CN210134394U - Good gabion bank protection of stability - Google Patents

Good gabion bank protection of stability Download PDF

Info

Publication number
CN210134394U
CN210134394U CN201920563893.9U CN201920563893U CN210134394U CN 210134394 U CN210134394 U CN 210134394U CN 201920563893 U CN201920563893 U CN 201920563893U CN 210134394 U CN210134394 U CN 210134394U
Authority
CN
China
Prior art keywords
gabion
fixing
fixedly connected
frame
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920563893.9U
Other languages
Chinese (zh)
Inventor
蔡丽煌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201920563893.9U priority Critical patent/CN210134394U/en
Application granted granted Critical
Publication of CN210134394U publication Critical patent/CN210134394U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a gabion revetment with good stability, which relates to the field of ecological environment protection and comprises a frame, wherein a plurality of fixed columns are fixedly connected in the frame, a gabion mechanism is arranged between the fixed columns, pull ropes are fixedly connected at four corners of the frame, the pull ropes are fixedly connected with fixed rings, and fixed holes are formed in the fixed rings, the gabion mechanism comprises four fixed seats, the four fixed seats are positioned on the same horizontal plane and distributed in a matrix manner, a connecting frame and a side steel wire mesh are connected between every two adjacent fixed seats, and the side steel wire mesh is positioned above the connecting frame, so that stones can be loaded by arranging a plurality of gabion mechanisms in the frame, and a bottom buffer spring and a side buffer spring are arranged at the bottom and the side of the gabion mechanism, so that the gabion mechanism has good buffering capacity when being impacted, and the stability of the gabion mechanism is improved, the service life of the gabion revetment is prolonged.

Description

Good gabion bank protection of stability
Technical Field
The utility model relates to an ecological environment protection field specifically is a gabion bank protection that stability is good.
Background
Slope protection refers to the general name of various pavements and plants on the slope surface for preventing the side slope from being washed away, the concave bank of the river bank is washed away by water flow year by year, the river bank can be continuously collapsed, and in order to protect the safety of bridges and embankments, protective buildings need to be built on the concave bank.
The utility model discloses a be CN 208517894U's chinese utility model patent document, an ecological gabion bank protection is disclosed, the device has installed the strengthening rib, the convenient protection compressive capacity who strengthens the device, damp-eliminating guard plate and support column have been installed, the damp-eliminating guard plate is the arc structure towards the one side of river, it is convenient when the tide rises, can make the wave tide rise again, the impact force of wave tide to the device has been reduced, the afforestation vegetation has been set up, cultivate and plant soil and protection fender net, make things convenient for the better growth of afforestation vegetation of microorganism nutrient messenger in the river to utilize, the aesthetic measure of the device has been promoted, but under the long-time washing of river, because river bank earth is soft, certain displacement can take place for the gabion bank protection, thereby can appear the gabion bank protection and take place deformation, lead to the gabion bank protection damage, be difficult to reach original effect.
SUMMERY OF THE UTILITY MODEL
The utility model provides a gabion bank protection that stability is good has solved the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme:
the utility model provides a gabion bank protection that stability is good, includes the frame, and a plurality of fixed columns of fixed connection are equipped with gabion mechanism between a plurality of fixed columns in the frame, the equal fixed connection stay cord in four corners of frame, the solid fixed ring of stay cord fixed connection have seted up the fixed orifices on the solid fixed ring, gabion mechanism includes four fixing bases, and four fixing bases are located same horizontal plane and are the matrix distribution, all are connected with link and side wire net between per two adjacent fixing bases, and side wire net is located the top of link, is connected with end wire net, every between four links all be connected with side buffer spring between fixing base and the adjacent fixed column.
As a preferred technical scheme of the utility model, the bottom fixed connection end protection network of frame, fixedly connected with bottom buffer spring between end protection network and the end wire net.
As an optimized technical scheme of the utility model, the nail is inserted to fixed connection on the end protective screen.
As an optimized technical scheme of the utility model, fixed connection dead lever between two adjacent fixed columns.
As an optimal technical scheme of the utility model, side buffer spring's both ends all are equipped with the couple, all set up on fixing base and the fixed column with the corresponding hanging hole of couple.
The utility model discloses have following useful part: the utility model discloses a set up a plurality of gabion mechanisms inside the frame to can load the stone, set up bottom buffer spring and side buffer spring through bottom and side at gabion mechanism, thereby make gabion mechanism possess good buffer capacity when receiving the impact, increase the stability of gabion mechanism, improve the life of gabion bank protection.
Drawings
Fig. 1 is a schematic structural diagram of a gabion revetment with good stability.
Fig. 2 is a structural schematic diagram of the inside of an outer frame in the gabion revetment with good stability.
Fig. 3 is a schematic view of a three-dimensional structure of a gabion mechanism in a gabion slope protection with good stability.
In the figure: 1. an outer frame; 2. fixing a column; 3. a gabion mechanism; 4. a side buffer spring; 5. a bottom buffer spring; 6. a ground inserting nail; 7. pulling a rope; 8. a fixing ring; 9. a fixed seat; 10. a connecting frame; 11. a side wire mesh; 12. a bottom steel wire mesh; 13. hanging holes; 14. a fixing hole; 15. fixing the rod; 16. bottom protective screening.
Detailed Description
The preferred embodiments of the present invention will be described in conjunction with the accompanying drawings, and it will be understood that they are presented herein only to illustrate and explain the present invention, and not to limit the present invention.
It should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of describing the present invention and simplifying the description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed in a specific orientation, and be operated, and thus should not be construed as limiting the present invention.
Example 1
Referring to fig. 1-3, a gabion slope protection with good stability comprises an outer frame 1, wherein a plurality of fixing columns 2 are fixedly connected in the outer frame 1, gabion mechanisms 3 are arranged among the fixing columns 2, four corners of the outer frame 1 are fixedly connected with pull ropes 7, the pull ropes 7 are fixedly connected with fixing rings 8, fixing holes 14 are formed in the fixing rings 8, each gabion mechanism 3 comprises four fixing seats 9, the four fixing seats 9 are located on the same horizontal plane and distributed in a matrix mode, a connecting frame 10 and a side steel wire net 11 are connected between every two adjacent fixing seats 9, the side steel wire net 11 is located above the connecting frame 10, bottom steel wire nets 12 are connected between the four connecting frames 10, and side buffer springs 4 are connected between each fixing seat 9 and the adjacent fixing column 2.
The bottom end of the outer frame 1 is fixedly connected with a bottom protective screen 16, a bottom buffer spring 5 is fixedly connected between the bottom protective screen 16 and the bottom steel wire mesh 12, nails 6 are inserted into the bottom protective screen 16 in a fixedly connected mode, and a fixing rod 15 is fixedly connected between two adjacent fixing columns 2.
Example 2
Referring to fig. 1-3, the other contents of the present embodiment are the same as embodiment 1, except that: the both ends of side buffer spring 4 all are equipped with the couple, all set up on fixing base 9 and the fixed column 2 with the corresponding hanging hole 13 of couple.
The utility model discloses in the implementation process, will fix fixed ring 8 earlier through external fixture and be fixed in the river bank, it is fixed to realize the four corners of device, then will insert nail 6 and insert ground, realize the complete fixation of device, then pack the stone to 3 intussuseptions of gabion mechanism, under the condition that takes place external force factor, side buffer spring 4 and bottom buffer spring 5 can play good buffering effect.
The utility model discloses a set up a plurality of gabion mechanisms 3 inside the frame to can load the stone, set up bottom buffer spring 5 and side buffer spring 4 through bottom and side at gabion mechanism 3, thereby make gabion mechanism 3 possess good buffer capacity when receiving the impact, increase the stability of gabion mechanism 3, improve the life of gabion bank protection.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (5)

