CN104184071B - Unmanned plane installs 110kV 500kV line security ground wire device - Google Patents
Unmanned plane installs 110kV 500kV line security ground wire device Download PDFInfo
- Publication number
- CN104184071B CN104184071B CN201410426240.8A CN201410426240A CN104184071B CN 104184071 B CN104184071 B CN 104184071B CN 201410426240 A CN201410426240 A CN 201410426240A CN 104184071 B CN104184071 B CN 104184071B
- Authority
- CN
- China
- Prior art keywords
- wire
- upper arm
- arm card
- ground
- unmanned plane
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
The present invention relates to a kind of safety grounding device of high-voltage electric power circuit, especially a kind of unmanned plane installing 110kV 500kV line security ground wire device.Described inclusion unmanned plane body, unmanned plane suspension arrangement, wire, wall built-up card, ground wire and balancing weight;Balancing weight is fixedly mounted on wall built-up card;Wire, wall built-up card and ground wire are activity electrical connection in sequential series.The present invention has the characteristics that using safety and simple operation, ensure the safety of staff, avoid high-altitude Danger Electric shock risk, and safety ground operating process is convenient and swift, reduce the difficulty carrying out earthing lines of power transmission lines overhauling operation, decrease the labor intensity of staff, saved the loss bringing that has a power failure, had significant economic benefit.
Description
Technical field
The present invention relates to a kind of safety grounding device of high-voltage electric power circuit, especially a kind of unmanned plane installing 110kV-
500kV line security ground wire device.
Background technology
Power failure, electrical verification, hanging earthing conductor are to ensure that the safe important technique measure of transmission line of electricity interruption maintenance, and earth lead is electricity
Commonly used security tool in power safety in production.According to the planning of earthing tool, homework type and whole grid maintenance with specifically
Implement operation or work standard to require, existing primary ground line method for security protection, typically according to operation plan and the unified peace that has a power failure
Row, work unit, according to the fixed earth lead group number of work ticket row and shaft tower comparison, after whole piece line outage, sends work and refers to
Order;Staff handles work ticket, explains safety measure and dangerous spot;Operating personnel reaches work ticket institute column position, electrical verification, does
Need protective grounding safety measure, protection section both sides need multiple working groups to carry out ground protection measure.When stepping on bar work high above the ground,
Electric pressure is higher, and earth point is also bigger with the distance of wire, and the overhead line structures corner number of degrees are bigger, earth lead require more long,
Just it is less susceptible to during personnel's operation hang;Sometimes meet wind, the suspension time required for operation is just longer.On bar in operation process
High with personnel labor intensity under bar, easily cause muscle fatigue and cause danger.The operating personnel of particularly shaft tower, easily occurs high
Empty falling accident.Because earth lead hangs, the time is long, and active section cannot be protected, and other working groups also cannot start working, just
Job schedule and delay activity duration can be affected.Therefore, prior art is all by manually being implemented, low for electric pressure
When can implement, and implement just extremely difficult on supertension and extra high voltage line.
Content of the invention
The technical problem to be solved is to provide unmanned plane installing 110kV-500kV line security ground wire device,
Solve to carry out earthing lines of power transmission lines overhauling task difficulty greatly using prior art, activity duration length and maintainer easily send out
The problem of electric pole tower accident is stepped in life.
In order to solve above-mentioned technical problem, the technical scheme is that and be achieved in that:
Unmanned plane install 110kV-500kV line security ground wire device, including unmanned plane body, unmanned plane suspension arrangement,
Wire, upper arm card, ground wire and balancing weight;Balancing weight is fixedly mounted on upper arm card;Wire, upper arm card and ground wire are in sequential series
Activity electrical connection.
