CN210489851U CN201922013689.2U CN201922013689U CN210489851U CN 210489851 U CN210489851 U CN 210489851U CN 201922013689 U CN201922013689 U CN 201922013689U CN 210489851 U CN210489851 U CN 210489851U
Authority
CN
China
Prior art keywords
fixed
copper
base
plate
survey
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922013689.2U
Other languages
Chinese (zh)
Inventor
曹微
蒋东寿
陈昱哲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Yuzhi Electric Power Design Co Ltd
Original Assignee
Wuhan Yuzhi Electric Power Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Yuzhi Electric Power Design Co Ltd filed Critical Wuhan Yuzhi Electric Power Design Co Ltd
Priority to CN201922013689.2U priority Critical patent/CN210489851U/en
Application granted granted Critical
Publication of CN210489851U publication Critical patent/CN210489851U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)

Abstract

The utility model discloses an electric power engineering design is with avoiding electric leakage survey device, including base and fixed plate, the fixed plate passes through the bracing piece to be supported to be fixed directly over the base, and the bracing piece is four, the right side upper end of fixed plate supports through branch and is fixed with places the pipe clamp, and places the pipe clamp and go up the card and put and be fixed with solid fixed cylinder, and solid fixed cylinder's left side is connected with the laminating dish, and the left side of laminating dish is inside to be fixed with the copper, and the laminating dish surface of copper outer lane is encircleed the laminating and is fixed with magnet, the bottom left side and the equal welded fastening in right side of base. The utility model discloses a be provided with a grounding cylinder and copper on base bottom and the fixed plate that are used for supporting to play the survey equipment respectively, survey the during operation, make the survey equipment supported on the fixed plate, then can make the surface contact of copper and equipment, can lead to the earth's surface through the wire with the electric leakage that equipment surface probably exists, avoid the electric leakage to cause the injury to the workman.