1. A gabion revetment with good stability comprises an outer frame (1), a plurality of fixing columns (2) are fixedly connected in the outer frame (1), a gabion mechanism (3) is arranged among the fixing columns (2), four corners of the outer frame (1) are fixedly connected with pull ropes (7), the pull ropes (7) are fixedly connected with fixing rings (8), the fixing rings (8) are provided with fixing holes (14), the gabion mechanism is characterized in that the gabion mechanism (3) comprises four fixing seats (9), the four fixing seats (9) are located on the same horizontal plane and distributed in a matrix mode, a connecting frame (10) and a side steel wire net (11) are connected between every two adjacent fixing seats (9), the side steel wire net (11) is located above the connecting frame (10), a bottom steel wire net (12) is connected between the four connecting frames (10), and each fixing seat (9) and the adjacent fixing column (2) are connected with a side buffer spring (4).
2. The gabion revetment with good stability according to claim 1, wherein a bottom protective mesh (16) is fixedly connected to the bottom end of the outer frame (1), and a bottom buffer spring (5) is fixedly connected between the bottom protective mesh (16) and the bottom steel wire mesh (12).
3. The gabion revetment with good stability according to claim 2, wherein the bottom protective mesh (16) is fixedly connected with ground insertion nails (6).
4. The gabion revetment with good stability according to claim 1, wherein a fixing rod (15) is fixedly connected between two adjacent fixing posts (2).
5. The gabion revetment with good stability according to claim 3 or 4, wherein hooks are provided at both ends of the side buffer spring (4), and hanging holes (13) corresponding to the hooks are provided on the fixing seat (9) and the fixing column (2).
CN201920563893.9U 2019-04-24 2019-04-24 Good gabion bank protection of stability Expired - Fee Related CN210134394U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920563893.9U CN210134394U (en) 2019-04-24 2019-04-24 Good gabion bank protection of stability

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920563893.9U CN210134394U (en) 2019-04-24 2019-04-24 Good gabion bank protection of stability

Publications (1)

Publication Number Publication Date
CN210134394U true CN210134394U (en) 2020-03-10

Family

ID=69703712

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920563893.9U Expired - Fee Related CN210134394U (en) 2019-04-24 2019-04-24 Good gabion bank protection of stability

Country Status (1)

Country Link
CN (1) CN210134394U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113875534A (en) * 2021-10-13 2022-01-04 西南科技大学 Moss greening method for steep rock slope

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113875534A (en) * 2021-10-13 2022-01-04 西南科技大学 Moss greening method for steep rock slope

Similar Documents

Publication Publication Date Title
CN210134394U (en) Good gabion bank protection of stability
CN217438758U (en) Slope gravel anti-falling structure for water conservancy and hydropower
CN211395708U (en) Novel water conservancy slope protection net
CN212612282U (en) Fixed hydraulic engineering bank protection of tractive
CN213539010U (en) Side slope surface rock fall prevention net body structure
CN219690603U (en) Earthquake-resistant foundation structure
CN209760887U (en) Multi-functional protection canopy of manual hole digging pile fore shaft
CN112761172A (en) Integral anchor rod geocell
CN212154374U (en) Annular net rigid guardrail
KR100525327B1 (en) Fixing unit of construction stone and fixing method of construction stone that use it
CN213391404U (en) Novel reinforcing bar processing canopy that stability is strong
CN218417658U (en) Protection device for planting grape in field planting ditch
AU2018100196A4 (en) Bracket for supporting rock-fall network
CN211596477U (en) Environment-friendly passive protective net
CN215252937U (en) Integral anchor rod geocell
CN201560614U (en) Grid net fixing pile
CN215925854U (en) Anti-impact pile
CN2763377Y (en) Reinforced concrete tube structure with built in support
CN216999785U (en) Mining area side slope supporting construction
CN116607463A (en) Mud-rock flow easily sends out section protective structure
CN219227494U (en) Photovoltaic board flexible supporting structure
CN211948502U (en) Protective net easy to dredge rockfall
CN211498550U (en) Single-span separation type flexible blocking net
CN211713988U (en) Ecological protective structure of stone abrupt slope plant biological bag
CN106988449B (en) A kind of building damper

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200310

CF01 Termination of patent right due to non-payment of annual fee