CN210712945U - Connecting structure of underground comprehensive pipe gallery - Google Patents

Connecting structure of underground comprehensive pipe gallery Download PDF

Info

Publication number
CN210712945U
CN210712945U CN201921712609.6U CN201921712609U CN210712945U CN 210712945 U CN210712945 U CN 210712945U CN 201921712609 U CN201921712609 U CN 201921712609U CN 210712945 U CN210712945 U CN 210712945U
Authority
CN
China
Prior art keywords
comprehensive pipe
pipe gallery
steel plate
utility tunnel
plate strip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921712609.6U
Other languages
Chinese (zh)
Inventor
马振邦
高晨皓
方浩杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201921712609.6U priority Critical patent/CN210712945U/en
Application granted granted Critical
Publication of CN210712945U publication Critical patent/CN210712945U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a connecting structure of an underground comprehensive pipe gallery, which comprises a comprehensive pipe gallery body, wherein the comprehensive pipe gallery body comprises a deformation joint along the axial direction and a plurality of connecting structures arranged at the deformation joint, and all the connecting structures are uniformly distributed along the circumferential direction of the comprehensive pipe gallery body; the connecting structure comprises a steel plate strip and at least two anchor bolts, sliding grooves are formed in two ends of the steel plate strip, anchor bolt holes are formed in the front side and the rear side of each deformation joint of the comprehensive pipe gallery body, and the anchor bolt holes correspond to the sliding grooves in the radial direction of the section of the comprehensive pipe gallery body; all anchor bolts respectively penetrate through the two sliding grooves in the steel plate strip and are anchored into corresponding anchor bolt holes on the front side and the rear side of the deformation joint; both ends of the steel plate strip are respectively fixedly connected to the inner wall of the comprehensive pipe gallery body through anchor bolts. Can be convenient for observe and maintain the settlement dislocation of utility tunnel through this connection structure, the initial stage that takes place to subside relatively at the movement joint can carry out effective processing to the movement joint, and then maintains utility tunnel's safe operation.

Description

Connecting structure of underground comprehensive pipe gallery
Technical Field
The utility model belongs to the technical field of municipal administration underground infrastructure, concretely relates to underground utility tunnel's connection structure.
Background
The underground comprehensive pipe gallery is used as an important city infrastructure, and the continuous length is very large. The utility tunnel generally adopts the concrete as raw and other materials, consequently needs to set up the movement joint. The processing of the movement joint of current utility tunnel generally adopts the rod iron of fat liquoring to connect in movement joint department: as shown in fig. 1, spaces for a plurality of steel bars are reserved when concrete is poured, and the steel bars are inserted along the longitudinal direction of the comprehensive pipe gallery after the concrete is made; the steel bar can move properly in the horizontal direction, and belongs to flexible connection; the device is immovable in the vertical direction and belongs to rigid connection; and the steel bar is used as a shear-resistant member of the deformation joint connecting part.
But because the outside of utility tunnel all has the compaction soil layer all around, therefore if the rod iron receives destruction, the utility tunnel local settlement deformation that arouses in movement joint department can not the performance very obvious, also difficult observation. And the settlement dislocation that arouses transmits on the inside pipeline of utility tunnel, will lead to utility tunnel's waterproofing membrane to be torn, and then leads to whole utility tunnel waterproof failure, influences utility tunnel's safe operation. And the rod iron is buried inside the concrete of utility tunnel, even if subside has taken place, also is difficult to the restoration processing in the later stage.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problem that a connection structure of utility tunnel underground is provided, can be convenient for observe and maintain utility tunnel's settlement dislocation through this connection structure, the initial stage that takes place to subside relatively at the movement joint can carry out effective processing to the movement joint, and then maintains utility tunnel's safe operation.
The technical scheme of the utility model as follows: the connecting structure of the underground comprehensive pipe gallery comprises a comprehensive pipe gallery body, wherein the comprehensive pipe gallery body comprises a deformation joint along the axial direction, and also comprises a plurality of connecting structures arranged at the deformation joint, and all the connecting structures are uniformly distributed and arranged along the circumferential direction of the comprehensive pipe gallery body; the connecting structure comprises a steel plate strip and at least two anchor bolts, sliding grooves are formed in two ends of the steel plate strip, and the length direction of each sliding groove is consistent with the axial direction of the comprehensive pipe gallery body; the front side and the rear side of each deformation joint of the comprehensive pipe gallery body are provided with anchor bolt holes, and the anchor bolt holes correspond to the sliding grooves in the radial direction of the section of the comprehensive pipe gallery body; all anchor bolts respectively penetrate through the two sliding grooves in the steel plate strip and are anchored into corresponding anchor bolt holes on the front side and the rear side of the deformation joint; the both ends of steel sheet strip are respectively through crab-bolt fixed connection in the inner wall of utility tunnel body.
Further: the steel plate strip and the axial direction of the comprehensive pipe gallery body form an inclination angle of 45 degrees.
Further: the connecting structure further comprises an embedded steel plate and a sleeve arranged along the radial direction of the comprehensive pipe gallery body, and the embedded steel plate is embedded in the comprehensive pipe gallery body; the sleeve is in one-to-one correspondence with the anchor bolt hole, and the hollow cavity of the sleeve is the anchor bolt hole.
Further: and a plastic film is sleeved outside the steel plate strip.
Further: the plastic film is double-layer.
Further: the length of spout is 3 cm.
Further: the two ends of the steel plate strip are arc-shaped.
The beneficial effect of this scheme: this scheme utilization connection structure to replace prior art's rod iron to the processing of the movement joint of utility tunnel body. The connecting structure in the scheme has the following advantages: 1. the steel plate strips are fixed on the inner wall of the comprehensive pipe gallery body through anchor bolts, namely the steel plate strips are exposed, so that the observation and the maintenance are convenient; 2. the steel plate is connected with the comprehensive pipe gallery body through anchor bolts, so that the steel plate strips can be conveniently replaced; 3. the sleeve is fixed with the comprehensive pipe gallery body by only buying the steel plate, and the hollow cavity of the sleeve is used for replacing the anchor bolt hole, so that the anchor bolt can be connected with the comprehensive pipe gallery body more firmly, and the anchor bolt hole is prevented from being damaged by the anchor bolt; 4. the steel plate strips and the comprehensive pipe rack body are axially inclined, the inclination angle is 45 degrees, and meanwhile, the length direction of the sliding groove is consistent with the axial direction of the comprehensive pipe rack body, so that the destructive force generated when the deformation joint settlement occurs can be effectively dispersed from the mechanical angle, and the destructive force is decomposed along the length direction of the steel plate strips and the length direction of the sliding strips, so that the steel plate strips, the comprehensive pipe rack and the like are protected, local excessive damage is prevented, and local damage of the connecting part of the steel plate strips and the comprehensive pipe rack body is also prevented; 5. the rust-proof mode of the steel plate strip disclosed in the scheme is also sleeved with the plastic film, and the two ends of the steel plate strip are optimized to be arc-shaped, so that the service life of the steel plate strip is prolonged, and the normal operation of the comprehensive pipe gallery body is further facilitated.
Drawings
Fig. 1 is a schematic view of a connection structure of a steel bar in the present invention;
fig. 2 is a schematic view of the mounting structure of the connecting assembly of the present invention;
fig. 3 is a schematic view of an installation structure of a pre-buried steel plate in the utility model;
fig. 4 is a schematic structural diagram of the middle steel plate strip of the present invention.
Detailed Description
The invention will be further explained with reference to the following figures and examples:
as shown in fig. 1, fig. 2, fig. 3 and fig. 3, the utility model discloses a connection structure of utility tunnel, including utility tunnel body 1, be provided with a plurality of coupling assembling in utility tunnel body 1's movement joint department, all coupling assembling are arranged along utility tunnel body 1's cross-section circumference equipartition. In the scheme, the connecting assembly comprises a steel strip 3 and a plurality of anchor bolts 4. Spout 31 has all been seted up at the both ends of steel strip 3, and the long direction of spout 31 is unanimous with utility tunnel body 1's axial. Both sides all are provided with the anchor bolt hole around the movement joint, and this anchor bolt hole can reserve, also can punch at the later stage and bore and get in the concrete pouring. The anchor bolt holes correspond to the sliding grooves 31 in the radial direction of the section of the comprehensive pipe gallery body 1. As shown in fig. 3, in the preferred embodiment, each runner 31 corresponds to two anchor bolts 4, i.e. one runner 31 corresponds to two anchor bolt holes. The steel plate strip 3 and the axial direction of the comprehensive pipe gallery body 1 form an inclination angle of 45 degrees. After the anchor bolts 4 penetrate through the two sliding grooves 31 on the steel plate strip 3, the anchor bolts 4 are continuously anchored into the anchor bolt holes on the two sides of the deformation joint. Both ends of the steel plate strip 3 are respectively fixed with the front side and the rear side of the deformation joint through anchor bolts 4, and the steel plate strip 3 is fixed on the inner wall of the comprehensive pipe gallery body 1. Simultaneously, utilize the lath 3 to maintain the movement joint state, prevent that utility tunnel from producing at movement joint department and subsiding the dislocation.
As shown in fig. 3, an optimization is also given in the optimized embodiment for the connection structure of the anchor bolt 4 and the utility tunnel body 1. When pouring the concrete of utility tunnel body 1, bury pre-buried steel sheet 5 in utility tunnel body 1 in advance to weld two sleeves 6 on pre-buried steel sheet 5, the axial perpendicular to pre-buried steel sheet 5's of sleeve 6 face, also the radial setting of cross-section along utility tunnel body 1 of sleeve 6. After the anchor bolt 4 runs through the sliding groove 31, the anchor bolt can be fixed with the sleeve 6, so that the force transmission mode between the anchor bolt 4 and the concrete of the comprehensive pipe gallery body 1 becomes more uniform. The method does not damage the concrete and is more beneficial to maintaining the integral integrity of the concrete. And through the connection of sleeve 6 and pre-buried steel sheet 5, this kind of method is more effective to preventing that crab-bolt 4 from taking place to cut the perk destruction, simultaneously can save material, and finally, compare and place sleeve 6 alone, this kind of method can avoid sleeve 6 to take place relative displacement under the temperature stress effect. Simultaneously because the lifting surface between pre-buried steel sheet 5 and utility tunnel body 1 is great, can effectively resist the pulling force of sleeve 6, make crab-bolt 4 can be more firm realize fixed connection with utility tunnel body 1, and then make the connection between 3 of steel sheet strip and the utility tunnel body 1 more firm.
In the scheme, in order to prolong the service life of the steel plate strip 3: the steel plate strip 3 is sleeved with a double-layer plastic film. Can stop like this to corrode 3 steel sheet strips through the sewage of utility tunnel body 1, and then make 3 steel sheet strips corroded the destruction as early as possible. The double-layer plastic film has a better protection function. For the structural design of the existing comprehensive pipe gallery body 1, the length of the sliding groove 31 is set to be 3cm, the sliding groove 31 with the size accords with the connection design of most existing general grid pipe gallery bodies through design calculation, and further design optimization of an operator is avoided. As shown in fig. 4, two end faces of the steel strip 3 in the present case adopt the structure of the arc chamfer, and compared with the steel strip 3 adopting the rectangular structure, the arc chamfer can effectively prevent the end part of the steel strip 3 from scratching the inner wall of the utility tunnel body 1, and has a certain protective effect on the utility tunnel body 1.
The implementation principle of the scheme is as follows: among the prior art, the fat liquoring steel sheet is the inside of embedding in utility tunnel body 1, when consequently scribbling 2 destroys of rod iron, hardly thought to observe, and in case the displacement joint department takes place to subside the dislocation, then will arouse 1 waterproof failures of utility tunnel body, is difficult for changing and restoreing scribbling rod iron 2 moreover. In the scheme, the steel plate strips 3 and the anchor bolts 4 are exposed on the inner wall of the comprehensive pipe gallery body 1, so that the steel plate strips 3 can be observed manually frequently, the uneven settlement of the structure belongs to a long process, and if damage occurs, the anchor bolts 4 can be detached and the damaged or deformed steel plate strips 3 can be replaced. The uneven settlement is still acted on the utility tunnel body 1, but the newly-replaced steel plate strip 3 of the utility tunnel body 1 can continuously provide continuous resistance, can continue to guarantee that the uneven settlement is in the allowed range, and waterproofing membrane also can not be torn simultaneously, and the integrality of whole structure is still better, and the pipeline of inside is still protected fine, and this embodies the "recoverability" of structure.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the present invention, and any modifications, equivalents and improvements made within the spirit and principles of the present invention are intended to be included within the scope of the present invention.

Claims (7)

1. The utility model provides an underground utility tunnel's connection structure, includes utility tunnel body (1), utility tunnel body (1) is including the movement joint along the axial, its characterized in that: the connecting structure is characterized by also comprising a plurality of connecting structures arranged at the deformation joint, wherein all the connecting structures are uniformly distributed and arranged along the circumferential direction of the comprehensive pipe rack body (1); the connecting structure comprises a steel plate strip (3) and at least two anchor bolts (4), sliding grooves (31) are formed in two ends of the steel plate strip (3), and the length direction of each sliding groove (31) is consistent with the axial direction of the comprehensive pipe gallery body (1); the front side and the rear side of each deformation joint of the comprehensive pipe gallery body (1) are respectively provided with an anchor bolt hole, and the anchor bolt holes correspond to the sliding grooves (31) in the radial direction of the section of the comprehensive pipe gallery body (1); all anchor bolts (4) respectively penetrate through the two sliding grooves (31) on the steel plate strip (3) and are anchored into corresponding anchor bolt holes on the front side and the rear side of the deformation joint; the both ends of steel sheet strip (3) are respectively through crab-bolt (4) fixed connection in the inner wall of utility tunnel body (1).
2. The underground utility tunnel's connection structure of claim 1, characterized in that: the steel plate strip (3) and the axial direction of the comprehensive pipe gallery body (1) form an inclination angle of 45 degrees.
3. The connecting structure of an underground utility tunnel according to claim 2, wherein: the connecting structure further comprises an embedded steel plate (5) and a sleeve (6) arranged along the radial direction of the comprehensive pipe gallery body (1), and the embedded steel plate (5) is embedded in the comprehensive pipe gallery body (1); the sleeves (6) correspond to the anchor bolt holes one by one, and the hollow cavities of the sleeves (6) are the anchor bolt holes.
4. A coupling structure of an underground utility tunnel according to claim 2 or 3, characterized in that: the outside of the steel plate strip (3) is sleeved with a plastic film.
5. The underground utility tunnel connection structure of claim 4, characterized in that: the plastic film is double-layer.
6. The underground utility tunnel connection structure of claim 5, wherein: the length of the sliding chute (31) is 3 cm.
7. The underground utility tunnel connection structure of claim 5, wherein: the two ends of the steel plate strip (3) are arc-shaped.
CN201921712609.6U 2019-10-12 2019-10-12 Connecting structure of underground comprehensive pipe gallery Expired - Fee Related CN210712945U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921712609.6U CN210712945U (en) 2019-10-12 2019-10-12 Connecting structure of underground comprehensive pipe gallery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921712609.6U CN210712945U (en) 2019-10-12 2019-10-12 Connecting structure of underground comprehensive pipe gallery

Publications (1)

Publication Number Publication Date
CN210712945U true CN210712945U (en) 2020-06-09

Family

ID=70930547

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921712609.6U Expired - Fee Related CN210712945U (en) 2019-10-12 2019-10-12 Connecting structure of underground comprehensive pipe gallery

Country Status (1)

Country Link
CN (1) CN210712945U (en)

Similar Documents

Publication Publication Date Title
CN206174001U (en) Prefabricated movement joint tube coupling and prefabricated assembled utility tunnel
CN210712945U (en) Connecting structure of underground comprehensive pipe gallery
CN210917343U (en) Can dismantle locking-type device of anchor rope
CN111364479A (en) Inclined support threaded pile supporting structure for foundation pit enclosure and construction method thereof
CN204738309U (en) Immersed tube tunnel is with holding structure of sealing up a door
CN106337437A (en) Prefabricated Deformation Joint Pipe Joint and Prefabricated Composite Pipe Gallery
CN212537127U (en) Splicing lining structure for repairing large-caliber drainage pipeline
CN212452659U (en) A diagonal bracing screw thread pile supporting construction for foundation ditch enclosure
CN114411694A (en) Ground connection wall internal connector embedded positioning system and construction method thereof
CN210597338U (en) Foundation pit slope stability maintaining device
CN209838426U (en) Segment lining structure suitable for large deformation of surrounding rock
CN114961780A (en) Tunnel temporary supporting structure and using method thereof
CN113756326B (en) Deep weak soil foundation ditch pit bottom utility tunnel environmental protection formula underground structure supporting device
CN220416427U (en) Connection structure of semi-rigid pipe-jacking pipe joint suitable for complex stratum
CN219175316U (en) Structure for controlling settlement and water seepage of open cut tunnel in soft soil area
CN205742150U (en) High fault tolerance recyclable piling bar socket join structure
CN105507172B (en) A kind of inner bearing type connection structure for steel reinforced concrete pipe culvert reparation
CN214464212U (en) Interim bearing structure in tunnel
CN219654710U (en) Anti-seismic waterproof flexible structure for shield tunnel segment joint
CN216238546U (en) Anti soil nail that floats convenient to dismantle
CN212510001U (en) PE pipeline and geomembrane butt-joint structural
CN214743929U (en) Semi-rigid concrete drainage pipeline connects auxiliary device
CN114991170B (en) Hollow interlayer steel pipe concrete supporting system and construction method thereof
JP2002227187A (en) Joint for steel pipe sheet pile and its execution method
CN211817043U (en) Expansion joint decorative structure for construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200609

Termination date: 20211012

CF01 Termination of patent right due to non-payment of annual fee