Further, described ground wire is aerial earth wire or ground connection ground wire;
Further, described wire is three-phase conducting wire or two phase conductors;
Further, described upper arm card is divided into wire upper arm card and ground wire upper arm card;Wire upper arm card is three-phase upper arm card
Or biphase upper arm card, all it is made up of copper pipe, wire dop, coil tension spring dop and drop hanger, and wire upper arm card can be used in parallel,
Wire dop and the activity of coil tension spring dop electrically connect each phase conductor;Ground wire upper arm card is biphase upper arm card, by copper pipe, wire card
Head, coil tension spring dop and drop hanger composition, wire dop phase conductor any one with wire activity electrically connects, coil tension spring dop and
Aerial earth wire activity electrical connection;
Further, described unmanned plane body and unmanned plane suspension arrangement are installation tool, described by wire upper arm card
It is placed on wire, and ground wire upper arm card is placed on wire and aerial earth wire, wire, wire upper arm card, ground wire upper arm
Card and aerial earth wire activity in sequential series are electrically connected to form good conducting, and complete ground connection operation.
Further, described unmanned plane body and unmanned plane suspension arrangement are installation tool, described will be grounded ground wire and
Any one mutually activity electrical connection of wire, and wire upper arm card is placed on wire, wire, wire upper arm card and ground connection ground
Line activity in sequential series is electrically connected to form good conducting, and completes ground connection operation.
Present invention beneficial effect compared to existing technology:
The present invention has the characteristics that the safety having ensured staff using safety and simple operation, it is to avoid high-altitude is touched
Electricity is dangerous, and safety ground operating process is convenient and swift, reduces the difficulty carrying out earthing lines of power transmission lines overhauling operation, subtracts
Lack the labor intensity of staff, saved the loss bringing that has a power failure, had significant economic benefit.
Brief description
Fig. 1 is three-phase upper arm card structure figure in the present invention.
Fig. 2 is biphase upper arm card structure figure in the present invention.
Fig. 3 is the safety line installation diagram of present invention when wire is horizontally arranged.
Fig. 4 is the safety line installation diagram of present invention during wire triangle arrangement.
Fig. 5 is the safety line installation diagram of present invention when wire is arranged vertically.
Fig. 6 is the structural representation of four axle unmanned plane bodies and unmanned plane suspension arrangement in the present invention.
Fig. 7 is the structural representation of four rotor wing unmanned aerial vehicle bodies and unmanned plane suspension arrangement in the present invention.
Specific embodiment
Below in conjunction with accompanying drawing, the present invention is described in further detail.
As shown in figure 1, three-phase upper arm card structure includes copper pipe 1, wire dop 2, the first coil tension spring dop in the present invention
3rd, the second coil tension spring dop 4 and drop hanger 5.
As shown in Fig. 2 biphase upper arm card structure includes copper pipe 1, wire dop 2, coil tension spring dop 3 and hangs in the present invention
Hook 5.
As shown in Fig. 3,6 and 7, when wire is horizontally arranged, the safety line mounting structure of the present invention includes three-phase conducting wire 6, two
Phase upper arm card 11, aerial earth wire 7 and balancing weight;Balancing weight is fixedly mounted on biphase upper arm card 11;Three-phase conducting wire 6, biphase extension
Arm card 11 and aerial earth wire 7 are activity electrical connection in sequential series.Biphase upper arm card has three, and two of which is as wire upper arm
Card, another is as ground wire upper arm card;Unmanned plane body 8 and unmanned plane suspension arrangement 9 are installation tool, by two wire upper arms
Card activity is fastened on to be formed on the three-phase conducting wire 6 of horizontal positioned and is electrically connected in series, and ground wire upper arm card activity is fastened on three
In any one phase and aerial earth wire 7 of phase conductor 6, three-phase conducting wire 6, wire upper arm card, ground wire upper arm card and aerial earth wire 7 are sequentially
Series connection activity is electrically connected to form good conducting, and completes ground connection operation.
As shown in Fig. 4,6 and 7, during wire triangle arrangement, the safety line mounting structure of the present invention includes three-phase conducting wire 6, two
Phase upper arm card 11, aerial earth wire 7 and balancing weight;Balancing weight is fixedly mounted on biphase upper arm card 11;Three-phase conducting wire 6, biphase extension
Arm card 11 and aerial earth wire 7 are activity electrical connection in sequential series.Biphase upper arm card has three, and two of which is as wire upper arm
Card, another is as ground wire upper arm card;Unmanned plane body 8 and unmanned plane suspension arrangement 9 are installation tool, by two wire upper arms
Card activity is fastened on to be formed on the three-phase conducting wire 6 of triangle placement and is electrically connected in series, and ground wire upper arm card activity is fastened on three
In any one phase and aerial earth wire 7 of phase conductor 6, three-phase conducting wire 6, wire upper arm card, ground wire upper arm card and aerial earth wire 7 are sequentially
Series connection activity is electrically connected to form good conducting, and completes ground connection operation.
As shown in Fig. 5,6 and 7, when wire is arranged vertically, the safety line mounting structure of the present invention includes three-phase conducting wire 6, three
Phase upper arm card 10, biphase upper arm card 11, aerial earth wire 7 and balancing weight;Balancing weight is fixedly mounted on upper arm card;Three-phase conducting wire 6,
Three-phase upper arm card 10, biphase upper arm card 11 and aerial earth wire 7 are activity electrical connection in sequential series.Biphase upper arm card is ground wire upper arm
Card, three-phase upper arm card is wire upper arm card;Unmanned plane body 8 and unmanned plane suspension arrangement 9 are installation tool, by wire upper arm card
Activity is fastened on the three-phase conducting wire 6 being disposed vertically, and ground wire upper arm card activity is fastened on any one phase of three-phase conducting wire 6
On aerial earth wire 7, three-phase conducting wire 6, wire upper arm card 10, ground wire upper arm card 11 and aerial earth wire 7 activity in sequential series are electrically connected
Connect good the conducting of formation, complete ground connection operation.
Operational approach of the present utility model:
When wire need to install no aerial earth wire 7 at ground wire, will be able to be connect by unmanned plane body 8 and unmanned plane suspension arrangement 9
Ground ground wire activity is fastened in any one phase of wire.Then it is fastened on the wire of different modes of emplacements with wire upper arm card activity
On, wire upper arm card, wire and ground connection ground wire activity in sequential series are electrically connected to form good conducting, and complete ground connection operation.
In sum, these are only presently preferred embodiments of the present invention, be not intended to limit protection scope of the present invention.
All any modification, equivalent substitution and improvement within the spirit and principles in the present invention, made etc., should be included in the present invention's
Within protection domain.
Claims (1)
1. a kind of unmanned plane installing 110kV-500kV line security ground wire device it is characterised in that:Including unmanned plane body(8)、
Unmanned plane suspension arrangement(9), wire, upper arm card, ground wire and balancing weight;Balancing weight is fixedly mounted on upper arm card;Wire, upper arm
Card and ground wire are activity electrical connection in sequential series;Ground wire is aerial earth wire(7);Wire is three-phase conducting wire(6);Upper arm card is divided into leads
Line upper arm card and ground wire upper arm card;Wire upper arm card is three-phase upper arm card(10)Or biphase upper arm card(11), three-phase upper arm card
(10)By copper pipe(1), wire dop(2), the first coil tension spring dop(3), the second coil tension spring dop(4)And drop hanger(5)Group
Become, biphase upper arm card(11)By copper pipe(1), wire dop(2), coil tension spring dop(3)And drop hanger(5)Composition, and wire extension
Arm card can be used in parallel, wire dop(2)And the activity of coil tension spring dop electrically connects each phase conductor;Ground wire upper arm card is biphase extension
Arm card(11), by copper pipe(1), wire dop(2), coil tension spring dop(3)And drop hanger(5)Composition, wire dop(2)With wire
Any one phase conductor activity electrical connection, coil tension spring dop(3)With aerial earth wire(7)Activity electrical connection;Described unmanned plane is originally
Body(8)And unmanned plane suspension arrangement(9)For installation tool, wire upper arm card activity is fastened on formation series connection on wire and is electrically connected
Connect, and ground wire upper arm card activity is fastened on any one phase of wire and aerial earth wire(7)On, wire, wire upper arm card, ground wire
Upper arm card and aerial earth wire(7)Activity in sequential series is electrically connected to form good conducting, and completes ground connection operation;During operation, no
Man-machine body(8)And unmanned plane suspension arrangement(9)Any one mutually movable by ground connection ground wire and wire electrically connects, and by wire
Upper arm card is placed on wire, and wire, wire upper arm card and ground connection ground wire activity in sequential series are electrically connected to form good conductance
Logical, complete ground connection operation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410426240.8A CN104184071B (en) | 2014-08-27 | 2014-08-27 | Unmanned plane installs 110kV 500kV line security ground wire device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410426240.8A CN104184071B (en) | 2014-08-27 | 2014-08-27 | Unmanned plane installs 110kV 500kV line security ground wire device |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104184071A CN104184071A (en) | 2014-12-03 |
CN104184071B true CN104184071B (en) | 2017-03-01 |
Family
ID=51964918
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410426240.8A Expired - Fee Related CN104184071B (en) | 2014-08-27 | 2014-08-27 | Unmanned plane installs 110kV 500kV line security ground wire device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104184071B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108347007A (en) * | 2018-04-28 | 2018-07-31 | 广东电网有限责任公司 | Unmanned aerial vehicle carrying hook for overhead transmission line |
CN113161919A (en) * | 2020-01-07 | 2021-07-23 | 中国电力科学研究院有限公司 | Power transmission line unmanned aerial vehicle auxiliary operation method and device |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201038346Y (en) * | 2006-12-25 | 2008-03-19 | 云南电网公司思茅供电局 | Transmission line short circuit grounding wire clamp device |
CN201274324Y (en) * | 2008-08-01 | 2009-07-15 | 渭南供电局 | Operation apparatus of ultra-high-voltage grounding wire |
US8720863B2 (en) * | 2012-03-29 | 2014-05-13 | Vmr Aviation Ltd. | Apparatus for stringing a line underneath a cross member |
CN103368103B (en) * | 2013-05-09 | 2016-01-20 | 衡水众翔电子科技有限公司 | For hanging flight instruments and the method for sag rope to transmission line |
CN204144786U (en) * | 2014-08-27 | 2015-02-04 | 李明明 | Unmanned plane installing 110kV-500kV line security ground wire device |
-
2014
- 2014-08-27 CN CN201410426240.8A patent/CN104184071B/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
CN104184071A (en) | 2014-12-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202384510U (en) | Grounding device for overhauling overhead line | |
CN205015377U (en) | A insulating fixing device for electric energy meter is electrified to be changed | |
CN203932553U (en) | A kind of portable earth connection spooler using on extra high voltage direct current transmission line | |
CN104184071B (en) | Unmanned plane installs 110kV 500kV line security ground wire device | |
CN204144786U (en) | Unmanned plane installing 110kV-500kV line security ground wire device | |
CN204167694U (en) | Switch cubicle secondary line routing device | |
CN209607932U (en) | A kind of ground line electroscopic device | |
CN207895922U (en) | A kind of ground wire deicing insulation suspension string | |
CN107247224B (en) | The device and test method of suspension insulator pressure resistance can quickly be tested | |
CN202094327U (en) | Portable ground wire power used in transmission line | |
CN104113007A (en) | Operation method for replacing strain insulator of 35kV overhead distribution line in live state | |
CN103332608A (en) | Special suspender for replacing GW6 disconnector knob insulator | |
CN204332890U (en) | With the fuse switch of electricity-detection grounding device | |
CN202503194U (en) | Suspension type lightning arrester applicable to power transmission lines | |
CN205646747U (en) | 800 kilovolt direct current line gap installation device | |
CN110829337B (en) | Grounding device and grounding method for power transmission line externally hung on unmanned aerial vehicle | |
CN201234089Y (en) | Protective interval for live operation on 1000kV AC very high voltage line | |
CN203085783U (en) | 10kV overhead line fixed-point installation grounding device | |
CN203026397U (en) | Grounding hook | |
CN203347676U (en) | Multifunctional insulating ladder end hanger | |
CN206804694U (en) | Zinc-Oxide Arrester Leakage Current test servicing unit | |
CN202550391U (en) | High-voltage power maintenance implement | |
CN105762753A (en) | +/-800kV DC line arrester installing device and method | |
CN205120774U (en) | Sensor supporting device | |
CN104113006A (en) | Operation method for replacing linear rod angle steel cross arm of 35kV overhead distribution line in live state |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170301 Termination date: 20170827 |
|
CF01 | Termination of patent right due to non-payment of annual fee |