CN210483712U CN201920987060.5U CN201920987060U CN210483712U CN 210483712 U CN210483712 U CN 210483712U CN 201920987060 U CN201920987060 U CN 201920987060U CN 210483712 U CN210483712 U CN 210483712U
Authority
CN
China
Prior art keywords
pipeline
pressure
pressure gauge
pipe
test
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920987060.5U
Other languages
Chinese (zh)
Inventor
顾占闯
任国
于万琦
王宝洪
马进
程彦符
刘�东
郭山川
王利
张巍
胡京生
薛芳
曹玉
郝君研
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Petrochina Co Ltd
Original Assignee
Petrochina Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Petrochina Co Ltd filed Critical Petrochina Co Ltd
Priority to CN201920987060.5U priority Critical patent/CN210483712U/en
Application granted granted Critical
Publication of CN210483712U publication Critical patent/CN210483712U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Measuring Fluid Pressure (AREA)

Abstract

The utility model provides a double-joint table bushing and oil production pipeline, double-joint table bushing includes: a pressure resistant pipe; one end of the pressure gauge pipeline is communicated with the pressure pipe, and the other end of the pressure gauge pipeline is used for connecting a pressure gauge; one end of the test pipeline is communicated with the pressure pipe, the other end of the test pipeline is used for connecting a test device, and the pressure gauge pipeline and the test pipeline are arranged in parallel; and the stop valve is arranged on the pressure gauge pipeline and the test pipeline and can control the opening degree of the pressure gauge pipeline and the test pipeline. The beneficial effects of the utility model are that, through setting up manometer pipeline and test pipeline, can avoid relapseing the dismouting, alleviateed because of dismantling, put the extra work load of pressing, installation manometer, reduce staff intensity of labour.

Description

Double-joint meter core-filling and oil production pipeline
Technical Field
The utility model relates to a pumping well test liquid level instrument field, concretely relates to double-joint meter bushing and oil production pipeline.
Background
In the mechanical oil extraction process, in order to record the pressure of a casing, a gauge bushing is often installed on a casing valve, and a pressure gauge with a suitable measuring range is installed on the gauge bushing. In order to master the production dynamics of an oil pumping well and judge the working condition of underground equipment, an echo detector is usually adopted to test the liquid level condition of an annular space of an oil jacket, a pressure gauge joint on a gauge bushing is required to be used for testing, only one needle type valve is arranged on the gauge bushing at present, the gauge bushing valve needs to be closed before the liquid level is tested, then the liquid level is emptied, the liquid level test is carried out after the pressure is discharged, the pressure gauge is troublesome and easy to damage, if a tester does not wear tools or save trouble, the pressure gauge is directly installed by hands, the situation of air leakage without screwing is easy to occur, and the potential safety and environmental protection hazards are caused.
SUMMERY OF THE UTILITY MODEL
The utility model provides a double-joint meter bushing and oil production pipeline to reach the purpose of avoiding destroying the manometer.
The utility model provides a technical scheme that its technical problem adopted is: a dual-joint watch bushing, comprising: a pressure resistant pipe; one end of the pressure gauge pipeline is communicated with the pressure pipe, and the other end of the pressure gauge pipeline is used for connecting a pressure gauge; one end of the test pipeline is communicated with the pressure pipe, the other end of the test pipeline is used for connecting a test device, and the pressure gauge pipeline and the test pipeline are arranged in parallel; and the stop valve is arranged on the pressure gauge pipeline and the test pipeline and can control the opening degree of the pressure gauge pipeline and the test pipeline.
Further, the pressure-resistant pipe is provided with a vent pipe.
Further, the emptying pipe is provided with an emptying bolt.
Further, the emptying bolt comprises a bolt head and a screw rod, and a groove is formed in one end, far away from the bolt head, of the screw rod.
Further, the blow-down pipe is provided with a first connecting hole and a second connecting hole, the first connecting hole is communicated with the pressure-resistant pipe and used for setting the blow-down bolt, the second connecting hole is connected with the first connecting hole and the outside of the blow-down pipe respectively, and the blow-down bolt can block the second connecting hole.
The utility model also provides a production line, including casing pressure valve and foretell double-joint table bushing.
Furthermore, one end of the pressure-resistant pipe is connected with the sleeve pressure valve through the clamp head.
The beneficial effects of the utility model are that, through setting up manometer pipeline and test pipeline, can avoid relapseing the dismouting, alleviateed because of dismantling, put the extra work load of pressing, installation manometer, reduce staff intensity of labour.
Drawings
The accompanying drawings, which form a part of the present application, are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention and together with the description serve to explain the invention and not to limit the invention. In the drawings:
fig. 1 is a schematic structural diagram of an embodiment of the present invention;
FIG. 2 is a schematic view of the construction of the flare bolt.
Reference numbers in the figures: 10. a pressure resistant pipe; 11. an emptying pipe; 20. a pressure gauge pipeline; 30. testing the pipeline; 40. a shut-off valve; 50. emptying the bolt; 51. a bolt head; 52. a screw; 53. a groove; 60. a clamp head.
Detailed Description
It should be noted that the embodiments and features of the embodiments in the present application may be combined with each other without conflict. The present invention will be described in detail below with reference to the accompanying drawings in conjunction with embodiments.
As shown in fig. 1 and 2, an embodiment of the present invention provides a dual-joint bushing for a meter, including a pressure pipe 10, a pressure gauge pipe 20, a testing pipe 30, and a shut-off valve 40. One end of the pressure gauge pipeline 20 is communicated with the pressure pipe 10, and the other end is used for connecting a pressure gauge. One end of the test pipeline 30 is communicated with the pressure pipe 10, the other end of the test pipeline is used for connecting a test device, and the pressure gauge pipeline 20 and the test pipeline 30 are arranged in parallel. The shut-off valves 40 are provided on the pressure gauge line 20 and the test line 30, and can control the opening degrees of the pressure gauge line 20 and the test line 30.
Through setting up manometer pipeline 20 and test pipeline 30, can avoid relapseing the dismouting, alleviate because of dismantling, put the extra work load of pressing, installation manometer, reduce staff intensity of labour.
As shown in FIG. 1, a vent pipe 11 is provided in the pressure pipe 10. The vent pipe 11 is provided with a vent bolt 50.
Set up blow-down pipe 11 and blow-down bolt 50, can realize the operation of putting the pressure after the cover pressure valve closes, the staff of being convenient for puts the pressure, avoids having pressure and accidentally injures the staff. Meanwhile, the emptying pipe 11 is arranged downwards along the vertical direction, and a corresponding storage container can be arranged below, so that the oil is prevented from polluting the ground.
The double-joint gauge bushing has the pressure gauge pipeline 20 and the test pipeline 30, the test pipeline 30 is specially used for testing the liquid level, the pressure gauge pipeline 20 is specially used for monitoring the casing pressure, repeated disassembly and assembly are avoided, the test and production errors are avoided, and the working efficiency is improved.
Specifically, blow-down pipe 11 has first connecting hole and second connecting hole, and first connecting hole communicates with withstand voltage pipe 10 and is used for setting up blow-down bolt 50, and first connecting hole and 11 outsides of blow-down pipe are connected respectively to the second connecting hole, and blow-down bolt 50 can the shutoff second connecting hole.
During operation, will empty air bolt 50 and twist into in the first connecting hole, can the shutoff second connecting hole, when needs empty, twist and twist empty air bolt 50, make first connecting hole and second connecting hole switch on to realize the operation of pressure release unloading.
The opening degree of the second connecting hole can be adjusted through the screwing height of the emptying bolt 50, and the purpose of adjusting emptying flow is achieved.
As shown in fig. 2, the vent bolt 50 includes a bolt head 51 and a threaded shaft 52, and a groove 53 is formed in an end of the threaded shaft 52 remote from the bolt head 51. The groove 53 enables the second connecting hole to be more smoothly communicated with the first connecting hole, and meanwhile, the high-pressure fluid is prevented from deflecting and impacting the joint of the first connecting hole and the second connecting hole, and damage is avoided.
The utility model also provides a production line, including casing pressure valve and double-joint table bushing, double-joint table bushing is foretell double-joint table bushing. Wherein, one end of the pressure pipe 10 is connected with the sleeve pressure valve through the clamp head 60.
The use of the double-joint meter bushing lightens the extra workload of disassembling, releasing and installing the pressure meter and reduces the labor intensity of workers. And has great popularization significance in the oil field with large testing workload of the pumping well.
From the above description, it can be seen that the above-mentioned embodiments of the present invention achieve the following technical effects:
1. the extra workload of disassembling, emptying and installing the pressure gauge is reduced, the labor intensity of workers is reduced, and the working efficiency of testers is improved.
2. The double-joint meter bushing can avoid the air leakage caused by the non-standard installation of the pressure meter.
3. The damage of the pressure gauge caused by repeated disassembly and assembly is reduced.
4. The double-joint watch bushing has the advantages of low cost, simple structure and convenient operation.
The above description is only for the specific embodiments of the present invention, and the scope of the present invention can not be limited by the embodiments, so that the replacement of the equivalent components or the equivalent changes and modifications made according to the protection scope of the present invention should still belong to the scope covered by the present patent. In addition, the utility model provides an between technical feature and the technical feature, between technical feature and the technical scheme, all can the independent assortment use between technical scheme and the technical scheme.

Claims (7)

1. A dual-joint watch bushing, comprising:
a pressure resistant tube (10);
one end of the pressure gauge pipeline (20) is communicated with the pressure pipe (10), and the other end of the pressure gauge pipeline is connected with a pressure gauge;
one end of the test pipeline (30) is communicated with the pressure pipe (10), the other end of the test pipeline is used for connecting a test device, and the pressure gauge pipeline (20) and the test pipeline (30) are arranged in parallel;
and the stop valve (40) is arranged on the pressure gauge pipeline (20) and the test pipeline (30) and can control the opening degrees of the pressure gauge pipeline (20) and the test pipeline (30).
2. Double-joint watch bushing according to claim 1, characterized in that the pressure pipe (10) is provided with a blow-down pipe (11).
3. The double-joint watch bushing according to claim 2, characterized in that the blow-down tube (11) is provided with a blow-down bolt (50).
4. The double-joint watch refill according to claim 3, wherein the vent bolt (50) comprises a bolt head (51) and a threaded rod (52), and wherein a groove (53) is formed in an end of the threaded rod (52) away from the bolt head (51).
5. The dual-joint watch bushing of claim 4, wherein the vent pipe (11) has a first connection hole and a second connection hole, the first connection hole communicates with the pressure pipe (10) and is used for arranging a vent bolt (50), the second connection hole is respectively connected with the first connection hole and the outside of the vent pipe (11), and the vent bolt (50) can block the second connection hole.
6. A production string comprising a casing pressure valve and a dual-joint face bushing, wherein the dual-joint face bushing is the dual-joint face bushing of any one of claims 1 to 5.
7. The riser string according to claim 6, characterized in that one end of the pressure pipe (10) is connected to the casing pressure valve by means of a clamp (60).
CN201920987060.5U 2019-06-27 2019-06-27 Double-joint meter core-filling and oil production pipeline Active CN210483712U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920987060.5U CN210483712U (en) 2019-06-27 2019-06-27 Double-joint meter core-filling and oil production pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920987060.5U CN210483712U (en) 2019-06-27 2019-06-27 Double-joint meter core-filling and oil production pipeline

Publications (1)

Publication Number Publication Date
CN210483712U true CN210483712U (en) 2020-05-08

Family

ID=70514959

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920987060.5U Active CN210483712U (en) 2019-06-27 2019-06-27 Double-joint meter core-filling and oil production pipeline

Country Status (1)

Country Link
CN (1) CN210483712U (en)

Similar Documents

Publication Publication Date Title
CN210065276U (en) Metering pump set integrating pressure stabilization, overflow and metering
CN113295533A (en) Test device and method for simulating buckling failure of lining pipe
CN210483712U (en) Double-joint meter core-filling and oil production pipeline
CN102980718B (en) On-line pressure detecting method and device thereof
CN202974549U (en) Online pressure detection device
CN204202830U (en) A kind of sealing bearing air-tightness detection device
CN103558090A (en) Water pressure testing device and method for single joint of major-diameter pressure-bearing pipeline
CN202909702U (en) Combined type multi-section fixed bed reactor
CN209339897U (en) Drilling pressurized-water grouting orifice device
CN209014251U (en) A kind of jack for plane axletree pressure loading test device
CN111272361B (en) Single tube pressure test and leakage detection tool for tube type heat exchanger
CN210689950U (en) Casing head sealing performance testing device
CN208867084U (en) A kind of bulb draws Ma seat and straight and horizontal adjusting rod bulb tool special for dismounting
CN204126637U (en) The pneumatic pressure testing device of oil field operation
CN201973004U (en) Pressure withstanding test device for hydraulic oil cylinder
CN111693217A (en) Device for verification test of valve core and valve cage sealing of side-discharge valve
CN106404298A (en) Fire hydrant hydraulic pressure sealing test device
CN102901671A (en) Water pressure testing system of manual pressure container
CN207197952U (en) Storage pressure tests water jacket
CN206458834U (en) A kind of automobile-used LNG gas cylinders switching valve body
CN201705290U (en) Novel constant pressure relief valve
CN211347274U (en) Corrugated pipe mechanical seal pressure testing device
CN214621375U (en) Liquid level measuring system of high-pressure heater
CN104034594A (en) Water-pressure airtight experimental device for especially-changed insulators
CN210893680U (en) Valve pressure testing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant