CN210393419U - Multifunctional integrated ALC zero-splicing fast hoisting frame - Google Patents

Multifunctional integrated ALC zero-splicing fast hoisting frame Download PDF

Info

Publication number
CN210393419U
CN210393419U CN201920921658.4U CN201920921658U CN210393419U CN 210393419 U CN210393419 U CN 210393419U CN 201920921658 U CN201920921658 U CN 201920921658U CN 210393419 U CN210393419 U CN 210393419U
Authority
CN
China
Prior art keywords
alc
zero
fossil fragments
hoist
splicing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920921658.4U
Other languages
Chinese (zh)
Inventor
刘若南
刘伟
郭志鹏
王羽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Science and Technology Group Co Ltd
Original Assignee
China Construction Science and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Science and Technology Co Ltd filed Critical China Construction Science and Technology Co Ltd
Priority to CN201920921658.4U priority Critical patent/CN210393419U/en
Application granted granted Critical
Publication of CN210393419U publication Critical patent/CN210393419U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a whole quick hoist and mount frame of zero piecing together of multi-functional integration ALC, including the whole big board of zero piecing together of back hoist and mount frame and ALC, back hoist and mount frame sets up on the terminal surface of the whole big board of zero piecing together of ALC, wherein, back hoist and mount frame includes lug, a plurality of horizontal fossil fragments and a plurality of vertical fossil fragments, the lug with horizontal fossil fragments are connected, horizontal fossil fragments with vertical fossil fragments mutually perpendicular connects, even on the horizontal fossil fragments set up a plurality of fluting holes. The utility model discloses improved the hoist and mount mode of ALC peripheral dado in assembled concrete frame structure and steel construction, reduced high altitude construction, reduced the on-the-spot transport number of times, improved hoist and mount efficiency, strengthened the construction continuity, rationally carry out the process and alternate between the different operations, move the high altitude construction of most side fascia to ground, reduce the high altitude construction degree of difficulty and danger, guarantee ALC slat board seam connection quality realizes high-efficient construction, improves the building quality.

Description

Multifunctional integrated ALC zero-splicing fast hoisting frame
Technical Field
The utility model belongs to the technical field of building board, concretely relates to complete quick hoist and mount frame of zero piecing together of multi-functional integration ALC.
Background
An ALC (autoclaved aerated concrete) plate is a high-performance and multipurpose porous concrete forming plate which is formed by curing siliceous materials (silica sand, fly ash or siliceous tailings) and calcareous materials (cement, lime and the like) serving as main materials, generally aluminum powder serving as a gas former at high temperature and high pressure by steam. Under the background of the rapid development of the fabricated building at present, due to the characteristics of good light weight, heat preservation, heat insulation, sound insulation and earthquake resistance of the ALC board, the ALC board becomes one of the preferable materials of the fabricated concrete frame structure and the steel structure outer enclosure wall body.
At present, the production of the ALC lath has the advantages of industrialization, scale and standardization, and the degree of mechanization in the production process is high, but due to the particularity of the production process of the ALC plate, the ALC plate is generally prepared into a lath with the width of 600mm, and the plate width is limited. In the field assembly process of the ALC plate, auxiliary equipment such as hoisting equipment, a trolley, a support frame and the like is generally needed, a single slat is transported to an operation surface through a lifter to be installed, the transportation frequency is high, the installation efficiency is low, the workload is large, high-altitude operation is needed for installing each slat, and the safety of constructors is difficult to guarantee; in addition, the high-altitude processing quality at the batten splicing seam is difficult to guarantee. Cannot be realized.
SUMMERY OF THE UTILITY MODEL
In order to solve the problems, the multifunctional integrated ALC zero-splicing fast hoisting frame is provided, the ALC ribbon boards are pre-spliced on the ground, and the ribbon board seam connection is finished on the ground, so that the connection quality is guaranteed; the door and window openings are reserved in the assembling process, and the whole plate can be directly connected with the main body structure, so that overhead operation is reduced; the back hoist and mount frame set up consider embedded, two kinds of node forms of external hanging and construction environment, and the installation and the dismantlement of being convenient for reduce the hoist and mount and hang the number of times, improve assembly efficiency, specific technical scheme as follows:
the utility model provides a whole quick hoist and mount frame of zero piecing together of multi-functional integration ALC, includes that back hoist and mount frame and the whole big board of zero piecing together of ALC, back hoist and mount frame sets up on the terminal surface of the whole big board of zero piecing together of ALC, wherein, back hoist and mount frame includes lug, a plurality of horizontal fossil fragments and a plurality of vertical fossil fragments, the lug with horizontal fossil fragments are connected, horizontal fossil fragments with vertical fossil fragments mutually perpendicular connects, even on the horizontal fossil fragments set up a plurality of fluting holes.
Preferably, the transverse keel passes through the slotted hole through a fixing bolt to be fixedly connected with the ALC zero-alignment large plate and is fixed on the ALC zero-alignment large plate.
In any of the above schemes, preferably, the lifting lug is provided with a lifting hole.
In any of the above solutions, it is preferable that the slotted hole has a circular structure and an opening is provided at the top of the circular structure.
In any of the above schemes, preferably, the transverse keel and the vertical keel are fixedly connected through bolts.
In any of the above schemes, preferably, the lifting lug and the cross keel are connected by welding.
In any of the above schemes, preferably, the ALC zero-splicing large panel is formed by splicing a plurality of ALC ribbon boards.
The utility model has the advantages that: the lifting mode of the ALC peripheral wall panel in the assembled concrete frame structure and the steel structure is improved, high-altitude operation is reduced, the number of times of field carrying is reduced, the lifting efficiency is improved, the construction continuity is enhanced, process alternation is reasonably carried out between different operations, the high-altitude operation of most external wall panels is moved to the ground, the difficulty and the danger of the high-altitude operation are reduced, the ALC slat plate joint quality is guaranteed, high-efficiency construction is realized, and the building quality is improved.
Drawings
FIG. 1 is a schematic view of a preferred embodiment of a multifunctional integrated ALC zero-splicing fast hoisting frame according to the present invention;
FIG. 2 is a schematic view of the embodiment of FIG. 1 of the multifunctional integrated ALC zero-splicing fast hoisting frame according to the present invention;
figure 3 is according to the utility model discloses a partial enlarged view of slotted hole position of figure 1 embodiment of multi-functional integrated ALC zero piecing together quick hoisting frame.
The figures are labeled as follows: 1-a back hoisting frame; 2-ALC zero-splicing large plate; 3-hoisting holes; 4-lifting lugs; 5-transverse keel; 6-fixing the bolt; 7-grooving holes; 8-longitudinal keel.
Detailed Description
In order to further understand the present invention, the present invention will be described in detail with reference to the following embodiments.
As shown in fig. 1 to 3, the multifunctional integrated ALC zero-splicing fast hoisting frame provided by the present invention comprises a back hoisting frame 1 and an ALC zero-splicing large plate 2, wherein the back hoisting frame 1 is disposed on one end surface of the ALC zero-splicing large plate 2, wherein the back hoisting frame 1 comprises a lifting lug 4, a plurality of transverse keels 5 and a plurality of vertical keels 8, the lifting lug 4 is connected with the transverse keels 5 by welding, the transverse keels 5 are perpendicular to the vertical keels 8 and are uniformly fixed on the ALC zero-splicing large plate 2 by bolts, the transverse keels 5 are uniformly provided with a plurality of slotted holes 7, the slotted holes 7 are of circular structure and are provided with an opening at the top of the circular structure, the transverse keels 4 pass through the slotted holes 7 through fixing bolts 6 and are fixedly connected with the ALC zero-splicing large plate 2 and fix the transverse keels 5 on the ALC zero-splicing large plate 2, lifting eyes 3 are arranged on the lifting lugs 4.
The ALC zero-splicing large plate is formed by connecting a plurality of ALC strips through upper and lower long connecting angle steels by bolts to form a large plate, and the angle steels are provided with vertical long round holes so as to facilitate the adjustment of the upper and lower positions during installation; in order to prevent disturbance, displacement and damage of connection between plates when the ALC zero-splicing large plate is hoisted, galvanized steel pipes are embedded at the upper end and the lower end of the side surface of the plate and connected in a mode of penetrating through transverse lacing wires; the plates are connected through bonding mortar to ensure integrity; have the region of door and window entrance to a cave, reserve the entrance to a cave position through the angle steel, the vertical angle steel of entrance to a cave is connected with the zero twice of piecing together whole big board of ALC and leading to long angle steel, the utility model discloses during hoist and mount with the zero angle steel connecting point bolted connection of piecing together whole big board 2 of ALC, the back of taking one's place is hoisted and mounted to not hard up bolt and is removed, this portion hoist and mount frame 1 with the zero whole big board 2 separation of piecing together of ALC can.
The utility model discloses a concrete mounting process as follows:
① marking and punching the ALC lath according to the drawing;
② ALC laths are placed on the temporary home part mounting rack 1, the seams of the laths are brushed with adhesives, and transverse steel bars are penetrated;
③ hoisting frames are placed at the upper ends of the plates, and angle steels are placed at the lower ends of the plates and are fastened and connected through bolts;
④ the lifting appliance passes through the lifting eye reserved lifting hole for lifting;
⑤ welding part of angle steel to fix the installation position of wall board;
⑥ loosening the bolt and withdrawing from the back hoisting frame;
⑦ fastening bolts and welding angle steel to finish the installation.
It will be understood by those skilled in the art that the multifunctional ALC zero-splicing fast hoisting frame of the present invention includes the above-mentioned components of the present invention, and any combination of the components shown in the drawings, which are limited to space and not described in any combination for the sake of brevity. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (7)

