CN210825123U - Hoisting lug assembly for cold box plate of fractionating tower - Google Patents

Hoisting lug assembly for cold box plate of fractionating tower Download PDF

Info

Publication number
CN210825123U
CN210825123U CN201921636878.9U CN201921636878U CN210825123U CN 210825123 U CN210825123 U CN 210825123U CN 201921636878 U CN201921636878 U CN 201921636878U CN 210825123 U CN210825123 U CN 210825123U
Authority
CN
China
Prior art keywords
lug
cold box
bolt
fractionating tower
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921636878.9U
Other languages
Chinese (zh)
Inventor
张尚成
叶德全
卫红庆
任清雷
吴志伟
韩平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG INDUSTRIAL EQUIPMENT INSTALLATION GROUP CO LTD
Original Assignee
ZHEJIANG INDUSTRIAL EQUIPMENT INSTALLATION GROUP CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG INDUSTRIAL EQUIPMENT INSTALLATION GROUP CO LTD filed Critical ZHEJIANG INDUSTRIAL EQUIPMENT INSTALLATION GROUP CO LTD
Priority to CN201921636878.9U priority Critical patent/CN210825123U/en
Application granted granted Critical
Publication of CN210825123U publication Critical patent/CN210825123U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Separation By Low-Temperature Treatments (AREA)

Abstract

The utility model discloses a fractionating tower cold box plate hoist and mount lug assembly relates to the empty system oxygen trade fractionating tower field that divides of metallurgical chemical industry. At present, fractionating tower cold box board hoist and mount lug adopts the gas cutting to cut the hole at cold box board skeleton hoisting point position, passes through the hole with the lug and is connected with the shackle, has destroyed the integrality of skeleton itself to need drop into gas cutting instrument and professional constructor and carry out the gas welding cutting operation during cold box skeleton is prefabricated, construction cost is high. The utility model discloses a lug, with lug welding lug connecting plate and the reinforced rib plate of an organic whole, pass bolt hole on the cold box skeleton and behind the bolted connection hole that the lug is connected through the bolt, adopt two nut fastenings again. Bolt hole installation lug assembly when utilizing fractionating tower cold box board to install avoids cutting the trompil on the cold box skeleton, has protected the integrality of steel construction, does not need repeated dismantlement rigging during hoist and mount many times, convenient operation, repeatedly usable effectively reduces construction cost.

Description

Hoisting lug assembly for cold box plate of fractionating tower
Technical Field
The utility model relates to a space division system oxygen trade fractionating tower field of metallurgical chemical industry especially relates to fractionating tower cold box board hoist and mount lug assembly.
Background
At present, fractionating tower cold box board hoist and mount lug is before the hoist and mount of cold box steel sheet, adopts the gas cutting to cut the hole in cold box board skeleton hoisting point position, passes through the hole with the lug and is connected with the shackle, need increase a great steel sheet in order to increase the contact surface between lug connecting plate and cold box skeleton simultaneously to reduce the local atress of cutting position, hoist and mount at every turn and all need dismantle the rigging, and increased first section material and cut with the gas material input. In addition, adopt the gas cutting to cut the cold box skeleton, destroyed the integrality of skeleton itself and damaged the paint on steel construction surface, and need drop into gas cutting instrument and professional constructor and carry out the gas welding cutting operation during cold box skeleton prefabrication.
SUMMERY OF THE UTILITY MODEL
The to-be-solved technical problem of the utility model and the technical task who provides are perfect and improve prior art scheme, provide fractionating tower cold box board hoist and mount lug assembly to simplify lug installation operation, reduce construction cost for the purpose. Therefore, the utility model adopts the following technical scheme.
Fractionating tower cold box board hoist and mount lug subassembly, including lug, lug connecting plate, bolt, nut, the lug connect and be fixed in on the lug connecting plate, the lug connecting plate on be equipped with a plurality of bolted connection holes, bolted connection hole position corresponds with the mounting bolt hole position on the cold box skeleton of cold box board, the bolt pass the mounting bolt hole of cold box board and the bolted connection hole of lug connecting plate, fasten through the nut. Lug fixed mounting is realized to the mode of fixing through the bolt to the lug connecting plate, bolt hole when can make full use of fractionating tower cold box board installation, avoided cutting the trompil on the cold box skeleton, the integrality of protection steel construction that can be fine only needs to use monkey wrench or box spanner, does not need the cooperation of professional gas cutting constructor, just can accomplish the installation of lug, does not need repeated dismantlement rigging during hoist and mount many times, and convenient operation can also used repeatedly, effectively reduces construction cost.
As a further improvement and supplement to the above technical solution, the present invention further comprises the following additional technical features.
As a preferable technical means: and flat washers are respectively arranged on the lower side of the mounting bolt hole and the upper side of the bolt connecting hole on the bolt. Through setting up the plain washer, can increase the bearing area at bolt-up position, dispersion pressure prevents to cause the damage to the junction.
As a preferable technical means: the nut adopts double nuts. The double-nut structure can effectively prevent looseness.
As a preferable technical means: and reinforcing rib plates are symmetrically arranged between the lifting lugs and the lifting lug connecting plate. The structural strength can be effectively increased, and the bearing capacity of the lifting lug assembly is improved.
As a preferable technical means: the lifting lugs and the lifting lug connecting plates are connected in a welding mode, and the reinforcing rib plates are connected with the lifting lugs and the lifting lug connecting plates in a welding mode. Adopt welding mode to connect, the wholeness is good, and structural strength is high, simple structure.
Has the advantages that: lug fixed mounting is realized to the mode of fixing through the bolt to the lug connecting plate, bolt hole when can make full use of fractionating tower cold box board installation, avoided cutting the trompil on the cold box skeleton, the integrality of protection steel construction that can be fine only needs to use monkey wrench or box spanner, does not need the cooperation of professional gas cutting constructor, just can accomplish the installation of lug, does not need repeated dismantlement rigging during hoist and mount many times, and convenient operation can also used repeatedly, effectively reduces construction cost.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is the schematic view of the hoisting connection structure of the utility model.
In the figure: 1-lifting lugs; 2-a lifting lug connecting plate; 3-a reinforcing rib plate; 4-a bolt; 5-a nut; 6-flat washer; 7-a cold box framework; 8-cold box plate.
Detailed Description
The technical solution of the present invention will be further described in detail with reference to the accompanying drawings.
As shown in fig. 1-2, fractionating tower cold box plate hoist and mount lug assembly, including lug (1), lug connecting plate 2, bolt 4, nut 5, lug 1 and lug connecting plate 2 welded connection, be equipped with 4 bolt 4 connecting holes on lug connecting plate 2 symmetrically, bolt 4 connecting hole position corresponds with 4 hole positions of construction bolt on the cold box skeleton 7 of cold box plate 8, bolt 4 passes 4 holes of construction bolt of cold box plate 8 and 4 connecting holes of bolt of lug connecting plate 2, fastens through nut 5.
As a further improvement and supplement to the above technical solution, the present invention further comprises the following additional technical features.
In order to increase the bearing area of the fastening part of the bolt 4, a flat washer 6 is respectively arranged on the bolt 4 at the lower side of the mounting bolt 4 hole and at the upper side of the connecting hole of the bolt 4. Through setting up plain washer 6, can increase the bearing area of 4 fastening parts of bolts, dispersion pressure prevents to cause the damage to the junction.
In order to improve the anti-loosening effect of the bolt 4, the nut 5 adopts a double nut 5. The double-nut 5 structure can effectively prevent looseness.
In order to improve the structural strength of the lifting lug 1 assembly, reinforcing ribs 3 are symmetrically welded between the lifting lug 1 and the lifting lug connecting plate 2. The structural strength can be effectively increased, and the bearing capacity of the lifting lug 1 component is improved.
Realize 1 fixed mounting of lug through the mode that bolt 4 fixes lug connecting plate 2, bolt 4 hole when 8 installation of cold box plates of make full use of fractionating tower, cut the trompil on cold box skeleton 7 has been avoided, the integrality of protection steel construction that can be fine, only need use monkey wrench or box spanner, do not need the cooperation of professional gas cutting constructor, just can accomplish the installation of lug 1, do not need repeated dismantlement rigging during hoist and mount many times, and convenient for operation, can also used repeatedly, effectively reduce construction cost.
The above hoisting lug assembly for the cold box plate of the fractionating tower shown in fig. 1-2 is a specific embodiment of the present invention, and it has been demonstrated that the substantial features and the progress of the present invention can be modified according to the actual use requirements, and the same modifications in the aspects of shape, structure, etc. are performed to the hoisting lug assembly, all within the protection scope of the present solution.

Claims (5)

1. Cold boxboard hoist and mount lug subassembly of fractionating tower, its characterized in that: including lug (1), lug connecting plate (2), bolt (4), nut (5), lug (1) connect and be fixed in on lug connecting plate (2), lug connecting plate (2) on be equipped with a plurality of bolt (4) connecting holes, bolt (4) connecting hole position corresponds with mounting bolt (4) hole position on cold box skeleton (7) of cold box board (8), bolt (4) pass mounting bolt (4) hole and the bolt (4) connecting hole of lug connecting plate (2) of cold box board (8), fasten through nut (5).
2. The fractionating tower cold box plate lifting lug assembly according to claim 1, wherein: and a flat washer (6) is respectively arranged on the lower side of the bolt (4) and the upper side of the bolt (4) connecting hole, wherein the lower side of the bolt (4) is positioned in the mounting bolt hole.
3. The fractionating tower cold box plate lifting lug assembly according to claim 1, wherein: the nut (5) adopts double nuts (5).
4. The fractionating tower cold box plate lifting lug assembly according to claim 1, wherein: reinforcing rib plates (3) are symmetrically arranged between the lifting lugs (1) and the lifting lug connecting plates (2).
5. The fractionating tower cold box plate lifting lug assembly according to claim 4, wherein: the lifting lugs (1) are connected with the lifting lug connecting plates (2), and the reinforcing rib plates (3) are connected with the lifting lugs (1) and the lifting lug connecting plates (2) in a welding mode.
CN201921636878.9U 2019-09-27 2019-09-27 Hoisting lug assembly for cold box plate of fractionating tower Active CN210825123U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921636878.9U CN210825123U (en) 2019-09-27 2019-09-27 Hoisting lug assembly for cold box plate of fractionating tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921636878.9U CN210825123U (en) 2019-09-27 2019-09-27 Hoisting lug assembly for cold box plate of fractionating tower

Publications (1)

Publication Number Publication Date
CN210825123U true CN210825123U (en) 2020-06-23

Family

ID=71263925

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921636878.9U Active CN210825123U (en) 2019-09-27 2019-09-27 Hoisting lug assembly for cold box plate of fractionating tower

Country Status (1)

Country Link
CN (1) CN210825123U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112482789A (en) * 2020-11-27 2021-03-12 深圳海龙建筑科技有限公司 Detachable support frame for hoisting large-span prefabricated member and manufacturing technology thereof
CN113428557A (en) * 2021-06-30 2021-09-24 成都飞机工业(集团)有限责任公司 Shifting device and shifting method for flat wallboard part

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112482789A (en) * 2020-11-27 2021-03-12 深圳海龙建筑科技有限公司 Detachable support frame for hoisting large-span prefabricated member and manufacturing technology thereof
CN112482789B (en) * 2020-11-27 2022-03-29 深圳海龙建筑科技有限公司 Detachable support frame for hoisting large-span prefabricated part and manufacturing method thereof
CN113428557A (en) * 2021-06-30 2021-09-24 成都飞机工业(集团)有限责任公司 Shifting device and shifting method for flat wallboard part

Similar Documents

Publication Publication Date Title
CN210825123U (en) Hoisting lug assembly for cold box plate of fractionating tower
CN202439709U (en) Railway wagon center sill
CN201457691U (en) Manhole safety guardrail
CN2926005Y (en) Buckled connector
CN2851632Y (en) Combined type wind power generation tower tube
CN213173791U (en) Assembled landing stage pile cap
CN112196869B (en) Bolt mounting structure for car roof battery
CN214092596U (en) Bolt mounting structure for car roof battery
CN212093167U (en) Anti-tearing vibrating screen
CN203094184U (en) Tank truck frame longitudinal beam structure
CN202935454U (en) Cab fixing structure of mining dump vehicle
CN201800809U (en) Vehicle water tank frame upper beam extending plate structure
CN212685717U (en) Novel auxiliary beam of lorry-mounted crane transport vehicle
CN220615966U (en) Magnesium alloy electric automobile cabin beam
CN213539129U (en) Loader hood and frame bolted connection anti loosening structure
CN211519480U (en) Movable mounting joist for inflating pump
CN219295637U (en) Mounting structure of propeller strut connecting rod of full-circle crane
CN210594897U (en) Size-adjustable multifunctional spindle fixing device for air separation and replacement of gear box
CN110329140A (en) It is used to support the crossbeam of container and the vehicle with it
CN219651075U (en) Lightweight circular arc carriage
CN102060239B (en) Horizontal wheel set for trolleys on multifunctional overhead crane for electrolysis
CN204004045U (en) Be exclusively used in the driving-shaft assembly of electric truck
CN203472994U (en) Mining dump truck platform
CN219175462U (en) Simple steel construction steel platform mounting structure
CN220376203U (en) Combined pin pulling structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant