleeper is used to the shield structure. A novel sleeper for a shield is formed by welding a trolley supporting platform and a fixed connecting section, wherein the trolley supporting platform is formed by a supporting surface and a side surface perpendicular to the supporting surface, and the supporting surface and the side surface are formed by vertically welding two steel plates with the same thickness; the bottom of the supporting surface of the trolley supporting platform is welded with a triangular reinforcing rib, and two sections of reinforcing steel bars are vertically welded on the central axis of the surface of the supporting surface; the fixed connection section is 12-type I-shaped steel, the fixed connection section is welded with the side face of the trolley supporting platform, and the welding included angle is 95-100 degrees. The utility model provides a pair of shield constructs uses novel sleeper, its simple structure, installation aspect, operate steadily, improved the safety and stability nature. The problem that the trolley is derailed due to collision between the battery car and the trolley possibly caused in the duct piece assembling process is effectively solved.
Description
Technical Field
The utility model relates to a supporting platform truck track sleeper technical field behind shield tunnel construction storage battery car, the shield constructs the machine specifically is a novel sleeper is used to the shield structure.
Background
In the past decades, the technology for developing underground space by tunneling in China has been established, but is continuously perfected. In general, the shield method has wide application range and prospect. At the present stage, large and medium-sized cities build subways or underground pipelines and use a shield technology.
The laying of the shield sleeper is particularly important on the premise that the requirement for the construction period is short and the safety performance is guaranteed to be large. The sleeper in the past passes through the bolt fastening on the section of jurisdiction, because at the section of jurisdiction in-process of assembling, the sleeper produces the rotation easily and leads to storage battery car and platform truck collision to make the platform truck derail, and fixing bolt's construction volume is also great moreover.
SUMMERY OF THE UTILITY MODEL
The above-mentioned defect to prior art, the utility model provides a pair of shield constructs uses novel sleeper has guaranteed the safe distance between platform truck and the storage battery car, effectively solves the section of jurisdiction and assembles the problem that the in-process probably leads to storage battery car and platform truck collision messenger platform truck derail, has not only improved the efficiency of construction, has still effectively ensured construction safety.
In order to achieve the above object, the utility model provides a following technical scheme:
a novel sleeper for a shield is formed by welding a trolley supporting platform and a fixed connecting section, wherein the trolley supporting platform is formed by a supporting surface and a side surface perpendicular to the supporting surface, and the supporting surface and the side surface are formed by vertically welding two steel plates with the same thickness; the bottom of the supporting surface of the trolley supporting platform is welded with a triangular reinforcing rib, and two sections of reinforcing steel bars are vertically welded on the central axis of the surface of the supporting surface; the fixed connection section is 12 type I-shaped steel, and the fixed connection section is welded with the side face of the trolley supporting platform.
The thickness of the supporting surface of the trolley supporting platform and the thickness of the steel plate on the side surface are 1 cm.
The height of each two sections of steel bars on the supporting surface of the trolley supporting platform is 6.5cm, the distance between each two sections of steel bars is 12cm, and the distance between each two sections of steel bars and each end of the trolley supporting platform is 5.3 cm.
And the welding included angle between the fixed connecting section and the side surface of the trolley supporting platform is 95-100 degrees.
The utility model has the advantages that: the novel sleeper for the shield has simple structure, convenient installation and stable operation, and improves the safety and stability; the safety distance between the trolley and the battery car is ensured, and the problem that the battery car and the trolley collide to cause the trolley to derail in the duct piece assembling process is effectively solved; the novel sleeper is laid without a pressing plate and without screwing bolts, and is convenient to install and dismantle, so that the construction efficiency is improved, and the construction safety is effectively guaranteed.
For a better understanding of the features and technical content of the present invention, reference should be made to the following detailed description of the present invention and accompanying drawings, which are provided for the purpose of illustration and description and are not intended to limit the present invention.
Drawings
The technical solution and other advantages of the present invention will become apparent from the following detailed description of the embodiments of the present invention with reference to the accompanying drawings.
Fig. 1 is the structural schematic diagram of the novel sleeper for the shield of the utility model.
Detailed Description
To further illustrate the technical means and effects of the present invention, the following detailed description is given with reference to the preferred embodiments of the present invention and the accompanying drawings.
Referring to fig. 1, a novel sleeper for a shield is formed by welding a trolley supporting platform and a fixed connecting section 5, wherein the trolley supporting platform is formed by a supporting surface 1 and a side surface 2 perpendicular to the supporting surface, and the supporting surface 1 and the side surface 2 are formed by vertically welding two steel plates with the same thickness; the bottom of a supporting surface 1 of the trolley supporting platform is welded with a triangular reinforcing rib 3, and two sections of reinforcing steel bars 4 are vertically welded on a central axis of the surface of the supporting surface; the fixed connection section 5 is 12 type I-shaped steel, and the fixed connection section 5 is welded with the side face 2 of the trolley supporting platform.
Further, the thickness of the steel plate of the supporting surface 1 and the side surface 2 of the trolley supporting platform is 1 cm.
Further, the height of each two sections of steel bars 4 on the supporting surface 1 of the trolley supporting platform is 6.5cm, the distance between each two sections of steel bars 4 is 12cm, and the distance between each two sections of steel bars 4 and the two ends of the trolley supporting platform is 5.3 cm.
Furthermore, the welding included angle between the fixed connecting section 5 and the side face 2 of the trolley supporting platform is 95-100 degrees.
The using method comprises the following steps: the welded novel sleeper is installed on a designated position, and the fixed connecting section is clamped on the segment hoisting protrusion to lean against the sleeper of the battery car, so that the novel sleeper is formed into a whole. The steel rail is laid between two steel bars of the supporting surface of the trolley supporting platform. In order to ensure the flatness of the steel rail after the novel sleeper is installed, a wedge can be inserted to ensure the straightness and smoothness of the steel rail.
Novel sleeper cyclic utilization: in the process of continuing the shield tunneling, the trolley continues to advance along with the continuous increase of the shield distance, the sleeper at the rear can be detached and placed at the front part of the trolley according to the mounting method, and therefore the sleeper can be recycled.
The above description is only for the specific embodiments of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art can easily think of the changes or substitutions within the technical scope of the present invention, and all should be covered within the protection scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the claims.
Claims (4)
1. The novel sleeper for the shield is characterized by being formed by welding a trolley supporting platform and a fixed connecting section, wherein the trolley supporting platform is formed by a supporting surface and a side surface perpendicular to the supporting surface, and the supporting surface and the side surface are formed by vertically welding two steel plates with the same thickness; the bottom of the supporting surface of the trolley supporting platform is welded with a triangular reinforcing rib, and two sections of reinforcing steel bars are vertically welded on the central axis of the surface of the supporting surface; the fixed connection section is 12 type I-shaped steel, and the fixed connection section is welded with the side face of the trolley supporting platform.
2. The novel sleeper for the shield according to claim 1, wherein the thickness of the steel plate on the supporting surface and the side surface of the trolley supporting platform is 1 cm.
3. The novel sleeper for the shield tunneling machine as claimed in claim 1, wherein the height of the two sections of steel bars on the supporting surface of the trolley supporting platform is 6.5cm, the distance between the two sections of steel bars is 12cm, and the distance from the two sections of steel bars to the two ends of the trolley supporting platform is 5.3 cm.
4. The novel sleeper for the shield according to claim 1, wherein a welding included angle between the fixed connection section and the side surface of the trolley support platform is 95-100 degrees.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921129308.0U CN210916822U (en) | 2019-07-12 | 2019-07-12 | Shield constructs uses novel sleeper |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921129308.0U CN210916822U (en) | 2019-07-12 | 2019-07-12 | Shield constructs uses novel sleeper |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210916822U true CN210916822U (en) | 2020-07-03 |
Family
ID=71361551
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921129308.0U Expired - Fee Related CN210916822U (en) | 2019-07-12 | 2019-07-12 | Shield constructs uses novel sleeper |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210916822U (en) |
-
2019
- 2019-07-12 CN CN201921129308.0U patent/CN210916822U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101787891B (en) | Station-crossing construction method and station-crossing construction device of wheel type mobile foundation | |
CN105369699A (en) | Construction method for dividing sleeper of portable novel shielding tunneling machine backup trailer and accumulator car system | |
CN102174790B (en) | Assembled sleeper for shield construction and construction method thereof | |
CN210105876U (en) | Subway construction tunnel segment support | |
CN210916822U (en) | Shield constructs uses novel sleeper | |
CN204475070U (en) | Portable combined shield machine sleeper | |
CN104562870B (en) | Portable combined shield machine sleeper | |
CN201952686U (en) | Assembled sleeper for shield construction | |
CN211141349U (en) | Track panel well gantry crane foundation fixing structure | |
CN107574727B (en) | Conveniently-installed shield trolley combined sleeper and use method thereof | |
CN215444056U (en) | Long-distance air-propelled station-crossing shield tunneling machine bracket | |
CN107489447B (en) | Temporary track fixing system in tunnel and construction method thereof | |
CN207212401U (en) | Temporary track fixed system in a kind of tunnel | |
CN209836697U (en) | Long steel rail cross-track shifting device | |
CN219637588U (en) | Sleeper device of shield machine trolley and locomotive | |
CN202945544U (en) | Novel ballastless track | |
CN105239470B (en) | Portable independent suspended railway sleeper for subsequent trolley matched with shield tunneling machine | |
CN215856962U (en) | Prefabricated part for tunnel sleeper construction | |
CN207277104U (en) | A kind of easy assembling type shield trolley composite sleeper | |
CN208518665U (en) | A kind of rising device of the rear mating trolley integrally to miss the stop for shield machine | |
CN216894403U (en) | TBM construction track connecting piece, track bracket component and track structure | |
CN213653066U (en) | Light sleeper combination for shield construction | |
CN221277812U (en) | Novel evacuation platform applied to tunnel | |
CN203514765U (en) | Large overhanging frame body supporting structure | |
CN204982562U (en) | Shield constructs construction and uses tie device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200703 |
|
CF01 | Termination of patent right due to non-payment of annual fee |