CN210032406U - Old district transformation construction is with ladder of registering one's residence - Google Patents

Old district transformation construction is with ladder of registering one's residence Download PDF

Info

Publication number
CN210032406U
CN210032406U CN201920712065.7U CN201920712065U CN210032406U CN 210032406 U CN210032406 U CN 210032406U CN 201920712065 U CN201920712065 U CN 201920712065U CN 210032406 U CN210032406 U CN 210032406U
Authority
CN
China
Prior art keywords
side beam
construction
fixed
ladder
column frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920712065.7U
Other languages
Chinese (zh)
Inventor
陈振华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201920712065.7U priority Critical patent/CN210032406U/en
Application granted granted Critical
Publication of CN210032406U publication Critical patent/CN210032406U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Steps, Ramps, And Handrails (AREA)

Abstract

The utility model relates to the technical field of building construction equipment, in particular to an entrance ladder for old community reconstruction construction, which comprises a column frame, a side beam, a stair step and a handrail; the column frame is in an inverted U shape and is arranged in front of an original building crossing for old community reconstruction construction; two side beams are arranged in parallel, one end of each side beam is fixed with the upper part of the column frame and connected with the half-floor position of the original building, and the other end of each side beam extends to the ground after penetrating through the additionally-installed elevator shaft; the stair steps are detachably arranged on the side beams; the handrail sets up on the curb girder of the both sides of stair step, and the curb girder includes that a plurality of links up fixed curb girder section. The utility model provides an entrance ladder for old community reconstruction construction, which solves the problem that the original ladder can not come in and go out in the construction process of old community reconstruction and elevator installation; the side beam adopts a mode that a plurality of side beam sections can be disassembled and fixed, so that the side beam is more convenient to transport and install.

Description

Old district transformation construction is with ladder of registering one's residence
Technical Field
The utility model relates to an elevator installs technical field additional, specifically is an old district reforms transform construction and is used into family ladder.
Background
In the work progress of at present old district transformation installs the elevator additional, often need original stair entrance to be under construction, influence people's normal discrepancy, need the resident to move other dwellings and live, it is troublesome hard relatively. Some add existing elevator technology and adopt the flat bed to enter one's residence, though original corridor does not occupy, but the corridor entrance is under construction, has the problem that people can't come in and go out among the work progress.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an old district reforms transform construction and uses ladder of registering one's residence solves old district and reforms transform the problem that original stair can't come in and go out in the work progress of installing the elevator additional.
The utility model provides an entrance ladder for old community reconstruction construction, which comprises a column frame, a side beam, a stair step and a handrail; the column frame is in an inverted U shape and is arranged in front of an original building crossing for old community reconstruction construction; two side beams are arranged in parallel, one end of each side beam is fixed with the upper part of the column frame and connected with the half-floor position of the original building, and the other end of each side beam extends to the ground after penetrating through the additionally-installed elevator shaft; the stair steps are detachably arranged on the side beams; the handrails are arranged on the side beams at two sides of the stair steps.
The side beam comprises a plurality of fixedly connected side beam sections.
In a further improvement, the side beam is made of ㄈ steel.
In a further improvement, the side beam sections are fixedly connected through steel beam connecting pieces.
In a further improvement, the steel beam connecting pieces are provided with bolt holes, the side beam sections are provided with corresponding bolt holes, and the side beam sections are fixed in a bolt fixing mode through the steel beam connecting pieces.
The stair step is fixed with the side beam through an L-shaped connecting plate, and the L-shaped connecting plate is located on the inner side of the side beam and above the stair step.
In a further improvement, handrail slots are welded on the side beams, and the bottom ends of the handrails are inserted into the handrail slots to be assembled and fixed.
In a further improvement, the stair steps are formed by welding steel plates.
The utility model provides an old district reforms transform construction and is used ladder of registering one's residence possesses following beneficial effect: the problem that an original stair cannot go in and out in the construction process of modifying and installing an elevator in an old community is solved; the side beam adopts a mode that a plurality of side beam sections can be disassembled and fixed, so that the side beam is more convenient to transport and install.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is an exploded view of the present invention;
fig. 3 is a schematic structural view of the lowermost side beam section of the present invention.
In the figure: 1 post frame, 2 curb girders, 3 stair steps, 4 handrails, 5 steel beam connecting pieces, 6L-shaped connecting pieces, 7 handrail slots and 8 side girder sections.
Detailed Description
As shown in the figure, the indoor ladder for old community reconstruction construction comprises a post frame 1, a side beam 2, a stair step 3 and a handrail 4; the column frame 1 is in an inverted U shape and is arranged in front of an original building crossing for old community reconstruction construction; two side beams 2 are arranged in parallel, one end of each side beam 2 is fixed with the upper part of the column frame 1, and the other end of each side beam extends to the ground; the stair steps 3 are detachably arranged on the side beams 2; handrail 4 sets up on the curb girder 2 of the both sides of stair step 3, and curb girder 2 adopts ㄈ shaped steel, and every curb girder 2 includes 4 fixed curb girder sections 8 that link up, the curb girder section passes through girder steel connection piece 5 connection fixed, and girder steel connection piece 5 is in the curb girder outside. The steel beam connecting pieces 5 are provided with bolt holes, the side beam sections are provided with corresponding bolt holes, and the side beam sections are fixed in a bolt fixing mode through the steel beam connecting pieces 5.
Stair step 3 adopts the steel sheet welding to form, and stair step 3 is fixed through L type connecting plate 6 with curb girder 2, and L type connecting plate welding is inboard at curb girder 2, is located stair step 3 top, and stair step 3 passes through L type connecting plate and 2 bolt fixings of curb girder.
The side beam 2 is welded with handrail slots 7, and the bottom ends of the handrails 4 are inserted into the handrail slots 7 for assembly and fixation.
The working principle is as follows: when the elevator is installed, the fixed column frame 1 is installed firstly, the support is built to install the side beam 2 in a segmented mode, the side beam 2 penetrates through an additional elevator shaft in construction, and then the stair step 3 and the handrail 4 are installed on the side beam 2. Residents can enter the half-floor platform of the original corridor through the step ladder, so that the residents can enter the house.
The sectional installation of the side beam 2 and the detachable installation of the handrail and the side beam are convenient for construction and transportation.

