CN210562166U - Anchor rod construction device for constructional engineering - Google Patents

Anchor rod construction device for constructional engineering Download PDF

Info

Publication number
CN210562166U
CN210562166U CN201920942191.1U CN201920942191U CN210562166U CN 210562166 U CN210562166 U CN 210562166U CN 201920942191 U CN201920942191 U CN 201920942191U CN 210562166 U CN210562166 U CN 210562166U
Authority
CN
China
Prior art keywords
pipe
rod
pouring
stock
pours
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920942191.1U
Other languages
Chinese (zh)
Inventor
施华锋
张秋玲
孙久瑞
董博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201920942191.1U priority Critical patent/CN210562166U/en
Application granted granted Critical
Publication of CN210562166U publication Critical patent/CN210562166U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a stock construction equipment that building engineering used, the electric iron comprises a pole body, movable mounting has the connecting pipe between the body of rod, and is equipped with the adjustment tank on the connecting pipe, one side fixed mounting of the body of rod is connected with pours the pipe, and is equipped with on pouring the pipe and pours the mouth, it is equipped with supporting spring to pour inside one side of pipe, one side movable mounting of supporting spring has the closing plate, the top of pouring the pipe is equipped with the air vent, and the inside of pouring the pipe is equipped with the breather pipe. The utility model discloses be provided with supporting spring and closing plate cooperation, can seal the pouring mouth, cause the condition of pouring the mouth and stopping up because of earth when avoiding the stock insert hole body, improved the practicality of stock, be provided with air vent and breather pipe cooperation, can ventilate the inside of the hole body, be provided with only starch stopper and baffle cooperation, can go out to seal stock and drill way, avoided the thick liquid from the condition that the export spilt, make stock convenient to use more, convenient to popularize and use.

Description

Anchor rod construction device for constructional engineering
Technical Field
The utility model relates to a construction technical field specifically is an anchor rod construction equipment that building engineering used.
Background
The anchor rod is the most basic component of roadway support in the contemporary coal mine, and the anchor rod reinforces the surrounding rocks of the roadway together to support the surrounding rocks per se. The conventional anchor rod is not only used for mines, but also used in engineering technology for reinforcing main bodies of slopes, tunnels and dams. The anchor rod is used as a tension member penetrating into the stratum, one end of the anchor rod is connected with an engineering structure, the other end of the anchor rod penetrates into the stratum, the whole anchor rod is divided into a free section and an anchoring section, the free section is an area for transmitting the tension at the head of the anchor rod to an anchoring body, and the anchor rod is used for applying prestress to the anchor rod.
The existing anchor rod has the following defects that 1, when the existing anchor rod enters a foundation, a cement pouring opening is easily blocked by soil, so that the practicability of the anchor rod is reduced; 2. simultaneously current stock when carrying out mud and filling, because of the outside seal condition that leads to the mud outflow not tight, reduced the fastness of mud in inside, reduced the practicality of stock.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an stock construction equipment that building engineering used to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides an anchor rod construction equipment that building engineering used, includes the body of rod, movable mounting has the connecting pipe between the body of rod, and is equipped with the adjustment tank on the connecting pipe, one side fixed mounting of the body of rod is connected with pours the pipe, and pours and be equipped with on the pipe and pour the mouth, the inside one side of pouring is equipped with supporting spring, one side movable mounting of supporting spring has the closing plate, the top of pouring the pipe is equipped with the air vent, and the inside of pouring the pipe is equipped with the breather pipe, one side fixed mounting who pours the pipe has the anchor head, the outside cover of the body of rod has only to starch the stopper, and only one side movable mounting who star.
Preferably, one side of the threaded rod is rotatably provided with a supporting plate, and the supporting plate is provided with anti-skidding threads.
Preferably, one side of the vent pipe is fixedly connected with a rotary joint.
Preferably, one side of the baffle is rotatably provided with an adjusting pipe.
Preferably, one side of the rod body is fixedly provided with a connecting seat.
Preferably, the other side of the threaded rod is fixedly provided with an adjusting wheel.
Compared with the prior art, the beneficial effects of the utility model are that: compared with the traditional anchor rod device, the anchor rod construction device for the building engineering is provided with the rod body matched with the connecting pipe, can transmit slurry, can adjust the length of the anchor rod according to actual conditions, has the practicability of the anchor rod, enlarges the application range, can pour the slurry in the hole body by being provided with the pouring port, improves the practicability of the anchor rod, can seal the pouring port by being provided with the supporting spring matched with the sealing plate, avoids the condition that the pouring port is blocked due to the soil when the anchor rod is inserted into the hole body, improves the practicability of the anchor rod, is provided with the air vent matched with the air vent pipe, can ventilate the inside of the hole body, improves the practicability of the anchor rod device, can seal the anchor rod and the hole outlet by being provided with the grout stop plug matched with the baffle, avoids the condition that the slurry leaks from the outlet, and ensures that the anchor rod is more convenient to, the application range is enlarged, and the popularization and the use are convenient.
Drawings
Fig. 1 is a schematic front structural view of the present invention;
FIG. 2 is a partial internal schematic view of the present invention;
fig. 3 is a schematic view of a partial structure of the present invention.
In the figure: 1. an anchor head; 2. pouring a pipe; 3. pouring a mouth; 4. a vent hole; 5. a rod body; 6. a connecting pipe; 7. an adjustment groove; 8. a grout stopping plug; 9. a baffle plate; 10. an adjusting tube; 11. a connecting seat; 12. a breather pipe; 13. a rotary joint; 14. a support spring; 15. a sealing plate; 16. a support plate; 1601. anti-skid lines; 17. a threaded rod; 18. and an adjusting wheel.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "both ends", "one end", "the other end" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element to which the reference is made must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "disposed," "connected," and the like are to be construed broadly, and for example, "connected" may be either fixedly connected or detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Referring to fig. 1-3, the present invention provides an embodiment: a roof bolt construction device for construction engineering comprises rod bodies 5, connecting pipes 6 are rotatably arranged between the rod bodies 5 through bolts, the connecting pipes 6 can connect the rod bodies 5, the extension length of the rod bodies 5 is increased, adjusting grooves 7 are formed in the connecting pipes 6, the adjusting grooves 7 are convenient for an adjusting wrench to tighten and fix the adjusting grooves 7, the situation that joints of the rod bodies 5 are loosened and fall off when in use is avoided, the firmness of the rod bodies 5 in use is improved, one side of each rod body 5 is bestrewed with a pouring pipe 2 through welding, the pouring pipe 2 is provided with a pouring port 3, the pouring port 3 is convenient for discharging slurry outwards, one side inside the pouring pipe 2 is provided with a supporting spring 14, one side of the supporting spring 14 is fixedly provided with a sealing plate 15 through welding, the sealing plate 15 seals the pouring port 3 when the rod bodies 5 enter a drill hole, and the situation that slurry cannot flow out due to the fact that the pouring port 3 is blocked by soil when the rod bodies 5, meanwhile, after the slurry enters the rod body 5, the sealing plate 15 is pushed to one side by pressure, so that the slurry is discharged outside through the pouring opening 3, the top of the pouring pipe 2 is fixedly provided with a vent hole 4 by welding, and the inside of the pouring pipe 2 is fixedly connected with a vent pipe 12, the vent pipe 12 is connected with the vent hole 4 to ventilate the inside of the hole body, thereby avoiding the situation that the mud in the vacuum state in the hole body can not be injected, one side of the pouring pipe 2 is fixedly provided with an anchor head 1 through a bolt, the anchor head 1 is convenient for inserting an anchor rod into the hole body, the outside of the other side of the rod body 5 is sleeved with a grout stop plug 8, the grout stop plug 8 can seal the inlet of the hole body, the condition that slurry flows out from the outlet when the slurry is poured is avoided, stop a thick liquid stopper 8 one side cover and have baffle 9, baffle 9 is convenient for fill in and be fixed stopping thick liquid stopper 8, and threaded rod 17 is installed in the last rotation of baffle 9.
Further, one side of the threaded rod 17 is rotatably provided with a support plate 16, and the support plate 16 is provided with anti-skidding lines 1601. In the embodiment, the bearing area of the threaded rod 17 is increased by the support plate 16, the support plate 16 is convenient for the threaded rod 17 to be connected with a pile body, the anti-skid grains 1601 increase the anti-skid performance of the support plate 16, and the situation that the anchor rod drops when being used transversely is avoided.
Further, a rotary joint 13 is fixedly connected to one side of the vent pipe 12. In the embodiment, the rotary joint 13 is convenient to be connected with an external air pipe, so that the winding condition of the air pipe 12 during rotation of the anchor rod is avoided, and the practicability during use is improved.
Further, one side of the baffle 9 is rotatably provided with an adjusting pipe 10. In the embodiment, the adjusting pipe 10 can fix the baffle 9 and the grout stopping plug 8 through rotation adjustment, so that the condition that the grout stopping plug 8 falls off due to pressure when grout is poured is avoided, and the stability of the grout stopping plug 8 is improved.
Further, a connecting seat 11 is fixedly installed on one side of the rod body 5. In the embodiment, the connecting seat 11 is convenient for be connected with the slip casting device, the condition of leaking thick liquid appears when having avoided the slip casting, has increased the practicality of stock.
Further, an adjusting wheel 18 is fixedly arranged on the other side of the threaded rod 17. In the embodiment, the adjusting wheel 18 is fixedly installed through a bolt, and a worker can rotate and adjust the threaded rod 17 through the adjusting wheel 18, so that the practicability of the anchor rod is improved.
The working principle is as follows: connect through connecting pipe 6 between the body of rod 5 to can increase and adjust the length of stock according to actual conditions, the thick liquid pours into mouthful 3 through body of rod 5 is inside with pouring, and closing plate 15 has avoided earth to block up with the cooperation of supporting spring 14 and has pour mouthful 3, and only thick liquid stopper 8 can seal up the entry in the hole body, and adjusting tube 10 and baffle 9 cooperation are fixed only thick liquid stopper 8.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (6)

1. The utility model provides an anchor rod construction equipment that building engineering used, includes the body of rod, its characterized in that: the utility model discloses a grout stop pipe, including the body of rod, the connecting pipe is equipped with the adjustment tank, one side fixed mounting of the body of rod is connected with pours the pipe, and pours and be equipped with on the pipe and pour the mouth, it is equipped with supporting spring to pour inside one side of pipe, one side movable mounting of supporting spring has the closing plate, the top of pouring the pipe is equipped with the air vent, and pours the inside of pipe and be equipped with the breather pipe, one side fixed mounting of pouring the pipe has the anchor head, the outside cover.
2. A rock bolt working apparatus for construction work according to claim 1, wherein: one side of threaded rod is rotated and is installed the backup pad, and is equipped with anti-skidding line in the backup pad.
3. A rock bolt working apparatus for construction work according to claim 1, wherein: one side fixed connection of breather pipe has rotary joint.
4. A rock bolt working apparatus for construction work according to claim 1, wherein: and one side of the baffle is rotatably provided with an adjusting pipe.
5. A rock bolt working apparatus for construction work according to claim 1, wherein: and one side of the rod body is fixedly provided with a connecting seat.
6. A rock bolt working apparatus for construction work according to claim 1, wherein: and the other side of the threaded rod is fixedly provided with an adjusting wheel.
CN201920942191.1U 2019-06-21 2019-06-21 Anchor rod construction device for constructional engineering Expired - Fee Related CN210562166U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920942191.1U CN210562166U (en) 2019-06-21 2019-06-21 Anchor rod construction device for constructional engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920942191.1U CN210562166U (en) 2019-06-21 2019-06-21 Anchor rod construction device for constructional engineering

Publications (1)

Publication Number Publication Date
CN210562166U true CN210562166U (en) 2020-05-19

Family

ID=70631728

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920942191.1U Expired - Fee Related CN210562166U (en) 2019-06-21 2019-06-21 Anchor rod construction device for constructional engineering

Country Status (1)

Country Link
CN (1) CN210562166U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116263053A (en) * 2021-12-14 2023-06-16 中国五冶集团有限公司 Vacuum suction type anti-floating anchor rod

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116263053A (en) * 2021-12-14 2023-06-16 中国五冶集团有限公司 Vacuum suction type anti-floating anchor rod

Similar Documents

Publication Publication Date Title
CN207739264U (en) A kind of Grouting Pipe
CN210562166U (en) Anchor rod construction device for constructional engineering
CN201129183Y (en) Tubule subsection repeat grouting apparatus
CN105781586B (en) A kind of solid pipe method for blocking of gushing water borehole wall filter stream pressure relief vent inner sleeve
CN201241344Y (en) Controllable capsule type expansion device
CN101324064B (en) Controllable expansion extrusion soil body apparatus for geotechnical engineering and use thereof
CN112482406A (en) Anchor rod supporting device for slope support
CN103912238A (en) Passive up hole grouting hole sealing and check plug and grouting hole sealing method
CN111764959B (en) Gas-liquid linkage high-concentration slurry grouting device and method for deep water-rich goaf
CN207062938U (en) Tubaeform mud jacking head and squeezing unit
CN210798920U (en) Underground drilling plugging device
CN112682003A (en) Dual-functional drilling tool for hole forming and grouting
CN201649099U (en) Grout injector metal casting
CN107816041B (en) Non-dumping hole-forming prestressed anchor rod, anchor hole leakage-proof structure and construction method thereof
CN207498973U (en) A kind of power station grout curtain cuts dirty drainage tube
CN106640159A (en) Connecting sleeve sealing structure for self-drilling type hollow grouting anchors
CN201292528Y (en) Grouting machine
CN113944194B (en) Pile foundation isolation anti-freezing measure adapting to underground water level
CN205955761U (en) Not fragile self -drilling cavity slip casting stock
CN108193688A (en) The orifice sealing device device and method of horizontal comprehensive superhigh pressure jetting slip casting method
CN210829331U (en) Prestressed anchor rod for tunnel or culvert construction
CN209227571U (en) Plugging dewatering well tool during a kind of dewatering construction
CN209468762U (en) A kind of novel grouting device
CN113107564A (en) Anchor rod structure for fixing water-rich karst tunnel surrounding rock and using method thereof
CN206280099U (en) A kind of filling borehole of replaceable filling pipeline

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200519

Termination date: 20210621

CF01 Termination of patent right due to non-payment of annual fee