CN210315080U - Railway track lays and uses track connecting tool - Google Patents

Railway track lays and uses track connecting tool Download PDF

Info

Publication number
CN210315080U
CN210315080U CN201920920490.5U CN201920920490U CN210315080U CN 210315080 U CN210315080 U CN 210315080U CN 201920920490 U CN201920920490 U CN 201920920490U CN 210315080 U CN210315080 U CN 210315080U
Authority
CN
China
Prior art keywords
slide rail
face
rail
clamping block
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920920490.5U
Other languages
Chinese (zh)
Inventor
马海龙
陈国光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN201920920490.5U priority Critical patent/CN210315080U/en
Application granted granted Critical
Publication of CN210315080U publication Critical patent/CN210315080U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model relates to a railway rails lays equipment technical field, specifically is a railway rails lays and uses rail coupling instrument, including first slide rail, the fixed welding of front end inner chamber of first slide rail is provided with the second slide rail by a pair of inserted bar of bilateral mutual symmetry, the preceding terminal surface of first slide rail, and the outer wall of inserted bar is all pegged graft and is had the connecting plate, and beneficial effect is: the utility model arranges the left and right symmetrical plugboards on the first slide rail, and utilizes the chutes on the plugboards to ensure that the second slide rail keeps vertically descending when descending under the action of the crane, thereby improving the installation precision between the adjacent rails; through the clamping blocks arranged on the second rail in bilateral symmetry, the pre-tightening installation between the adjacent sliding rails is realized by utilizing the clamping grooves at the lower ends of the clamping blocks, so that the adjacent sliding rails are always kept relatively parallel in the installation process, and the deviation caused by the installation of the rails is avoided.

Description

Railway track lays and uses track connecting tool
Technical Field
The utility model relates to a railway rails lays equipment technical field, specifically is a railway rails lays and uses rail fastening instrument.
Background
When the railway track is laid, in order to ensure the running stability of a train, the gap between adjacent tracks needs to be small, the installation precision is high, but because the railway track is heavy in weight and long in length, the meeting level is difficult to maintain during hoisting and installation, fine adjustment of the installation precision is difficult to realize by manpower, the installation precision of the railway track cannot meet the requirement, the running safety performance of the train is reduced, and the noise is high.
To this end, a rail coupling tool for laying railway rails is provided for achieving accurate installation between adjacent rails.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a railway rails lays and uses rail fastening instrument to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
a rail connecting tool for laying a railway rail comprises a first slide rail, wherein a pair of insertion rods which are symmetrical left and right are fixedly welded in the front end cavity of the first slide rail, a second slide rail is arranged on the front end surface of the first slide rail, a connecting plate is inserted into the outer wall of each insertion rod, a jack is formed in the other end surface of the connecting plate, the jack is arranged to be a T-shaped cross section, a first insertion plate and a second insertion plate are respectively inserted into the inner walls of the jacks which are symmetrical left and right, stand columns are welded at the front ends and the rear ends of the first insertion plate and the second insertion plate in parallel, a sliding groove is formed in one side, close to the first slide rail, of the upper end surface of each stand column, a stop block is arranged in the rear end cavity of the second slide rail, a first clamping block and a second clamping block which are symmetrically distributed left and right are inserted into the upper ends of the rear end surface of, limiting rods are vertically welded at the front end and the rear end of the upper end face of the first clamping block and the upper end face of the second clamping block.
Preferably, the first slide rail and the second slide rail are both arranged to be I-shaped guide rails, a gap is reserved between the upper end face of the inner cavity of the first slide rail and the inserted rod, and the length of the gap is larger than the thickness of the upper end of the connecting plate.
Preferably, the lower end face of the stop block is fixedly welded on the lower end face of the inner cavity of the second slide rail, and the rear end face of the stop block is tightly attached to the front end faces of the first fixture block and the second fixture block.
Preferably, the outer end faces of the first clamping block and the second clamping block are vertically welded with sliding blocks which are installed in a matched mode with the sliding grooves, and the first clamping block and the second clamping block are respectively inserted into the second inserting plate and the first inserting plate in a sliding mode through the sliding blocks.
Preferably, the inner wall of the clamping groove is tightly attached to the outer wall of the second sliding rail, and the lower end of the clamping groove extends to the inner cavity of the second sliding rail.
Preferably, the upper end faces of the first clamping block and the second clamping block are provided with limiting insertion plates, the limiting insertion plates are provided with limiting insertion holes which are symmetrical left and right, the limiting insertion plates are inserted into the outer wall of the limiting rod through the limiting insertion holes, and the lower end faces of the limiting insertion plates are tightly attached to the upper end faces of the first clamping block and the second clamping block.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model arranges the left and right symmetrical plugboards on the first slide rail, and utilizes the chutes on the plugboards to ensure that the second slide rail keeps vertically descending when descending under the action of the crane, thereby improving the installation precision between the adjacent rails;
2. the utility model discloses a set up bilateral symmetry's fixture block on the second track, utilize the draw-in groove of fixture block lower extreme, realize the pretension installation between the adjacent slide rail for adjacent slide rail remains relatively parallel in the installation throughout, avoids the track to cause the skew when the installation.
Drawings
Fig. 1 is a schematic perspective view of the present invention;
FIG. 2 is a schematic view of a three-dimensional structure of a fixture block of the present invention;
fig. 3 is a schematic view of a first slide rail mounting structure of the present invention;
fig. 4 is a schematic view of the pre-tightening mounting structure of the present invention.
In the figure: the device comprises a first slide rail 1, a second slide rail 2, an inserting rod 3, a stop block 4, a first inserting plate 5, a second inserting plate 6, a first clamping block 7, a second clamping block 8, a clamping groove 9, a limiting rod 10, a limiting inserting plate 11, a sliding block 12, a sliding groove 13, an upright post 14, a jack 15 and a connecting plate 16.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1 to 4, the present invention provides a technical solution:
the utility model provides a railway rails lays and uses rail connection instrument, includes first slide rail 1, the fixed welding of front end inner chamber of first slide rail 1 is by a pair of inserted bar 3 of bilateral mutual symmetry, and the outer wall of inserted bar 3 all is pegged graft and has been had connecting plate 16, utilizes inserted bar 3 to connect connecting plate 16, realizes the injecing to connecting plate 16 position.
The jack 15 is arranged on the other end face of the connecting plate 16, the jack 15 is provided with a T-shaped section, the inner walls of the jacks 15 which are symmetrical left and right are respectively inserted with the first inserting plate 5 and the second inserting plate 6, and the jacks 15 with the T-shaped sections are utilized to enable the first inserting plate 5 and the second inserting plate 6 to be horizontally inserted on the connecting plate 16, so that the installation levelness is improved.
Equal parallel welding of the front and back end of first picture peg 5 and second picture peg 6 has stand 14, spout 13 has been seted up to one side that the up end of stand 14 is close to first slide rail 1, the equal vertical welding of the outer terminal surface of first fixture block 7 and second fixture block 8 has slider 12 with spout 13 cooperation installation, first fixture block 7 and second fixture block 8 slide respectively through slider 12 and peg graft on second picture peg 6 and first picture peg 5, utilize the cooperation of slider 12 and spout 13, and then make the steady perpendicular grafting of first fixture block 7 and second fixture block 8 at the preceding terminal surface of first track 1, position about injecing the installation, the accurate installation between first track 1 and the second track 2 has been realized.
The front end face of the first slide rail 1 is provided with a second slide rail 2, the rear end inner cavity of the second slide rail 2 is provided with a stop block 4, the lower end face of the stop block 4 is fixedly welded on the lower end face of the inner cavity of the second slide rail 2, the rear end face of the stop block 4 is tightly attached to the front end faces of the first fixture block 7 and the second fixture block 8, the front end positions of the first fixture block 7 and the second fixture block 8 are limited by the stop block 4, the front end face of the first slide rail 1 and the rear end face of the second slide rail 2 can be attached to each other, and the front position and the rear position of the installation process of the adjacent slide rails are limited by.
The upper end of the rear end face of the second slide rail 2 is connected with a first clamping block 7 and a second clamping block 8 which are symmetrically distributed in a bilateral mode in an inserted mode, the lower ends of the first clamping block 7 and the second clamping block 8 are provided with clamping grooves 9 matched with the outer contour of the second slide rail 2, the inner wall of each clamping groove 9 is tightly attached to the outer wall of the second slide rail 2, the lower ends of the clamping grooves 9 extend to the inner cavity of the second slide rail 2, and the clamping grooves 9 are utilized to enable the first clamping block 7 and the second clamping block 8 to carry out limiting clamping on the left and right positions of the first rail 1 and the second.
Both ends all have the gag lever post 10 in the front of the up end of first fixture block 7 and second fixture block 8, the up end of first fixture block 7 and second fixture block 8 is provided with spacing picture peg 11, be provided with the spacing jack of left and right mutual symmetry on the spacing picture peg 11, spacing picture peg 11 is pegged graft at the outer wall of gag lever post 10 through spacing jack, and the lower terminal surface of spacing picture peg 11 closely laminates with the up end of first fixture block 7 and second fixture block 8, utilize spacing picture peg 11 and gag lever post 10, make first fixture block 7 and the mutual fixed connection of second fixture block 8, be convenient for the quick dismantlement between first fixture block 7 and the second fixture block 8 simultaneously.
First slide rail 1 and second slide rail 2 all set up to the I-shaped guide rail, leave the clearance between the inner chamber up end of first slide rail 1 and the inserted bar 3, and the length in clearance is greater than the upper end thickness of connecting plate 16 for connecting block 16 can realize breaking away from with inserted bar 3 when upwards lifting up, and then realizes the quick dismantlement of first picture peg 5 and second picture peg 6.
The working principle is as follows: firstly, when a railway is laid, one of adjacent rails is a fixed rail, the other is a splicing rail, taking a first slide rail 1 as the fixed rail and a second slide rail 2 as the splicing rail as an example: firstly, the connecting plate 16 is inserted into the inserting rod 3, and then the first inserting plate 5 and the second inserting plate 6 are respectively inserted into the outer end inserting hole 15 of the connecting plate 16, so that the pre-installation of the first sliding rail 1 is completed.
Utilize draw-in groove 9 to peg graft first fixture block 7 and second fixture block 8 of mutual bilateral symmetry respectively at the rear end of second track 2, utilize spacing picture peg 11 and gag lever post 10's cooperation, realize the fixed connection between first fixture block 7 and the second fixture block 8, then peg graft in spout 13 with the slider 12 of first fixture block 7 and the 8 outer ends of second fixture block, make second slide rail 2 drop to the preceding terminal surface of first slide rail 1 perpendicularly, utilize first picture peg 5 and second picture peg 6 to realize the injecing of first slide rail 1 and second slide rail 2 left and right sides position, utilize dog 4 and inserted bar 3, injecing the front and back position of adjacent slide rail installation, and then make the installation accuracy improve.
Then, the first inserting plate 5 and the second inserting plate 6 are pulled upwards, a gap is reserved between the upper end face of the inner cavity of the first sliding rail 1 and the inserting rod 3, and the length of the gap is larger than the thickness of the upper end of the connecting plate 16, so that the connecting plate 16 can be separated from the inserting rod 3 when lifted upwards, the first inserting plate 5 and the second inserting plate 6 can be disassembled quickly, the first clamping block 7 and the second clamping block 8 are used for carrying out limiting clamping on the left and right positions of the first rail 1 and the second rail 2 through the clamping groove 9, pre-tightening installation of the first rail 1 and the second rail 2 is realized, and deviation of relative positions is avoided during subsequent fixed installation.
After the fixing and mounting are finished, the limiting insertion plate 11 is taken down, so that the first clamping block 7 and the second clamping block 8 can be conveniently and quickly detached.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a railway rails lays and uses rail fastening tool, includes first slide rail (1), its characterized in that: the front end inner chamber of first slide rail (1) is fixed and welded by a pair of inserted bars (3) which are symmetrical left and right, the front end face of first slide rail (1) is provided with a second slide rail (2), the outer wall of inserted bar (3) is spliced with a connecting plate (16), another end face of connecting plate (16) is provided with a jack (15), jack (15) is arranged into a T-shaped cross section, the inner wall of jack (15) which is symmetrical left and right is spliced with a first inserted plate (5) and a second inserted plate (6) respectively, the front end and the rear end of first inserted plate (5) and second inserted plate (6) are welded with a stand column (14) in parallel, one side of the upper end face of stand column (14) close to first slide rail (1) is provided with a chute (13), the rear end inner chamber of second slide rail (2) is provided with a stop block (4), and the upper end of the rear end face of second slide rail (2) is spliced with a first fixture block (7), the lower ends of the first clamping block (7) and the second clamping block (8) are provided with clamping grooves (9) matched with the outer contour of the second sliding rail (2), and the front end and the rear end of the upper end face of the first clamping block (7) and the upper end face of the second clamping block (8) are vertically welded with limiting rods (10).
2. A rail connecting tool for railway track laying according to claim 1, wherein: the first sliding rail (1) and the second sliding rail (2) are both arranged to be I-shaped guide rails, a gap is reserved between the upper end face of the inner cavity of the first sliding rail (1) and the inserted rod (3), and the length of the gap is larger than the thickness of the upper end of the connecting plate (16).
3. A rail connecting tool for railway track laying according to claim 1, wherein: the lower end face of the stop block (4) is fixedly welded on the lower end face of the inner cavity of the second slide rail (2), and the rear end face of the stop block (4) is tightly attached to the front end faces of the first clamping block (7) and the second clamping block (8).
4. A rail connecting tool for railway track laying according to claim 1, wherein: the outer end faces of the first clamping block (7) and the second clamping block (8) are vertically welded with sliding blocks (12) installed in a matched mode with the sliding grooves (13), and the first clamping block (7) and the second clamping block (8) are respectively inserted into the second inserting plate (6) and the first inserting plate (5) in a sliding mode through the sliding blocks (12).
5. A rail connecting tool for railway track laying according to claim 1, wherein: the inner wall of the clamping groove (9) is tightly attached to the outer wall of the second sliding rail (2), and the lower end of the clamping groove (9) extends to the inner cavity of the second sliding rail (2).
6. A rail connecting tool for railway track laying according to claim 1, wherein: the upper end face of the first clamping block (7) and the upper end face of the second clamping block (8) are provided with limiting insertion plates (11), the limiting insertion plates (11) are provided with limiting insertion holes which are symmetrical left and right, the limiting insertion plates (11) are inserted into the outer wall of the limiting rod (10) through the limiting insertion holes, and the lower end face of each limiting insertion plate (11) is tightly attached to the upper end face of the first clamping block (7) and the upper end face of the second clamping block (8).
CN201920920490.5U 2019-06-19 2019-06-19 Railway track lays and uses track connecting tool Expired - Fee Related CN210315080U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920920490.5U CN210315080U (en) 2019-06-19 2019-06-19 Railway track lays and uses track connecting tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920920490.5U CN210315080U (en) 2019-06-19 2019-06-19 Railway track lays and uses track connecting tool

Publications (1)

Publication Number Publication Date
CN210315080U true CN210315080U (en) 2020-04-14

Family

ID=70144838

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920920490.5U Expired - Fee Related CN210315080U (en) 2019-06-19 2019-06-19 Railway track lays and uses track connecting tool

Country Status (1)

Country Link
CN (1) CN210315080U (en)

Similar Documents

Publication Publication Date Title
CN102587229B (en) Joint for track panel and manufacturing and installing method
CN207147429U (en) Depth of parallelism squareness measurement all-in-one
CN215563547U (en) BIM-based fabricated component for building construction
CN210315080U (en) Railway track lays and uses track connecting tool
CN103572975A (en) Back-off-type rail sliding system and sliding method thereof
CN212387617U (en) Tower crane base convenient for bidirectional combination reinforcement
CN213204449U (en) Laminated plate type shear wall splicing structure
CN202730555U (en) Track skeleton connector
CN114000406A (en) Prefabricated T-beam structure convenient to assemble and construction method
CN211690872U (en) Assembled concrete structure thermal insulation wall
CN214692774U (en) Elevator top-penetrating device for construction of super high-rise core tube creeping formwork system
CN210764091U (en) High-rise building construction is with playing gallows convenient to stable concatenation is used
CN202021677U (en) Recycling production system of precast beam plate
CN210025689U (en) Novel concrete fracture toughness casting mold
CN220816768U (en) Integrated comprehensive supporting and hanging frame with independent bearing function
CN218406571U (en) Movable T-beam steel bar binding clamping fixture
CN213359005U (en) Lifting wall body capable of being spliced flatly
CN211278957U (en) Mould for building mould platform mould
CN214055152U (en) Workbench for metrological verification
CN213950269U (en) Elevator guide rail connection structure
CN217324953U (en) Novel bridge connection supporting structure and integral framework composed of same
CN219195897U (en) Auxiliary alignment assembly under water and oversized jacket
CN211401021U (en) Measuring structure of external locking turnout locking quantity
CN220837603U (en) Clamping device for pipe bending machine
CN219673016U (en) Quickly assembled ground rail

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200414

CF01 Termination of patent right due to non-payment of annual fee