High-rise building construction is with playing gallows convenient to stable concatenation is used Download PDFInfo
- Publication number
- CN210764091U CN210764091U CN201921082297.5U CN201921082297U CN210764091U CN 210764091 U CN210764091 U CN 210764091U CN 201921082297 U CN201921082297 U CN 201921082297U CN 210764091 U CN210764091 U CN 210764091U
- Authority
- CN
- China
- Prior art keywords
- groove
- supporting rod
- building construction
- rise building
- rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a high-rise building construction is with having played gallows convenient to stable concatenation is used, including crossbeam, second recess, elastic spring and slide rail, the bottom left and right sides of crossbeam all is fixed with the bottom plate, and the left and right sides of bottom plate all is provided with the fixed block to the bottom of bottom plate is connected with the connecting rod, the internal connection of draw-in groove has the check lock lever, the below of first bracing piece is provided with the second bracing piece, both sides all are provided with the diagonal brace around the second bracing piece, the slide rail sets up in the top of crossbeam, and installs the slider on the slide rail to the lifting hook is installed to the bottom of slider. This high-rise building construction is with playing gallows convenient to stable concatenation is used is connected through second recess and connecting plate between first bracing piece and the second bracing piece to make this play gallows be convenient for dismantle when not using, can effectively reduce occupation space, and when damaging, can carry out local change maintenance, reduce economic cost.
Description
Technical Field
The utility model relates to a building construction equipment technical field specifically is a gallows is used in high-rise building construction convenient to stable concatenation is used.
Background
In the building construction engineering, it is also one of the indispensable equipment more common to play the gallows, can make the object carry out vertical migration or horizontal direction's removal, plays the effect of transportation.
But present hoisting accessory still has some weak points in the use, for example play the gallows bulky, be not convenient for transport and carry, inconvenient splice the gallows, occupation space relatively, be not convenient for the local maintenance of changing when damaging moreover, generally need whole change, increased economic cost to cause and reduce the practicality to playing the gallows, so we have proposed a high-rise building construction that is convenient for stably splice the use and have played the gallows, so that solve the problem that proposes in the aforesaid.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a high-rise building construction is with having risen gallows convenient to stable concatenation is used to solve the gallows volume that rises on the existing market that above-mentioned background art provided great, the transportation of being not convenient for is carried, and is inconvenient to splice the gallows, and occupation space is more, and the maintenance is changed to the part of being not convenient for when damaging moreover, generally needs the whole change, has increased economic cost, thereby causes the problem that the practicality to having risen the gallows reduces.
In order to achieve the above object, the utility model provides a following technical scheme: a high-rise building construction lifting frame convenient for stable splicing comprises a cross beam, second grooves, an elastic spring and slide rails, wherein bottom plates are fixed on the left side and the right side of the bottom of the cross beam, fixed blocks are arranged on the left side and the right side of the bottom plate, the bottom of the bottom plate is connected with a connecting rod, the connecting rod is connected with a first supporting rod through a first groove, the first groove is arranged in the middle of the inner center of the first supporting rod, clamping grooves are formed in the left side and the right side of the inner portion of the first supporting rod and the inner portion of the fixed blocks, a locking rod is connected with the inner portion of each clamping groove, a second supporting rod is arranged below the first supporting rod, the second groove is arranged at the bottom of the first supporting rod, limiting grooves are formed in the left side and the right side of the second groove, limiting blocks are connected with the inner portions of the limiting grooves, the elastic spring is arranged between the connecting plates, the driving lever is installed on the outer wall of each connecting plate, the inclined support rods are arranged on the front side and the rear side of each second support rod, the slide rails are arranged at the tops of the cross beams, the slide blocks are installed on the slide rails, and the lifting hooks are installed at the bottoms of the slide blocks.
Preferably, the connecting rod and the bottom plate are of an integrated structure, and the connecting rod and the first supporting rod form a dismounting structure through the first groove.
Preferably, the locking rod is in threaded connection with the first supporting rod and the clamping groove in the fixed block, and the depth of the clamping groove is smaller than that of the first groove.
Preferably, the size of the limiting groove is matched with that of the limiting block, two limiting grooves are arranged, and the 2 limiting grooves are symmetrically distributed around the longitudinal center line of the second groove.
Preferably, the limiting block and the connecting plate are of an integrated structure, and the connecting plate and the second supporting rod are connected in a sliding mode.
Preferably, the connecting plates are two, and a telescopic structure is formed between the 2 connecting plates through elastic springs.
Compared with the prior art, the beneficial effects of the utility model are that: the lifting frame for high-rise building construction convenient for stable splicing and use,
(1) the bottom of the bottom plate is provided with a connecting rod, the connecting rod and the first supporting rod form a dismounting structure through the first groove, meanwhile, the outer wall of the bottom plate is provided with a fixed block, the fixed block and the first supporting rod are both internally provided with clamping grooves, and the clamping grooves and the locking rods are in threaded connection, so that the bottom plate and the first supporting rod can be more firmly installed, and the stability of the lifting frame is ensured;
(2) the first supporting rod and the second supporting rod are connected with the connecting plate through the second groove, so that the lifting frame is convenient to disassemble when not used, the occupied space can be effectively reduced, partial replacement and maintenance can be carried out when the lifting frame is damaged, and the economic cost is reduced;
(3) the left and right sides of second recess all is provided with the spacing groove, and the size of spacing groove is identical with the size of stopper, and stopper and connecting plate all constitute extending structure through elastic spring, and then make between connecting plate and the second recess installation inseparabler, also make between first bracing piece and the second bracing piece assemble firmer, do not influence this normal use that plays the gallows.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
fig. 2 is a left-view structural schematic diagram of the connection between the second support rod and the diagonal rod of the present invention;
FIG. 3 is a schematic view of the connection of the first support rod and the slot of the present invention;
fig. 4 is a schematic view of the connection sectional structure of the first support rod and the second support rod of the present invention.
In the figure: 1. a cross beam; 2. a base plate; 3. a fixed block; 4. a connecting rod; 5. a first groove; 6. a first support bar; 7. a card slot; 8. a locking lever; 9. a second support bar; 10. a second groove; 11. a limiting groove; 12. a limiting block; 13. a connecting plate; 14. an elastic spring; 15. a deflector rod; 16. a diagonal brace; 17. A slide rail; 18. a slider; 19. and (4) a lifting hook.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: a high-rise building construction lifting frame convenient for stable splicing comprises a cross beam 1, a bottom plate 2, a fixed block 3, a connecting rod 4, a first groove 5, a first supporting rod 6, clamping grooves 7, locking rods 8, a second supporting rod 9, a second groove 10, a limiting groove 11, a limiting block 12, a connecting plate 13, an elastic spring 14, a driving rod 15, an inclined supporting rod 16, a sliding rail 17, a sliding block 18 and a lifting hook 19, wherein the bottom plate 2 is fixed on the left side and the right side of the bottom of the cross beam 1, the fixed block 3 is arranged on the left side and the right side of the bottom plate 2, the bottom of the bottom plate 2 is connected with the connecting rod 4, the connecting rod 4 is connected with the first supporting rod 6 through the first groove 5, the first groove 5 is arranged in the middle of the first supporting rod 6, the clamping grooves 7 are arranged on the left side and the right side of the inside of the first supporting rod 6, a second support rod 9 is arranged below the first support rod 6, a second groove 10 is formed in the bottom of the first support rod 6, limiting grooves 11 are formed in the left side and the right side of each second groove 10, limiting blocks 12 are connected inside the limiting grooves 11, one ends, far away from the limiting grooves 11, of the limiting blocks 12 are connected with connecting plates 13, elastic springs 14 are arranged between the connecting plates 13, deflector rods 15 are arranged on the outer walls of the connecting plates 13, inclined support rods 16 are arranged on the front side and the rear side of each second support rod 9, slide rails 17 are arranged at the top of the cross beam 1, slide blocks 18 are arranged on the slide rails 17, and lifting hooks 19 are arranged at the bottoms of the slide blocks 18;
the connecting rod 4 and the bottom plate 2 are of an integrated structure, and the connecting rod 4 and the first supporting rod 6 form a dismounting structure through the first groove 5, so that the connection between the connecting rod 4 and the bottom plate 2 is firmer, and meanwhile, when the lifting frame is not used, the dismounting is convenient, and the occupied space is reduced;
the locking rod 8, the first supporting rod 6 and the clamping groove 7 in the fixing block 3 are in threaded connection, and the depth of the clamping groove 7 is smaller than that of the first groove 5, so that the first supporting rod 6 and the bottom plate 2 can be fixed again, and the stability of the lifting frame in use is further ensured;
the size of the limiting grooves 11 is matched with that of the limiting blocks 12, two limiting grooves 11 are arranged, and 2 limiting grooves 11 are symmetrically distributed about the longitudinal center line of the second groove 10, so that the limiting blocks 12 can be clamped and fixed, and the connecting plate 13 is fixed;
the limiting block 12 and the connecting plate 13 are of an integrated structure, and the connecting plate 13 and the second supporting rod 9 are connected in a sliding mode, so that the distance between the connecting plates 13 can be conveniently adjusted, and convenience is brought to splicing work of workers;
connecting plate 13 is provided with two, and constitutes extending structure through elasticity spring 14 between 2 connecting plates 13, makes things convenient for the dismouting between connecting plate 13 and the second recess 10 to when damaging the maintenance, can change the part, need not whole change, reduced economic cost.
