CN210636916U - Road side slope construction protection fence - Google Patents

Road side slope construction protection fence Download PDF

Info

Publication number
CN210636916U
CN210636916U CN201921413890.3U CN201921413890U CN210636916U CN 210636916 U CN210636916 U CN 210636916U CN 201921413890 U CN201921413890 U CN 201921413890U CN 210636916 U CN210636916 U CN 210636916U
Authority
CN
China
Prior art keywords
protection
fixedly connected
fixed
rod
slope construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921413890.3U
Other languages
Chinese (zh)
Inventor
毛云峰
王文义
资新
王逸庶
杨俊毅
李健民
李正垣
廖旭初
陈登峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Highway Engineering Supervision Consulting Co ltd
Original Assignee
Yunnan Highway Engineering Supervision Consulting Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Highway Engineering Supervision Consulting Co ltd filed Critical Yunnan Highway Engineering Supervision Consulting Co ltd
Priority to CN201921413890.3U priority Critical patent/CN210636916U/en
Application granted granted Critical
Publication of CN210636916U publication Critical patent/CN210636916U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a road side slope construction protection rail, including the rail base, the last fixed surface of rail base is connected with the fixed column, the fender rod is connected with on the outer fixed surface of fixed column, go up the lower fixed surface of fender rod and be connected with the go-between under the fixed surface, the surface swing joint of go-between has connecting spring, connecting spring's one end fixedly connected with guard plate, the fender rod under the outer fixed surface of fixed column is connected with, the lower fixed surface of fender rod is connected with the protecting tube down. This road slope construction protection rail through the setting of solid fixed pressing plate, installation piece and inserted nail, at the job site, the accessible presses solid fixed pressing plate downwards for installation piece and inserted nail downstream make inserted nail insert soil, can strengthen the device and the joint strength on ground, strengthen the holistic stability of the device, help improving the easy unstable phenomenon of empting of focus of protection rail.

Description

Road side slope construction protection fence
Technical Field
The utility model relates to a road construction protection technology field specifically is a road side slope construction protection rail.
Background
Road slope construction protection rail can protect road slope job site on the one hand, prevents that the job site from suffering destruction, and on the other hand can prevent that vehicle or pedestrian that road slope was gone from meeting accident in the job site, plays the guard action to pedestrian and vehicle.
The existing road slope construction protection fence has certain defects when in use, the protection fence can not be spliced, the length of the fence is fixed, the length of the fence can not be adjusted in time according to the construction range, the protection plate of the fence is not convenient enough when in replacement, and due to the fact that the ground flatness of the construction part is poor, the protection fence is poor in stability and easy to topple over, certain influence is caused when in use, and therefore the road slope construction protection fence is designed.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a road side slope construction protection rail has solved the problem of proposing in the above-mentioned background art.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the utility model provides a road side slope construction protection rail, includes the rail base, the last fixed surface of rail base is connected with the fixed column, the fender rod is connected with to the surface fixed surface of fixed column, the lower fixed surface of going up the fender rod is connected with the go-between, the surface swing joint of go-between has connecting spring, connecting spring's one end fixedly connected with guard plate, the outer fixed surface of fixed column is connected with down the fender rod, the lower fixed surface of fender rod is connected with the protecting tube down, the quantity of protecting tube is a plurality of.
Optionally, the lower surface of the upper protection rod is fixedly connected with a protection guardrail, the lower surface of the protection guardrail is fixedly connected with the upper surface of the lower protection rod, and the outer surface of the protection guardrail is fixedly connected with a connecting ring.
Optionally, the number of the fixed columns is two, one of the fixed columns is fixedly connected with a connecting rod on the outer surface, the other fixed column is fixedly connected with a fixed shaft on the outer surface, and the outer surface of the fixed shaft is movably connected with an elastic clamping piece.
Optionally, a sliding groove is formed in the upper surface of the fence base, a sliding rod is movably connected inside the sliding groove, and a fixed pressing plate is fixedly connected to the upper surface of the sliding rod.
Optionally, the lower surface of the sliding rod is fixedly connected with an installation block, and the lower surface of the installation block is fixedly connected with an insertion nail.
Optionally, the outer surfaces of the upper protection rod and the lower protection rod are fixedly connected with warning strips.
(III) advantageous effects
The utility model provides a road side slope construction protection rail possesses following beneficial effect:
1. this road slope construction protection rail, setting through elasticity card and connecting rod, at the job site, the accessible fixed axle is opened the elasticity card, the connecting rod card with on another the device is in the inside of elasticity card, splice the rail, be convenient for adjust the contained angle between a plurality of protection rails according to the actual conditions in construction place, make the rail can surround the job site, also can improve the problem that protection rail corner space is too big to cause the potential safety hazard, the interact between guard plate accessible go-between and the coupling spring carries out quick change simultaneously, be convenient for change the warning sign denotation on the guard plate in the place of difference, the usability function of the device in the reinforcing.
2. This road slope construction protection rail through the setting of solid fixed pressing plate, installation piece and inserted nail, at the job site, the accessible presses solid fixed pressing plate downwards for installation piece and inserted nail downstream make inserted nail insert soil, can strengthen the device and the joint strength on ground, strengthen the holistic stability of the device, help improving the easy unstable phenomenon of empting of focus of protection rail.
Drawings
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic structural view of the fence base of the present invention;
fig. 3 is a schematic view of the upper guard bar of the present invention.
In the figure: 1. a fence base; 2. fixing a column; 3. an upper guard bar; 4. a connecting ring; 5. a connecting spring; 6. a protection plate; 7. a lower guard bar; 8. a protective tube; 9. a guard rail; 10. a connecting rod; 11. a fixed shaft; 12. an elastic card; 13. a sliding groove; 14. a slide bar; 15. fixing the pressing plate; 16. mounting blocks; 17. inserting a nail; 18. and (4) an alarm strip.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1 to 3, the present invention provides a technical solution: a road slope construction protection fence comprises a fence base 1, wherein the upper surface of the fence base 1 is provided with a sliding groove 13, the inside of the sliding groove 13 is movably connected with a sliding rod 14, the upper surface of the sliding rod 14 is fixedly connected with a fixed pressing plate 15, the lower surface of the sliding rod 14 is fixedly connected with an installation block 16, the lower surface of the installation block 16 is fixedly connected with an insertion nail 17, through the arrangement of the fixed pressing plate 15, the installation block 16 and the insertion nail 17, in a construction site, the installation block 16 and the insertion nail 17 can move downwards by pressing the fixed pressing plate 15 downwards, the insertion nail 17 is inserted into soil, the connection strength between the device and the ground can be enhanced, the integral stability of the device is enhanced, the phenomenon that the gravity center of the protection fence is easy to topple over is improved, the upper surface of the fence base 1 is fixedly connected with two fixed columns 2, the outer surface of one fixed column 2 is fixedly connected with a, the outer surface of the other fixed column 2 is fixedly connected with a fixed shaft 11, the outer surface of the fixed shaft 11 is movably connected with an elastic clamping piece 12, the elastic clamping piece 12 and a connecting rod 10 are arranged, the elastic clamping piece 12 can be opened through the fixed shaft 11 in a construction site, the connecting rod 10 on the other device is clamped in the elastic clamping piece 12 to splice the fences, so that the included angle between a plurality of protective fences can be conveniently adjusted according to the actual condition of the construction site, the fences can surround the construction site, and the problem of potential safety hazard caused by overlarge gaps at corners of the protective fences can be solved, the outer surface of the fixed column 2 is fixedly connected with an upper protective rod 3, the lower surface of the upper protective rod 3 is fixedly connected with a guardrail 9, the lower surface of the protective guardrail 9 is fixedly connected with the upper surface of a lower protective, go up protective rod 3's lower fixed surface and be connected with go-between 4, go-between 4's surface swing joint has connecting spring 5, connecting spring 5's one end fixedly connected with guard plate 6, the interact between 6 accessible go-between 4 of guard plate and connecting spring 5 carries out quick change, be convenient for change the warning sign denotation on guard plate 6 in the place of difference, the usability function of the device in the reinforcing, protective rod 7 under the outer fixed surface of fixed column 2 is connected with, go up protective rod 3 and the equal fixedly connected with warning strip 18 in surface of lower protective rod 7, the lower fixed surface of lower protective rod 7 is connected with protective tube 8, the quantity of protective tube 8 is a plurality of.
As an optimal technical solution of the utility model: the surface of guard plate 6 is provided with the warning sign denotation.
In conclusion, when the road slope construction protection fence is used, through the arrangement of the elastic clamping piece 12 and the connecting rod 10, in a construction site, the elastic clamping piece 12 can be opened through the fixing shaft 11, the connecting rod 10 on another device is clamped inside the elastic clamping piece 12, the fences are spliced, the included angles among a plurality of protection fences can be conveniently adjusted according to the actual conditions of the construction site, so that the fences can surround the construction site, the problem of potential safety hazards caused by overlarge gaps at the corners of the protection fences can be solved, meanwhile, the protection plates 6 can be rapidly replaced through the interaction between the connecting rings 4 and the connecting springs 5, warning sign slogans on the protection plates 6 can be conveniently replaced in different sites, the usability function of the device is enhanced, through the arrangement of the fixed pressing plate 15, the mounting blocks 16 and the inserting nails 17, in the construction site, the fixed pressing plate 15 can be pressed, make installation piece 16 and peg 17 remove downwards, make peg 17 insert soil, can strengthen the device and the intensity of connection on ground, strengthen the holistic stability of the device, help improving the easy unstable phenomenon of toppling over of focus of protection rail.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. The utility model provides a road side slope construction protection rail, includes rail base (1), its characterized in that: the fence comprises a fence base (1), and is characterized in that a fixing column (2) is fixedly connected to the upper surface of the fence base (1), an upper protection rod (3) is fixedly connected to the outer surface of the fixing column (2), a connecting ring (4) is fixedly connected to the lower surface of the upper protection rod (3), a connecting spring (5) is movably connected to the outer surface of the connecting ring (4), a protection plate (6) is fixedly connected to one end of the connecting spring (5), a lower protection rod (7) is fixedly connected to the outer surface of the fixing column (2), a protection pipe (8) is fixedly connected to the lower surface of the lower protection rod (7), and the number of the protection pipes (8) is multiple.
2. The road slope construction protection fence according to claim 1, characterized in that: the lower fixed surface of going up protection pole (3) is connected with protection railing (9), the lower fixed surface of protection railing (9) is connected with the upper surface of protection pole (7) down, the outer fixed surface of protection railing (9) is connected with go-between (4).
3. The road slope construction protection fence according to claim 1, characterized in that: the number of the fixed columns (2) is two, the outer surface of one of the fixed columns (2) is fixedly connected with a connecting rod (10), the outer surface of the other fixed column (2) is fixedly connected with a fixed shaft (11), and the outer surface of the fixed shaft (11) is movably connected with an elastic clamping piece (12).
4. The road slope construction protection fence according to claim 1, characterized in that: the fence is characterized in that a sliding groove (13) is formed in the upper surface of the fence base (1), a sliding rod (14) is movably connected inside the sliding groove (13), and a fixed pressing plate (15) is fixedly connected to the upper surface of the sliding rod (14).
5. The road slope construction protection fence according to claim 4, characterized in that: the lower surface of the sliding rod (14) is fixedly connected with an installation block (16), and the lower surface of the installation block (16) is fixedly connected with an inserted nail (17).
6. The road slope construction protection fence according to claim 1, characterized in that: the outer surfaces of the upper protection rod (3) and the lower protection rod (7) are fixedly connected with warning strips (18).
CN201921413890.3U 2019-08-28 2019-08-28 Road side slope construction protection fence Expired - Fee Related CN210636916U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921413890.3U CN210636916U (en) 2019-08-28 2019-08-28 Road side slope construction protection fence

