CN210710341U - Hoisting frame for curtain wall glass construction - Google Patents
Hoisting frame for curtain wall glass construction Download PDFInfo
- Publication number
- CN210710341U CN210710341U CN201921216398.7U CN201921216398U CN210710341U CN 210710341 U CN210710341 U CN 210710341U CN 201921216398 U CN201921216398 U CN 201921216398U CN 210710341 U CN210710341 U CN 210710341U
- Authority
- CN
- China
- Prior art keywords
- hoisting
- curtain wall
- wall glass
- frame
- vertical rectangular
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000011521 glass Substances 0.000 title claims abstract description 36
- 238000010276 construction Methods 0.000 title claims abstract description 13
- 238000013016 damping Methods 0.000 claims abstract description 5
- 230000002093 peripheral effect Effects 0.000 claims description 5
- 238000000034 method Methods 0.000 abstract description 7
- 230000035939 shock Effects 0.000 abstract description 6
- 230000003139 buffering effect Effects 0.000 abstract description 4
- 238000010521 absorption reaction Methods 0.000 description 2
- 239000000919 ceramic Substances 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 230000006837 decompression Effects 0.000 description 1
- 239000011094 fiberboard Substances 0.000 description 1
- 239000011152 fibreglass Substances 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
Images
Landscapes
- Load-Bearing And Curtain Walls (AREA)
- Securing Of Glass Panes Or The Like (AREA)
Abstract
The utility model discloses a curtain wall glass construction is with hoist and mount frame relates to curtain erection equipment technical field. The utility model comprises a first hoisting belt, a second hoisting belt and a hoisting frame; the hoisting frame comprises a vertical rectangular plate; the upper end surface of the vertical rectangular plate is fixed with a damping lifting part; three rows of barbs are fixed on the opposite side surfaces of the vertical rectangular plate; the first hoisting belt and the second hoisting belt are both provided with tightening sleeves, and the first hoisting belt and the second hoisting belt are both of flat structures. The utility model discloses a curtain wall glass construction of design is with hoist and mount frame is reasonable simple, and convenient to use is reliable, and the shock attenuation of design is lifted by crane the effectual usefulness that plays the buffering of in-process of lifting by crane, has solved the limited problem of current sucking disc formula curtain wall glass hoist device service environment.
Description
Technical Field
The utility model belongs to the technical field of the curtain erection equipment, especially, relate to a curtain wall glass is hoist and mount frame for construction.
Background
The curtain wall is an outer wall protection enclosure of a building, is also called a hanging wall, and is a light wall with a decorative effect commonly used by modern large-scale and high-rise buildings. The building envelope structure consists of a structural frame, curtain wall glass and connecting pieces, and does not bear the load and the action of a main structure. The curtain wall is made of stone, ceramic plate, microcrystalline glass, high-pressure laminate, cement fiber board, glass, inorganic glass fiber reinforced plastic, pottery clay board, ceramic protective board, metal board, etc. The glass curtain wall is usually installed in commercial buildings in modern cities, so that the buildings are transparent, the lighting performance is good, and the appearance is attractive.
The installation of current curtain wall glass generally adopts the sucking disc to absorb the hoist and mount, and the sucking disc is in the state of slope at glass all the time in the use, and the sucking disc has the problem of vibrations decompression simultaneously in the local work progress that wind-force is great, rainy etc. causes the risk that half empty glass drops easily, uses the annular limited.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a curtain wall glass construction is with hoist and mount frame, the curtain wall glass construction through the design is with hoist and mount frame reasonable simple, and convenient to use is reliable, and the shock attenuation of design is lifted the effectual usefulness of playing the buffering of the in-process of lifting by crane, has solved the limited problem of current sucking disc formula curtain wall glass hoist device service environment.
In order to solve the technical problem, the utility model discloses a realize through following technical scheme:
the utility model relates to a hoisting frame for curtain wall glass construction, which comprises a first hoisting belt, a second hoisting belt and a hoisting frame;
the hoisting frame comprises a vertical rectangular plate; a damping lifting part is fixed on the upper end face of the vertical rectangular plate; three rows of barbs are fixed on the opposite side faces of the vertical rectangular plate;
the first hoisting belt and the second hoisting belt are both provided with tightening sleeves, the first hoisting belt and the second hoisting belt are of flat structures, the circular holes at two ends of the first hoisting belt are buckled on two corners of the lower end of the curtain wall glass, the middle part of the first hoisting belt is hung on the hoisting frame, the tightening sleeves are tightened, the circular holes at two ends of the second hoisting belt are buckled on two corners of the upper end of the curtain wall glass, then the lower end of the curtain wall glass is bypassed, the other side of the hoisting frame is hung on the middle part of the second hoisting belt, and the tightening sleeves are tightened.
Furthermore, the damping lifting part comprises two guide cylinders fixed on the upper end surface of the vertical rectangular plate and a lifting plate in sliding fit with the two guide cylinders; a limiting circular plate is fixed on the upper end surface of the guide cylinder; a first spring is sleeved on the side surface of the guide cylinder between the limiting circular plate and the opposite surface of the lifting plate; a second spring is sleeved on the peripheral side surface of the guide cylinder between the lifting plate and the upper surface of the vertical rectangular plate; and a hanging ring is fixed in the middle of the upper surface of the lifting plate.
Further, three columns of the barbs are arranged in a "Λ" shape.
The utility model discloses following beneficial effect has:
the utility model discloses a curtain wall glass construction is with hoist and mount frame is reasonable simple, and convenient to use is reliable, and the shock attenuation of design is lifted by crane the effectual usefulness that plays the buffering of in-process that lifts by crane, improves the stability of hoist and mount process.
Of course, it is not necessary for any particular product to achieve all of the above-described advantages at the same time.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art that other drawings can be obtained according to these drawings without creative efforts.
FIG. 1 is a schematic structural view of the front side of a hoisting frame when hoisting curtain wall glass;
FIG. 2 is a schematic structural view of the back surface of the hoisting frame when hoisting curtain wall glass;
FIG. 3 is an enlarged view of a portion of FIG. 1 at A;
FIG. 4 is a schematic structural view of a hoisting frame;
in the drawings, the components represented by the respective reference numerals are listed below:
1-a first hoisting belt, 2-a second hoisting belt, 3-a hoisting frame, 4-a vertical rectangular plate, 5-a shock absorption hoisting part, 6-a barb, 7-a tightening sleeve, 8-a guide cylinder, 9-a hoisting plate, 10-a limiting circular plate, 11-a first spring, 12-a second spring, 13-a hoisting ring and 14-curtain wall glass.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by a person of ordinary skill in the art without creative efforts belong to the protection scope of the present invention.
Referring to fig. 1-4, the utility model relates to a lifting frame for curtain wall glass construction, which comprises a first lifting belt 1, a second lifting belt 2 and a lifting frame 3;
the hoisting frame 3 comprises a vertical rectangular plate 4; a damping lifting part 5 is fixed on the upper end surface of the vertical rectangular plate 4; three rows of barbs 6 are fixed on one opposite side surface of the vertical rectangular plate 4, and the three rows of barbs 6 are arranged in an inverted V shape;
the first hoisting belt 1 and the second hoisting belt 2 are both provided with a tightening sleeve 7, the first hoisting belt 1 and the second hoisting belt 2 are both of a flat structure, the ring eyes at the two ends of the first hoisting belt 1 are buckled on the two corners at the lower end of the curtain wall glass 14, the middle part of the first hoisting belt 1 is hung on the hoisting frame 3, the tightening is realized through the tightening sleeve 7, the ring eyes at the two ends of the second hoisting belt 2 are buckled on the two corners at the upper end of the curtain wall glass 14, then the second hoisting belt 2 bypasses the lower end of the curtain wall glass 14 and is hung at the other side of the hoisting frame 3, the middle part of the second hoisting belt 2 is hung on the hoisting frame 3, and the tightening is realized through the;
the shock absorption lifting part 5 comprises two guide cylinders 8 fixed on the upper end surface of the vertical rectangular plate 4 and a lifting plate 9 in sliding fit with the two guide cylinders 8; a limiting circular plate 10 is fixed on the upper end surface of the guide cylinder 8; a first spring 11 is sleeved on the peripheral side surface of the guide cylinder 8 between the opposite surfaces of the limiting circular plate 10 and the lifting plate 9; a second spring 12 is sleeved on the peripheral side surface of the guide cylinder 8 between the lifting plate 9 and the upper surface of the vertical rectangular plate 4; a hanging ring 13 is fixed in the middle of the upper surface of the lifting plate 9.
One specific application of this embodiment is: in the using process, as shown in fig. 1-2, curtain wall glass 14 is bound on a hoisting frame 3 through a first hoisting belt 1 and a second hoisting belt 2, according to the curtain wall glass 14 with different sizes, a tightening sleeve 7 tightens the first hoisting belt 1 and the second hoisting belt 2 on barbs 6 in a middle column, the lower sides of tightening parts of the first hoisting belt 1 and the second hoisting belt 2 are lapped on the barbs 6 at two sides of the tightening sleeve 7, the tightening sleeve 7 naturally tightens under the action of gravity, the first hoisting belt 1 and the second hoisting belt 2 are adjusted to be hung on the barbs 6 with different heights so that the curtain wall glass 14 is in a vertical state, the curtain wall glass 14 is fixed on a steel frame through bolts after being hoisted in place, and then annular eyes at four corners of the curtain wall glass 14 are taken down; whole device design is simple reasonable, and convenient to use is reliable, and the shock attenuation of design lifts by crane portion 5 and effectual plays the effect of buffering at the in-process that lifts by crane, improves the stability of hoist and mount process.
In the description herein, references to the description of "one embodiment," "an example," "a specific example," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
The preferred embodiments of the present invention disclosed above are intended only to help illustrate the present invention. The preferred embodiments are not intended to be exhaustive or to limit the invention to the precise embodiments disclosed. Obviously, many modifications and variations are possible in light of the above teaching. The embodiments were chosen and described in order to best explain the principles of the invention and its practical applications, to thereby enable others skilled in the art to best understand the invention for and utilize the invention. The present invention is limited only by the claims and their full scope and equivalents.
Claims (3)
1. The utility model provides a curtain wall glass construction is with hoist and mount frame, includes first hoist and mount area (1), second hoist and mount area (2), its characterized in that: the device also comprises a hoisting frame (3);
the hoisting frame (3) comprises a vertical rectangular plate (4); a damping lifting part (5) is fixed on the upper end surface of the vertical rectangular plate (4); three rows of barbs (6) are fixed on one opposite side surface of the vertical rectangular plate (4);
and the first hoisting belt (1) and the second hoisting belt (2) are both provided with tightening sleeves (7).
2. The hoisting frame for curtain wall glass construction according to claim 1, wherein the shock-absorbing hoisting part (5) comprises two guide cylinders (8) fixed on the upper end surface of the vertical rectangular plate (4), and a hoisting plate (9) in sliding fit with the two guide cylinders (8); a limiting circular plate (10) is fixed on the upper end surface of the guide cylinder (8); a first spring (11) is sleeved on the peripheral side surface of the guide cylinder (8) between the opposite surfaces of the limiting circular plate (10) and the lifting plate (9); a second spring (12) is sleeved on the peripheral side surface of the guide cylinder (8) between the lifting plate (9) and the upper surface of the vertical rectangular plate (4); and a hanging ring (13) is fixed in the middle of the upper surface of the lifting plate (9).
3. The hanging frame for curtain wall glass construction according to claim 1, characterized in that three rows of the barbs (6) are arranged in a shape of 'Λ'.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921216398.7U CN210710341U (en) | 2019-07-30 | 2019-07-30 | Hoisting frame for curtain wall glass construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921216398.7U CN210710341U (en) | 2019-07-30 | 2019-07-30 | Hoisting frame for curtain wall glass construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210710341U true CN210710341U (en) | 2020-06-09 |
Family
ID=70964542
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921216398.7U Expired - Fee Related CN210710341U (en) | 2019-07-30 | 2019-07-30 | Hoisting frame for curtain wall glass construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210710341U (en) |
-
2019
- 2019-07-30 CN CN201921216398.7U patent/CN210710341U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103362147B (en) | The multidirectional Self-resetting isolation structure of a kind of building | |
CN204645305U (en) | A kind of novel energy-consumption shock-absorbing buckling restrained brace | |
CN211058363U (en) | Anti-falling safety device for building construction | |
CN210710341U (en) | Hoisting frame for curtain wall glass construction | |
CN204825626U (en) | Novel corner shock insulation rubber support by a wide margin | |
CN107724441B (en) | One kind having damping type building | |
CN204081264U (en) | A kind of outer wrapping Combined fireproof steel I-column | |
CN210944509U (en) | Plate hoisting clamping part for building construction | |
CN203846636U (en) | Novel anti-seismic house | |
CN209568564U (en) | A kind of civil engineering anti-seismic structure | |
CN208816874U (en) | A kind of pipe network supporting frame for municipal works | |
CN207390864U (en) | A kind of tower crane with stowable falling proof device | |
CN215829692U (en) | Lead core rubber shock insulation support capable of resetting | |
CN1074806C (en) | Large type anti-earthquake building, and the design method | |
CN210944543U (en) | Hoisting clamp for shock insulation support | |
CN201588432U (en) | Shock-absorbing support with damper arranged therein | |
CN211597875U (en) | Protection canopy for building engineering | |
CN210594825U (en) | Waterproof elevator structure | |
CN209261053U (en) | High-performance steel performance column | |
CN207159793U (en) | A kind of Bridge Seismic structure | |
CN206913803U (en) | A kind of antidetonation aluminium-plastic panel | |
CN218815119U (en) | Construction is with good transportation hanging flower basket of stability | |
CN201518219U (en) | Pyramidal suspension sound-absorbing body | |
CN207017683U (en) | A kind of support connection component for architectural engineering | |
CN204876324U (en) | Bearing wall body board |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200609 |