CN210105366U CN201920786680.2U CN201920786680U CN210105366U CN 210105366 U CN210105366 U CN 210105366U CN 201920786680 U CN201920786680 U CN 201920786680U CN 210105366 U CN210105366 U CN 210105366U
Authority
CN
China
Prior art keywords
door
elevator entrance
floor elevator
face
entrance guard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920786680.2U
Other languages
Chinese (zh)
Inventor
兰春晓
蒋励
颜恩历
王淇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Yinyu Construction Engineering Co ltd
Zhoushan Construction Management Service Center
Original Assignee
Zhejiang Silver Reputation Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Silver Reputation Construction Engineering Co Ltd filed Critical Zhejiang Silver Reputation Construction Engineering Co Ltd
Priority to CN201920786680.2U priority Critical patent/CN210105366U/en
Application granted granted Critical
Publication of CN210105366U publication Critical patent/CN210105366U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

Floor elevator entrance to a cave guard gate, including the guard gate body, the guard gate body include a plurality of door plant of dismantling, connecting, the door plant include two pillars and locate the crossing axle between two pillars, the guard gate body includes a plurality of door plants that can dismantle, connect, can connect a plurality of door plants or dismantle the door plant and satisfy the width of entrance to a cave according to the width of floor elevator entrance to a cave.

Description

Floor elevator entrance to a cave guard gate
Technical Field
The utility model discloses mainly used building construction place elevator entrance to a cave protection belongs to the building engineering construction field.
Background
The fence door is adopted to protect the elevator entrance to a building construction site in China at present, so that casualty accidents caused by falling of people are prevented, but the elevator entrance to a building construction site is large or small, so that the protective door needs to be made into various sizes.
SUMMERY OF THE UTILITY MODEL
For solving the above problem, the utility model provides a floor elevator entrance to a cave guard gate.
The specific technical scheme is as follows: floor elevator entrance to a cave guard gate, including the guard gate body, the guard gate body include a plurality of door plant of dismantling, connecting, the door plant include two pillars and locate the crossing axle between two pillars.
The door plate is characterized in that a sliding strip is arranged on the left end face of the door plate, a sliding groove is arranged on the right end face of the door plate, and the adjacent door plates are fixedly connected with each other through the sliding strip and the sliding groove in a matched mode.
The width from the top end to the bottom end of the slide bar is reduced from large to small.
And a gear block is arranged on the lower end face of the sliding groove.
The door plate is characterized in that a mounting hole is formed in the front end face of the door plate, a mounting column is arranged on the rear end face of the door plate, and the door plate is connected with the mounting column in a matched and folding mode through the mounting hole.
Pulleys are installed on two sides of the lower end face of the protective door body.
The protective door comprises a protective door body and is characterized in that connecting strips are installed on the left side and the right side of the protective door body, connecting holes are formed in the connecting strips, and the connecting holes are fixedly connected with a wall through bolts.
The support is connected with the crossed shaft through welding.
Has the advantages that:
the protective door body comprises a plurality of detachable and connected door plates, and the width of the opening can be met by connecting the door plates or detaching the door plates according to the width of the opening of the floor elevator.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
FIG. 2 is a schematic view of a door panel.
FIG. 3 is a schematic view of a door panel.
FIG. 4 is a schematic view of a door panel.
Fig. 5 is a schematic view of the stacking of the present invention.
The protective door comprises a protective door body 1, a door plate 2, a support column 3, a cross shaft 4, a sliding strip 5, a sliding groove 6, a mounting hole 7, a mounting column 8, a pulley 9, a connecting strip 10 and a connecting hole 11.
Detailed Description
The following description of the specific embodiments of the present invention with reference to the drawings refers to the drawings and provides a floor elevator entrance to a cave protection door, including a protection door body 1, the protection door body 1 includes a plurality of door panels 2 that can be dismantled, connected, the door panel 2 include two pillars 3 and locate two intersecting axes 4 between pillars 3, the protection door body 1 includes a plurality of door panels 2 that can be dismantled, connected, can connect a plurality of door panels 2 or dismantle door panel 2 and satisfy the width of entrance to a cave according to the width of floor elevator entrance to a cave.
The door plate 2 left end face be equipped with draw runner 5, 2 right-hand member face of door plate be equipped with spout 6, through draw runner 5 and 6 cooperation fixed connection of spout between the adjacent door plate 2.
The width from the top end to the bottom end of the sliding strip 5 is reduced from large to small, and the sliding strip can be better installed and connected from large to small
The door plant 2 preceding terminal surface be equipped with mounting hole 7, 2 rear end faces of door plant be equipped with erection column 8, door plant 2 between through mounting hole 7 and 8 cooperation folding joint of erection column.
Pulleys 9 are arranged on two sides of the lower end face of the protective door body 1.
When not using the guard gate, dismantle door plant 2 one by one, then stack door plant 2 and pass through mounting hole 7 and erection column 8 fixed connection simultaneously, then carry out the position through pulley 9 and shift, the problem of guard gate large tracts of land occupation space and the problem of transport have been solved in the setting up of this structure.
The protective door comprises a protective door body 1 and is characterized in that connecting strips 10 are installed on the left side and the right side of the protective door body 1, connecting strips 10 are provided with connecting holes 11, and the connecting holes 11 are fixedly connected with a wall through bolts.
The support 3 is connected with the cross shaft 4 through welding.

Claims (8)

1. Floor elevator entrance to a cave guard gate, its characterized in that: including guard gate body (1), guard gate body (1) including a plurality of door plant (2) of dismantling, connecting, door plant (2) include two pillar (3) and locate crossing axle (4) between two pillar (3).
2. The floor elevator entrance guard door of claim 1, characterized in that: the door plate is characterized in that a sliding strip (5) is arranged on the left end face of the door plate (2), a sliding groove (6) is formed in the right end face of the door plate (2), and the adjacent door plates (2) are fixedly connected with the sliding groove (6) in a matched mode through the sliding strip (5).
3. The floor elevator entrance guard door of claim 2, characterized in that: the width from the top end to the bottom end of the slide bar (5) is reduced from large to small.
4. The floor elevator entrance guard door of claim 3, characterized in that: the lower end face of the sliding groove (6) is provided with a gear block.
5. The floor elevator entrance guard door of claim 4, characterized in that: the door plate is characterized in that a mounting hole (7) is formed in the front end face of the door plate (2), a mounting column (8) is arranged on the rear end face of the door plate (2), and the door plate (2) is connected with the mounting column (8) in a matched and folding mode through the mounting hole (7).
6. The floor elevator entrance guard door of claim 5, characterized in that: pulleys (9) are installed on two sides of the lower end face of the protective door body (1).
7. The floor elevator entrance guard door of claim 1, characterized in that: protection door body (1) left and right sides install connecting strip (10), connecting strip (10) be equipped with connecting hole (11), connecting hole (11) pass through bolt and wall fixed connection.
8. The floor elevator entrance guard door of claim 1, characterized in that: the support column (3) is connected with the cross shaft (4) through welding.
CN201920786680.2U 2019-05-29 2019-05-29 Floor elevator entrance to a cave guard gate Expired - Fee Related CN210105366U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920786680.2U CN210105366U (en) 2019-05-29 2019-05-29 Floor elevator entrance to a cave guard gate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920786680.2U CN210105366U (en) 2019-05-29 2019-05-29 Floor elevator entrance to a cave guard gate

Publications (1)

Publication Number Publication Date
CN210105366U true CN210105366U (en) 2020-02-21

Family

ID=69562111

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920786680.2U Expired - Fee Related CN210105366U (en) 2019-05-29 2019-05-29 Floor elevator entrance to a cave guard gate

Country Status (1)

Country Link
CN (1) CN210105366U (en)

Similar Documents

Publication Publication Date Title
CN210508327U (en) Scaffold board subplate and turn over board of scaffold
CN215407311U (en) A protective structure for climbing frame group seam department
CN106193563B (en) E type adaptation module fast assembling-disassembling construction operation platforms
EP2163700A2 (en) Glass facade
CN105735479B (en) Wallboard Foldable prefabricated house
CN210105366U (en) Floor elevator entrance to a cave guard gate
CN204174953U (en) Temporory structure integrated rain-proof is anti-pounds canopy
CN202560079U (en) Instrumentalizing work site gate
CN206667589U (en) A kind of band hole assembling type outer wall construction
CN209704028U (en) A kind of assembled architecture standardization protection system
CN211666341U (en) Can have enough to meet need flexible book curtain of preventing raise dust and enclose box-like mortar stirring protection canopy
CN210767970U (en) Assembled foundation pit ladder
CN208023608U (en) A kind of post-cast strip can have enough to meet the need steel channel formwork system
CN209211948U (en) A kind of box light steel house structure
CN207436260U (en) The assembling type steel structure occlusion splicing system of node rigid connection
CN203308339U (en) Finalized protective door of elevator shaft opening
CN105544730A (en) Prefabricated house easy to assemble
CN206016160U (en) A kind of sky parking on aluminum floor
CN212406195U (en) Modularization instrument formula entrance to a cave protector
CN206071080U (en) A kind of scalable faces side protection tool
CN204960081U (en) Floor
CN215594816U (en) Assembling type operating platform for pier column construction
CN219569669U (en) Assembled drawknot protection shed
CN219451415U (en) Portable steel structure welding operation platform
CN201826450U (en) Lifting appliance for color-steel contour plates for elongated roofs

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201127

Address after: 316100 No. 2168 Donghai West Road, Zhoushan, Zhejiang, Putuo District

Patentee after: ZHEJIANG YINYU CONSTRUCTION ENGINEERING Co.,Ltd.

Patentee after: Zhoushan Construction Management Service Center

Address before: 316100 No. 2168 Donghai West Road, Zhoushan, Zhejiang, Putuo District

Patentee before: ZHEJIANG YINYU CONSTRUCTION ENGINEERING Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200221