CN210632095U - Prevent leaching tower that acid gas leaked - Google Patents
Prevent leaching tower that acid gas leaked Download PDFInfo
- Publication number
- CN210632095U CN210632095U CN201921223310.4U CN201921223310U CN210632095U CN 210632095 U CN210632095 U CN 210632095U CN 201921223310 U CN201921223310 U CN 201921223310U CN 210632095 U CN210632095 U CN 210632095U
- Authority
- CN
- China
- Prior art keywords
- tower
- acid
- cover body
- acid gas
- tower body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Physical Or Chemical Processes And Apparatus (AREA)
- Gas Separation By Absorption (AREA)
Abstract
The utility model discloses a prevent leaching tower that acid gas leaked, first acid-resistant brick and the acid-resistant brick of second through setting up, build the acid-resistant brick of two-layer thickness with the tower body by laying bricks or stones, increase the thickness of brick and can effectual improve equipment's life, realize the chemical corrosion reaction that prevents the steel casing through isolated outside air, thereby realize the protection of tower body, through the cover body that sets up, through the fixed position of adjusting the connecting rod, adjust the position of the cover body, conveniently add scrap iron bits and handle from the feed inlet combustion gas. Through setting up the cover body, when not increasing the slitter edge, the cover body is closed, and when needing to add, the cover body is opened.
Description
Technical Field
The utility model relates to a leaching tower technical field specifically is a prevent leaching tower that acid gas leaked.
Background
The leaching tower is a core device in a desilication pretreatment system, and the process of generating FeCl2 through free acid combination reaction in waste acid occurs in the device.
And current leaching tower casing itself is not anticorrosive, and the anticorrosive structure of leaching tower is more single, can not be fine play anticorrosive effect, makes the leaching tower take place accidents such as acid leakage easily, and the reaction that the leaching tower takes place has combustible gas to produce, and open structure need handle its gas that gives off to avoid causing the atmosphere pollution.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a: in order to solve the problems that the corrosion-resistant structure of the leaching tower is single, so that the leaching tower is easy to generate accidents such as acid leakage and the like, combustible gas can be generated in the leaching tower, and the gas emitted by the leaching tower needs to be treated by an open structure so as to avoid the problem of atmospheric pollution, the leaching tower for preventing the acid gas from leaking is provided.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a prevent leaching tower that acid gas leaked, includes the tower body, the outside of tower body bottom is provided with the base, the inner wall of tower body has set gradually first acid-resistant brick, the acid-resistant brick of second, acid-resistant rubber, steel casing and coating from outside to inside, the top of tower body is provided with the feed inlet, the top of tower body one side is provided with the overflow mouth, the fan is installed to one side at base top, one side of fan is provided with the support frame, the output of fan is connected with the tuber pipe that extends to the support frame top, the end-to-end connection of tuber pipe has the bellows, the end of bellows is fixed with the cover body, the both ends of cover body bottom all rotate and are connected with the connecting rod.
Preferably, both ends of the support frame and the bottom of the connecting rod are provided with a plurality of groups of corresponding threaded holes, and the connecting rod and the support frame are fixedly connected through a screw rod.
Preferably, the bottom of tower body is provided with the feed inlet, and feed inlet and feedway all are the toper structure.
Preferably, the cross section of the cover body is in a trapezoidal structure.
Preferably, the top of the support frame is provided with a groove.
Preferably, the outer surface of the tower body is provided with a heat insulation layer.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses a first acid-resistant brick and the acid-resistant brick of second that set up build the acid-resistant brick of two-layer thickness with the tower body by laying bricks or stones, increase the thickness of brick can effectual improve equipment's life, the electrochemical corrosion reaction of steel casing is blocked that the coating can be fine, realize preventing the chemical corrosion reaction of steel casing through isolating the outside air, thereby realize the protection of tower body, through the cover body that sets up, through the fixed position of adjusting the connecting rod, adjust the position of the cover body, conveniently add scrap iron bits and handle the gas that discharges from the feed inlet; through setting up the cover body, when not increasing the slitter edge, the cover body is closed, and when needing to add, the cover body is opened.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of a partial structure of the present invention;
fig. 3 is a schematic structural diagram of the cover body and the supporting frame of the present invention.
In the figure: 1. a tower body; 2. a base; 3. a first acid-resistant brick; 4. a second acid-resistant brick; 5. acid-resistant rubber; 6. a steel shell; 7. a coating layer; 8. a feedwell; 9. an overflow port; 10. a fan; 11. an air duct; 12. a support frame; 13. a bellows; 14. a cover body; 15. a threaded hole; 16. a connecting rod.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The fans mentioned in the utility model (model is QS48-6Y) can be purchased in the market or by private ordering.
