CN210563341U CN201921229911.6U CN201921229911U CN210563341U CN 210563341 U CN210563341 U CN 210563341U CN 201921229911 U CN201921229911 U CN 201921229911U CN 210563341 U CN210563341 U CN 210563341U
Authority
CN
China
Prior art keywords
perforation
channel
big
little
rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921229911.6U
Other languages
Chinese (zh)
Inventor
梁苏珊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kaiping Pengfeng Metal Frame Factory
Original Assignee
Kaiping Pengfeng Metal Frame Factory
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kaiping Pengfeng Metal Frame Factory filed Critical Kaiping Pengfeng Metal Frame Factory
Priority to CN201921229911.6U priority Critical patent/CN210563341U/en
Application granted granted Critical
Publication of CN210563341U publication Critical patent/CN210563341U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The utility model discloses a scaffold puts up connecting pull rod that anticreep goes out, including the body of rod and the connector of setting at body of rod both ends, the connector includes big perforation, little perforation and anticreep portion, big fenestrate radius is greater than little fenestrate radius, anticreep portion sets up will between big perforation and the little perforation big perforation is separated with little perforation, big perforation and little perforation are in through a setting the other installation passageway intercommunication of anticreep portion, anticreep portion supports the top fastener and prevents that the fastener from following little perforation is deviate from the straight line and is arrived big perforation. The embodiment of the utility model provides an utilize anticreep portion to form the structure of supporting to the fastener, can prevent that the fastener pine from directly leading to the problem that scaffold overall structure collapses when taking off, improved the security that scaffold used.

Description

Anti-falling scaffold connecting pull rod
Technical Field
The utility model relates to a scaffold frame accessory, in particular to scaffold frame connecting pull rod that anticreep goes out.
Background
The connecting pull rod of the scaffold generally adopts the following connecting heads: referring to fig. 1, the connector is a flat connector, a large through hole and a small through hole are punched on the surface of the flat connector, the large through hole and the small through hole are communicated through a linear channel, a fastener, usually a bolt and a nut, integrally penetrates through the large through hole, then moves into the small through hole through a bolt channel, and the nut is screwed in the small through hole due to the fact that the radius of the small through hole is smaller than that of the nut, and the flat connector is compressed through the nut to achieve fixing; but foretell connection structure has certain potential safety hazard, because the nut of screwing relies on manual operation, the nut probably pine takes off after repetitious usage, in case the pine takes off, the bolt directly landing is to the big perforation in, causes scaffold overall structure to collapse, the incident appears easily.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to solve one of the technical problem that exists among the prior art at least, provide a scaffold puts up connecting rod that prevents deviating from, can prevent that the fastener from deviating from.
The utility model provides a scaffold puts up connecting pull rod that anticreep goes out, including the body of rod and the connector of setting at body of rod both ends, the connector includes big perforation, little perforation and anticreep portion, big fenestrate radius is greater than little fenestrate radius, anticreep portion sets up will between big perforation and the little perforation big perforation is separated with little perforation, big perforation and little perforation are in through a setting the other installation passageway intercommunication of anticreep portion, anticreep portion supports the top fastener and prevents that the fastener from following little perforation is deviate from the straight line and is arrived big perforation.
The anti-disengaging scaffold connecting pull rod at least has the following beneficial effects: the fastener wholly penetrates big perforation to in the installation passageway removes little perforation, because not straight line intercommunication between big perforation and the little perforation, consequently even the fastener takes off from little perforation, also can be withstood by anticreep portion, can not deviate from to the big perforation by the straight line, consequently can keep the overall structure of scaffold frame, reduce the emergence of incident.
Further, according to the utility model relates to a scaffold puts up connecting rod that anticreep goes out, the installation passageway includes first passageway and second passageway, first passageway and second passageway are not on same straight line, first passageway intercommunication the big perforation, the second passageway intercommunication little perforation. Since the separation preventing portion separates the large through hole and the small through hole, the installation passage bypasses the separation preventing portion to communicate the two through holes, thereby forming a first passage and a second passage which are connected.
Further, according to the utility model relates to a scaffold puts up connecting rod that anticreep goes out, first passageway and second passageway are mutually perpendicular, the junction of first passageway and second passageway is the fillet. For the right-angle bent installation channel, the fastener needs force in at least two directions for releasing, and the connection pull rod usually only has force in the axial direction or the angle near the axial direction, so the right-angle bent installation channel can effectively prevent the fastener from releasing.
Further, according to the utility model a scaffold puts up connecting rod that anticreep goes out, an limit of first passageway with it is tangent to bore greatly, an limit of second passageway with it is tangent to bore for a short time. In order to ensure that the fastener moves smoothly in the installation channel, the channel is smooth in a tangent mode, and the installation is convenient.
Further, according to the utility model relates to a scaffold puts up connection pull rod that anticreep goes out, big perforation and little perforation are pressed the length direction of the body of rod distributes, the length direction of first passageway with the length direction of the body of rod is the same. The length direction of the second channel is equal to the length direction of the rod body, the length direction of the second channel is perpendicular to the length direction of the rod body, and the second channel is abutted to the small through hole, and the fastener penetrates into the small through hole to be fastened, so that the fastener is not easy to slip into the first channel even if the fastener is separated.
Further, according to the utility model relates to a scaffold puts up connection pull rod that anticreep goes out, the connector is flat joint, the connector with the body of rod integrated into one piece, the connector is gone out by stamping equipment punching press after flattening big perforation, little perforation and installation passageway. The thickness of the flat joint is the thickness of two layers of rod body walls, and the structure is firmer.
Drawings
The present invention will be further described with reference to the accompanying drawings and examples;
FIG. 1 is a schematic view of a conventional tie rod;
fig. 2 is a schematic structural diagram of an embodiment of the present invention;
fig. 3 is a schematic view of an installation structure of an embodiment of the present invention;
fig. 4 and 5 are two overall structures of the embodiment of the present invention, respectively.
Detailed Description
This section will describe in detail the embodiments of the present invention, preferred embodiments of the present invention are shown in the attached drawings, which are used to supplement the description of the text part of the specification with figures, so that one can intuitively and vividly understand each technical feature and the whole technical solution of the present invention, but they cannot be understood as the limitation of the protection scope of the present invention.
In the description of the present invention, it should be understood that the orientation or positional relationship indicated with respect to the orientation description, such as up, down, front, rear, left, right, etc., is based on the orientation or positional relationship shown in the drawings, and is only for convenience of description and simplification of description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.
In the description of the present invention, a plurality of means are one or more, a plurality of means are two or more, and the terms greater than, less than, exceeding, etc. are understood as not including the number, and the terms greater than, less than, within, etc. are understood as including the number. If the first and second are described for the purpose of distinguishing technical features, they are not to be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated or implicitly indicating the precedence of the technical features indicated.
In the description of the present invention, unless there is an explicit limitation, the words such as setting, installation, connection, etc. should be understood in a broad sense, and those skilled in the art can reasonably determine the specific meanings of the above words in combination with the specific contents of the technical solution.
Referring to fig. 2 and 3, an embodiment of the present invention relates to an anti-slip scaffold connecting rod, including a rod body 1 and connectors 100 disposed at two ends of the rod body 1, the connectors 100 include a large perforation 110, a small perforation 120 and an anti-slip portion 130, a radius of the large perforation 110 is greater than a radius of the small perforation 120, the anti-slip portion 130 is disposed between the large perforation 110 and the small perforation 120 to separate the large perforation 110 from the small perforation 120, the large perforation 110 and the small perforation 120 are communicated through an installation channel 140 disposed beside the anti-slip portion 130, and the anti-slip portion 130 supports a fastener to prevent the fastener from being linearly released from the small perforation 120 to the large perforation 110.
In this embodiment, referring to fig. 3, the fastener is exemplified by a bolt 2 and a nut 3, wherein the diameter of the external screw rod 4 in the bolt 2 is smaller than the width of the installation channel 140, the radius of the head 5 of the bolt 2 and the outer diameter of the nut 3 are both larger than the radius of the small through hole 120 and smaller than the radius of the large through hole 110, when installing, the fastener integrally penetrates the large through hole 110, the large through hole 110 is located between the head 5 of the bolt 2 and the nut 3, then the fastener enters the small through hole 120 along the installation channel 140, and by screwing the nut 3, the head 5 of the bolt 2 and the nut 3 form a clamping structure on both sides of the small through hole 120, thereby being fixed.
The installation channel 140 includes a first channel 141 and a second channel 142, the first channel 141 and the second channel 142 are not in the same line, the first channel 141 communicates with the large through hole 110, and the second channel 142 communicates with the small through hole 120. Regarding the shape of the mounting channel 140, it is preferable that the first channel 141 and the second channel 142 are perpendicular to each other, and a junction of the first channel 141 and the second channel 142 is rounded. In addition to the right-angled bending, other bending forms such as obtuse-angled bending may be used, and at this time, the shape of the anti-slip part 130 is changed accordingly while the anti-slip function is maintained. The utility model discloses connector 100 is flat joint, connector 100 and body of rod 1 integrated into one piece, and connector 100 is through flattening the back by stamping equipment punching press out big perforation 110, little perforation 120 and installation passageway 140, consequently according to the shape of punching press different, and anticreep portion 130's shape is also different.
One side of the first channel 141 is tangent to the large perforation 110 and one side of the second channel 142 is tangent to the small perforation 120. The large perforation 110 and the small perforation 120 are distributed along the length direction of the rod body 1, and the length direction of the first channel 141 is the same as the length direction of the rod body 1. This structure of the connecting rod is generally applied to a cross brace, i.e. a diagonal draw bar, and is installed along the length direction of the rod body 1, so that the first channel 141 of the installation channel 140 is installed more easily in the same direction as the length of the rod body 1.
Overall speaking, the connectors 100 at two ends of the rod body 1 according to the embodiment of the present invention have a plurality of distribution modes, for example, referring to fig. 4 and 5, the connectors 100 at two ends respectively have central symmetry and axial symmetry, and different forms of connecting pull rods can be selected according to the connecting structure of the actual scaffold.
The embodiment of the utility model provides an utilize anticreep portion 130 to form the structure of supporting to the fastener, can prevent that the fastener from directly leading to the problem that scaffold overall structure collapses when taking off, improved the security that scaffold used.
The embodiments of the present invention have been described in detail with reference to the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made without departing from the gist of the present invention within the knowledge range of those skilled in the art.

Claims (6)

1. The utility model provides a scaffold puts up connecting rod that anticreep is gone out which characterized in that: including the body of rod (1) and set up connector (100) at body of rod (1) both ends, connector (100) are including big perforation (110), little perforation (120) and anticreep portion (130), the radius of big perforation (110) is greater than the radius of little perforation (120), anticreep portion (130) set up between big perforation (110) and the little perforation (120) will big perforation (110) and little perforation (120) separate, big perforation (110) and little perforation (120) are in through a setting the other erection channel (140) intercommunication of anticreep portion (130), anticreep portion (130) are supported the fastener and are prevented the fastener follow little perforation (120) straight line is deviate from to big perforation (110).
2. An anti-drop scaffolding tie rod according to claim 1, wherein: the mounting channel (140) comprises a first channel (141) and a second channel (142), the first channel (141) and the second channel (142) are not on the same straight line, the first channel (141) is communicated with the big perforation (110), and the second channel (142) is communicated with the small perforation (120).
3. An anti-drop scaffolding tie rod according to claim 2, wherein: the first channel (141) and the second channel (142) are perpendicular to each other, and the joint of the first channel (141) and the second channel (142) is a round angle.
4. An anti-drop scaffolding tie rod according to claim 2, wherein: one side of the first channel (141) is tangent to the large perforation (110) and one side of the second channel (142) is tangent to the small perforation (120).
5. An anti-drop scaffolding tie rod according to claim 2, wherein: the large perforation (110) and the small perforation (120) are distributed along the length direction of the rod body (1), and the length direction of the first channel (141) is the same as the length direction of the rod body (1).
6. An anti-drop scaffolding tie rod according to claim 1, wherein: connector (100) are flat joint, connector (100) with body of rod (1) integrated into one piece, connector (100) are through flattening back by stamping equipment punching press play big perforation (110), little perforation (120) and installation passageway (140).
CN201921229911.6U 2019-07-31 2019-07-31 Anti-falling scaffold connecting pull rod Active CN210563341U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921229911.6U CN210563341U (en) 2019-07-31 2019-07-31 Anti-falling scaffold connecting pull rod

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921229911.6U CN210563341U (en) 2019-07-31 2019-07-31 Anti-falling scaffold connecting pull rod

Publications (1)

Publication Number Publication Date
CN210563341U true CN210563341U (en) 2020-05-19

Family

ID=70623282

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921229911.6U Active CN210563341U (en) 2019-07-31 2019-07-31 Anti-falling scaffold connecting pull rod

Country Status (1)

Country Link
CN (1) CN210563341U (en)

Similar Documents

Publication Publication Date Title
US3672710A (en) Coupling for connecting together building units
US7404736B2 (en) Patch panel and strain relief bar assembly
DE20116248U1 (en) Device for joining boards
CN210563341U (en) Anti-falling scaffold connecting pull rod
WO2016012081A1 (en) Fastener for a mounting rail
CN111502165A (en) Pull buckle leveling installation structure and method for assembly type wallboard
DE202018006297U1 (en) A support frame for an insulation frame for a roof window
CN206129813U (en) Stand and crossbeam connection structure
DE102010018983B4 (en) Attachment for a component, in particular on the body of a motor vehicle
CN212405878U (en) Pull buckle leveling installation structure of assembled wallboard
CN211817441U (en) Pull rod connecting sleeve
CN213174198U (en) Plate groove embedded part convenient to install
EP2498356A1 (en) Theft protection device for a system that can be fixed to the wall
CN211219675U (en) Fastening device
CN204520060U (en) Photo frame buckles
CN213243685U (en) Motor rapid Assembly structure
CN219513353U (en) Parallel groove clamp
CN215055563U (en) Adjustable steel mesh net connecting piece
CN217079641U (en) Building outer wall climbing frame support device
CN210870561U (en) Drawing board for children
CN212534679U (en) After-loading connector for internal expanding groove pipe
CN103527579B (en) For connecting the connection part of facial canal
CN216892899U (en) Connecting assembly for heat preservation system and heat preservation system
CN214302824U (en) Scaffold wall connecting piece
CN211548723U (en) Cross bar