CN210395888U - Building drainage device - Google Patents

Building drainage device Download PDF

Info

Publication number
CN210395888U
CN210395888U CN201921215962.3U CN201921215962U CN210395888U CN 210395888 U CN210395888 U CN 210395888U CN 201921215962 U CN201921215962 U CN 201921215962U CN 210395888 U CN210395888 U CN 210395888U
Authority
CN
China
Prior art keywords
clearance
pipe groove
collecting pipe
fixture block
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921215962.3U
Other languages
Chinese (zh)
Inventor
刘景国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201921215962.3U priority Critical patent/CN210395888U/en
Application granted granted Critical
Publication of CN210395888U publication Critical patent/CN210395888U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sink And Installation For Waste Water (AREA)

Abstract

The utility model discloses a building drainage device, including first collecting pipe groove, aqueduct and second collecting pipe groove, still include clearance mechanism and docking mechanism, the top of first collecting pipe groove has seted up down the water strainer hole, wherein clearance mechanism installs on first collecting pipe groove corresponding to the position department of water strainer hole, clearance mechanism includes clearance support, protection ceiling, bearing fan and clearance silver, clearance support rotates and connects at the top of first collecting pipe groove; install the clearance silver in clearance support bottom through the design to and the bearing fan in the clearance support top outside is installed in the design, and under the drive of wind-force, realize the clearance to blockking up filter screen hole outside debris that catchments, install the protection ceiling at first catchment tube seat top through the design simultaneously, avoided rainwater or other debris direct contact to catchment filter screen hole under, lead to the condition that first catchment tube seat blockked up the damage.

Description

Building drainage device
Technical Field
The utility model belongs to the technical field of drainage device, concretely relates to building drainage device.
Background
Roof drainage, namely rapidly draining rain and snow water on the roof to avoid the generation of roof water accumulation.
The existing building drainage device is arranged on a roof when in use, and is extremely inconvenient to carry out slag removal and ash removal treatment on the blocking part outside the protective filter screen, so that a sewer pipe is blocked, the roof drainage efficiency is greatly influenced, and meanwhile, a plurality of water collecting pipe grooves are extremely inconvenient to carry out quick butt joint and disassembly, so that the roof residence time of maintenance personnel is greatly increased, the maintenance difficulty is increased, and therefore, the building drainage device is provided.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a building drainage device to the inconvenient quick butt joint dismouting problem that carries out of the inconvenient clearance in the protection filter screen outside and the water collecting pipe groove that proposes among the above-mentioned background of the solution.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a building drainage device, includes first collecting pipe groove, aqueduct and second collecting pipe groove, still includes clearance mechanism and docking mechanism, the filter mesh hole under having seted up at the top in first collecting pipe groove, wherein clearance mechanism installs the position department that corresponds filter mesh hole under on first collecting pipe groove, clearance mechanism includes clearance support, protection ceiling, bearing fan and clearance silver, clearance support rotates the top of connecting at first collecting pipe groove, wherein clearance support's bottom is fixed with the clearance silver, the top outside fixed mounting of clearance support has the bearing fan, just the pole portion position of protection ceiling runs through the central point that clears up the support puts, and with first collecting pipe groove fixed connection.
Preferably, the docking mechanism is located at the joint position of the first water collecting pipe groove and the second water collecting pipe groove, the docking mechanism comprises a docking tank box, a docking fixture block, a fixed fixture block and a bearing spring, the docking tank box is fixedly mounted on two sides of the first water collecting pipe groove, the docking fixture block is fixedly mounted on two sides of the second water collecting pipe groove, the fixed fixture block is movably mounted at the top of the docking fixture block, and a fixing hole is formed in the joint position of the inner side of the docking tank box corresponding to the docking fixture block.
Preferably, the bottom of the first water collecting pipe groove is fixedly connected with a water guide pipe at a position right below the lower water filter screen hole.
Preferably, a buffer hole is formed in the center of the cleaning support corresponding to the penetrating position of the protective ceiling, wherein the section diameter of the buffer hole is larger than that of the rod part of the protective ceiling.
Preferably, the outer side of the fixed clamping block is correspondingly provided with a convex limiting block, and the fixed clamping block and the butt-joint clamping block are in sliding connection through the convex limiting block.
Compared with the prior art, the beneficial effects of the utility model are that:
(1) install the clearance silver in clearance support bottom through the design, and the bearing fan in the clearance support top outside is installed in the design, and under the drive of wind-force, realize the clearance to blockking up at the clearance of filter screen hole outside debris that catchments, the filter screen hole jam condition that catchments has reduced, the periodic interval who overhauls has been increased simultaneously, cost of maintenance's use has been reduced, install the protection ceiling at first collecting pipe groove top through the design simultaneously, the filter screen hole under rainwater or other debris direct contact has been avoided, lead to the condition that first collecting pipe groove blockked up the damage.
(2) Install the butt joint groove box on first collecting pipe groove through the design to and the butt joint fixture block on the second collecting pipe groove is installed in the design, realized the quick assembly disassembly to first collecting pipe groove and second collecting pipe groove, install the bearing spring in fixed fixture block bottom through the design simultaneously, very big increase the steadiness that first collecting pipe groove and second collecting pipe groove are connected, guaranteed the normal use of first collecting pipe groove and second collecting pipe groove.
Drawings
Fig. 1 is a schematic view of the overall cross-sectional structure of the present invention;
fig. 2 is a schematic overall top view structure of the present invention;
FIG. 3 is a schematic view of the sectional structure of the assembly of the docking slot and the docking fixture block of the present invention;
FIG. 4 is a schematic top view of the cleaning support and the protective ceiling of the present invention;
in the figure: 1. a first header tank; 2. a water conduit; 3. cleaning the bracket; 4. a protective ceiling; 5. a bearing fan; 6. cleaning cotton slivers; 7. a sewage filter mesh hole; 8. a second header tank; 9. butt joint of the groove boxes; 10. butting the clamping blocks; 11. fixing the fixture block; 12. a load bearing spring.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: a building drainage device comprises a first water collecting pipe groove 1, a water guide pipe 2, a second water collecting pipe groove 8, a cleaning mechanism and a butt joint mechanism, wherein the top of the first water collecting pipe groove 1 is provided with a lower water filter screen hole 7, the cleaning mechanism is arranged on the first water collecting pipe groove 1 corresponding to the position of the lower water filter screen hole 7 and comprises a cleaning support 3, a protective ceiling 4, a bearing fan 5 and a cleaning cotton strip 6, the cleaning support 3 is rotatably connected to the top of the first water collecting pipe groove 1 through a rotating shaft, the cleaning cotton strip 6 is fixed to the bottom of the cleaning support 3, the bearing fan 5 is fixedly arranged on the outer side of the top of the cleaning support 3, the rod part of the protective ceiling 4 penetrates through the central position of the cleaning support 3 and is screwed and fixed with the first water collecting pipe groove 1 through threads, the cleaning cotton strip 6 arranged on the bottom of the cleaning support 3 through design and the bearing fan 5 arranged on the outer side of the top of the cleaning support 3, and under the drive of wind-force, realize the clearance to blockking up at the outside debris of offal filter screen hole 7, reduced the offal filter screen hole 7 and blockked up the condition, increased the cycle interval of maintenance simultaneously, reduced cost of maintenance's use, install the protection ceiling 4 at first collecting pipe box 1 top through the design simultaneously, avoided rainwater or other debris direct contact offal filter screen hole 7, lead to the condition that first collecting pipe box 1 blockked up the damage.
In the embodiment, preferably, the docking mechanism is located at the connection position of the first water collecting pipe groove 1 and the second water collecting pipe groove 8, the docking mechanism includes a docking box 9, a docking fixture block 10, a fixing fixture block 11 and a bearing spring 12, the docking box 9 is fixedly installed at both sides of the first water collecting pipe groove 1, wherein the docking fixture block 10 is fixedly installed at both sides of the second water collecting pipe groove 8, the fixing fixture block 11 is movably installed at the top of the docking fixture block 10, and a fixing hole is formed at the inner side of the docking box 9 corresponding to the connection position of the docking fixture block 10, by designing the docking box 9 installed on the first water collecting pipe groove 1 and the docking fixture block 10 installed on the second water collecting pipe groove 8, the first water collecting pipe groove 1 and the second water collecting pipe groove 8 can be quickly disassembled and assembled, and by designing the bearing spring 12 installed at the bottom of the fixing fixture block 11, the connection stability of the first water collecting pipe groove 1 and the second water collecting pipe groove 8 is greatly increased, the normal use of the first and second header tanks 1 and 8 is ensured.
In order to realize the normal use of the drainage device, in the present embodiment, it is preferable that the water guide pipe 2 is fixedly connected to the bottom of the first water collecting pipe tank 1 at a position corresponding to a position right below the lower water strainer hole 7.
In order to realize the free rotation of the cleaning support 3, in this embodiment, preferably, a buffer hole is formed in a position, corresponding to the penetrating position of the protective ceiling 4, of the central position of the cleaning support 3, wherein the section diameter of the buffer hole is larger than the section diameter of the rod part of the protective ceiling 4.
In order to avoid dropping of the fixed fixture block 11, in this embodiment, preferably, a convex stopper is correspondingly disposed on the outer side of the fixed fixture block 11, and the fixed fixture block 11 and the docking fixture block 10 are slidably connected through the convex stopper.
The utility model discloses a theory of operation and use flow: when the building drainage device meets the weather of strong wind and rain, under the driving of natural wind, the wind drives the bearing fan 5 to rotate, under the driving condition of the bearing fan 5, the cleaning bracket 3 drives the cleaning cotton strip 6 to clean the blockage on the outer side of the lower water filter mesh 7 and moves into the water guide pipe 2 under the washing of the rain, the blockage of dust, impurities and the like on the lower water filter mesh 7 is reduced, meanwhile, when the first water collecting pipe groove 1 and the second water collecting pipe groove 8 need to be butted, the butting clamping block 10 on the second water collecting pipe groove 8 is butted with the butting groove box 9 on the first water collecting pipe groove 1, the fixing clamping block 11 is contained in the inner side of the butting clamping block 10, the fixing clamping block 11 is moved to the position of the fixing hole on the butting groove box 9, and the butting clamping block 9 and the butting clamping block 10 are clamped and fixed under the tension of the bearing spring 12, and (6) finishing the butt joint.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides a building drainage device, includes first collecting pipe groove (1), aqueduct (2) and second collecting pipe groove (8), its characterized in that: still include clearance mechanism and docking mechanism, lower water strainer hole (7) have been seted up at the top of first header pipe groove (1), wherein clearance mechanism installs the position department that corresponds lower water strainer hole (7) on first header pipe groove (1), clearance mechanism is including clearance support (3), protection ceiling (4), bearing fan (5) and clearance silver (6), clearance support (3) rotate the top of connecting in first header pipe groove (1), wherein the bottom of clearance support (3) is fixed with clearance silver (6), the top outside fixed mounting of clearance support (3) has bearing fan (5), just the pole portion position of protection ceiling (4) runs through the central point that clearance support (3) puts, and with first header pipe groove (1) fixed connection.
2. A building drainage system as claimed in claim 1, wherein: docking mechanism is located the hookup location department of first collecting pipe groove (1) and second collecting pipe groove (8), docking mechanism includes butt joint groove box (9), butt joint fixture block (10), fixed fixture block (11) and bearing spring (12), butt joint groove box (9) fixed mounting is in the both sides of first collecting pipe groove (1), wherein butt joint fixture block (10) fixed mounting is in the both sides of second collecting pipe groove (8), just the top movable mounting of butt joint fixture block (10) has fixed fixture block (11), just the inboard hookup location department that corresponds butt joint fixture block (10) of butt joint groove box (9) has seted up the fixed orifices.
3. A building drainage system as claimed in claim 1, wherein: the bottom of the first water collecting pipe groove (1) is fixedly connected with a water guide pipe (2) at a position right below the corresponding lower water filter mesh (7).
4. A building drainage system as claimed in claim 1, wherein: the center position of the cleaning support (3) is provided with a buffer hole corresponding to the penetrating position of the protective ceiling (4), wherein the section diameter of the buffer hole is larger than that of the rod part of the protective ceiling (4).
5. A building drainage system as claimed in claim 2, wherein: the outer side of the fixed clamping block (11) is correspondingly provided with a convex limiting block, and the fixed clamping block (11) and the butt-joint clamping block (10) are connected in a sliding mode through the convex limiting block.
CN201921215962.3U 2019-07-30 2019-07-30 Building drainage device Expired - Fee Related CN210395888U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921215962.3U CN210395888U (en) 2019-07-30 2019-07-30 Building drainage device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921215962.3U CN210395888U (en) 2019-07-30 2019-07-30 Building drainage device

Publications (1)

Publication Number Publication Date
CN210395888U true CN210395888U (en) 2020-04-24

Family

ID=70357282

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921215962.3U Expired - Fee Related CN210395888U (en) 2019-07-30 2019-07-30 Building drainage device

Country Status (1)

Country Link
CN (1) CN210395888U (en)

Similar Documents

Publication Publication Date Title
CN112900762A (en) Balcony sun shield for green building
CN212200618U (en) Water supply and drainage anti-clogging device for building
CN107090954B (en) Roof rainwater collecting and recycling system
CN210395888U (en) Building drainage device
CN112681627A (en) Energy-saving building
CN210797850U (en) Pipeline is from cleaning device
CN110318503A (en) A kind of detachable rain-harvesting trough of greenhouse
CN216109429U (en) Rain shield for building
CN116479995A (en) Water-saving building house structure for recycling rainwater domestic water
CN216275314U (en) Temporary guide sign for traffic safety vehicle
CN216380284U (en) Building structure design roof eaves mouth waterproof construction
CN205759936U (en) A kind of rain water on roof vertical filter unit
CN111088898A (en) Platform canopy
CN210887408U (en) Drainage device is collected to well site weather enclosure rainwater
CN112227461B (en) Green building rainwater drainage equipment
CN203795510U (en) Slope roof rainwater collecting device
CN220928444U (en) House structure with rainwater collection function
CN219327249U (en) Roof rainwater collecting device
CN216475343U (en) Integrated pump station with cleaning function
CN221073250U (en) Roof drainage structure of sunshine house
CN217032541U (en) Building engineering environment monitoring device
CN220771078U (en) LED tile lamp
CN219514028U (en) Automatic cleaning device for solar cover plate glass
CN220117388U (en) Self-cleaning drainage structure of public building
CN216440066U (en) Device for taking river water to irrigate

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200424

Termination date: 20210730