CN210002786U - super high-rise shaft air pipe device - Google Patents

super high-rise shaft air pipe device Download PDF

Info

Publication number
CN210002786U
CN210002786U CN201920584155.2U CN201920584155U CN210002786U CN 210002786 U CN210002786 U CN 210002786U CN 201920584155 U CN201920584155 U CN 201920584155U CN 210002786 U CN210002786 U CN 210002786U
Authority
CN
China
Prior art keywords
tuber pipe
air pipe
air
inner flange
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920584155.2U
Other languages
Chinese (zh)
Inventor
叶国昌
孙忠辉
韩凯凯
苏伟
任远敏
韩承成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau First Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau First Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority to CN201920584155.2U priority Critical patent/CN210002786U/en
Application granted granted Critical
Publication of CN210002786U publication Critical patent/CN210002786U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses an super high-rise shaft tuber pipe device, include group tuber pipe (2) that constitute by galvanized steel sheet, every tuber pipe (2) both ends inner wall all is equipped with inner flange (1), and inner flange (1) between tuber pipe (2) and tuber pipe (2) are connected through bolt (3), the utility model discloses a flange installation space of outer flange can be practiced thrift to the tuber pipe of inner flange structure, makes large-scale tuber pipe under the prerequisite that satisfies the design specification requirement, can install in shaft tuber pipe limit and the extremely constrictive well on well limit, and provides convenience for the installation of tuber pipe external fixation support.

Description

super high-rise shaft air pipe device
Technical Field
The utility model discloses the technique relates to super high-rise shaft tuber pipe devices belongs to the electromechanical technical field that installs of construction.
Background
In a super high-rise building, vertical pipes such as a fresh air pipe, a ventilation pipe, a fire-fighting pressurized air supply pipe, and a fire-fighting smoke exhaust pipe are generally provided, and the vertical pipes are collectively called as a shaft air pipe. The main function of the vertical shaft air pipe is ventilation, and meanwhile, the vertical shaft air pipe can also be used for arrangement and installation of electromechanical professional pipelines. The shaft air pipe is vertically installed in a shaft of the building. In the prior art, in order to facilitate installation of the shaft air pipe, the cross section of the shaft is usually designed to be larger, and an operation platform for installing the shaft air pipe can be erected between the shaft air pipe and the inner wall of the shaft. Therefore, the vertical shaft air pipe adopted by the prior art is mostly of an outer flange connecting structure. However, due to the structural limitation of some super high-rise buildings, the cross section of the vertical shaft cannot be designed to be large, so that the distance between the outer wall of the air pipe of the vertical shaft and the wall of the vertical shaft is less than 3 cm. This causes great difficulties in the installation of the shaft air duct. Therefore, the installation can not be carried out according to the construction process of the existing vertical shaft air pipe. And a new construction process is required to be adopted to complete the installation of the vertical shaft air pipe.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide kinds of superelevation layer shaft tuber pipe devices to solve because of the undersize of interval between shaft tuber pipe outer wall and the shaft inner wall, the technical problem of the unable installation of prior art, thereby overcome prior art's not enough.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model discloses an super high-rise shaft tuber pipe device, the device include group tuber pipes that constitute by galvanized steel sheet, every tuber pipe both ends inner wall all is equipped with the inner flange, and the inner flange between tuber pipe and the tuber pipe is through bolted connection the inner flange is the angle bar finished piece, and the angle bar plane at inner flange both ends is outside with the galvanized steel sheet welding, is equipped with the bolt hole of group equipartitions on the inner flange, the bolt from top to bottom is to wearing the bolt hole and the nut connects soon.
Since the technical scheme is used, the utility model discloses compare with prior art, the utility model discloses a flange mounting space of outer flange can be practiced thrift to the tuber pipe of interior flange structure makes large-scale tuber pipe under the prerequisite that satisfies the design standard requirement, can install in shaft tuber pipe limit and the extremely narrow well on well limit, and provides convenience for the installation of the outer fixed bolster of tuber pipe. The air pipe and the accessories are manufactured by adopting a specialized factory, so that the tolerance can be strictly controlled, the installation is convenient, and the effects of high efficiency, accuracy and adjustability are realized. The flame-retardant adhesive tape is adopted to improve the air pipe tightness, so that the air pipe working efficiency is improved. An operation platform does not need to be erected at the floor and the like, so that the working efficiency is improved, the labor cost is saved, the requirement on the construction working face of the site is low, and the construction progress is convenient to improve.
Drawings
Fig. 1 is a schematic view of the construction process of the utility model.
The labels in the figures are: 1-an inner flange; 2-air pipe; 3-a bolt; 4-a base; 5-a pedal; 6-a rope; 7-flame retardant adhesive tape; 8-bolt hole.
Detailed Description
The present invention will be described in further detail in with reference to the following drawings and examples.
The utility model discloses a super high-rise shaft air duct installation process, as shown in figure 1, the process adopts a plurality of sections of air ducts 2 with an inner flange 1 connection structure to install, the air ducts 2 are installed from bottom to top section by section to top, an operator connects the inner flange 1 at the lower end of the upper section of air duct with the inner flange 1 at the upper end of the lower section of air duct by bolts 3 in the air ducts 2 until reaching the design height, at least two persons are matched during installation, the specific process is constructed according to the following steps that ①, a base 4, the air ducts 2 and pedals 5 are manufactured by a professional factory, and fittings of the bolts 3 are purchased, ②, the base 4 is installed on the bottom surface of the shaft, ③, the inner flanges 1 of the two sections of air ducts 2 are connected into a body through the bolts 3, ④, the bottom ends of the two sections of the air ducts 2 connected into the body are connected with the base 4 through the bolts 3, and persons enter the air ducts 2 to lay the pedals 5 on the inner flange 1 at the connection position of the two sections of the air ducts 2, the other persons connect the air ducts air ducts with the top end of the installed pedals 2, the upper end of the air ducts 2, the upper end of the lower section of the air ducts is connected with the inner flange 2, the inner flange is connected with the inner flange of the inner flange 2.
The length of the pedal 5 is less than the distance between the inner walls of the two opposite sides of the galvanized sheet outside the air pipe 2 and is greater than the distance between the inner edges of the flanges inside the air pipe; the thickness of the pedal 5 is not less than 10 mm. A rope 6 is fixed on the pedal 5, and when the pedal 5 needs to move upwards, a person outside the air pipe 2 pulls the pedal 5 upwards. When the bolts 3 are screwed up, the bolts 3 for connecting the air pipes are all screwed up from top to bottom. The joint of the inner flanges 1 of the two air pipes 2 is padded with a flame-retardant adhesive tape 7; the type of the flame retardant tape 7 is selected according to the use of the air duct.