Description

Electric power engineering design is with avoiding electric leakage survey device
Technical Field
The utility model relates to an electric power engineering technical field specifically is an electric power engineering design is with avoiding electric leakage to survey device.
Background
At present, electric power engineering, namely engineering related to the production, transmission and distribution of electric energy, also includes engineering of applying electricity as power and energy in various fields in a broad sense, the use of electric energy has penetrated all fields of national economy and people's life, becomes a main power form of industry, agriculture, transportation and national defense and an indispensable energy source in people's family life, and has been widely applied in the aspects of dragging, lighting, electric heating, electrochemistry, communication and the like.
Electric power engineering equipment need use various consumer when surveying the inspection, and survey engineering owing to some and need will survey the elevated use of equipment, lead to the unable smooth earth's surface of inserting of earth connection of these survey equipment, the phenomenon of electric leakage takes place easily, causes the potential safety hazard to the personnel of surveying. Therefore, we propose an electrical engineering design to avoid electrical leakage survey apparatus.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an electric power engineering design is with avoiding electric leakage survey device, through be provided with a grounding cylinder and copper on base bottom and the fixed plate that are used for supporting survey equipment respectively, survey the during operation, make survey equipment supported on the fixed plate, then can make the surface contact of copper and equipment, can lead to the earth's surface through the wire with the electric leakage that probably exists on the equipment surface, avoid the electric leakage to cause the injury to the workman, the problem of proposing among the background art has been solved.
In order to achieve the above object, the utility model provides a following technical scheme: a leakage-avoiding surveying device for electric power engineering design comprises a base and four fixing plates, wherein the fixing plates are supported and fixed right above the base through supporting rods;
the utility model discloses a fixing plate, including base, fixing plate, copper plate outer lane, laminating dish, copper bar, copper plate outer lane, base, copper bar, copper plate outer lane, copper plate.
As a preferred embodiment of the utility model, the left side surface of copper is provided with the bump, and the bump is a plurality of, and the even distribution of a plurality of bumps is on the copper surface, and the copper passes through the spring on right side to be fixed inside the left side of laminating dish.
As an optimal implementation manner of the utility model, the brake truckle is all installed in the bottom four corners of base, the brake truckle is four.
As a preferred embodiment of the utility model, the vertical welded fastening in left side front end surface of fixed plate has the cat ladder, and the cat ladder is located the front side of fixed plate.
As a preferred embodiment of the present invention, the surface of the upper end outer ring of the fixing plate is fixed with a guardrail, and the guardrail surrounds the upper end outer ring of the fixing plate.
Compared with the prior art, the beneficial effects of the utility model are as follows:
1. the utility model discloses an electric power engineering design is with avoiding electric leakage to survey device through being provided with a grounding cylinder and copper on base bottom and the fixed plate that are used for supporting survey equipment respectively, surveys the during operation, makes survey equipment supported on the fixed plate, then can make the surface contact of copper and equipment, can lead to the earth's surface through the wire with the electric leakage that equipment surface probably exists, avoids the electric leakage to cause the injury to the workman.
2. The utility model discloses an electric power engineering design is with avoiding electric leakage survey device is provided with the bump through the left side surface that makes the copper, and the bump is a plurality of, and the even distribution of a plurality of bumps is on the copper surface, and the copper passes through the spring on right side to be fixed inside the left side of laminating dish, and a plurality of bumps are located one side of copper to can make the external world of copper and equipment have better contact effect under the pressure effect of moving of spring, make electrically conductive effect better.
Drawings
Other features, objects and advantages of the invention will become more apparent upon reading of the detailed description of non-limiting embodiments with reference to the following drawings:
fig. 1 is a schematic view of the overall structure of the electric leakage prevention survey device for electric power engineering of the present invention;
fig. 2 is the detailed structure diagram of a place a of the electric leakage prevention survey device for electric power engineering design of the present invention.
In the figure: 1. a base; 2. a fixing plate; 3. a guardrail; 4. climbing a ladder; 5. a support bar; 6. braking the caster; 7. a spring; 8. a grounding cylinder; 9. an iron rod; 10. a copper sheet; 11. a strut; 12. a fixed cylinder; 13. a gluing plate; 14. placing a pipe clamp; 15. a magnet; 16. salient points; 17. a copper plate; 18. and (4) conducting wires.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
In the description of the present invention, it should be noted that, unless explicitly stated or limited otherwise, the terms "mounted," "connected" and "disposed" are to be interpreted broadly, and may be, for example, fixedly connected, disposed, detachably connected, disposed, or integrally connected and disposed; the utility model discloses in provide only supply the reference with the model of electrical apparatus. For those skilled in the art, different types of electrical appliances with the same function can be replaced according to actual use conditions, and for those skilled in the art, the specific meaning of the above terms in the present invention can be understood in specific situations.
Referring to fig. 1-2, the present invention provides a technical solution: a leakage-avoiding surveying device for electric power engineering design comprises a base 1 and fixed plates 2, wherein the fixed plates 2 are supported and fixed right above the base 1 through four support rods 5;
the utility model discloses a fixed plate 2, including base 1, fixing plate 2, support rod 11, copper plate 9, copper plate 17 outer lane, base 1, spring 7, copper sheet 10, copper sheet 9, copper plate 17, copper plate 9, copper plate 17, copper plate 9, copper sheet 10, left side are fixed with in the bottom left side of base 1 and the equal welded fastening in right side of ground connection section of thick bamboo 8, and all be connected through spring 7 and be fixed with iron rod 9 in the ground connection section of thick bamboo 8, right side, iron rod 9 passes through wire 18 and base 1 electric connection, right side iron rod 9 passes through wire 18 and copper 17 electric connection on placing plate 14 and the card is put and is fixed with solid fixed cylinder 12, and solid fixed with magnet 17, and the left side is connected through spring.
In the embodiment (see fig. 1 and 2), the grounding cylinder 8 and the copper plate 17 are respectively arranged on the bottom of the base 1 and the fixing plate 2 for supporting the surveying equipment, so that the surveying equipment is supported on the fixing plate 2 during surveying work, and then the copper plate 17 can be in contact with the surface of the equipment, thereby conducting electric leakage possibly existing on the surface of the equipment to the ground surface through the lead 18 and avoiding the damage of the electric leakage to workers.
Wherein, the left side surface of copper 17 is provided with bump 16, and bump 16 is a plurality of, and the even distribution of a plurality of bumps 16 is on copper 17 surface, and copper 17 passes through spring 7 on right side to be fixed in the left side inside of laminating dish 13.
In this embodiment (see fig. 2), the left side surface of the copper plate 17 is provided with a plurality of bumps 16, the bumps 16 are uniformly distributed on the surface of the copper plate 17, the copper plate 17 is fixed inside the left side of the bonding plate 13 through the spring 7 on the right side, the bumps 16 are located on one side of the copper plate 17, and the copper plate 17 can be in good contact with the outside of the device under the pressing action of the spring 7, so that the conductive effect is better.
Wherein, brake truckles 6 are all installed to the bottom four corners of base 1, brake truckles 6 are four.
In this embodiment (please refer to fig. 1), the base 1 and the fixing plate 2 of the device can be conveniently moved to the supporting position by the brake caster 6 installed at the bottom of the base 1.
Wherein, the vertical welded fastening in left side front end surface of fixed plate 2 has cat ladder 4, and cat ladder 4 is located the front side of fixed plate 2.
In this embodiment (see fig. 1), a worker can conveniently climb to the upper end of the fixing plate 2 through the ladder stand 4 by using the ladder stand 4.
The guardrail 3 is fixed on the surface of the outer ring at the upper end of the fixing plate 2, and the guardrail 3 surrounds the outer ring at the upper end of the fixing plate 2.
In this embodiment (see fig. 1), the guard rail 3 has a certain protection effect on workers and equipment located on the fixing plate 2.
It should be noted that the utility model relates to an electric power engineering design is with avoiding electric leakage surveying device, including base 1, fixed plate 2, guardrail 3, cat ladder 4, bracing piece 5, brake truckle 6, spring 7, grounding tube 8, iron rod 9, copper sheet 10, branch 11, fixed tube 12, laminating dish 13, place pipe clamp 14, magnet 15, bump 16, copper 17, wire 18, the part is general standard component or the part that technical staff in this field knows, its structure and principle all can learn through the technical manual or through conventional experimental method, in operation, can make it roll on ground through brake truckle 6, until base 1 and fixed plate 2 move to the place that needs to use, then lock brake truckle 6, make surveying equipment hoist to be hoisted to fixed plate 2 upper end through hoisting equipment, this moment, iron rod 9 in grounding tube 8 is pushed down under the effect of spring 7, make it through the fine contact of copper sheet 10 with ground, when using surveying equipment, follow and place fixed cylinder 12 and laminating dish 13 of taking out in the pipe clamp 14, then make laminating dish 13 adsorb on the surface of equipment shell through magnet 15, the bump 16 on copper 17 surface is fine and the equipment shell intercommunication under the pressure of spring 7 this moment, and then when can making equipment electric leakage, through copper 17, wire 18 and iron bar 9 will leak electric conduction to ground, electric leakage on fixed plate 2 and the base 1 can be led to ground by left iron bar 9.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above, it will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, but that the invention may be embodied in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (5)

1. The utility model provides an electric power engineering design is with avoiding electric leakage survey device, includes base (1) and fixed plate (2), its characterized in that: the fixed plate (2) is supported and fixed right above the base (1) through four support rods (5);
the upper end of the right side of the fixed plate (2) is supported and fixed with a placing pipe clamp (14) through a support rod (11), a fixed cylinder (12) is clamped and fixed on the pipe clamp (14), the left side of the fixed cylinder (12) is connected with a bonding disc (13), a copper plate (17) is fixed inside the left side of the bonding disc (13), a magnet (15) is fixed on the surface of the bonding disc (13) at the outer ring of the copper plate (17) in a surrounding bonding way, the left side and the right side of the bottom of the base (1) are both welded and fixed with grounding cylinders (8), and all connect through spring (7) in a grounding section of thick bamboo (8) and be fixed with iron rod (9), iron rod (9) are fixed in a grounding section of thick bamboo (8) through the restriction of top stopper, and the bottom of iron rod (9) is connected and is fixed with copper sheet (10), left side iron rod (9) pass through wire (18) and base (1) electric connection, right side iron rod (9) pass through wire (18) and copper (17) electric connection.
2. An electrical leakage avoidance survey apparatus according to claim 1 wherein: the left side surface of copper (17) is provided with bump (16), and bump (16) are a plurality of, and the even distribution of a plurality of bumps (16) is on copper (17) surface, and copper (17) are fixed inside the left side of laminating dish (13) through spring (7) on right side.
3. An electrical leakage avoidance survey apparatus according to claim 1 wherein: brake truckles (6) are all installed in the bottom four corners of base (1), brake truckles (6) are four.
4. An electrical leakage avoidance survey apparatus according to claim 1 wherein: the ladder stand is characterized in that a ladder stand (4) is vertically welded and fixed on the surface of the front end of the left side of the fixing plate (2), and the ladder stand (4) is located on the front side of the fixing plate (2).
5. An electrical leakage avoidance survey apparatus according to claim 1 wherein: the guardrail (3) is fixed on the surface of the outer ring at the upper end of the fixing plate (2), and the guardrail (3) surrounds the outer ring at the upper end of the fixing plate (2).
CN201922013689.2U 2019-11-20 2019-11-20 Electric power engineering design is with avoiding electric leakage survey device Active CN210489851U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922013689.2U CN210489851U (en) 2019-11-20 2019-11-20 Electric power engineering design is with avoiding electric leakage survey device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922013689.2U CN210489851U (en) 2019-11-20 2019-11-20 Electric power engineering design is with avoiding electric leakage survey device