1. The utility model provides a whole quick hoist and mount frame of zero piecing together of multi-functional integration ALC, includes that back hoist and mount frame and the whole big board of zero piecing together of ALC, back hoist and mount frame sets up on the terminal surface of the whole big board of zero piecing together of ALC, a serial communication port, back hoist and mount frame includes lug, a plurality of horizontal fossil fragments and a plurality of vertical fossil fragments, the lug with horizontal fossil fragments are connected, horizontal fossil fragments with vertical fossil fragments mutually perpendicular connects, even on the horizontal fossil fragments set up a plurality of fluting holes.
2. The multifunctional integrated ALC zero-splicing fast hoisting frame according to claim 1, characterized in that said transverse keel passes through said slotted hole through fixing bolt to be fixedly connected with said ALC zero-splicing large plate and fix said transverse keel on said ALC zero-splicing large plate.
3. The multifunctional integrated ALC zero-splicing fast hoisting frame according to claim 1, characterized in that the lifting eye is provided with a hoisting hole.
4. The multifunctional integrated ALC zero-splicing fast hoisting frame according to claim 1, characterized in that said slotted hole is of a circular structure and an opening is provided at the top of said circular structure.
5. The multifunctional integrated ALC zero-splicing fast hoisting frame according to claim 1, characterized in that the horizontal keel and the vertical keel are fixedly connected through bolts.
6. The multifunctional integrated ALC zero-splicing quick hoisting frame according to claim 1, characterized in that the lifting lug is connected with the transverse keel in a welding manner.
7. The multifunctional integrated ALC zero-splicing fast hoisting frame of claim 1, characterized in that the ALC zero-splicing large plate is assembled by a plurality of ALC laths.
CN201920921658.4U 2019-06-19 2019-06-19 Multifunctional integrated ALC zero-splicing fast hoisting frame Active CN210393419U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920921658.4U CN210393419U (en) 2019-06-19 2019-06-19 Multifunctional integrated ALC zero-splicing fast hoisting frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920921658.4U CN210393419U (en) 2019-06-19 2019-06-19 Multifunctional integrated ALC zero-splicing fast hoisting frame

Publications (1)

Publication Number Publication Date
CN210393419U true CN210393419U (en) 2020-04-24

Family

ID=70349637

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920921658.4U Active CN210393419U (en) 2019-06-19 2019-06-19 Multifunctional integrated ALC zero-splicing fast hoisting frame

Country Status (1)

Country Link
CN (1) CN210393419U (en)

Similar Documents

Publication Publication Date Title
CN112854570A (en) Shock attenuation joins externally prefabricated wallboard
CN210393419U (en) Multifunctional integrated ALC zero-splicing fast hoisting frame
CN213087282U (en) Unit type heat preservation and decoration integrated plate outer wall system of stone panel
CN210562682U (en) Multifunctional ALC zero-splicing integral peripheral wall panel
CN217105790U (en) Heat-insulating energy-saving wall structure
CN213296679U (en) Shear wall for enhancing shear resistance
CN212984192U (en) Assembled steel construction light concrete building
CN211447587U (en) Assembled frame construction cladding construction node
CN210947273U (en) Assembled antidetonation crack control partition plate subassembly
CN203760292U (en) Transformer sound insulation device
CN102953572A (en) Sound insulation room of Roots motor
CN209066794U (en) A kind of fastener veneer wall system
CN113719137A (en) Construction engineering secondary structure and masonry engineering and main body engineering synchronous construction method
CN107217783B (en) Assembled integral external wall panel
CN212200935U (en) Assembled steel structure concrete side fascia, assembled steel structure girder steel and couple formula lightweight concrete side fascia node
CN111719795A (en) Unit type heat preservation and decoration integrated plate outer wall system of stone panel
CN216446592U (en) Prevent assembly room of wind husky
CN211775639U (en) Embedded plate type hanging basket mounting structure
CN215888945U (en) Modular fan structure capable of preventing water
CN203008436U (en) Roots motor sound insulation room
CN214658438U (en) Assembled wall body component connection reinforcing apparatus
CN220908782U (en) Novel assembled exterior wall cladding installing support
CN219137746U (en) Prefabricated rail top air duct connection structure based on foamed ceramic composite board
CN110284680B (en) Vertical connecting structure of assembled concrete exterior wall cladding and construction method thereof
CN210636650U (en) Hidden curtain wall of steel structure building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant