CN210366306U - Pay-off for construction - Google Patents

Pay-off for construction Download PDF

Info

Publication number
CN210366306U
CN210366306U CN201921269752.2U CN201921269752U CN210366306U CN 210366306 U CN210366306 U CN 210366306U CN 201921269752 U CN201921269752 U CN 201921269752U CN 210366306 U CN210366306 U CN 210366306U
Authority
CN
China
Prior art keywords
shaft
rotating shaft
hanging
sleeve
rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921269752.2U
Other languages
Chinese (zh)
Inventor
鞠林群
秦春华
李林
邰宏年
王骏
张忠斌
孙伟
孙浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Urban Construction 13 Engineering Co ltd
Original Assignee
Urban Construction 13 Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Urban Construction 13 Engineering Co ltd filed Critical Urban Construction 13 Engineering Co ltd
Priority to CN201921269752.2U priority Critical patent/CN210366306U/en
Application granted granted Critical
Publication of CN210366306U publication Critical patent/CN210366306U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The utility model discloses a paying-off device for building construction, which structurally comprises a fixed block, a supporting body, a guide wheel seat, an operating rod, a shaft lever, a bearing, a hanging ring and a protective frame, and in order to improve the practicability of the device, hanging and connecting rings are respectively arranged on two sides of the structure, the hanging and connecting rings are positioned on notches on two sides of the upper end of the protective frame, the surface of the partition board is horizontal and the fixed position is unchanged, a rotating shaft positioned at the upper end is arranged on one side of the upper supporting ring, the rotating shaft vertically corresponds to the fixed shaft sleeves which are arranged at intervals, the protective structure is in a closed state, the gap is blocked, the movable rod is held and applies force outwards, the blocking block is butted with the rotating shaft when rotating outwards synchronously, the blocking block is screwed out from the upper layer of the partition board, the position of the central shaft can be kept unchanged when rotating, the gap of the supporting, and then carry out the hoist and mount step, can alternate according to the operation demand and grab ground position, and then accelerated the work efficiency of device.

Description

Pay-off for construction
Technical Field
The utility model relates to a pay-off for construction belongs to cable unwrapping wire technical field.
Background
In the process of engineering construction, two cable paying-off methods are generally used. One of the methods is to set up a simple rack for paying off, and the rack in the method has certain ground gripping weight, is heavy and is inconvenient to change positions.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a pay-off for construction to the not enough of prior art existence, the utility model aims at providing a solve at the in-process of engineering construction, the cable unwrapping wire method of using generally has two kinds. One of them is to set up a simple and easy shelf and pay off, and the shelf of this kind of mode has certain ground weight of grabbing, and is comparatively heavy and the inconvenient problem of transform position.
In order to achieve the above purpose, the present invention is realized by the following technical solution: the utility model provides a pay-off for construction, its structure includes fixed block, supporter, guide wheel seat, action bars, axostylus axostyle, bearing, connects ring, protection frame, be equipped with the equal altitude protection frame of setting up both sides separately on the supporter, the built on stilts department between the supporter is equipped with the axostylus axostyle of horizontal installation, the bearing outer end cross-under bearing center through-hole, the bearing is installed on corresponding left protection frame upper portion, be equipped with the unchangeable axostylus axostyle of mounting height between the protection frame, the axostylus axostyle inner scarf joint guide wheel seat center through-hole, the guide wheel seat is installed on the right top position of supporter, protection frame upper end.
Furthermore, the hanging ring comprises a partition plate, a fixed shaft sleeve, a guide sleeve, a stop block, a movable rod, a rotating shaft and a support ring, the left point and the right point of the partition plate correspond to the support ring of the U-shaped structure, the rotating shaft and the fixed shaft sleeve which correspond to each other vertically are arranged on one side of the support ring, the stop block is arranged between the rotating shaft and the fixed shaft sleeve, the guide sleeve which is formed at the bottom of the stop block is arranged at a through hole of the stop block, the guide sleeve is provided with a hollow channel through which the movable rod can vertically penetrate, and the lower end of the movable rod can vertically correspond to a.
Further, a shaft rod positioned at the top is arranged between the protection frames.
Further, the operating rod is arranged at the overhead position between the supporting bodies.
Furthermore, an operating rod matched and connected with the shaft rod is arranged at one side of the shaft rod close to the inner side.
Furthermore, a stop block is arranged at the partition section of the support ring.
Furthermore, the block is provided with a movable rod which can be connected with the slotted hole in a penetrating way.
Advantageous effects
The utility model relates to a pay-off for construction, in order to improve the practicality of device, be equipped with the socket ring in structure both sides branch, be located the both sides notch of protection frame upper end, baffle surface level and fixed position are unchangeable, upper portion support ring one side is equipped with the pivot that is located upper end department, correspond looks spaced fixed axle sleeve perpendicularly, be protective structure under the closed state, the space is hindered, live the movable rod and outwards apply force, the butt joint pivot when the piece that hinders rotates outwards in step, screw out from the baffle upper strata, can keep central axis rigidity unchangeable during the rotation, the support ring space has been opened, the cover operation of wearing of rope of can being convenient for, and then develop the hoist and mount step, can grab ground position according to the operation demand transform, and then the work efficiency of device has been accelerated.
Drawings
Other features, objects and advantages of the invention will become more apparent upon reading of the detailed description of non-limiting embodiments with reference to the following drawings:
FIG. 1 is a schematic structural view of a construction pay-off device of the present invention;
fig. 2 is a schematic view of the assembly structure of the suspension ring of the present invention.
In the figure: the device comprises a fixed block-1, a support body-2, a guide wheel seat-3, an operating rod-4, a shaft rod-5, a bearing-6, a hanging ring-7, a partition plate-71, a fixed shaft sleeve-72, a guide sleeve-73, a stop block-74, a movable rod-75, a rotating shaft-76, a support ring-77 and a protection frame-8.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
Referring to fig. 1-2, the present invention provides a technical solution: a pay-off device for building construction structurally comprises a fixed block 1, a support body 2, guide wheel seats 3, an operating rod 4, a shaft rod 5, bearings 6, hanging rings 7 and protective frames 8, wherein the support body 2 is provided with equal-height protective frames 8 with two sides respectively, the shaft rod 5 transversely installed is arranged at an overhead position between the support bodies 2, the outer end of the shaft rod 5 is connected with a central through hole of the bearing 6 in a penetrating manner, the bearing 6 is arranged at the upper part of the protective frame 8 corresponding to the left side, the shaft rod 5 with unchanged installation height is arranged between the protective frames 8, the inner end of the shaft rod 5 is embedded in the central through hole of the guide wheel seat 3, the guide wheel seat 3 is arranged at the right top position of the support body 2, the hanging rings 7 respectively arranged at two sides are arranged at the upper end of the protective frame 8, each hanging ring 7 comprises a partition plate 71, a fixed shaft sleeve 72, a guide sleeve 73, a block 74, the left point and the right point of the partition plate 71 correspond to a support ring 77 of a U-shaped structure, a rotating shaft 76 and a fixed shaft sleeve 72 which correspond to each other up and down are arranged on one side of the support ring 77, a block 74 is arranged between the rotating shaft 76 and the fixed shaft sleeve 72, a guide sleeve 73 which is formed at the bottom of the block 74 is arranged at the through hole, a hollow channel through which the movable rod 75 can vertically penetrate is arranged on the guide sleeve 73, the lower end of the movable rod 75 can vertically correspond to a notch at the upper end of the protection frame 8, a shaft rod 5 which is positioned at the top is arranged between the protection frames 8, the operating rod 4 is arranged at the overhead position between the support bodies 2, the operating rod 4 which is matched and connected with each other is arranged on one inner side of the shaft rod 5, the block 74 is arranged at the spacing section of.
The shaft 76 is a shaft member used for connecting the support ring 77 and the block 74, and is used for rotation, and the shaft member can keep the position of the central shaft constant during rotation, and the butt-joint structure of the inner and outer embedded parts can facilitate the rotation operation.
For example: when the device is used, in order to improve the practicability of the device, the hanging and connecting rings 7 are arranged on two sides of the structure respectively, the hanging and connecting rings are positioned on notches on two sides of the upper end of the protective frame 8, the horizontal surface and the fixed position of the partition plate 71 are unchanged, the rotating shaft 76 positioned at the upper end is arranged on one side of the upper supporting ring 77, the upper supporting ring 72 vertically corresponds to the fixed shaft sleeve 72 at intervals, the protective structure is in a closed state, the gap is blocked, the movable rod 75 is held and applies force outwards, the blocking block 74 synchronously rotates outwards and is abutted to the rotating shaft 76, the upper layer of the partition plate 71 is screwed out, the position of the central shaft can be kept unchanged during rotation, the gap of the supporting ring 77 is opened, the rope sleeving operation can be facilitated, the hanging step can be carried out, the ground.
The utility model provides an in-process at the engineering construction, the cable unwrapping wire method of use generally has two kinds. One of them is to set up a simple and easy shelf and carry out the unwrapping wire, and the shelf of this kind of mode has certain ground weight of grabbing, and is comparatively heavy and transform the position inconvenient, the utility model discloses a combination of each other of above-mentioned part is equipped with in structure both sides branch and hangs the link for the practicality of improving the device, can be convenient for the rope wear the cover operation, and then develop the hoist and mount step, can grab the ground position according to the operation demand transform, and then accelerated the work efficiency of device.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above, it will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, but that the invention may be embodied in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.

Claims (5)

1. The utility model provides a pay-off for construction, its structure includes fixed block (1), supporter (2), guide wheel seat (3), action bars (4), axostylus axostyle (5), bearing (6), connects ring (7), protection frame (8), its characterized in that:
the supporting body (2) is provided with equal-height protection frames (8) which are respectively arranged at two sides, a shaft lever (5) which is transversely installed is arranged at an overhead position between the supporting bodies (2), the outer end of the shaft lever (5) is connected with a central through hole of a bearing (6) in a penetrating manner, the bearing (6) is installed on the upper portion of the protection frame (8) corresponding to the left side, the shaft lever (5) with unchanged installation height is arranged between the protection frames (8), the inner end of the shaft lever (5) is embedded in the central through hole of a guide wheel seat (3), the guide wheel seat (3) is installed on the right top of the supporting body (2), and hanging and connecting rings (7) which are respectively arranged at two sides are arranged at the.
2. The line laying device for building construction according to claim 1, characterized in that: the hanging ring (7) comprises a partition plate (71), a fixed shaft sleeve (72), a guide sleeve (73), a blocking block (74), a movable rod (75), a rotating shaft (76) and a support ring (77), the left point and the right point of the partition plate (71) correspond to the support ring (77) of the U-shaped structure, the rotating shaft (76) and the fixed shaft sleeve (72) which correspond to each other are arranged on one side of the support ring (77), the blocking block (74) is arranged between the rotating shaft (76) and the fixed shaft sleeve (72), the guide sleeve (73) which is arranged at the bottom of the blocking block (74) is provided with a through hole, the guide sleeve (73) is provided with an empty channel which can be vertically penetrated by the movable rod (75), and the lower end of the movable rod (75) can vertically correspond to a notch at the.
3. The line laying device for building construction according to claim 1, characterized in that: a shaft rod (5) positioned at the top is arranged between the protection frames (8).
4. The line laying device for building construction according to claim 1, characterized in that: the operating rod (4) is arranged at the overhead position between the supporting bodies (2).
5. The line laying device for building construction according to claim 1, characterized in that: and an operating rod (4) matched and connected with the shaft lever (5) is arranged at one side close to the inner side.
CN201921269752.2U 2019-08-07 2019-08-07 Pay-off for construction Active CN210366306U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921269752.2U CN210366306U (en) 2019-08-07 2019-08-07 Pay-off for construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921269752.2U CN210366306U (en) 2019-08-07 2019-08-07 Pay-off for construction

Publications (1)

Publication Number Publication Date
CN210366306U true CN210366306U (en) 2020-04-21

Family

ID=70249445

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921269752.2U Active CN210366306U (en) 2019-08-07 2019-08-07 Pay-off for construction

Country Status (1)

Country Link
CN (1) CN210366306U (en)

Similar Documents

Publication Publication Date Title
CN101548100A (en) Suspension device for wind wheel blade, method of mounting wind wheel blade, and method of constructing wind-driven generator
CN207339088U (en) Transmission line of electricity straight line pole aerial earth wire overhauls stent
KR20120056960A (en) Assistant apparatus for carrying a cable drum
CN105398990A (en) Auxiliary lifting device for electric angle iron tower
CN210366306U (en) Pay-off for construction
CN214227617U (en) Distribution network is wire abrasionproof for unwrapping wire decreases line frame device more
CN205187730U (en) Electric power angle -steel tower is with supplementary hoisting device
CN207381872U (en) A kind of cable pulley block
CN107181198B (en) Lift single pole crossing frame
CN210918212U (en) Wall-attached support structure of creeping formwork device
CN207002096U (en) A kind of distribution auxiliary hanging device
CN214227626U (en) Movable wire crossing device capable of reducing wire abrasion
CN205676052U (en) Bench type transformer crane device
CN112897241A (en) Distribution network is wire abrasionproof for unwrapping wire decreases line frame device more
CN210182910U (en) Simple insulator lifting device for concrete pole
CN202368578U (en) Whole-course anti-excessive deflection protective device for hanging seat of aerial manned device for mining
CN206620023U (en) Motor pole dismantling device
JP3161094U (en) Conveyor device to transfer overhead ground wire and power line simultaneously
CN205687384U (en) A kind of tower balance beam for hoisting
CN219932200U (en) Colliery underworkings prevents outstanding supporting equipment
CN211421805U (en) Construction hanging basket for constructional engineering
CN204927955U (en) Support of using when overhead transmission line let -down ground wire, optical cable
CN210167783U (en) Electric power cable support
CN210418947U (en) Anti-swing lifting hook group
CN210182911U (en) Simple insulator lifting device for iron tower

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant