CN209924447U - Connecting structure between concrete pouring formworks of building - Google Patents

Connecting structure between concrete pouring formworks of building Download PDF

Info

Publication number
CN209924447U
CN209924447U CN201920576493.1U CN201920576493U CN209924447U CN 209924447 U CN209924447 U CN 209924447U CN 201920576493 U CN201920576493 U CN 201920576493U CN 209924447 U CN209924447 U CN 209924447U
Authority
CN
China
Prior art keywords
steel
mould
steel mould
die
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920576493.1U
Other languages
Chinese (zh)
Inventor
赵素改
杨凯
张智慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Fushun Industrial Group Co.,Ltd.
Original Assignee
赵素改
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 赵素改 filed Critical 赵素改
Priority to CN201920576493.1U priority Critical patent/CN209924447U/en
Application granted granted Critical
Publication of CN209924447U publication Critical patent/CN209924447U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a concrete placement template connection structure between room, including first steel mould, "T" type structure recess has all been seted up to first steel mould left and right sides outer wall, and a horizontal through-hole has all been seted up to first steel mould upper end both sides, and first steel mould one side is provided with the second steel mould, and second steel mould left and right sides outer wall all is provided with "T" type structure lug, and a horizontal through-hole has all been seted up to second steel mould upper end both sides. This room building concrete placement template connection structure's first steel mould and crisscross the putting of second steel mould, make "T" type structure lug of second steel mould both sides link together the two in "T" type structure recess of first steel mould both sides, make the two can constitute a whole, then two vertical adjacent first steel moulds can alternate in "T" type structure recess of first steel mould and vertical adjacent first steel mould one side through "T" type structure lug of steel angle mould both sides and constitute a whole with vertical adjacent first steel mould.

Description

Connecting structure between concrete pouring formworks of building
Technical Field
The utility model relates to a cast in situ concrete struts technical field, specifically is a connection structure between concrete placement template is built in room.
Background
The concrete pouring refers to the process from pouring concrete into a mold until plasticizing, in the building construction, materials such as concrete are put into the mold to be made into a preset shape, the free height of the concrete is not more than 2m when the concrete is poured, and corresponding measures are taken when the free height of the concrete exceeds 3 m.
The adjacent templates can be connected together by means of external force between the existing concrete pouring templates, so that the templates are relatively complicated in installation and disassembly, a large amount of manpower and time are needed to be spent to support the templates, the work efficiency is not improved, and the slurry explosion phenomenon is easily caused.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a connection structure between concrete placement template is built in room to solve the loaded down with trivial details problem of connection structure between the concrete placement template that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a room building concrete placement template connection structure between, includes first steel mould, "T" type structure recess has all been seted up to first steel mould left and right sides outer wall, and a horizontal through-hole has all been seted up to first steel mould upper end both sides, and first steel mould one side is provided with the second steel mould, and second steel mould left and right sides outer wall all is provided with "T" type structure lug, and a horizontal through-hole has all been seted up to second steel mould upper end both sides, and first steel mould is identical with second steel mould size to second steel mould lug cooperatees with first steel mould recess and is connected, first steel mould (1) and second steel mould (4) through-hole interlude have steel pipe (3), and steel pipe (3) are "U" type structure to steel pipe (3) tip passes through fastener (2) and fixes.
Preferably, a sealing strip is arranged at the joint of the first steel die and the second steel die, and the sealing strip is made of rubber.
Preferably, a steel angle die is arranged between the first steel die and the vertically adjacent first steel die, the outer walls of two sides of the steel angle die are provided with T-shaped structure convex blocks, and the steel angle die convex blocks are matched and connected with the first steel die grooves.
Preferably, the first steel die and the second steel die are matched in through hole position and size.
Preferably, the first steel die and the second steel die are L-shaped structures, and the thickness of the base of the first steel die and the thickness of the base of the second steel die are larger than the thickness of the base of the first steel die and the thickness of the base of the second steel die.
Preferably, the outer wall of the end part of the steel pipe and the inner wall of the fastener are both in a threaded structure, and the threads of the outer wall and the inner wall of the fastener are matched.
Compared with the prior art, the beneficial effects of the utility model are that: the first steel mould and the second steel mould of the connecting structure between the house building concrete pouring formworks are arranged in a staggered way, so that T-shaped structure convex blocks at two sides of the second steel mould can be inserted into T-shaped structure grooves at two sides of the first steel mould to connect the first steel mould and the second steel mould together to form a whole, then two vertically adjacent first steel moulds can be inserted into the T-shaped structure grooves at one side of the first steel mould and the vertically adjacent first steel mould through the T-shaped structure convex blocks at two sides of the steel angle mould to form a whole with the vertically adjacent first steel mould, the mounting and the connecting of the device are more convenient, the working efficiency of concrete pouring formwork supporting is improved, the integrity of the device is enhanced through the insertion of every two steel moulds, the phenomenon of grout explosion can be avoided, and the connecting gap between the first steel mould and the second steel mould can be sealed through a sealing strip arranged at the connecting position of the first steel mould and the second steel mould, so that a relatively sealed environment can be formed inside the slurry tank, and the slurry leakage phenomenon is avoided.
Drawings
FIG. 1 is a schematic view of the connection structure between concrete pouring formworks of the house building of the present invention;
FIG. 2 is a schematic view of the connection structure between the first steel form and the vertically adjacent first steel form of the connection structure between the concrete pouring formworks of the house building of the present invention;
FIG. 3 is a schematic structural view of a sealing strip at the joint of a first steel mould and a second steel mould of the connection structure between concrete pouring formworks of the building of the utility model;
FIG. 4 is a schematic side view of a first steel form of a connection structure between concrete pouring formworks of a house building of the present invention;
fig. 5 is the utility model relates to a connection structure steel pipe and fastener threaded connection sectional structure sketch map between concrete placement template is built in room.
In the figure: 1. the steel angle die comprises a first steel die, 2, a fastener, 3, a steel pipe, 4, a second steel die, 5, a steel angle die, 6 and a sealing strip.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-5, the present invention provides a technical solution: a house building concrete pouring template connection structure comprises a first steel mould 1, wherein T-shaped structure grooves are formed in the outer walls of the left side and the right side of the first steel mould 1, a transverse through hole is formed in each of the two sides of the upper end of the first steel mould 1, a steel angle mould 5 is arranged between the first steel mould 1 and a vertically adjacent first steel mould 1, T-shaped structure lugs are arranged on the outer walls of the two sides of the steel angle mould 5, the steel angle mould 5 lugs are matched and connected with the grooves of the first steel mould 1, the first steel mould 1 and the vertically adjacent first steel mould 1 can be connected together to form a whole through the steel angle mould 5, accordingly, grout explosion can not occur at the edge of the device, a second steel mould 4 is arranged on one side of the first steel mould 1, T-shaped structure lugs are arranged on the outer walls of the left side and the right side of the second steel mould 4, a transverse through hole is formed in each of the two sides of the upper end of the second steel mould 4, the first steel mould 1 and the second steel mould 4 are L-shaped structures, the thickness of the base of the first steel mould 1 and the second steel mould 4 is larger than that of the first steel mould 1 and the second steel mould 4, the first steel mould 1 and the second steel mould 4 of the structure can be placed on the ground without being supported by other components, the installation work of the first steel mould 1 and the second steel mould 4 is convenient, the first steel mould 1 is identical with the second steel mould 4 in size, a convex block of the second steel mould 4 is matched and connected with a groove of the first steel mould 1, the through holes of the first steel mould 1 and the second steel mould 4 are corresponding in position and identical in size, steel pipes 3 are inserted in the through holes of the first steel mould 1 and the second steel mould 4, the steel pipes 3 are U-shaped structures, the end parts of the steel pipes 3 are fixed by fasteners 2, the outer walls of the end parts of the steel pipes 3 are thread structures, the threads of the steel pipes 3 are matched, the structures are inserted at the upper ends of the first steel mould 1 and the second steel mould 4, the steel mould structure can prevent the first steel mould 1 and the second steel mould 4 from moving up and down in the first steel mould 1 under the vibration of the concrete, so that the first steel mould 1 and the second steel mould 4 are staggered up and down, the first steel mould 1 and the second steel mould 4 can be always positioned on the same plane through the steel pipe 3, the sealing strip 6 is arranged at the joint of the first steel mould 1 and the second steel mould 4, the sealing strip 6 is made of rubber material, the structure leads T-shaped structure lugs at two sides of the second steel mould 4 to be inserted into T-shaped structure grooves at two sides of the first steel mould 1 to connect the first steel mould 1 and the second steel mould 4 through sequentially and alternately placing the first steel mould 1 and the second steel mould 4, not only the device is more convenient and fast in installation and connection, the working efficiency of a concrete pouring template can be improved, but also the first steel mould 1 and the second steel mould 4 can form a whole to strengthen the integrity of the device, the sealing strip 6 arranged at the joint of the first steel mould 1 and the second steel mould 4 can seal the joint gap between the first steel mould and the second steel mould, so that a relatively sealed environment can be formed inside the sealing strip, and the phenomenon of slurry leakage is avoided.
The working principle is as follows: when the connecting structure between the house building concrete pouring formworks is installed, firstly, a first steel mould 1 is placed on the outer wall of a tied steel reinforcement cage, then a second steel mould 4 is lifted to the top end of the first steel mould 1, then a T-shaped structure lug on one side of the second steel mould 4 is downwards inserted into a T-shaped structure groove of the first steel mould 1, the connecting outer wall of the first steel mould 1 and the second steel mould 4 is attached together through a sealing strip 6, then a steel pipe 3 is inserted into a through hole of the first steel mould 1 and the second steel mould 4, then the end part of the steel pipe is fixed through a fastener 2, then the first steel mould 1 is lifted to the top end of the second steel mould 4, the T-shaped structure groove of the first steel mould 1 is downwards inserted into the T-shaped structure lug on the other side of the second steel mould 4, then the connection work of the remaining first steel mould 1 and the second steel mould 4 is completed according to the method, after the connection of the transverse first steel mould 1 and the second steel mould 4 is completed, finishing the vertical connection work of the first steel die 1 and the second steel die 4, vertically placing the first steel die 1 on one side of the first steel die 1 adjacent to the transverse row to enable the first steel die 1 to be attached to the outer wall of the first steel die 1 adjacent to the transverse row, inserting the T-shaped structure convex blocks on two sides of the steel angle die 5 into the grooves on one side of the first steel die 1 and the first steel die 1 adjacent to the transverse row to fixedly connect the first steel die 1 and the second steel die together, and finishing the vertical connection work of the remaining first steel die 1 and the second steel die 4 according to the method, which is the installation work process of the connecting structure between the concrete pouring formworks of the building.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.

Claims (6)

1. The utility model provides a connection structure between concrete placement template in room, its characterized in that: including first steel mould (1), "T" type structure recess has all been seted up to first steel mould (1) left and right sides outer wall, a horizontal through-hole has all been seted up to first steel mould (1) upper end both sides, and first steel mould (1) one side is provided with second steel mould (4), and second steel mould (4) left and right sides outer wall all is provided with "T" type structure lug, and a horizontal through-hole has all been seted up to second steel mould (4) upper end both sides, and first steel mould (1) is identical with second steel mould (4) size to second steel mould (4) lug cooperatees with first steel mould (1) recess and is connected, steel pipe (3) have been interlude in first steel mould (1) and second steel mould (4) through-hole, steel pipe (3) are "U" type structure to steel pipe (3) tip passes through fastener (2) and fixes.
2. The concrete casting form connection structure for house buildings according to claim 1, wherein: the sealing strip is characterized in that a sealing strip (6) is arranged at the joint of the first steel die (1) and the second steel die (4), and the sealing strip (6) is made of rubber.
3. The concrete casting form connection structure for house buildings according to claim 1, wherein: be provided with steel angle mould (5) between first steel mould (1) and the vertical adjacent first steel mould (1), steel angle mould (5) both sides outer wall all is provided with "T" type structure lug, and steel angle mould (5) lug and first steel mould (1) recess cooperate to be connected.
4. The concrete casting form connection structure for house buildings according to claim 1, wherein: the first steel die (1) corresponds to the second steel die (4) in through hole position and is identical in size.
5. The concrete casting form connection structure for house buildings according to claim 1, wherein: the first steel die (1) and the second steel die (4) are of L-shaped structures, and the thickness of the base of the first steel die (1) and the thickness of the base of the second steel die (4) are larger than the thickness of the first steel die (1) and the thickness of the base of the second steel die (4).
6. The concrete casting form connection structure for house buildings according to claim 4, wherein: the outer wall of the end part of the steel pipe (3) and the inner wall of the fastener (2) are both of a threaded structure, and the threads of the outer wall and the inner wall are matched.
CN201920576493.1U 2019-04-25 2019-04-25 Connecting structure between concrete pouring formworks of building Active CN209924447U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920576493.1U CN209924447U (en) 2019-04-25 2019-04-25 Connecting structure between concrete pouring formworks of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920576493.1U CN209924447U (en) 2019-04-25 2019-04-25 Connecting structure between concrete pouring formworks of building

Publications (1)

Publication Number Publication Date
CN209924447U true CN209924447U (en) 2020-01-10

Family

ID=69075202

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920576493.1U Active CN209924447U (en) 2019-04-25 2019-04-25 Connecting structure between concrete pouring formworks of building

Country Status (1)

Country Link
CN (1) CN209924447U (en)

Similar Documents

Publication Publication Date Title
CN104631512A (en) Post-cast strip beam and slab construction method adopting formwork hanging method
CN112359994A (en) CL heat preservation system construction method
CN215106098U (en) Prefabricated post connection structure
CN207177286U (en) Add region mould after fabricated shear wall is reserved
CN209924447U (en) Connecting structure between concrete pouring formworks of building
CN211817040U (en) Slurry leakage prevention structure at splicing part of assembled laminated slab
CN107558483A (en) A kind of building foundation and its construction method for installing wallboard
CN109356126B (en) Semi-prefabricated gallery structure and gallery construction method
CN216787229U (en) Basement outer wall post-cast strip assembled shutoff steel sheet structure
CN214364434U (en) Assembled constructional column suitable for prefabricated wallboard of frame construction
CN211691450U (en) Slurry leakage prevention device for prefabricated side embedded steel bars of laminated slab beam
CN210238440U (en) Simple water stop template fixing structure
CN204645615U (en) Top board rubber watertight strip fixed mould
CN106013254B (en) A kind of construction method of the concrete works swaging die with skeleton
CN108843016B (en) Shear wall template internal stay and tie bar combined type component and method
CN108442698B (en) Deformation joint split bolt pvc sleeve plugging method and plugging fixing sleeve
CN202745370U (en) Concrete reserved hole without formwork removal
CN104847090A (en) Construction method of small-size section ventilating duct
CN205935312U (en) Panel house wall's reinforced concrete frame structure
CN220814887U (en) Contain waterstop side wall end wall structure template
CN219219779U (en) Wall pouring device
CN220666918U (en) Cast-in-situ plastic formwork for dense rib floor concrete
CN218622339U (en) Prefabricated part for plugging post-cast strip of basement outer wall
CN210562802U (en) Portable is full of permanent stone shear force wall structure and is full of permanent stone shear force wall
CN218028146U (en) Prefabricated assembled template that foundation engineering used

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20211117

Address after: 450000 No. 325, floor 26, unit 2, building 1, No. 59, East Street, Guancheng Hui District, Zhengzhou City, Henan Province

Patentee after: Henan Fushun Industrial Group Co.,Ltd.

Address before: 450000 room 2203, unit 2, building 8, yard 2, Mianfang West Road, Zhongyuan District, Zhengzhou City, Henan Province

Patentee before: Zhao Sugai

TR01 Transfer of patent right