The working principle is as follows: when the lifting frame convenient for stably splicing and using for high-rise building construction is used, as shown in fig. 1 and fig. 4, firstly, a worker pushes 2 lifting rods 15 towards the direction of the central line of the second supporting rod 9, so that the lifting rods 15 drive the connecting plates 13 to slide along the outer wall of the second supporting rod 9 and gradually approach, when the sum of the widths of the 2 connecting plates 13 and the limiting blocks 12 is smaller than that of the second groove 10, the worker inserts the connecting plates 13 and the limiting blocks 12 into the second groove 10 together, then loosens the lifting rods 15, and at the moment, under the reset action of the elastic springs 14, the distance between the connecting plates 13 and the limiting blocks 12 is gradually increased, so that the limiting blocks 12 are clamped into the limiting grooves 11, and the installation between the second supporting rod 9 and the first supporting rod 6 is firmer;
then the worker fastens the first groove 5 above the inside of the first supporting rod 6 with the connecting rod 4 at the bottom of the bottom plate 2, and the clamping grooves 7 are arranged on the left side and the right side of the inside of the fixing block 3 and the left side of the inside of the first supporting rod 6, so after the first groove 5 and the connecting rod 4 are fastened, the fixing block 3 and the clamping grooves 7 inside the first supporting rod 6 are aligned with each other, as shown in fig. 3, the worker rotates the locking rod 8 into the clamping grooves 7 again to fix the bottom plate 2 and the first supporting rod 6 again, and the stability in later use is ensured, as shown in fig. 4, the inclined supporting rods 16 are arranged on the front side and the rear side of the second supporting rod 9, so that the hanger can be used more stably, the phenomenon of shaking is effectively prevented, and then the worker can convey an object through the lifting hook 19, which is the working process of the whole device, and the content which is not described in detail in the specification belongs to the prior art known by the professional skilled.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.
Claims (6)
1. The utility model provides a high-rise building construction is with playing gallows convenient to stable concatenation is used, includes crossbeam (1), second recess (10), elasticity spring (14) and slide rail (17), its characterized in that: the bottom left and right sides of the beam (1) are both fixed with a bottom plate (2), the left and right sides of the bottom plate (2) are both provided with a fixed block (3), the bottom of the bottom plate (2) is connected with a connecting rod (4), the connecting rod (4) is connected with a first supporting rod (6) through a first groove (5), the first groove (5) is arranged in the middle of the inside of the first supporting rod (6), clamping grooves (7) are arranged on the left and right sides of the inside of the first supporting rod (6) and the inside of the fixed block (3), a locking rod (8) is connected inside the clamping groove (7), a second supporting rod (9) is arranged below the first supporting rod (6), a second groove (10) is arranged at the bottom of the first supporting rod (6), the left and right sides of the second groove (10) are both provided with limiting grooves (11), and the inside of the limiting grooves (11) is connected with a limiting block (12), and the end, far away from the limiting groove (11), of the limiting block (12) is connected with a connecting plate (13), an elastic spring (14) is arranged between the connecting plates (13), a driving lever (15) is installed on the outer wall of the connecting plate (13), inclined support rods (16) are arranged on the front side and the rear side of the second support rod (9), a sliding rail (17) is arranged at the top of the cross beam (1), a sliding block (18) is installed on the sliding rail (17), and a lifting hook (19) is installed at the bottom of the sliding block (18).
2. The hoisting frame for high-rise building construction convenient for stable splicing use according to claim 1, wherein: connecting rod (4) and bottom plate (2) formula structure as an organic whole, and connecting rod (4) constitute through first recess (5) and first bracing piece (6) and dismantle the structure.
3. The hoisting frame for high-rise building construction convenient for stable splicing use according to claim 1, wherein: the locking rod (8) is in threaded connection with the first supporting rod (6) and the clamping groove (7) in the fixing block (3), and the depth of the clamping groove (7) is smaller than that of the first groove (5).
4. The hoisting frame for high-rise building construction convenient for stable splicing use according to claim 1, wherein: the size of the limiting grooves (11) is matched with that of the limiting blocks (12), two limiting grooves (11) are arranged, and the 2 limiting grooves (11) are symmetrically distributed around the longitudinal central line of the second groove (10).
5. The hoisting frame for high-rise building construction convenient for stable splicing use according to claim 1, wherein: the limiting block (12) and the connecting plate (13) are of an integrated structure, and the connecting plate (13) is connected with the second supporting rod (9) in a sliding mode.
6. The hoisting frame for high-rise building construction convenient for stable splicing use according to claim 1, wherein: the number of the connecting plates (13) is two, and the 2 connecting plates (13) form a telescopic structure through elastic springs (14).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921082297.5U CN210764091U (en) | 2019-07-11 | 2019-07-11 | High-rise building construction is with playing gallows convenient to stable concatenation is used |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921082297.5U CN210764091U (en) | 2019-07-11 | 2019-07-11 | High-rise building construction is with playing gallows convenient to stable concatenation is used |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210764091U true CN210764091U (en) | 2020-06-16 |
Family
ID=71039008
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921082297.5U Expired - Fee Related CN210764091U (en) | 2019-07-11 | 2019-07-11 | High-rise building construction is with playing gallows convenient to stable concatenation is used |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210764091U (en) |
-
2019
- 2019-07-11 CN CN201921082297.5U patent/CN210764091U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210764091U (en) | High-rise building construction is with playing gallows convenient to stable concatenation is used | |
CN207974007U (en) | A kind of municipal administration bridge construction supporting rack | |
CN217859672U (en) | Construction steel bar welding device | |
CN212128820U (en) | Underframe for supporting and fixing bridge | |
CN211848937U (en) | Bridge floor is decorated construction and is used hanging cage with protective structure | |
CN211186648U (en) | Adjustable multilayer goods shelf | |
CN211473345U (en) | Support is used in civil engineering construction | |
CN209948574U (en) | High-stability wiring rack structure | |
CN213464268U (en) | Goods shelf convenient to install | |
CN218346992U (en) | Combined arc-shaped group photo frame | |
CN211817802U (en) | Gardens building engineering is with portable scaffold frame | |
CN212773349U (en) | Construction frame reinforcing apparatus | |
CN218264885U (en) | Attached type lifting scaffold protective net | |
CN217812226U (en) | Construction scaffold | |
CN209924392U (en) | Scaffold frame for building engineering convenient to concatenation | |
CN216687371U (en) | Electromechanical mounting bracket | |
CN216766858U (en) | Anti-falling device of building element for building construction | |
CN220247534U (en) | Scaffold with auxiliary inclined supporting structure | |
CN221662479U (en) | Tower machine rail guard convenient to installation is fixed | |
CN213597433U (en) | Insulating fast-assembling scaffold frame | |
CN218559634U (en) | Cable spool storage rack | |
CN220639914U (en) | Fastener for template transportation | |
CN219059784U (en) | Bridge expansion bracket for bridge construction | |
CN216516130U (en) | Stable I-shaped steel beam column structure | |
CN215857843U (en) | A template support system for vault underground structure engineering construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |