CN210483237U CN201920910913.5U CN201920910913U CN210483237U CN 210483237 U CN210483237 U CN 210483237U CN 201920910913 U CN201920910913 U CN 201920910913U CN 210483237 U CN210483237 U CN 210483237U
Authority
CN
China
Prior art keywords
fixedly connected
rod
plate
horizontal pole
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920910913.5U
Other languages
Chinese (zh)
Inventor
桑玉龙
朱柳芳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201920910913.5U priority Critical patent/CN210483237U/en
Application granted granted Critical
Publication of CN210483237U publication Critical patent/CN210483237U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a construction rail guard is built in room, including the montant, the bottom fixedly connected with fixing base of montant, the top fixedly connected with horizontal pole on montant right side, the bottom fixedly connected with bottom plate on montant right side, the jack has been seted up to the inner chamber of horizontal pole, the inner chamber of jack is pegged graft and is had the inserted bar, the bottom joint of inserted bar has an inserted section of thick bamboo, the front side fixedly connected with regulating plate of an inserted section of thick bamboo, the right side fixedly connected with bracing piece of regulating plate, the left bottom fixedly connected with connecting rod of bracing piece. The utility model discloses a jack, regulating plate, bracing piece, connecting rod, fixed plate, walking wheel, spout, bottom plate, inserted bar, the cooperation of inserting a section of thick bamboo, pulley and support column is used, has solved current building construction rail guard and has not possessed adjustable function when using, all is the connection installation that needs one usually, just can reach the effect that protective area enlarges, wastes time and energy like this, the problem that people used not convenient for.

Description

Building construction protective fence
Technical Field
The utility model relates to a construction technical field is built in the room specifically is a construction rail guard is built in room.
Background
The building construction engineering profession refers to various building constructions and their auxiliary facilities, and the matching line, pipeline, equipment installation engineering and indoor and outdoor decoration engineering, generally called building engineering, and is an engineering entity for carrying out various technical works and accomplishments such as investigation, planning, design, construction, installation and maintenance for newly building, reconstructing or extending building buildings and auxiliary structures.
The building construction also becomes the indispensable part of social development, when the building construction, need use the rail guard to protect, current rail guard when using, all need the connection installation of one usually, just can reach the effect that protective area enlarges, wastes time and energy like this, is not convenient for people to use.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
The utility model provides a not enough to prior art, the utility model provides a construction rail guard is built in room possesses adjustable advantage, has solved current room and has built the construction rail guard and do not possess adjustable function when using, all is the connection installation that needs one usually, just can reach the effect that protective area enlarges, wastes time and energy like this, the problem that people used not convenient for.
(II) technical scheme
For the purpose of realizing above-mentioned adjustable, the utility model provides a following technical scheme: the utility model provides a construction rail guard is built in room, includes the montant, the bottom fixedly connected with fixing base of montant, the top fixedly connected with horizontal pole on montant right side, the bottom fixedly connected with bottom plate on montant right side, the jack has been seted up to the inner chamber of horizontal pole, the inner chamber of jack is pegged graft and is had the inserted bar, the bottom joint of inserted bar has an inserted section of thick bamboo, the front side fixedly connected with regulating plate of an inserted section of thick bamboo, the right side fixedly connected with bracing piece of regulating plate, the left bottom fixedly connected with connecting rod of bracing piece, the fixedly connected with second prevents the railing between regulating plate and the connecting rod, the left side fixedly connected with support column at connecting rod.
Preferably, the first guard rail of fixedly connected with between horizontal pole and the bottom plate, the quantity of first guard rail is a plurality of, and a plurality of first guard rail are the equidistance and distribute between horizontal pole and bottom plate.
Preferably, the bottom fixedly connected with fixed plate of bracing piece, there is the walking wheel bottom of fixed plate through round pin axle swing joint, the walking wheel is same level setting with the fixing base.
Preferably, the bottom of the bottom plate is provided with a sliding chute matched with the pulley for use, and the inner wall of the sliding chute is in sliding connection with the surface of the pulley.
Preferably, the number of the jacks is multiple, the opening depths of the jacks are the same, and the jacks are distributed in the inner cavity of the cross rod at equal intervals.
(III) advantageous effects
Compared with the prior art, the utility model provides a construction rail guard is built in room possesses following beneficial effect:
1. the utility model uses the jack, the adjusting plate, the supporting rod, the connecting rod, the fixing plate, the walking wheel, the sliding chute, the bottom plate, the inserted bar, the inserted cylinder, the pulley and the supporting column in cooperation, the supporting rod is pushed to the right side, the supporting rod drives the fixing plate to move, the fixing plate drives the walking wheel to rotate, the connecting rod is driven to move through the movement of the supporting rod, the pulley slides in the sliding chute by the movement of the connecting rod, the adjusting plate is driven to move by the supporting rod, when the adjusting plate moves to a proper distance, a user inserts the inserted bar into the jack, then inserts the inserted bar into the inner cavity of the inserted cylinder, the inserted bar and the inserted cylinder are clamped, the adjustable advantage is achieved, the problem that the existing protective guard for house construction does not have the adjustable function when in use is solved, one connecting installation is usually, thus, the utility model is time-consuming, labor-consuming and inconvenient for people to use.
2. The utility model discloses a walking wheel has made things convenient for the pulling of user to the bracing piece, lets user labour saving and time saving when using.
3. The utility model discloses a jack makes the inserted bar can anastomotic insert to fix the distance of adjusting plate, reach the effect of adjusting.
4. The utility model discloses a spout plays spacing effect to the pulley, prevents that the situation of skew can appear at the slip in-process to the pulley.
Drawings
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is a top view of the cross bar structure of the present invention;
fig. 3 is a bottom view of the bottom plate structure of the present invention.
In the figure: 1. a vertical rod; 2. a first guard rail; 3. a cross bar; 4. a jack; 5. an adjusting plate; 6. a support bar; 7. a second guard rail; 8. a connecting rod; 9. a fixing plate; 10. a traveling wheel; 11. a chute; 12. a base plate; 13. a fixed seat; 14. inserting a rod; 15. inserting a cylinder; 16. a pulley; 17. and (4) a support column.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "both ends", "one end", "the other end", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element to be referred must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted", "provided", "connected", and the like are to be construed broadly, such as "connected", which may be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
The utility model discloses a montant 1, first protection railing 2, horizontal pole 3, jack 4, regulating plate 5, bracing piece 6, second protection railing 7, connecting rod 8, fixed plate 9, walking wheel 10, spout 11, bottom plate 12, fixing base 13, inserted bar 14, insert a section of thick bamboo 15, pulley 16 and support column 17 part and be the parts that general standard or technical personnel in the field know, its structure and principle all are that this technical personnel all can learn through the technical manual or learn through conventional experimental method.
Referring to fig. 1-3, a building construction protective guard comprises a vertical rod 1, a fixed base 13 is fixedly connected to the bottom of the vertical rod 1, a cross rod 3 is fixedly connected to the top of the right side of the vertical rod 1, a bottom plate 12 is fixedly connected to the bottom of the right side of the vertical rod 1, a plurality of first protective railings 2 are fixedly connected between the cross rod 3 and the bottom plate 12, the plurality of first protective railings 2 are equidistantly distributed between the cross rod 3 and the bottom plate 12, a plurality of jacks 4 are formed in an inner cavity of the cross rod 3, the number of the jacks 4 is equal to the opening depth of the plurality of jacks 4, the jacks 4 are equidistantly distributed in the inner cavity of the cross rod 3, the jacks 4 allow the jacks 14 to be inserted in an inosculated manner, so as to fix the distance of an adjusting plate 5 and achieve an adjusting effect, the jacks 14 are inserted in the inner cavities of the jacks 4, and an inserting barrel 15 is clamped, an adjusting plate 5 is fixedly connected to the front side of the inserting cylinder 15, a supporting rod 6 is fixedly connected to the right side of the adjusting plate 5, a fixing plate 9 is fixedly connected to the bottom of the supporting rod 6, a walking wheel 10 is movably connected to the bottom of the fixing plate 9 through a pin shaft, the walking wheel 10 and a fixing seat 13 are arranged in the same horizontal direction, the supporting rod 6 is conveniently pulled by a user through the walking wheel 10, time and labor are saved when the user uses the device, a connecting rod 8 is fixedly connected to the bottom of the left side of the supporting rod 6, a second protective barrier 7 is fixedly connected between the adjusting plate 5 and the connecting rod 8, a supporting column 17 is fixedly connected to the left side of the top of the connecting rod 8, a pulley 16 is movably connected to the top of the supporting column 17, a chute 11 matched with the pulley 16 is formed in the bottom, preventing the pulley 16 from shifting during sliding.
When in use, when the protective area of the protective guard is adjusted, firstly, a user moves the support rod 6 to the right side, the support rod 6 drives the fixing plate 9 to move, the movement of the fixing plate 9 drives the traveling wheels 10 to slide with the ground, secondly, the connecting rod 8 is driven to move by the movement of the supporting rod 6, the supporting column 17 is driven to move by the movement of the connecting rod 8, the pulley 16 is driven to slide in the sliding groove 11 by the movement of the supporting column 17, and finally, the adjusting plate 5 is driven to move by the movement of the supporting rod 6, the inserting cylinder 15 is driven to move by the movement of the adjusting plate 5, when the position of the inserting cylinder 15 and the inserting hole 4 is vertical, the user inserts the inserting rod 14 into the inserting hole 4 and the inserting cylinder 15, and the inserting rod 14 is clamped with the inserting cylinder 15, thereby fix the position of bracing piece 6, form the rail guard under the effect of first protection railing 2 and second protection railing 7 after bracing piece 6 is fixed.
In summary, the following steps: this construction rail guard is built in room, through jack 4, regulating plate 5, bracing piece 6, connecting rod 8, fixed plate 9, walking wheel 10, spout 11, bottom plate 12, inserted bar 14, insert a section of thick bamboo 15, pulley 16 and support column 17's cooperation is used, solved current room and built construction rail guard and do not possess adjustable function when using, all be the connection installation that needs one usually, just can reach the effect that protective area enlarges, waste time and energy like this, the problem that people not convenient for used.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides a construction rail guard is built in room, includes montant (1), its characterized in that: the bottom of the vertical rod (1) is fixedly connected with a fixed seat (13), the top of the right side of the vertical rod (1) is fixedly connected with a cross rod (3), the bottom of the right side of the vertical rod (1) is fixedly connected with a bottom plate (12), the inner cavity of the cross rod (3) is provided with an insertion hole (4), an insert rod (14) is inserted into the inner cavity of the insert hole (4), an insert cylinder (15) is clamped at the bottom of the insert rod (14), an adjusting plate (5) is fixedly connected with the front side of the inserting cylinder (15), a supporting rod (6) is fixedly connected with the right side of the adjusting plate (5), the bottom of the left side of the supporting rod (6) is fixedly connected with a connecting rod (8), a second guard rail (7) is fixedly connected between the adjusting plate (5) and the connecting rod (8), the left side fixedly connected with support column (17) at connecting rod (8) top, the top swing joint of support column (17) has pulley (16).
2. The building construction protective guard of claim 1, wherein: the utility model discloses a guardrail device, including horizontal pole (3), bottom plate (12), a plurality of first guardrail bar (2) of fixedly connected with between horizontal pole (3) and bottom plate (12), the quantity of first guardrail bar (2) is a plurality of, and a plurality of first guardrail bar (2) are equidistance and distribute between horizontal pole (3) and bottom plate (12).
3. The building construction protective guard of claim 1, wherein: the bottom fixedly connected with fixed plate (9) of bracing piece (6), there are walking wheel (10) bottom of fixed plate (9) through round pin axle swing joint, walking wheel (10) and fixing base (13) are same level setting.
4. The building construction protective guard of claim 1, wherein: the bottom of the bottom plate (12) is provided with a sliding groove (11) matched with the pulley (16) for use, and the inner wall of the sliding groove (11) is in sliding connection with the surface of the pulley (16).
5. The building construction protective guard of claim 1, wherein: the quantity of jack (4) is a plurality of, and the opening degree of a plurality of jacks (4) is the same, jack (4) are the inner chamber at horizontal pole (3) of equidistance distribution.
CN201920910913.5U 2019-06-17 2019-06-17 Building construction protective fence Expired - Fee Related CN210483237U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920910913.5U CN210483237U (en) 2019-06-17 2019-06-17 Building construction protective fence

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920910913.5U CN210483237U (en) 2019-06-17 2019-06-17 Building construction protective fence

Publications (1)

Publication Number Publication Date
CN210483237U true CN210483237U (en) 2020-05-08

Family

ID=70513920

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920910913.5U Expired - Fee Related CN210483237U (en) 2019-06-17 2019-06-17 Building construction protective fence

Country Status (1)

Country Link
CN (1) CN210483237U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114575670A (en) * 2022-05-06 2022-06-03 新乡市平原市政管理有限公司 Intelligent regulation installation formula rail for building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114575670A (en) * 2022-05-06 2022-06-03 新乡市平原市政管理有限公司 Intelligent regulation installation formula rail for building

Similar Documents

Publication Publication Date Title
US4490075A (en) Retaining wall system
CN111962683B (en) Prefabricated house and construction method thereof
CN210483237U (en) Building construction protective fence
CN209099369U (en) A kind of internal support of foundation pit device
CN212052485U (en) Green belt isolation guardrail for municipal works
CN213927845U (en) Municipal administration building construction is with protection fixed knot structure
CN209958800U (en) Interim stair rail guard
CN210483251U (en) Municipal works are with construction warning baffle
CN210482878U (en) Stone floor connecting structure
CN210827505U (en) Ecological slope protection net structure for ecological protection
CN209924903U (en) Steel ladder of marking time for foundation ditch side slope of adjustable angle of marking time
CN209976161U (en) Rail guard for construction
CN209212059U (en) A kind of guardrail of adjustable density
CN112196456A (en) Special telescopic ladder for inspection well
CN219548356U (en) Stair room prefabricated part installation operation platform
CN215212730U (en) Pit foundation protection fence for construction engineering construction
CN214273013U (en) Building construction foundation ditch guardrail
CN213890693U (en) Height-adjustable auxiliary drilling support
CN219638388U (en) Novel wall form is fixed device
CN110751880B (en) Telegraph pole assembling or centralizing training device and method
US682259A (en) Picket fence.
CN220790692U (en) Deep foundation pit operation safety device
CN212773786U (en) Protective guardrail for construction engineering foundation pit
CN215055683U (en) But angle regulation's foundation ditch steel ladder for side slope marks steps
CN212956550U (en) Foundation ditch construction support for railway engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200508

Termination date: 20210617