monitoring
vertical rod
arc
monitoring equipment
lower flange
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921039080.6U
Other languages
Chinese (zh)
Inventor
施轶凡
余泽泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Anxin Kechuang Technology Co ltd
Sichuan safety science and technology research institute
Sichuan Hengyuntong Technology Co ltd
Original Assignee
Sichuan Anxin Kechuang Technology Co ltd
Sichuan safety science and technology research institute
Sichuan Hengyuntong Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Anxin Kechuang Technology Co ltd, Sichuan safety science and technology research institute, Sichuan Hengyuntong Technology Co ltd filed Critical Sichuan Anxin Kechuang Technology Co ltd
Priority to CN201921039080.6U priority Critical patent/CN210460138U/en
Application granted granted Critical
Publication of CN210460138U publication Critical patent/CN210460138U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a temporary vertical rod applied to monitoring equipment, which comprises a vertical rod for installing the monitoring equipment and a spiral ground pile for fixing at a monitoring point; the spiral ground pile top is provided with lower flange, the montant bottom is provided with the upper flange, lower flange and upper flange mutual assembly. The utility model aims to provide a: the pole setting to current monitoring facilities adopts the mounting means of assembly on the concrete foundation, has the longer problem of installation time, provides a temporary pole setting of being applied to monitoring facilities. The temporary upright rod of the monitoring equipment does not need to be installed on the base, and can be directly installed in a required monitoring area, so that the monitoring equipment can be arranged quickly and timely.

Description

Be applied to monitoring facilities's interim pole setting
Technical Field
The utility model belongs to the technical field of the monitoring facilities pole setting. In particular to a temporary upright for monitoring equipment.
Background
The vertical rod is widely used in the fields of street lamps, monitoring equipment, traffic signals, indicating equipment and the like. Particularly in the field of monitoring equipment, serious loss is caused to the country and the society due to frequent accidents of natural landslides of Chinese mountains, landslides of roadbed slopes and the like in recent years. The slope monitoring equipment needs to be densely arranged to monitor the slope landslide condition and evacuate residents and property in time after dangerous situations are found so as to guarantee the life and property safety of people.
Typically, the monitoring equipment is mounted on a vertical pole, which is mounted on a base. When the base is constructed, a concrete pouring space of the base is constructed by adopting a mechanical pit drilling or manual pit digging mode according to design requirements, a ground cage is placed downwards after the pit depth reaches the design requirements, and finally concrete pouring is carried out. After the construction is completed, the vertical rod is installed on the base, and then the monitoring equipment is installed on the vertical rod to realize assembly.
Because the upright of the existing monitoring equipment is assembled by adopting a concrete base, the construction process is complicated, and the base position and the upright installation need to be accurately measured and positioned; and the base concrete requires a long airing time, resulting in a long period for the arrangement of the monitoring equipment. Secondly, the construction of the base needs to carry materials such as reinforcing steel bars, cement and river sand, and the side slope is located at the position where the field environment traffic is inconvenient, so that the preparation work is labor-consuming and time-consuming.
However, for some sudden dangerous areas and surrounding areas, corresponding monitoring equipment needs to be arranged quickly and timely so as to monitor occurrence of secondary disasters and evacuate residents and property timely after dangerous situations are found. Then, the pole setting of current monitoring facilities adopts the mode of assembly on the concrete foundation, can't satisfy the demand of arranging monitoring facilities fast in time.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a: the pole setting to current monitoring facilities adopts the mounting means of assembly on the concrete foundation, has the longer problem of installation time, provides a temporary pole setting of being applied to monitoring facilities. This interim pole setting need not to install on the base, but direct mount in required monitoring area to can arrange monitoring facilities in time fast.
In order to realize the purpose, the utility model discloses a technical scheme be: a temporary upright post applied to monitoring equipment comprises a vertical post for mounting the monitoring equipment and a spiral ground pile for fixing at a monitoring point; the spiral ground pile top is provided with lower flange, the montant bottom is provided with the upper flange, lower flange and upper flange mutual assembly. According to the scheme, the monitoring points are fixed in a spiral ground pile mode, and the vertical rods are assembled and fixed with one another through the matched flange plates. Due to the adoption of the spiral ground piles, the vertical rods are very convenient to fix, and monitoring equipment can be arranged quickly and timely.
As the preferred scheme, the screw hole of lower flange dish is the arc hole, and the circular centre of a circle and the montant axis coincidence in this arc hole place. The design that adopts the arc hole makes the pole setting adjust to the requirement to the pole position in the aspect of adaptation sun light angle, signal acquisition and transmission position etc..
As the preferred scheme, the arc holes are evenly distributed along the periphery of the vertical rod. Further, at least four arc holes are arranged, and each arc hole is located on the same circle, so that the vertical rod assembly is more stable, and the stability of the vertical rod assembly is further improved.
As the preferred scheme, be provided with deep floor between lower flange and the montant. Further, the reinforcing rib plates are uniformly arranged along the periphery of the vertical rod. Still further, the deep floor has arranged four at least to strengthen the structural strength of pole setting.
As the preferred scheme, the number of the arc-shaped holes is consistent with that of the reinforcing rib plates, and the arc-shaped holes and the reinforcing rib plates are arranged at intervals. The present solution provides an optimal design.
As another preferred scheme, the screw hole of the upper flange is an arc-shaped hole, and the circle center of the circle where the arc-shaped hole is located coincides with the axis of the vertical rod.
As the preferred scheme, the axis of montant and spiral ground pile coincide each other, and the axis of montant or spiral ground pile is mutually perpendicular with the plane of upper flange dish and lower flange dish. This scheme can guarantee the accuracy of pole setting assembly when carrying out the fine setting to the pole.
To sum up, owing to adopted above-mentioned technical scheme, compare in prior art, the beneficial effects of the utility model are that: the utility model adopts the scheme of the spiral ground pile, solves the problem of the airing period of the cement pre-buried ground cage, and can shift the monitoring equipment at any time according to the position change of the monitoring point; and the purchase and the transport problem of cement river sand and water have been solved, monitoring facilities's installation cost has been reduced. In addition, the utility model adopts the scheme of the arc-shaped hole, technically solves the problem of installation matching of the wire pole, and saves the installation time; meanwhile, the wire rod is rotatable, the conversion efficiency of the solar photovoltaic panel is utilized to the maximum extent, and the photovoltaic panel can also provide power input for normal operation of equipment in a special environment.
Drawings
Fig. 1 is a first schematic structural diagram of the embodiment.
Fig. 2 is a schematic structural diagram of the second embodiment.
Fig. 3 is a schematic top view of the embodiment.
Reference numbers for parts in the drawings: 1-vertical rod, 2-spiral ground pile, 3-lower flange, 4-upper flange, 5-arc hole of lower flange, 6-reinforcing rib plate, C-arc hole, and theta-arc hole radian range.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the invention.
Example 1
The embodiment discloses a temporary vertical rod applied to monitoring equipment, which comprises a vertical rod for installing the monitoring equipment and a spiral ground pile for fixing a monitoring point, as shown in figures 1-2; the spiral ground pile top is provided with lower flange, the montant bottom is provided with the upper flange, lower flange and upper flange mutual assembly.
As shown in fig. 3, the screw hole of the lower flange is an arc hole, and the center of the circle where the arc hole is located coincides with the axis of the vertical rod. The radian range of the arc-shaped hole is pi/6 +/-pi/12, so that the vertical rod can rotate by a corresponding angle. The arc holes are uniformly arranged along the periphery of the vertical rod. Four arc holes are arranged, and each arc hole is positioned on the same circle.
As shown in figures 1-2, a reinforcing rib plate is arranged between the lower flange plate and the vertical rod. The reinforcing rib plates are uniformly arranged along the periphery of the vertical rod. Four reinforcing rib plates are arranged. The number of the arc holes is consistent with that of the reinforcing rib plates, and the arc holes and the reinforcing rib plates are arranged at intervals.
As shown in fig. 1-2, the axes of the vertical rod and the spiral ground pile are coincident with each other, and the axes of the vertical rod or the spiral ground pile are perpendicular to the planes of the upper flange plate and the lower flange plate.
For solving the interim installation problem of monitoring facilities, this embodiment designs a replacement cement and buries installation mode of ground cage type base in advance. Based on the information, the existing spiral ground embedded pile on the market is utilized to replace the existing concrete base, the flange matched with the monitoring equipment is added on the spiral ground pile, when the monitoring equipment is temporarily required to be installed, the spiral ground pile is screwed into the bottom, and then the lower flange of the monitoring equipment and the upper flange of the spiral pile are fixed mutually. Therefore, the problem of the airing period of the cement embedded ground cage is solved, and the monitoring equipment can be displaced at any time according to the position change of the monitoring point; and the purchase and the transport problem of cement river sand and water have been solved, monitoring facilities's installation cost has been reduced.
In addition, the big problem of the installation degree of difficulty when this embodiment is unmatched for solving traditional line pole and base ground cage screw rod position to and the influence to the power supply when photovoltaic board and sunshine angular deviation, design a monitoring facilities installation angle's that can manual or automatically regulated scheme. Specifically, the traditional line pole mounting hole is a single hole, so that the line pole is easy to mount with high difficulty and small adjustable range under the condition that the size of the mounting screw is not correct; in addition, monitoring facilities installation angle is single, is unfavorable for under the special environment like the installation when adjusting the photovoltaic board according to the illumination angle. Based on the above situation, this embodiment makes the mounting hole both can satisfy the installation requirement with the scheme that adopts the arc hole, can realize line pole rotation regulation again by manual mode. In addition, the solar photovoltaic module can be adjusted in an automatic mode, specifically, a driving motor is arranged on the inner wall of the upright post, the driving motor rotates clockwise or anticlockwise at a constant speed by taking the ground as an acting point, the controller detects an analog quantity signal output by photovoltaic according to the fact that the solar photovoltaic panel serves as an optical sensor, so that the illumination intensity is judged, and then the rotation angle of the rod body is reasonably controlled. Therefore, the installation problem of the wire pole bottom plate is technically solved, and the installation time is saved; meanwhile, the wire rod is rotatable, the conversion efficiency of the solar photovoltaic panel is utilized to the maximum extent, and the photovoltaic panel can also provide power input for normal operation of equipment in a special environment.
Example 2
In contrast to embodiment 1, this embodiment provides an arc-shaped hole on the helical pile. Specifically, the screw hole of the ground flange plate is an arc-shaped hole, and the circle center of the circle where the arc-shaped hole is located coincides with the axis of the vertical rod.
The above description is only exemplary of the present invention and should not be taken as limiting the scope of the present invention, as any modifications, equivalents, improvements and the like made within the spirit and principles of the present invention are intended to be included within the scope of the present invention.

Claims (10)

1. The utility model provides a be applied to monitoring facilities's interim pole setting which characterized in that: the device comprises a vertical rod for installing monitoring equipment and a spiral ground pile for fixing a monitoring point; the spiral ground pile top is provided with lower flange, the montant bottom is provided with the upper flange, lower flange and upper flange mutual assembly.
2. Temporary upright for monitoring equipment, according to claim 1, characterized in that: the screw hole of the lower flange plate is an arc-shaped hole, and the circle center of the circle where the arc-shaped hole is located coincides with the axis of the vertical rod.
3. Temporary upright for monitoring equipment, according to claim 2, characterized in that: the arc holes are uniformly arranged along the periphery of the vertical rod.
4. A temporary upright for monitoring devices, according to claim 3, characterized in that: at least four arc holes are arranged, and each arc hole is positioned on the same circle.
5. Temporary upright for monitoring devices according to claim 4, characterized in that: a reinforcing rib plate is arranged between the lower flange plate and the vertical rod.
6. Temporary upright for monitoring devices, according to claim 5, characterized in that: the reinforcing rib plates are uniformly arranged along the periphery of the vertical rod.
7. Temporary upright for monitoring equipment, according to claim 6, characterized in that: at least four stiffener plates are arranged.
8. Temporary upright for monitoring equipment, according to claim 7, characterized in that: the number of the arc holes is consistent with that of the reinforcing rib plates, and the arc holes and the reinforcing rib plates are arranged at intervals.
9. Temporary upright for monitoring equipment, according to claim 1, characterized in that: the screw hole of the upper flange is an arc-shaped hole, and the circle center of the circle where the arc-shaped hole is located coincides with the axis of the vertical rod.
10. Temporary upright for monitoring equipment, according to claim 2, characterized in that: the axes of the vertical rod and the spiral ground pile are superposed with each other, and the axes of the vertical rod or the spiral ground pile are vertical to the planes of the upper flange plate and the lower flange plate.
CN201921039080.6U 2019-07-04 2019-07-04 Be applied to monitoring facilities's interim pole setting Active CN210460138U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921039080.6U CN210460138U (en) 2019-07-04 2019-07-04 Be applied to monitoring facilities's interim pole setting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921039080.6U CN210460138U (en) 2019-07-04 2019-07-04 Be applied to monitoring facilities's interim pole setting

Publications (1)

Publication Number Publication Date
CN210460138U true CN210460138U (en) 2020-05-05

Family

ID=70443749

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921039080.6U Active CN210460138U (en) 2019-07-04 2019-07-04 Be applied to monitoring facilities's interim pole setting

Country Status (1)

Country Link
CN (1) CN210460138U (en)

Similar Documents

Publication Publication Date Title
US8684632B2 (en) Systems and methods for laying out and installing a solar panel array
KR100905069B1 (en) Solar beam module support fundamental file
CN210460138U (en) Be applied to monitoring facilities's interim pole setting
CN108824423B (en) Bored pile construction alarm device
CN112394749A (en) Solar photovoltaic operation and maintenance control system based on tracking control and field data acquisition
CN110904877A (en) New forms of energy safety warning device
CN103487023B (en) Board is sighted in the transmission of long distance and high precision elevation
CN102628277A (en) Transition section-free monopile offshore wind turbine foundation structure
CN211257106U (en) Foundation pit deformation monitoring mark
CN211479281U (en) Traffic information data acquisition device
KR102449783B1 (en) Supporting structure for solar photovoltaic power generation module
CN208186206U (en) A kind of solar street light recycles pedestal
KR102000103B1 (en) Height adjustment device for solar power plant for soft ground
CN221297997U (en) Monitoring and early warning device for support deflection of subway foundation pit
CN211014689U (en) On-site assembling type rain condition monitoring device
CN216770463U (en) Fixing device of small deformation radar of tunnel foundation
CN220792621U (en) High water level real-time supervision alarm device in reservoir pond
CN218263964U (en) Leveling upright rod foundation embedded part for high-wind-speed area
CN205883153U (en) Photovoltaic module array clearance reflex reflector
CN216108590U (en) Combined foundation of tower crane
CN221237446U (en) Loess slope earth surface displacement monitoring facilities installation device
CN214173301U (en) Multifunctional bridge displacement detection platform
CN219587314U (en) Electric power pole tower
KR20190125566A (en) A pile
CN211952592U (en) Remote control type street lamp easy to assemble

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant