CN210422147U - Fender is enclosed with installing fast to construction - Google Patents

Fender is enclosed with installing fast to construction Download PDF

Info

Publication number
CN210422147U
CN210422147U CN201920966080.4U CN201920966080U CN210422147U CN 210422147 U CN210422147 U CN 210422147U CN 201920966080 U CN201920966080 U CN 201920966080U CN 210422147 U CN210422147 U CN 210422147U
Authority
CN
China
Prior art keywords
fixed
mounting
adjustment mechanism
quick installation
building construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920966080.4U
Other languages
Chinese (zh)
Inventor
白万利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Dinghui Construction Group Co Ltd
Original Assignee
Guangxi Dinghui Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Dinghui Construction Group Co Ltd filed Critical Guangxi Dinghui Construction Group Co Ltd
Priority to CN201920966080.4U priority Critical patent/CN210422147U/en
Application granted granted Critical
Publication of CN210422147U publication Critical patent/CN210422147U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a fender is enclosed with quick installation to construction, including soil layer and two bracing pieces, all be equipped with the spout on two bracing pieces, all be equipped with adjustment mechanism in two spouts, all be fixed with first mounting on two adjustment mechanism, all rotate on two first mountings and be connected with the connecting rod, all be fixed with the second mounting on the one end lateral wall of two bracing pieces, rotate on the second mounting and be connected with the dead lever, the upper end of two dead levers all is fixed with the montant, and the upper end of two connecting rods rotates respectively and connects on two montants. The utility model discloses reached enclose the fender to a plurality of and carry out the purpose of installing fast and dismantling for the installation rate, simultaneously, improved the stability of enclosing the fender to, conveniently adjust the mounting height as required, improved stability, alleviateed constructor's installation intensity, easy operation, convenient to use.

Description

Fender is enclosed with installing fast to construction
Technical Field
The utility model relates to a construction technical field especially relates to a fender is enclosed with quick installation to construction.
Background
The enclosure is a measure taken to isolate a construction site from the external environment and enable the construction site to be a relatively closed space, and comprises enclosures built by various masonry materials, maintenance bodies formed by various formed plates and the like.
At present, when the fender is enclosed in the installation, the support frame is regarded as the support system for the majority, and rethread square timber and bolt are installed fixedly, and this kind of mounting means not only wastes time and energy, and the installation effectiveness is low simultaneously, has increased constructor's intensity of labour, can not reach the purpose of quick installation and dismantlement to, the current fender that encloses, inconvenient carrying can occupy a large amount of spaces, and for this reason, we have proposed a building construction and have enclosed the fender with quick installation and solve above-mentioned problem.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the shortcoming that exists among the prior art, and the fender is enclosed with quick installation to construction that proposes.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a fender is enclosed with quick installation to construction, includes soil layer and two bracing pieces, all is equipped with the spout on two bracing pieces, all is equipped with adjustment mechanism in two spouts, all is fixed with first mounting on two adjustment mechanism, all rotates on two first mountings to be connected with the connecting rod, all is fixed with the second mounting on the one end lateral wall of two bracing pieces, it is connected with the dead lever to rotate on the second mounting, and the upper end of two dead levers all is fixed with the montant, and the upper end of two connecting rods rotates respectively to be connected on two montants, and is a set of with a montant and an adjustment mechanism of one side, has set up the baffle jointly on a montant and the adjustment mechanism in the same set of, and the one end interconnect of two.
Preferably, the adjusting mechanism comprises a partition board fixed between opposite side walls in the chute, a bearing penetrates through and is fixed on the partition board, a screw rod penetrates through the bearing, one end of the screw rod is fixed with a rotating wheel which is positioned in the chute, the other end of the screw rod is connected to one end side wall in the chute in a rotating manner, a slider is sleeved on the screw rod in a threaded manner, two ends of the slider are fixed with cross rods, the opposite side walls in the chute are provided with openings, one ends of the two cross rods penetrate through the openings and extend to two sides of the supporting rod respectively, one ends of the two cross rods are fixed with transverse plates, the first fixing part is fixed on one end side wall of the slider, one end side walls of the two transverse plates and one end side wall of the vertical rod are fixed with mounting plates, one end side wall of the three mounting plates is fixed with an L-shaped plate, one end side wall of the baffle is, one end of the L-shaped plate extends into the L-shaped groove, and the area of the L-shaped groove is larger than that of the L-shaped plate.
Preferably, the two sides of two baffles are all fixed with the fixed plate, and two fixed plates of adjacent one side are a set, run through jointly on two fixed plates in the same set and are equipped with the bolt.
Preferably, the lower extreme of bracing piece is fixed with the installation piece, the lower extreme of installation piece is fixed with four inserted bars, and the lower extreme of four inserted bars all extends to in the soil horizon.
Preferably, the baffle is made of color steel.
Preferably, the support rod is made of carbon steel.
Compared with the prior art, the beneficial effects of the utility model are that:
1. through the matching between the adjusting mechanism and the vertical rod, the function of rapidly installing a plurality of enclosure bars is realized, the installing and disassembling efficiency is improved, meanwhile, the stability of the enclosure bars can be improved, the enclosure bars are convenient to shrink, and the occupied area is reduced;
2. through the matching between the bolt and the fixing plate, the function of quickly splicing the enclosure protection plate is realized, the splicing steps are reduced, and the aim of quick installation is fulfilled;
to sum up, the utility model discloses reached and enclosed a plurality of purpose of keeping off and carrying out quick installation and dismantlement for the installation rate has improved the stability of enclosing the fender, simultaneously, conveniently adjust the mounting height as required, improved stability, alleviateed constructor's installation intensity to, make things convenient for the shrink and carry, reduced area, easy operation, convenient to use.
Drawings
Fig. 1 is a rear view of a rapid installation enclosure for building construction according to the present invention;
fig. 2 is a front view of a rapid installation enclosure for building construction proposed by the present invention;
fig. 3 is a schematic structural view of a fast-mounting enclosure supporting rod for building construction according to the present invention;
FIG. 4 is an enlarged view of the point A of the rapid installation enclosure for building construction provided by the present invention;
FIG. 5 is an enlarged view of the place B of the rapid installation enclosure for building construction provided by the utility model;
FIG. 6 is an enlarged view of the place C of the rapid installation enclosure for building construction provided by the utility model;
FIG. 7 is a side view of a fast-installed fencing baffle for construction according to the present invention;
fig. 8 is a front view of a fast-installed baffle for building construction according to the present invention;
FIG. 9 is an enlarged view of the fast-installed fence for building construction at position D of the present invention;
in the figure: the device comprises a soil layer 1, a mounting block 2, a baffle 3, a supporting rod 4, an inserted rod 5, a screw 6, a fixing plate 7, a connecting rod 8, a vertical rod 9, a transverse plate 10, a transverse rod 11, a groove 12L, a sliding block 13, a rotating wheel 14, a bearing 15, an opening 16, a partition plate 17, a bolt 18, a fixing rod 19, a mounting plate 20, a template 21L, a sliding groove 22, a first fixing part 23 and a second fixing part 24.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-9, a fast-mounting enclosure for building construction comprises a soil layer 1 and two support rods 4, wherein the support rods 4 are made of carbon steel, two slide grooves 22 are formed in the two support rods 4, adjusting mechanisms are arranged in the two slide grooves 22, under the action of the adjusting mechanisms, the height can be conveniently adjusted and the support rods can be conveniently unfolded and contracted, first fixing members 23 are fixed on the two adjusting mechanisms, the adjusting mechanisms drive the connecting rods 8 to move when moving, the connecting rods 8 are rotatably connected to the two first fixing members 23, second fixing members 24 are fixed on the side walls of one ends of the two support rods 4, fixing rods 19 are rotatably connected to the second fixing members 24, vertical rods 9 are fixed on the upper ends of the two fixing rods 19, the upper ends of the two connecting rods 8 are respectively rotatably connected to the two vertical rods 9, the connecting rods 8 drive the fixing rods 19 to adjust the inclination angle when moving, thereby conveniently driving the vertical rod 9 to adjust the inclination angle.
The utility model discloses in, be a set of with a montant 9 and an adjustment mechanism of one side, erect baffle 3 on montant 9 and the adjustment mechanism in the same group jointly, baffle 3 adopts various steel to make, and the one end interconnect of two baffles 3, under adjustment mechanism and montant 9's effect, easy to assemble and fixed stop 3 have improved baffle 3's stability, simultaneously, and convenient shrink has reduced area, convenient to carry.
The utility model discloses in, adjustment mechanism is including fixing the baffle 17 between the relative lateral wall in spout 22, run through and be fixed with bearing 15 on the baffle 17, run through being equipped with screw rod 6 in the bearing 15, the one end of screw rod 6 is fixed with rotates wheel 14, and rotate wheel 14 and be located spout 22, it rotates and drives screw rod 6 and rotate to rotate wheel 14, screw rod 6 rotates slider 13 and slides in spout 22, the other end of screw rod 6 rotates and connects on the one end lateral wall in spout 22, slider 13 has been cup jointed to screw 6 upper thread, slider 13's both ends all are fixed with horizontal pole 11, slider 13 drives two horizontal pole 11 shift positions when removing, horizontal pole 11 removes and can drive diaphragm 10 shift position.
In the utility model, the opposite side walls in the sliding groove 22 are both provided with openings 16, one ends of the two cross bars 11 are both penetrated through the openings 16 and respectively extended to the two sides of the supporting rod 4, one ends of the two cross bars 11 are both fixed with the transverse plates 10, the first fixing member 23 is fixed on one side wall of the sliding block 13, the sliding block 13 drives the connecting rod 8 on the first fixing member 23 to unfold so as to conveniently drive the vertical rod 9 to unfold, the side walls of one ends of the two transverse plates 10 and the vertical rod 9 are both fixed with the mounting plates 20, after the positions of the transverse plates 10 and the vertical rod 9 are adjusted, the L-shaped plates 21 are inserted in the L-shaped grooves 12 so as to conveniently mount and fix the baffle 3, the side walls of one ends of the three mounting plates 20 are both fixed with the L-shaped plates 21, the side wall of one end of the baffle 3 is provided with three L-shaped grooves 12 corresponding, the area of L type groove 12 is greater than the area of L template 21, through the cooperation between L template 21 and the L type groove 12, conveniently installs baffle 3 fast, has improved the efficiency of installation and dismantlement.
The utility model discloses in, two baffle 3's both sides all are fixed with fixed plate 7, and two fixed plates 7 of adjacent one side are a set of, run through jointly on two fixed plates 7 in same set of and be equipped with bolt 18, install two adjacent fixed plates 7 through bolt 18 convenience and fix.
The utility model discloses in, the lower extreme of bracing piece 4 is fixed with installation piece 2, and the lower extreme of installation piece 2 is fixed with four inserted bars 5, and in four inserted bars 5's lower extreme all extended to soil layer 1, through inject inserted bar 5 in soil layer 1 to the bracing piece 4 of the convenient 2 upper ends of installation piece carries out the outrigger.
In the utility model, when in use, firstly, the length of the enclosure which needs to be arranged is measured, the length and the total length of the enclosure are compared to confirm how many fixed points need to be fixed, after the fixed points are selected, the support rod 4 is taken out, then the inserted rod 5 is inserted into the soil layer 1, thereby the support rod 4 at the upper end of the installation block 2 is convenient to be installed and fixed, then the rotating wheel 14 is rotated, the rotating wheel 14 rotates to drive the screw rod 6 to rotate, the screw rod 6 rotates to drive the sliding block 13 to slide in the sliding groove 22, when the sliding block 13 slides, the transverse plates 10 at one end of the two transverse rods 11 are not only convenient to drive to adjust the height, but also the vertical rod 9 is convenient to unfold, after the vertical rod 9 and the two transverse plates 10 are adjusted to proper positions, the rotating wheel 14 stops rotating, then the baffle 3 is placed at proper positions, the L-shaped plate 21 is inserted into, after that, the two adjacent fixing plates 7 are inserted and fixed by the bolts 18.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (6)

1. The utility model provides a fender is enclosed with quick installation to construction, includes soil layer (1) and two bracing pieces (4), its characterized in that: all be equipped with spout (22) on two bracing pieces (4), all be equipped with adjustment mechanism in two spout (22), all be fixed with first mounting (23) on two adjustment mechanism, all rotate on two first mounting (23) and be connected with connecting rod (8), all be fixed with second mounting (24) on the one end lateral wall of two bracing pieces (4), it is connected with dead lever (19) to rotate on second mounting (24), and the upper end of two dead levers (19) all is fixed with montant (9), and the upper end of two connecting rod (8) rotates respectively and connects on two montants (9), and is a set of with montant (9) and an adjustment mechanism of one side, has erect baffle (3) jointly on montant (9) and the adjustment mechanism in the same set of, and the one end interconnect of two baffles (3).
2. The quick installation enclosure for building construction of claim 1, wherein: the adjusting mechanism comprises a partition plate (17) fixed between opposite side walls in a sliding groove (22), a bearing (15) penetrates through and is fixed on the partition plate (17), a screw rod (6) penetrates through the bearing (15), a rotating wheel (14) is fixed at one end of the screw rod (6), the rotating wheel (14) is located in the sliding groove (22), the other end of the screw rod (6) is rotatably connected to one side wall in the sliding groove (22), a sliding block (13) is sleeved on the screw rod (6) in a threaded manner, transverse rods (11) are fixed at two ends of the sliding block (13), openings (16) are arranged on the opposite side walls in the sliding groove (22), one ends of the two transverse rods (11) penetrate through the openings (16) and extend to two sides of a fixing piece (4) respectively, transverse plates (10) are fixed at one ends of the two transverse rods (11), and a first transverse plate (23) is fixed on one side wall of the sliding block (13), all be fixed with mounting panel (20) on the one end lateral wall of two diaphragm (10) and montant (9), all be fixed with L template (21) on the one end lateral wall of three mounting panel (20), be equipped with three L type groove (12) that correspond with L template (21) on the one end lateral wall of baffle (3), the one end of L template (21) extends to in L type groove (12), the area in L type groove (12) is greater than the area of L template (21).
3. The quick installation enclosure for building construction of claim 1, wherein: both sides of two baffles (3) all are fixed with fixed plate (7), and two fixed plate (7) of adjacent one side are a set of, run through jointly on two fixed plate (7) in the same group and are equipped with bolt (18).
4. The quick installation enclosure for building construction of claim 1, wherein: the lower extreme of bracing piece (4) is fixed with installation piece (2), the lower extreme of installation piece (2) is fixed with four inserted bars (5), and the lower extreme of four inserted bars (5) all extends to in soil layer (1).
5. The quick installation enclosure for building construction of claim 1, wherein: the baffle (3) is made of color steel.
6. The quick installation enclosure for building construction of claim 1, wherein: the support rod (4) is made of carbon steel.
CN201920966080.4U 2019-06-26 2019-06-26 Fender is enclosed with installing fast to construction Expired - Fee Related CN210422147U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920966080.4U CN210422147U (en) 2019-06-26 2019-06-26 Fender is enclosed with installing fast to construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920966080.4U CN210422147U (en) 2019-06-26 2019-06-26 Fender is enclosed with installing fast to construction

Publications (1)

Publication Number Publication Date
CN210422147U true CN210422147U (en) 2020-04-28

Family

ID=70377037

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920966080.4U Expired - Fee Related CN210422147U (en) 2019-06-26 2019-06-26 Fender is enclosed with installing fast to construction

Country Status (1)

Country Link
CN (1) CN210422147U (en)

Similar Documents

Publication Publication Date Title
CN210341974U (en) Foundation fixing device is used in street lamp installation
CN214784869U (en) Basement post-cast strip waterproof construction
CN210422147U (en) Fender is enclosed with installing fast to construction
CN214785841U (en) Bearing hanging rack for civil engineering construction
CN207484489U (en) A kind of foundation pit side-wall strengthens safeguard structure
CN214126425U (en) Fragrant pig is bred and uses pig house rail
CN204005140U (en) Outdoor electronic display screen support
CN211981436U (en) Cable bridge for site operation and mounting structure thereof
CN115233885A (en) Movable board house roof supporting structure
CN211818613U (en) Adjustable fender that encloses is used in construction
CN210661991U (en) Multi-head monitoring camera device
CN214273210U (en) Road fender device is enclosed in quick assembly disassembly
CN213682507U (en) Light steel plate house convenient to disassemble and assemble for building construction
CN215565018U (en) Simple connecting column of protective partition wall
CN220336514U (en) Building construction safety device
CN218843791U (en) A lattice column installation device for reverse construction method construction
CN215485197U (en) Ecological enclosure wall for building site
CN216547291U (en) Reinforcing bar rack for municipal building construction
CN219711024U (en) Steel construction platform convenient to installation
CN215948215U (en) Inner support pit bottom assembling device for half-cover deep digging foundation pit
CN220451562U (en) Auxiliary installation structure of steel wire mesh
CN210289378U (en) Novel road and bridge engineering safety enclosure device
CN113502912A (en) High adaptability steel house room frame of modularization
CN220301589U (en) Novel curved curtain wall
CN215859459U (en) Construction engineering construction is with enclosing fender

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200428

Termination date: 20210626

CF01 Termination of patent right due to non-payment of annual fee