According to the superelevation layer shaft tuber pipe installation technology constitution and be used for above-mentioned technology the utility model discloses an superelevation layer shaft tuber pipe devices, as shown in figure 1, the device includes group tuber pipe 2 that constitute by galvanized steel sheet, every tuber pipe 2 both ends inner wall all is equipped with inner flange 1, inner flange 1 between tuber pipe 2 and the tuber pipe 2 is connected through bolt 3, inner flange 1 is the angle bar finished piece, the angle bar plane at inner flange 1 both ends is outwards welded with galvanized steel sheet, be equipped with group's equipartition bolt hole 8 on inner flange 1, bolt 3 from top to bottom is to wearing bolt hole 8 and nut revolve joint.
Examples
The method comprises the following steps of firstly preparing preparation work, determining an air pipe installation and hoisting scheme, selecting materials according to the application and size of an air pipe, manufacturing air pipe flanges and accessories, and finally, installing the air pipe, wherein the installation sequence is installation section by section from bottom to top, firstly, bases are made of 50 multiplied by 5 steel angles at the bottom of a vertical shaft, the plane of the steel angles of the bases is downward, the size of the bases is suitable for the air pipe to be placed into, an air pipe shell is made of galvanized steel plates, and the thickness of the galvanized steel plates is determined according to the application and size of the air pipe, and is specifically shown in table 1:
TABLE 1
Figure DEST_PATH_IMAGE002
The materials used for the inner flange and the bracket of the air duct are shown in table 2.
Table 2:
serial number Dimension b of long side of air duct Specification of air pipe flange Specification of air duct bracket Bolt specification
1 630< b≤1500 ∟30*3 ∟40*4 M8*25
2 1500< b≤2500 ∟40*4 ∟40*4 M8*25
3 2500< b≤4000 ∟50*5 ∟50*5 M8*25
The galvanized steel plate and the angle steel adopt a joint angle or a snap-fastener type seaming, the dimension of the galvanized steel plate is allowed to have fixed deviation, the deviation is-1-0 mm when the side length is less than or equal to 300mm, the deviation is-2-0 mm when the side length is more than 300mm, the allowable deviation of the flange inner diameter or the inner edge length is + 1-3 mm, the flatness allowable deviation is +/-1 mm, in addition, the difference of two diagonal lines of a rectangular flange is not more than 2mm, the surfaces of an air pipe and an accessory are smooth, arcs are uniform, the seaming seam is tight, the width is , and a crisscross splicing seam is not required.
The material selection of the inner flange is in accordance with the design requirement and the regulation of the specification, the galvanized steel plate can be connected with the inner flange through rivets, the distance between the rivets is not more than 120mm, the distance between bolt holes of the inner flange is not more than 150mm, the welding seam of the inner flange has no defects of air holes, slag inclusion, cracks, welding leakage and the like, when the flanges are painted and prevented from being corroded, a paint film is uniform, the defects of accumulation, leakage coating, wrinkles, bubbles, color mixing and the like are avoided, when the air pipe is riveted, the center line of the rivet is required to be perpendicular to the plate surface, the rivet head is required to press the plate, the plate seam is closed, the rivets are arranged neatly and uniformly, when the air pipe is connected with the flanges, the flanges are smooth, the width is mm and is not less than 6mm, cracks and holes are avoided, when the side length of the rectangular air pipe is more than or equal to 630mm and the side length of the heat preservation air pipe is more than or equal to 800mm, when the length of the pipe section is more than 1200mm, reinforcing measures are adopted, the air pipe is connected with the flanges, the concave-convex ribs are prevented from being connected with the flanges, and the flanges are not overlapped after the inner flanges, the inner flanges are connected with the flanges, and the flanges are prevented.
When the air pipe is obviously installed, the verticality deviation per meter is less than 2mm, and the total deviation is less than 20 mm. The position of the air pipe is correct when the air pipe is installed in a concealed mode, and no obvious deviation exists. The bracket outside the wind pipe is directly fixed on a shear wall or a beam of the structural hole by adopting angle steel or channel steel. After the air pipes are qualified after arrival and inspection, the air pipes are arranged and installed according to a draft before installation. And hoisting according to the position of the drawing. In order to ensure the safety of operators, all bolts for connecting the air pipes are downward.
The joint of the air pipe and the air pipe is provided with a flame-retardant adhesive tape, and the air supply and the positive pressure air supply adopt 8501 flame-retardant adhesive tapes. The smoke exhaust system adopts 9501 flame-retardant adhesive tape.
Whether the size of a vertical shaft hole is correct or not needs to be checked before installation, whether building rubbish in the vertical shaft is cleaned up or not needs to be guaranteed, no movable object exists in the vertical shaft, the top of the vertical shaft is sealed by a reliable object, the objects on other floors are prevented from being hung into the vertical shaft, and operators are prevented from being injured by falling of the objects into the vertical shaft.
When the device is specifically installed, the device is installed,
firstly, two pedals with the sum being 10mm smaller than the inner diameter of the air duct are manufactured, the thickness of the pedals is more than 10mm, 30 x 3 angle iron is used for reinforcement, pedals with the same size are processed, two small holes are formed in the proper positions of the three pedals, ropes with proper lengths are tied for installing connecting pipes, the two sections of inner flange air ducts (wherein sections are seal heads and bolts are downward) are placed on a base which is installed on the lowest end well for adjustment, the air duct is fixed with the base, the two pedals are placed on an inner flange which is connected with the two sections of air ducts, people enter the pedals of the air duct, then the third pedal is placed in the air duct, the rest people place the lower section of air duct, the people in the air duct tighten the air duct on the bolts, the people in the air duct place the third pedal on an inner flange which is tightened by the upper section of air duct, the people stand to place the upper pedal and place the lower pedal until the upper flange 357 section of the upper section of the air duct is tightened by the people, and the people put the lower section of the upper section of the air duct on the lower section of the air duct, and the upper section of the lower section of the air duct, the pedals are placed until the upper section 355638 of the upper section of the lower section of the upper section of.

Claims (2)

  1. The utility model provides a super high-rise shaft air pipe device, which is characterized in that the device comprises groups of air pipes (2) formed by galvanized steel sheets, inner flanges (1) are arranged on the inner walls of two ends of each air pipe (2), and the inner flanges (1) between the air pipes (2) are connected through bolts (3).
  2. 2. The ultra-high-rise shaft air pipe device according to claim 1, wherein the inner flange (1) is an angle iron part, the angle iron planes at two ends of the inner flange (1) are outwards welded with the galvanized steel plate, groups of evenly distributed bolt holes (8) are formed in the inner flange (1), and the bolts (3) penetrate through the bolt holes (8) from top to bottom and are connected with nuts in a screwing mode.
CN201920584155.2U 2019-04-25 2019-04-25 super high-rise shaft air pipe device Active CN210002786U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920584155.2U CN210002786U (en) 2019-04-25 2019-04-25 super high-rise shaft air pipe device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920584155.2U CN210002786U (en) 2019-04-25 2019-04-25 super high-rise shaft air pipe device

Publications (1)

Publication Number Publication Date
CN210002786U true CN210002786U (en) 2020-01-31

Family

ID=69305037

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920584155.2U Active CN210002786U (en) 2019-04-25 2019-04-25 super high-rise shaft air pipe device

Country Status (1)

Country Link
CN (1) CN210002786U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111550012A (en) * 2020-04-29 2020-08-18 广州市房屋开发建设有限公司 Method for installing ventilation pipe
CN111623502A (en) * 2020-04-27 2020-09-04 余志锋 Civil engineering air duct internal air duct installation structure and installation method thereof
CN112376849A (en) * 2020-11-30 2021-02-19 北京城建道桥建设集团有限公司 Vertical ventilation pipe installed in narrow space and construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111623502A (en) * 2020-04-27 2020-09-04 余志锋 Civil engineering air duct internal air duct installation structure and installation method thereof
CN111550012A (en) * 2020-04-29 2020-08-18 广州市房屋开发建设有限公司 Method for installing ventilation pipe
CN111550012B (en) * 2020-04-29 2022-02-15 广州市房屋开发建设有限公司 Method for installing ventilation pipe
CN112376849A (en) * 2020-11-30 2021-02-19 北京城建道桥建设集团有限公司 Vertical ventilation pipe installed in narrow space and construction method

Similar Documents

Publication Publication Date Title
CN110206273B (en) Super high-rise vertical shaft air pipe installation process and air pipe device thereof
CN210002786U (en) super high-rise shaft air pipe device
CN109614719B (en) BIM technology-based refrigeration machine room assembly type construction method
CN110440429B (en) Subway arched roof ventilating pipeline assembling construction method
CN108591634B (en) Machine-made glass magnesium composite board air duct construction method
CN111139996A (en) Integrated fireproof heat-insulation assembled smoke-proof and smoke-discharging air pipe and preparation method thereof
CN210486028U (en) Static pressure box structure below grandstand ladder
CN111042573A (en) Construction method and structure for additionally arranging lift apartment sandwich floor without dehumidification operation
CN116927426A (en) Steel skeleton light roof board installation construction method
CN110645696A (en) Heating and ventilation static pressure box structure and construction method thereof
CN102556329B (en) Marine air-conditioner mounting method
CN113123560B (en) Layer-by-layer inverted mounting structure and construction method for ultra-large pipe well chimney
CN106939699B (en) Construction method for galvanized steel sheet waterproof layer on inner side of open type ceramic plate curtain wall
CN112727217B (en) Method for installing oil tank with steel membrane structure in shelter
CN114877128A (en) Air pipe installation method for narrow air shaft
US20210190368A1 (en) Plug for use in a process of forming an insulated register box
CN211369529U (en) A template for expansion joint department
CN203755568U (en) Combined height-adjustable support for overlength roof slab construction
CN206782858U (en) A kind of modularization coal transporting trestle
CN116480087A (en) Construction method of double-layer framework damage-free veneer
JP3177906B2 (en) Preceding partition wall construction method in the ceiling
WO2020134398A1 (en) Wiring device for oxygen belts and acetylene belts for installation of power station boiler
CN213847378U (en) Auxiliary heat dissipation system of high-voltage frequency converter
CN113216561B (en) Construction technology of small-section reinforced concrete air duct