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921413890.3U CN210636916U (en) 2019-08-28 2019-08-28 Road side slope construction protection fence

Publications (1)

Publication Number Publication Date
CN210636916U true CN210636916U (en) 2020-05-29

Family

ID=70790849

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921413890.3U Expired - Fee Related CN210636916U (en) 2019-08-28 2019-08-28 Road side slope construction protection fence

Country Status (1)

Country Link
CN (1) CN210636916U (en)

Similar Documents

Publication Publication Date Title
CN210636916U (en) Road side slope construction protection fence
CN210917142U (en) Road green belt isolation guardrail
CN212002670U (en) Rail guard is used in public road bridge roof beam construction
CN213710632U (en) Rail guard is used in municipal works construction
CN210316801U (en) Anti-climbing guardrail for municipal engineering
CN210798499U (en) Road and bridge engineering protector
CN211598006U (en) Highway maintenance engineering is with collapsible rail
CN209891816U (en) Protective fence for construction building
CN209620764U (en) Assembled moves construction guard fender
CN209456837U (en) Pavement Skid Resistance device
CN210178093U (en) Construction rail guard is built in portable formula room
CN216766981U (en) Building construction foundation ditch guardrail
CN204644867U (en) A kind of bridge Assembled fence
CN218263293U (en) Road safety protection combined brick for mountain road section
CN211446691U (en) Height limiting device for traffic
CN217642425U (en) Highway bridge central separation zone silicon core pipe box installation operation platform
CN214942675U (en) Rail guard simply assembles in bridge floor construction
CN219344312U (en) Construction fence
CN215056012U (en) Highway that stability is good rail guard for protection engineering
CN210976838U (en) Rail guard is used in municipal works road construction
CN204691290U (en) A kind of building site protector
CN208219504U (en) A kind of combination-type guardrail
CN216305591U (en) Protection device for highway construction
CN214143277U (en) Road and bridge rail guard supporting base
CN210216248U (en) Flexible protection device for road traffic facilities

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200529

Termination date: 20210828