CN210530322U - Assembled steel-concrete structure node pouring mold - Google Patents

Assembled steel-concrete structure node pouring mold Download PDF

Info

Publication number
CN210530322U
CN210530322U CN201920736769.8U CN201920736769U CN210530322U CN 210530322 U CN210530322 U CN 210530322U CN 201920736769 U CN201920736769 U CN 201920736769U CN 210530322 U CN210530322 U CN 210530322U
Authority
CN
China
Prior art keywords
concrete
steel
pouring
node
concrete structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920736769.8U
Other languages
Chinese (zh)
Inventor
赵力
徐国军
蒋路
赵阳
邓竞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Green Building Integration Technology Co Ltd
Original Assignee
Zhejiang Green Building Integration Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Green Building Integration Technology Co Ltd filed Critical Zhejiang Green Building Integration Technology Co Ltd
Priority to CN201920736769.8U priority Critical patent/CN210530322U/en
Application granted granted Critical
Publication of CN210530322U publication Critical patent/CN210530322U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model relates to an assembled steel-concrete structure node pouring mould, which is used for pouring concrete in a node pouring area between spliced steel-concrete structural members; the die comprises a die hanging piece, a die plate and a split screw; the die hanger comprises a mounting plate and a hook welded on the mounting plate; the mounting plate is fixed on one of the steel-concrete structural members; the template shields the node pouring area and is hung on the hook; the two templates are pulled by the oppositely-pulling screw rods, so that the templates are tightly attached to two sides of the steel-concrete structural part. The utility model discloses an assembled steel-concrete structure node pouring mould has simple structure, convenient to use, and with low costs and pour a great deal of advantage such as of high quality.

Description

Assembled steel-concrete structure node pouring mold
[ technical field ] A method for producing a semiconductor device
The utility model relates to a building mould, concretely relates to assembled steel-concrete structure node pouring mould belongs to building engineering technical field.
[ background of the invention ]
The steel-concrete partial combined member is a novel combined member proposed in Europe in the eighties of the twentieth century, and the basic type of the section of the combined member is that concrete is filled between flanges of an H-shaped steel member. The combined member has the advantages of large bearing capacity, large rigidity, good fire resistance and the like, and has no practical application at home at present.
In the prior art, steel-concrete part combined members are butted by adopting a cast-in-place mode generally, namely, one part is prefabricated and formed in a factory, and the other part is cast in site. However, the following drawbacks are often present during casting:
(1) after the pouring is finished, the combination of new and old concrete is not ideal, and a gap is formed at the interface.
(2) No key groove is arranged, and the structural reliability is problematic.
(3) The existing pouring mold has the defects of complex structure, troublesome manufacture, troublesome demolding and poor demolding quality.
(4) Without a fixing device, multiple persons are needed to cooperate, and time and labor are wasted.
(5) The flowability of the pouring material is poor, the aggregate is large, the pouring is not compact, and a honeycomb pitted surface appears.
(6) The concrete flow is unstable, and pressure is too big, causes pouring material to spill over, and the mould rises the mould.
Therefore, in order to solve the above technical problems, it is necessary to provide an innovative assembly type steel-concrete structure node casting mold to overcome the above-mentioned drawbacks in the prior art.
[ Utility model ] content
In order to solve the problem, the utility model aims to provide a simple structure, convenient to use, with low costs and pour the assembled steel-concrete structure node casting die of high quality.
In order to achieve the above purpose, the utility model adopts the following technical scheme: an assembled steel-concrete structure node pouring mold is used for pouring concrete in a node pouring area between spliced steel-concrete structural members; the die comprises a die hanging piece, a die plate and a split screw; the die hanger comprises a mounting plate and a hook welded on the mounting plate; the mounting plate is fixed on one of the steel-concrete structural members; the template shields the node pouring area and is hung on the hook; the two templates are pulled by the oppositely-pulling screw rods, so that the templates are tightly attached to two sides of the steel-concrete structural part.
The utility model discloses an assembled steel reinforced concrete structure node pouring die further includes: clamping grooves are respectively formed in the two sides of the template; the hook is clamped in the clamping groove.
The utility model discloses an assembled steel reinforced concrete structure node pouring die further includes: a key groove is formed in concrete of the reinforced concrete structural member and communicated with the node pouring area; the template is located below the key slot.
The utility model discloses an assembled steel reinforced concrete structure node pouring die further includes: the mounting plate is mounted on the concrete of the steel-concrete structural member through screws.
The utility model discloses an assembled steel reinforced concrete structure node pouring die still includes: the concrete-reinforced concrete structure is characterized in that a pouring round hole is formed in a web plate of the concrete-reinforced concrete structure, and the pouring round hole is communicated with node pouring areas on two sides of the web plate.
Compared with the prior art, the utility model discloses following beneficial effect has:
1. the utility model discloses an assembled steel concrete structure node pouring mould simple structure, convenient to use, it can pour the node regional fill full of, guarantees that the interface of new and old concrete combines intact.
2. The utility model discloses an assembled steel-concrete structure node pouring mould has avoided trompil on the mould, has not only reduced the preparation degree of difficulty of mould, has realized the standardized processing of mould simultaneously.
3. The utility model discloses a stability in the die setting process is pour to assembled steel-concrete structure node, saves time simultaneously, laborsaving.
4. The template of the assembled steel-concrete structure node pouring mould is smooth, and the pouring quality is good; the template directly adopts a flat plate, which saves the manufacturing cost and time and is convenient to install and disassemble.
[ description of the drawings ]
Fig. 1 is the utility model discloses an assembled steel-concrete structure node pouring mould's in service state picture.
Fig. 2 is a state view of fig. 1 with one side mold plate opened.
[ detailed description ] embodiments
Referring to the attached drawings 1 and 2 of the specification, the utility model relates to an assembly type steel-concrete structure node pouring mold, which is used for pouring concrete in a node pouring area 11 between two spliced steel-concrete structure members 10; the die is formed by assembling a die hanger 1, a die plate 2, a split screw 3 and the like.
The die hanger 1 is composed of a mounting plate 4 and a hook 5 welded on the mounting plate 4. The mounting plate 4 is fixed on one of the steel-concrete structural members 11, and specifically, the mounting plate 4 is mounted on the concrete 12 of the steel-concrete structural member 11 through a screw 41. The mould pendant 1 is welded with 2 couples 5.
The formwork 2 shields the node pouring area 11 and is hung on the hook 5. Specifically, the two sides of the template 2 are respectively provided with a clamping groove 21; the hooks 5 are clamped in the clamping grooves 21, so that the template 2 and the hooks 5 are combined, the stability of the die in the installation process is ensured, and time, labor and labor are saved.
The two templates 2 are tied by the oppositely-pulling screw rods 3, so that the templates 2 are tightly attached to two sides of the steel-concrete structural member 1, and concrete leakage is avoided when concrete is poured.
Furthermore, a key groove 13 is formed in the concrete 12 of the reinforced concrete structural member 11, and the key groove 13 is communicated with the node pouring area 11, so that cast-in-place concrete falls into the node pouring area 11. The keyway 3 is simultaneously done and is pour the hole, has avoided trompil on the mould, has not only reduced the preparation degree of difficulty of mould, has realized the standardized processing of mould simultaneously. The key slot 13 can also increase the connection between the cast-in-place concrete and the precast concrete, and ensure the reliability of the structure. The formwork 2 is located below the key groove 13 to stop cast-in-place pouring.
The casting round hole 15 is formed in the web 14 of the reinforced concrete structural member 11, the casting round hole 15 is communicated with the node casting areas 11 on two sides of the web 14, so that two sides of the shear wall can be cast on one side, and particularly when the shear wall faces outdoors, the other side of the shear wall does not need to be cast through a scaffold and a construction hanging basket.
In this embodiment, template 2 adopts the aluminum alloy material, and its surfacing is pour of high quality, saves the convenience of cost of manufacture, time and installation dismantlement.
When the assembly type steel-concrete structure node pouring mold is used, the mold hanging piece 1 is firstly fixed on the steel-concrete structure piece 11; then hanging the template 2 on the mould hanger 1; the split bolts 3 are then tied to the two forms 2. The concrete pouring equipment (not shown) injects concrete from the key groove 3 into the node pouring area 11, and falls to the node pouring area 11 on the other side through the pouring circular hole 15. The cast-in-place concrete is supported by the formwork 2, so that the whole node pouring area 11 and the key groove 3 can be filled, and the interface of new and old concrete is well combined.
The above embodiments are merely preferred embodiments of the present disclosure, which are not intended to limit the present disclosure, and any modifications, equivalents, improvements and the like, which are within the spirit and principle of the present disclosure, should be included in the scope of the present disclosure.

Claims (5)

1. An assembled steel-concrete structure node pouring mold is used for pouring concrete in a node pouring area between spliced steel-concrete structural members; the method is characterized in that: comprises a mould hanging piece, a template and a split screw; the die hanger comprises a mounting plate and a hook welded on the mounting plate; the mounting plate is fixed on one of the steel-concrete structural members; the template shields the node pouring area and is hung on the hook; the two templates are pulled by the oppositely-pulling screw rods, so that the templates are tightly attached to two sides of the steel-concrete structural part.
2. The assembly-type steel-concrete structure node casting mold of claim 1, wherein: clamping grooves are respectively formed in the two sides of the template; the hook is clamped in the clamping groove.
3. The assembly-type steel-concrete structure node casting mold of claim 1, wherein: a key groove is formed in concrete of the reinforced concrete structural member and communicated with the node pouring area; the template is located below the key slot.
4. The assembly-type steel-concrete structure node casting mold of claim 1, wherein: the mounting plate is mounted on the concrete of the steel-concrete structural member through screws.
5. The assembly-type steel-concrete structure node casting mold according to claim 3, wherein: the concrete-reinforced concrete structure is characterized in that a pouring round hole is formed in a web plate of the concrete-reinforced concrete structure, and the pouring round hole is communicated with node pouring areas on two sides of the web plate.
CN201920736769.8U 2019-05-22 2019-05-22 Assembled steel-concrete structure node pouring mold Active CN210530322U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920736769.8U CN210530322U (en) 2019-05-22 2019-05-22 Assembled steel-concrete structure node pouring mold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920736769.8U CN210530322U (en) 2019-05-22 2019-05-22 Assembled steel-concrete structure node pouring mold

Publications (1)

Publication Number Publication Date
CN210530322U true CN210530322U (en) 2020-05-15

Family

ID=70593505

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920736769.8U Active CN210530322U (en) 2019-05-22 2019-05-22 Assembled steel-concrete structure node pouring mold

Country Status (1)

Country Link
CN (1) CN210530322U (en)

Similar Documents

Publication Publication Date Title
CN113356582B (en) Mould for pouring steel beam concrete-wrapped outside and construction method
CN109138228B (en) Building wall and construction method thereof
CN110863507A (en) Integrated prefabricated base component additionally provided with elevator, forming die and using method
CN210530322U (en) Assembled steel-concrete structure node pouring mold
CN213417871U (en) Assembly type disassembly-free foundation template and cast-in-place foundation building structure
CN108896371B (en) Manufacturing tool and manufacturing method for new and old concrete junction surface oblique shear test piece
CN214834742U (en) Anti-bank template structure
CN108104466A (en) Cast-in-place structural moulding integrated construction dedicated templates and mold method
CN211941380U (en) Floor precast slab mould
CN112982968A (en) Inverted ridge template structure and construction method thereof
CN209304758U (en) Stair are prefabricated to pour mold
CN115126217B (en) Construction device for shear wall and floor slab formwork by adopting aluminum alloy formwork
CN112627570A (en) Repairing tool for repairing large gap of door opening and construction method thereof
CN215618858U (en) Slurry leakage-free device for casting concrete behind prefabricated member
CN217268355U (en) Constructional column non-disassembly pouring mold
CN211421845U (en) Clamping device for waterproof reverse ridge pouring template in toilet
CN106436973B (en) Steel column arranged in post-cast section of steel shear structure and casting method of steel column
CN220150865U (en) Rib beam forming member for cast-in-situ concrete
CN219411270U (en) Steel plate connecting piece for concrete post-pouring strip
CN220927518U (en) Bearing platform pier body integral type pouring die for bridge construction
CN220451424U (en) Template supporting system for integrally pouring beam plate and beam bottom L-shaped hanging plate
CN215471899U (en) Assembled wall processing die
CN212834999U (en) Be used for hanging to irritate roof beam segment web chamfer concrete and prevent turning over thick liquid device
CN219726669U (en) Assembled shear wall mould
CN216766233U (en) Node suitable for regional concrete placement is watered after assembled PEC post

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Anhui Zhihong Precision Construction Technology Co.,Ltd.

Assignor: ZHEJIANG GREEN BUILDING INTEGRATION TECHNOLOGIES Co.,Ltd.

Contract record no.: X2023990000037

Denomination of utility model: A pouring mould for prefabricated steel-concrete structure node

Granted publication date: 20200515

License type: Common License

Record date: 20230113

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Jiangxi Huahong Jinggong Steel Structure Co.,Ltd.

Assignor: ZHEJIANG GREEN BUILDING INTEGRATION TECHNOLOGIES Co.,Ltd.

Contract record no.: X2023980034645

Denomination of utility model: A prefabricated steel concrete structure node pouring mold

Granted publication date: 20200515

License type: Common License

Record date: 20230413

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Jiangsu Lvjian Jinggong Technology Co.,Ltd.

Assignor: ZHEJIANG GREEN BUILDING INTEGRATION TECHNOLOGIES Co.,Ltd.

Contract record no.: X2023980034833

Denomination of utility model: A prefabricated steel concrete structure node pouring mold

Granted publication date: 20200515

License type: Common License

Record date: 20230421

EE01 Entry into force of recordation of patent licensing contract