CN210771269U CN201921726301.7U CN201921726301U CN210771269U CN 210771269 U CN210771269 U CN 210771269U CN 201921726301 U CN201921726301 U CN 201921726301U CN 210771269 U CN210771269 U CN 210771269U
Authority
CN
China
Prior art keywords
chassis
installation
installation piece
bridge construction
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921726301.7U
Other languages
Chinese (zh)
Inventor
李天美
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Loudi Road And Bridge Construction Co ltd
Original Assignee
Hunan Loudi Road And Bridge Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Loudi Road And Bridge Construction Co ltd filed Critical Hunan Loudi Road And Bridge Construction Co ltd
Priority to CN201921726301.7U priority Critical patent/CN210771269U/en
Application granted granted Critical
Publication of CN210771269U publication Critical patent/CN210771269U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a concrete pouring machine fixing base for municipal bridge construction, including supporting the chassis, the four corners that supports the chassis is passed through the screw rod and is rotated and install the installation piece, and nut and installation piece fixed connection are passed through to the screw rod bottom, and installation piece left side has hydraulic cylinder through first bolt fixed mounting, and the through-hole has been seted up in installation piece left side, and hydraulic cylinder's telescopic link runs through the through-hole, and telescopic link bottom fixed mounting has the stabilizer blade, supports the chassis middle part welding and has the bearing block, and the bearing block top is passed through the bearing and is rotated the installation with the. The utility model discloses a set up first level gauge and second level gauge and come to adjust the horizontal installation who supports the chassis according to two sets of level gauge's demonstration, because support chassis top can be installed with the cooperation of combination high pole, the center height of combination high pole, must guarantee that the level that supports the chassis is placed, can prevent generating device and empty the accident.

Description

A concrete placement machine fixing base for municipal bridge construction
Technical Field
The utility model relates to a municipal bridge construction technical field specifically is a concrete pouring machine fixing base for municipal bridge construction.
Background
Concrete is essential building material among the municipal construction, and the concrete is transported through mixing earth tank car, can stir mixing earth in the transportation and prevent that the concrete from solidifying, and present building is all higher, mixes earth through artifical transportation, and efficiency is too slow, and what be most used at present is through the fixed conveyer pipe of combination high-pole. The conveyer pipe inserts and mixes earth tank car, transports the concrete on the high-rise of building through making up the high pole, and it is efficient to transport the concrete.
Carry the unable adjustment base through the vehicle among the prior art and come the high altitude through combination high pole complex device and transport muddy earth, unable adjustment base installation must horizontal installation, because central height when combination high pole extends completely requires the height to unable adjustment base's horizontal installation, otherwise the accident that the device topples over can take place.
In the process of implementing the invention, the inventor finds that at least the following problems in the prior art are not solved: 1. the base horizontal installation of the prior art does not have a precise instrument to judge whether the fixed base is horizontally installed or not; 2 the landing leg of prior art's base can not rotate, and inconvenient avoiding the pothole. This application is through setting up first horizontal measuring apparatu and second horizontal measuring apparatu, adjusts the stabilizer blade and reaches and support chassis horizontal installation, and the four corners through supporting the chassis is rotated through the screw rod and is installed the installation piece for the stabilizer blade can the adjusting position, avoids hollow department.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a concrete pouring machine fixing base for municipal bridge construction has solved the problem that proposes in the background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a concrete pouring machine fixing base for municipal bridge construction, which comprises a supporting pedestal and is characterized by further comprising, the four corners that supports the chassis is passed through the screw rod and is rotated and install the installation piece, nut and installation piece fixed connection are passed through to the screw rod bottom, installation piece left side has hydraulic cylinder through first bolt fixed mounting, the through-hole has been seted up on installation piece left side, hydraulic cylinder's telescopic link runs through the through-hole, telescopic link bottom fixed mounting has the stabilizer blade, it has the bearing block to support chassis mid-weld, the bearing block top is passed through the bearing and is rotated the installation with the installation cover, it has first level measurement appearance through two sets of second bolt fixed mounting to support chassis horizontal plane, it has the.
As a preferred embodiment of the present invention, the position where the first level gauge is installed is located on the vertical center line of the horizontal plane of the support chassis.
As a preferred embodiment of the present invention, the position where the second level gauge is installed is located on the horizontal center line of the horizontal plane of the support chassis.
As a preferred embodiment of the present invention, the distance between the top of the bearing block and the bottom of the mounting sleeve is 40 mm.
As a preferred embodiment of the present invention, the model of the first horizontal measuring instrument and the second horizontal measuring instrument is ACE-SP400C horizontal angle measuring instrument.
Compared with the prior art, the beneficial effects of the utility model are as follows:
1. the utility model discloses a set up first level gauge and second level gauge and come to adjust the horizontal installation who supports the chassis according to two sets of level gauge's demonstration, because support chassis top can be installed with the cooperation of combination high pole, the center height of combination high pole, must guarantee that the level that supports the chassis is placed, can prevent generating device and empty the accident.
2. The utility model discloses the four corners that supports the chassis is passed through the screw rod and is rotated and install the installation piece, and the through-hole has been seted up in installation piece left side, and hydraulic cylinder's telescopic link runs through the through-hole, and telescopic link bottom fixed mounting has the stabilizer blade, props up the support chassis through hydraulic cylinder drive telescopic link, because the installation piece is rotatable, conveniently adjusts the mounted position of stabilizer blade.
3. The utility model discloses support the welding of chassis middle part and have the bearing block, the bearing is passed through at the bearing block top and is rotated the installation with the installation cover, and the installation cover is used for installing with the cooperation of combination high pole, because the rotation installation of installation cover for the combination high pole can the pivoted, conveniently adjusts the turned angle who makes up the high pole.
Drawings
Other features, objects and advantages of the invention will become more apparent upon reading of the detailed description of non-limiting embodiments with reference to the following drawings:
FIG. 1 is a top view of a concrete pouring machine fixing base for municipal bridge construction according to the present invention;
figure 2 is the utility model relates to a front view of a concrete pouring machine fixing base for municipal bridge construction.
In the figure: 1 hydraulic cylinder, 2 installation blocks, 3 screw rods, 4 third bolts, 5 second horizontal measuring instruments, 6 second bolts, 7 first horizontal measuring instruments, 8 supporting chassis, 9 installation sleeves, 10 through holes, 11 first bolts, 12 bearing blocks, 13 bearings, 14 support legs, 15 telescopic rods and 16 nuts
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
As shown in fig. 1-2, the utility model provides a technical solution: the utility model provides a concrete pouring machine fixing base for municipal bridge construction, including supporting chassis 8, the four corners that supports chassis 8 is passed through screw rod 3 and is rotated and install installation piece 2, nut 16 and 2 fixed connection of installation piece are passed through to 3 bottoms of screw rod, 2 left sides of installation piece have hydraulic cylinder 1 through first bolt 11 fixed mounting, through-hole 10 has been seted up on 2 left sides of installation piece, hydraulic cylinder 1's telescopic link 15 runs through- hole 10, 15 bottom fixed mounting of telescopic link have stabilizer blade 14, 8 middle welding in support chassis have bearing block 12, bearing block 12 top is passed through bearing 13 and is rotated the installation with installation cover 9, 8 horizontal planes in support chassis have first spirit level meter 7 through 6 fixed mounting of two sets of second bolts, 8 horizontal planes in support chassis have second spirit level meter 5 through 4 fixed mounting of two sets of third bolts.
In this embodiment, as shown in fig. 1 and fig. 2, a first horizontal measuring instrument 7 is fixedly installed on a horizontal plane of a support chassis 8 through two sets of second bolts 6, a second horizontal measuring instrument 5 is fixedly installed on a horizontal plane of the support chassis 8 through two sets of third bolts 4, the horizontal installation of the support chassis 8 is adjusted according to the display of the two sets of horizontal measuring instruments by arranging the first horizontal measuring instrument 7 and the second horizontal measuring instrument 5, and since the top of the support chassis 8 is installed in cooperation with a combined high pole, the center of the combined high pole is high, and the horizontal placement of the support chassis 8 must be ensured, so that the occurrence of the device toppling accidents can be prevented.
The first horizontal measuring instrument 7 is arranged on the vertical central line of the horizontal plane of the supporting chassis 8, and the second horizontal measuring instrument 5 is arranged on the horizontal central line of the horizontal plane of the supporting chassis 8.
In this embodiment, as shown in fig. 1 and 2, the middle of the supporting chassis 8 is welded with the bearing block 12, the top of the bearing block 12 is rotatably installed with the installation sleeve 9 through the bearing 13, the installation sleeve 9 is used for being installed in cooperation with the combined high pole, and the combined high pole can rotate due to the rotation installation of the installation sleeve 9, so that the rotation angle of the combined high pole can be conveniently adjusted.
Wherein, the distance from the top of the bearing block 12 to the bottom of the mounting sleeve 9 is 40 mm.
As shown in fig. 1 and 2, in this embodiment, the four corners through supporting chassis 8 are rotated through screws 3 and are installed with installation block 2, through-hole 10 has been seted up on installation block 2 left side, hydraulic cylinder 1's telescopic link 15 runs through-hole 10, telescopic link 15 bottom fixed mounting has stabilizer blade 14, prop up supporting chassis 8 through hydraulic cylinder 1 drive telescopic link 15, because installation block 2 is rotatable, conveniently adjust the mounted position of stabilizer blade 14.
The first horizontal measuring instrument 7 and the second horizontal measuring instrument 5 are ACE-SP400C horizontal angle measuring instruments.
The working principle is as follows: when a concrete pouring machine fixing base for municipal bridge construction is used, the four groups of oil cylinders 1 extend out of the telescopic rods 15 through the pressure of hydraulic oil, support devices are arranged through the four groups of support legs 14, the horizontal installation of the support chassis 8 is adjusted according to the display of the two groups of horizontal measuring instruments by setting the first horizontal measuring instrument 7 and the second horizontal measuring instrument 5, the top of the support chassis 8 can be installed in a matching mode with a combined high rod, the center of the combined high rod is high, the horizontal placement of the support chassis 8 must be guaranteed, the accident of toppling of the device can be prevented, the installation sleeve 9 is used for being installed in a matching mode with the combined high rod, and due to the rotary installation of the installation sleeve 9, the combined high rod can rotate, and the rotating angle of the combined high rod can be adjusted.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above, it will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, but that the invention may be embodied in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (5)

1. The utility model provides a concrete pouring machine fixing base for municipal bridge construction, includes support chassis (8), its characterized in that: the four corners of supporting chassis (8) are rotated through screw rod (3) and are installed installation piece (2), nut (16) and installation piece (2) fixed connection are passed through to screw rod (3) bottom, installation piece (2) left side has hydraulic cylinder (1) through first bolt (11) fixed mounting, through-hole (10) have been seted up on installation piece (2) left side, telescopic link (15) of hydraulic cylinder (1) run through-hole (10), telescopic link (15) bottom fixed mounting has stabilizer blade (14), it has bearing block (12) to support chassis (8) middle part welding, bearing block (12) top is passed through bearing (13) and is rotated the installation with install sleeve (9), support chassis (8) horizontal plane and have first level measurement appearance (7) through two sets of second bolt (6) fixed mounting, support chassis (8) horizontal plane and have second level measurement appearance (5) through two sets of third bolt (4) fixed mounting.
2. The concrete pouring machine fixing seat for the municipal bridge construction according to claim 1, wherein: the first horizontal measuring instrument (7) is arranged on the vertical central line of the horizontal plane of the supporting chassis (8).
3. The concrete pouring machine fixing seat for the municipal bridge construction according to claim 1, wherein: the second level gauge (5) is mounted at a position on the transverse center line of the transverse horizontal plane of the support chassis (8).
4. The concrete pouring machine fixing seat for the municipal bridge construction according to claim 1, wherein: the distance between the top of the bearing block (12) and the bottom of the mounting sleeve (9) is 40 mm.
5. The concrete pouring machine fixing seat for the municipal bridge construction according to claim 1, wherein: the first horizontal measuring instrument (7) and the second horizontal measuring instrument (5) are ACE-SP400C horizontal angle measuring instruments.
CN201921726301.7U 2019-10-15 2019-10-15 A concrete placement machine fixing base for municipal bridge construction Active CN210771269U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921726301.7U CN210771269U (en) 2019-10-15 2019-10-15 A concrete placement machine fixing base for municipal bridge construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921726301.7U CN210771269U (en) 2019-10-15 2019-10-15 A concrete placement machine fixing base for municipal bridge construction

Publications (1)

Publication Number Publication Date
CN210771269U true CN210771269U (en) 2020-06-16

Family

ID=71066270

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921726301.7U Active CN210771269U (en) 2019-10-15 2019-10-15 A concrete placement machine fixing base for municipal bridge construction

Country Status (1)

Country Link
CN (1) CN210771269U (en)

Similar Documents

Publication Publication Date Title
CN102561712B (en) Accurate positioning frame for large steel column and equipment foundation fixing bolt and construction method thereof
CN203603586U (en) Equipment support regulating device
CN201071510Y (en) Lattice column locating and verticality adjusting guide frame device
CN207064854U (en) One kind is suitable for geology settling zone petroleum delivery pipeline support frame
CN210771269U (en) A concrete placement machine fixing base for municipal bridge construction
CN207277178U (en) A kind of pot bearing
CN214834947U (en) Horizontal and vertical positioning device for foundation bolt
CN206233261U (en) It is a kind of to can be used to pour the fixing device for reclaiming ground packing material
CN210199103U (en) Two-dimensional sand box model convenient to overturn, lay horizontally and drain water
CN205333072U (en) Portable whole hangs gravity anping building laser measuring instrument
CN212110827U (en) Former rock structural surface sample making devices
CN212840446U (en) Portable rain gauge support for weather
CN113175599A (en) On-spot measuring device for engineering cost
CN207048351U (en) A kind of steel structural upright column correction auxiliary tools
CN102616706A (en) Self-propelled aerial work platform automatic horizontal system
CN214117571U (en) Armor seam positioning device
CN207436090U (en) A kind of installation centering support parallels group and its base construction
CN221648161U (en) Water level gauge mounting bracket
CN221343626U (en) Leveling device for embedded support leg of tower crane
CN213328571U (en) Road surface leveling device for highway engineering
CN206462634U (en) Multifunction mapping platform
JPH10317391A (en) Foundation structure for steel tower and method for constructing the same
CN210507446U (en) One-pile one-column verticality adjusting frame for building construction topdown construction method
CN220432162U (en) Leveling and supporting device for embedded supporting leg of heavy tower crane
CN206677830U (en) A kind of groove type heat collector cantilever beam assembly tool