Claims (7)

1. The utility model provides an old district transformation construction is with ladder of going to home which characterized in that: comprises a column frame (1), a side beam (2), a stair step (3) and a handrail (4); the column frame (1) is in an inverted U shape and is arranged in front of an original building crossing for old and old community reconstruction construction; two side beams (2) are arranged in parallel, one end of each side beam (2) is fixed with the upper part of the column frame (1), and the other end of each side beam extends to the ground after penetrating through the additionally-installed elevator shaft; the stair steps (3) are detachably arranged on the side beams (2); the handrails (4) are arranged on the side beams (2) at two sides of the stair steps (3);
the side beam (2) comprises a plurality of fixedly connected side beam sections (8).
2. The step of claim 1, wherein the step comprises: the side beam (2) adopts ㄈ steel.
3. The step of claim 1, wherein the step comprises: the side beam sections (8) are fixedly connected through steel beam connecting pieces (5), and the steel beam connecting pieces (5) are arranged on the outer sides of the side beams.
4. The step of claim 3, wherein the step comprises: the steel beam connecting pieces (5) are provided with bolt holes, the side beam sections (8) are provided with corresponding bolt holes, and the side beam sections are fixed in a bolt fixing mode through the steel beam connecting pieces (5).
5. The step of claim 1, wherein the step comprises: the stair steps (3) are fixed with the side beams (2) through L-shaped connecting plates (6), and the L-shaped connecting plates are located on the inner sides of the side beams (2) and above the stair steps (3).
6. The step of claim 1, wherein the step comprises: the side beam (2) is welded with handrail slots (7), and the bottoms of the handrails (4) are inserted into the handrail slots (7) for assembly and fixation.
7. The step of claim 1, wherein the step comprises: the stair steps (3) are formed by welding steel plates.
CN201920712065.7U 2019-05-17 2019-05-17 Old district transformation construction is with ladder of registering one's residence Expired - Fee Related CN210032406U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920712065.7U CN210032406U (en) 2019-05-17 2019-05-17 Old district transformation construction is with ladder of registering one's residence

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920712065.7U CN210032406U (en) 2019-05-17 2019-05-17 Old district transformation construction is with ladder of registering one's residence

Publications (1)

Publication Number Publication Date
CN210032406U true CN210032406U (en) 2020-02-07

Family

ID=69366434

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920712065.7U Expired - Fee Related CN210032406U (en) 2019-05-17 2019-05-17 Old district transformation construction is with ladder of registering one's residence

Country Status (1)

Country Link
CN (1) CN210032406U (en)

Similar Documents

Publication Publication Date Title
CN108532769B (en) Jacking construction method of assembled additional elevator shaft structure
CN205444446U (en) Assembled industrialization steel construction house
CN107816223B (en) Safe and stable type station canopy station house and installation method thereof
CN106906984A (en) A kind of prefabricated assembled steel reinforced concrete framework elevator shaft structure and its construction method
CN106760561B (en) Assembling method of sectional sliding roof steel truss
CN106930401A (en) A kind of assembled industrialization steel structure house
CN210316454U (en) Large-span roof overhanging support system
CN109138431B (en) Super high-rise pump pipe bridge crossing device and construction method thereof
CN210032406U (en) Old district transformation construction is with ladder of registering one's residence
CN111270763A (en) Assembled concrete frame structure beam column with connected node
CN214996345U (en) Assembled overhanging pedestrian escalator for deep foundation pit
CN214169883U (en) Construction elevator adheres to frame
CN211201184U (en) Assembled steel structure system
CN210420840U (en) Cantilever light steel pedestrian truss bridge connecting system based on stay cable structure
CN210393329U (en) Assembled well of existing building with additional elevator
CN202882352U (en) Multi-layer steel structure connection corridor shaped like Chinese character 'gan' of old commercial and residential building adding elevator
CN206737358U (en) A kind of prefabricated assembled steel reinforced concrete framework elevator shaft structure
CN110593407A (en) I-shaped aluminum connection structure of aluminum alloy room
CN217518002U (en) Suspension assembly type steel stair system
CN210193157U (en) Assembled steel construction elevator's entrance hall system
CN219509265U (en) Two-section straight running type flat floor entrance additional elevator
CN217652238U (en) Solderless installs elevator well additional
CN218715464U (en) Prefabricated house unit of assembled composite building with terrace
CN219196541U (en) End hoisting plug-in type scissors stair
CN214942777U (en) Deep basal pit is with foldable cage ladder

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200207

Termination date: 20210517

CF01 Termination of patent right due to non-payment of annual fee