Publications (1)

Publication Number Publication Date
CN210489851U true CN210489851U (en) 2020-05-08

Family

ID=70511198

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922013689.2U Active CN210489851U (en) 2019-11-20 2019-11-20 Electric power engineering design is with avoiding electric leakage survey device

Country Status (1)

Country Link
CN (1) CN210489851U (en)

Similar Documents

Publication Publication Date Title
CN205015377U (en) A insulating fixing device for electric energy meter is electrified to be changed
CN204531457U (en) The three-dimensional operation protector of a kind of power construction easy for installation
CN210489851U (en) Electric power engineering design is with avoiding electric leakage survey device
CN109546373B (en) Grounding wire clamp installation device for transformer substation and installation method of grounding wire clamp
CN207765627U (en) A kind of Fast Installation and the grounding-for-lightning device of storage
CN204144786U (en) Unmanned plane installing 110kV-500kV line security ground wire device
CN203659573U (en) Electric equipment hoisting device
CN205777802U (en) A kind of high voltage power transmission transmission tower
CN205882560U (en) Special circulation cord rack device of distribution live working earth potential
CN213679698U (en) Auxiliary insulating platform of overhead vehicle
CN104184071B (en) Unmanned plane installs 110kV 500kV line security ground wire device
CN204575925U (en) Cable box more than transformer station OPGW optical cable
CN206575081U (en) Overhead transmission line insulated isolated device
CN102969671B (en) Equipotential outlet trolley for double bundle conductor
CN205141179U (en) Articulate ground wire
CN202026014U (en) Special isolation frame for overhauling GW16 type disconnecting link
CN205646197U (en) Novel high pressure bonding device
CN201694765U (en) Multi-frequency grounding device of construction tower crane
CN204510984U (en) A kind of emergency power circuit support bar
CN206611150U (en) A kind of many cable connection supports
CN203909227U (en) 220kV and 330kV insulation tool AC high-voltage holding test device
CN103738860A (en) Small interval dual-purpose hoisting device
CN105914489A (en) Civil-engineering distribution room transformer neutral point grounding system and grounding method thereof
CN203931765U (en) Oil-immersed transformer bushing antifouling cover
CN204205869U (en) Power cable intermediate junction device