Referring to fig. 1-3, an immersion tower for preventing acid gas from leaking comprises a tower body 1, a base 2 is arranged on the outer side of the bottom of the tower body 1, a first acid-resistant brick 3, a second acid-resistant brick 4, acid-resistant rubber 5, a steel shell 6 and a coating layer 7 are sequentially arranged on the inner wall of the tower body 1 from outside to inside, a feed port 8 is arranged at the top of the tower body 1, an overflow port 9 is arranged at the top of one side of the tower body 1, a fan 10 is installed at one side of the top of the base 2, a support frame 12 is arranged at one side of the fan 10, an output end of the fan 10 is connected with an air pipe 11 extending to the top of the support frame 12, a corrugated pipe 13 is connected to the tail end of the air pipe 11, a cover body 14.
The utility model discloses an overflow mouth 9 that sets up makes the acidizing fluid after 1 inside reactions of tower body flow from overflow mouth 9 to get into the cooler and carry out operation on next step, through the double-deck acidproof brick that sets up, increase the life that the thickness of acidproof brick can effectual improve equipment.
Please refer to fig. 1 and 3, two ends of the supporting frame 12 and the bottom of the connecting rod 16 are provided with a plurality of sets of corresponding threaded holes 15, and the connecting rod 16 and the supporting frame 12 are fixedly connected by a screw.
This kind of prevent leaching tower that acid gas leaked through screw hole 15 that sets up, screw hole 15 on connecting rod 16 and the support frame 12 aligns, facilitates the use screw rod to fix the cover body 14.
Please refer to fig. 1 and 2, a feed inlet is provided at the bottom of the tower body 1, and the feed inlet 8 are both cone-shaped.
This kind of prevent leaching tower that acid gas leaked through feed inlet and feed inlet 8 that set up, makes the acid body from the feed inlet by supreme tower body 1 that gets into down, the intensive mixing of the acid of being more convenient for of toper structure and waste material.
Referring now to fig. 1 and 2, the cover 14 has a trapezoidal cross-section.
The leaching tower for preventing the acid gas from leaking out has a trapezoidal structure through the cross section of the cover body 14, and the shape of the cover body 14 is matched with the feed port 8, so that the discharged gas can be better sucked away.
Referring to fig. 1 and 3, the top of the support frame 12 is provided with a groove.
This kind of prevent leaching tower that acid gas leaked carries on spacingly to the tuber pipe 11 of placing through the recess that sets up, and better cooperation connecting rod 16 is to the fixed of cover body 14.
Referring to fig. 1 and 2, the outer surface of the tower 1 is provided with a thermal insulation layer.
This kind of prevent leaching tower that acid gas leaked through the insulating layer that tower body 1 surface set up, the insulating layer can be thermal-insulated coating, can effectually protect the human body.
The working principle is as follows: waste materials are added into the tower body 1 through the feed port 8 by an external electromagnetic crane, in the normal work of the tower body 1, the inside of the tower body 1 is filled with the waste materials (such as waste scrap iron and the like), waste acid flows into equipment from the bottom of the tower body 1, under the condition of high temperature, the acid volatilizes and flows from bottom to top to fully react with the waste materials in the tower body 1, and then flows out from the overflow port 9 so as to enter a cooling process (the specific principle is not described herein), the coating layer 7 can be a metal base material protection system and consists of REMAKE metal base self-repairing bottom surface coating and surface isolation coating, the metal base self-repairing bottom surface coating can convert iron rust on the surface of the steel shell 6 into a compact oxidation film through chemical reaction, in addition, a cathode protection method is introduced into the coating, metal elements with strong activity are added in the coating, the anode protection effect is achieved, and the elements can be oxidized in preference to iron, thereby thoroughly blocked steel casing 6 and by further oxidation corrosion, surface isolation coating has efficient sealed effect, the coating that its formed can effectually block outside air, water, corrosive substance and steel casing 6 direct contact, fundamentally has prevented steel casing 6 from being by oxidation corrosion (can be the method of plating or spraying plating and cover on steel casing 6 surface, improve the corrosion resisting property of steel), when not adding the waste material to the tower body inside, the position of manual regulation cover body 14 makes the position of screw hole 15 aim at, makes cover body 14 aim at feed port 8, use the screw rod to tighten connecting rod 16, then fan 10 draws the gas of following feed port 8 exhaust, then discharge to the scrubbing tower in, handle the gas.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Claims (6)
1. The utility model provides a prevent leaching tower that acid gas leaked, includes tower body (1), its characterized in that: the outer side of the bottom of the tower body (1) is provided with a base (2), the inner wall of the tower body (1) is sequentially provided with a first acid-resistant brick (3), a second acid-resistant brick (4), acid-resistant rubber (5), a steel shell (6) and a coating layer (7) from outside to inside, the top of the tower body (1) is provided with a feed opening (8), the top of one side of the tower body (1) is provided with an overflow opening (9), a fan (10) is arranged on one side of the top of the base (2), a support frame (12) is arranged on one side of the fan (10), the output end of the fan (10) is connected with an air pipe (11) extending to the top of the support frame (12), the tail end of the air pipe (11) is connected with a corrugated pipe (13), the tail end of the corrugated pipe (13) is fixed with a cover body (14), both ends of the bottom of the cover body (14) are rotatably connected with connecting rods (16).
2. The leaching tower for preventing the acid gas from leaking out as claimed in claim 1, wherein: the two ends of the support frame (12) and the bottom of the connecting rod (16) are provided with a plurality of groups of corresponding threaded holes (15), and the connecting rod (16) and the support frame (12) are fixedly connected through a screw rod.
3. The leaching tower for preventing the acid gas from leaking out as claimed in claim 1, wherein: the bottom of tower body (1) is provided with the feed inlet, and feed inlet and feedwell (8) all are the toper structure.
4. The leaching tower for preventing the acid gas from leaking out as claimed in claim 1, wherein: the cross section of the cover body (14) is of a trapezoidal structure.
5. The leaching tower for preventing the acid gas from leaking out as claimed in claim 1, wherein: the top of the support frame (12) is provided with a groove.
6. The leaching tower for preventing the acid gas from leaking out as claimed in claim 1, wherein: and a heat insulation layer is arranged on the outer surface of the tower body (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921223310.4U CN210632095U (en) | 2019-07-31 | 2019-07-31 | Prevent leaching tower that acid gas leaked |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921223310.4U CN210632095U (en) | 2019-07-31 | 2019-07-31 | Prevent leaching tower that acid gas leaked |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210632095U true CN210632095U (en) | 2020-05-29 |
Family
ID=70791422
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921223310.4U Active CN210632095U (en) | 2019-07-31 | 2019-07-31 | Prevent leaching tower that acid gas leaked |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210632095U (en) |
-
2019
- 2019-07-31 CN CN201921223310.4U patent/CN210632095U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210632095U (en) | Prevent leaching tower that acid gas leaked | |
CN207774811U (en) | A kind of graphitizing furnace suitable for lithium battery graphite cathode material production line | |
CN101775611B (en) | Self-convection radiating electrolytic water oxyhydrogen gas generator | |
CN204707295U (en) | The quick detachable electrothermal tube of a kind of industrial anticorrosion | |
CN212283971U (en) | Pollution-reducing water reducing agent production equipment | |
CN212658050U (en) | Energy-saving scrap iron smelting furnace | |
CN220048055U (en) | Supercritical reactor structure | |
CN219734349U (en) | Protection structure of rotary valve | |
CN217781011U (en) | Kiln chimney with cooling function | |
CN219377103U (en) | High-temperature-resistant heat-insulation reaction inner cavity of semiconductor waste gas treatment equipment | |
CN210510759U (en) | Cement plant exhaust gas pipeline with anticorrosive insulation construction | |
CN208920180U (en) | A kind of immersion container type phase transition heat accumulation unit | |
CN210151200U (en) | Energy-saving galvanizing furnace for galvanizing | |
CN205347579U (en) | Acid copper chloride etching waste liquor regeneration recovery plant | |
CN219829487U (en) | Graphitization furnace for preparing lithium ion battery cathode material | |
CN212457949U (en) | Gas conversion heating electric furnace for heating element of stainless steel assembly | |
CN218705650U (en) | Polycarboxylate water reducing agent storage jar for concrete | |
CN213139909U (en) | Liquid sulfur containing tank used in chemical fertilizer production | |
CN212741496U (en) | Flue gas waste heat utilization device of hot galvanizing furnace | |
CN219981064U (en) | Anti-blocking heating rod for semiconductor tail gas pipeline | |
CN214650798U (en) | Sulfuric acid buffer tank that unloads | |
CN208995178U (en) | Vacuum distillation recycling subtracts top fixed gas device | |
CN212151629U (en) | Lithium battery negative electrode material tandem type vapor deposition graphitization purification furnace | |
CN214808550U (en) | Waste acid concentration jacket water-cooling ageing tank | |
CN216378283U (en) | Energy-saving device of VD (vacuum degassing) furnace |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |