CN209907370U CN201920340203.3U CN201920340203U CN209907370U CN 209907370 U CN209907370 U CN 209907370U CN 201920340203 U CN201920340203 U CN 201920340203U CN 209907370 U CN209907370 U CN 209907370U
Authority
CN
China
Prior art keywords
steel
pipe pile
plate
installation
arc
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920340203.3U
Other languages
Chinese (zh)
Inventor
姚建峰
赵�卓
吴铭
孔德盈
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xingtu Co ltd
Original Assignee
Zhejiang Emerging Native Bridge Temporary Steel Structural Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Emerging Native Bridge Temporary Steel Structural Engineering Co Ltd filed Critical Zhejiang Emerging Native Bridge Temporary Steel Structural Engineering Co Ltd
Priority to CN201920340203.3U priority Critical patent/CN209907370U/en
Application granted granted Critical
Publication of CN209907370U publication Critical patent/CN209907370U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

A mounting structure is stabilized to steel-pipe pile for steel-pipe bridge, including embracing hoop spare, spreader bar, diagonal brace, the hoop spare cover is established at the steel-pipe pile and is adopted the fastener fastening, and every steel-pipe pile is equipped with two at least embracing hoop spare, is equipped with the spreader bar between the adjacent steel-pipe pile, and the spreader bar both ends are connected with the hoop spare of establishing on the steel-pipe pile respectively, and the diagonal brace both ends are connected with the spreader bar respectively.

Description

Steel pipe pile stable installation structure for steel bridge beam
Technical Field
The utility model relates to a mounting structure is stabilized to steel-pipe pile for steel bridge roof beam.
Background
In the current foundation construction engineering of China, a large number of pile foundations of prestressed concrete pipe piles or steel pipe piles are adopted, the distance of the existing steel pipe piles driven into the water for enhancing the stability of the existing steel pipe piles is deep, otherwise, the pile foundations which adopt the steel pipe piles for bearing cannot meet the requirement of bearing capacity, and the driving cost is higher when the pile foundations are deeper.
SUMMERY OF THE UTILITY MODEL
The utility model aims to overcome the not enough of prior art existence, provide and to dismantle even as an organic whole between each steel-pipe pile to the steel-pipe pile stable erection structure who is used for the steel-pipe bridge roof beam of reinforcing stability.
A mounting structure is stabilized to steel-pipe pile for steel-pipe bridge roof beam, including embracing hoop spare, spreader bar, diagonal brace, the staple bolt sleeve is established at the steel-pipe pile and is adopted the fastener fastening, and every steel-pipe pile is equipped with two at least embracing hoop spare, is equipped with the spreader bar between the adjacent steel-pipe pile, and the spreader bar both ends are connected with the staple bolt spare of establishing on the steel-pipe pile respectively, and the diagonal brace both ends are connected with the spreader bar respectively.
The hoop comprises arc plates, one ends of the two arc plates are connected in a rotating mode, the other ends of the two arc plates are bent outwards to form flanges, holes are formed in the flanges, and the positions of the holes in the two flanges are corresponding.
Wherein, a connecting plate is arranged between the flanging and the outer wall of the arc-shaped plate, and a through hole is arranged on the connecting plate; the arc-shaped bolt comprises an arc-shaped plate and is characterized by further comprising a U-shaped bolt piece, wherein the U-shaped bolt piece comprises two bolt arms, one ends of the two bolt arms are fixedly connected, the other ends of the two bolt arms are open, and the two bolt arms are respectively embedded into through holes of a connecting plate arranged on the arc-shaped plate.
Wherein, be equipped with an otic placode on the horizontal stay bar, be equipped with a through-hole on the otic placode.
Wherein, the both ends of horizontal stay are equipped with first mounting panel respectively, and the outer wall of arc is equipped with the second mounting panel, are equipped with the clearance that can supply first mounting panel embedding between two second mounting panels, and first mounting panel and second mounting panel all are equipped with the through-hole, and the round pin axle is worn to establish the through-hole.
Compare solution in prior art, the utility model discloses the advantage is: the utility model can effectively improve the stability of the steel pipe piles, and the steel pipe piles are connected into a whole; the hooping piece and the steel pipe pile are detachably connected, and recycling can be achieved.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a schematic structural view of the hoop member of the present invention.
Detailed Description
The invention will be further explained by the embodiments with reference to the drawings.
Referring to fig. 1 to 2, a steel-pipe pile stabilizes mounting structure for steel-pipe bridge roof beam, including embracing hoop spare 1, spreader bar 2, diagonal brace 3, embrace hoop spare 1 cover and establish at steel-pipe pile 4 and adopt the fastener fastening, every steel-pipe pile 4 is equipped with two at least embracing hoop spare 1, is equipped with spreader bar 2 between the adjacent steel- pipe pile 4, and 2 both ends of spreader bar are connected with the hoop spare 1 of establishing on steel-pipe pile 4 respectively, and 3 both ends of diagonal brace are connected with spreader bar 2 respectively. Adopt horizontal stay bar 2, diagonal brace 3 to link as an organic wholely between adjacent steel-pipe pile 4 in this embodiment, overall structure is reliable and stable, has formed a whole between whole steel-pipe pile 4 basis, and after the use, the hoop member 1 can be dismantled with steel-pipe pile 4 to can realize reuse.
This embodiment the hoop member 1 includes the arc 11, and the one end of two arcs 11 is rotated and is connected, and the outside bending type in other end of two arcs 11 forms turn-ups 12, is equipped with trompil 120 on the turn-ups 12, and the trompil 120 position on two turn-ups 12 is corresponding, thereby the fastener wears to establish trompil 120 fastening installation.
In the embodiment, a connecting plate 5 is arranged between the turned-over edge 12 and the outer wall of the arc-shaped plate 11, and a through hole 50 is arranged on the connecting plate 5; still include a U type bolt piece 6, U type bolt piece 6 includes two bolt arms 61, and two bolt arms 61 one end stationary phase link, two bolt arms 61 other ends are open, and two bolt arms 61 imbed the through-hole 50 that sets up connecting plate 5 on arc 11 respectively. The original connection mode can be reinforced after the U-shaped bolt piece 6 is embedded into the through hole 50.
In this embodiment, the cross brace 2 is provided with an ear plate 21, and the ear plate 21 is provided with a through hole 50 ".
In this embodiment, two ends of the transverse supporting rod 2 are respectively provided with a first mounting plate 22, the outer wall of the arc plate 11 is provided with a second mounting plate 23, a gap for embedding the first mounting plate 22 is formed between the two second mounting plates 23, the first mounting plate 22 and the second mounting plate 23 are both provided with through holes 50 ', and the pin 7 penetrates through the through holes 50'. This structure can realize the quick assembly disassembly of spreader bar 2.
The foregoing is only a preferred embodiment of the present invention, and it should be understood that other modifications and adaptations can be made by those skilled in the art without departing from the principles of the present invention, and are intended to be within the scope of the invention as defined by the appended claims.

Claims (5)

1. A mounting structure is stabilized to steel-pipe pile for steel bridge roof beam, characterized by, including embracing hoop spare, spreader bar, diagonal brace, the hoop spare cover is established at the steel-pipe pile and is adopted the fastener fastening, and every steel-pipe pile is equipped with two at least embracing hoop spare, is equipped with the spreader bar between the adjacent steel-pipe pile, and the spreader bar both ends are connected with the hoop spare of establishing on the steel-pipe pile respectively, and the diagonal brace both ends are connected with the spreader bar respectively.
2. The stable installation structure of steel-pipe pile for steel bridge of claim 1, wherein said anchor ear member comprises two curved plates, one end of each curved plate is connected with the other end of each curved plate, the other end of each curved plate is bent outwards to form a flange, the flange is provided with openings, and the openings on the flanges are corresponding.
3. The stable steel pipe pile installation structure for the steel bridge as claimed in claim 2, wherein a connection plate is provided between the flange and the outer wall of the arc plate, the connection plate being provided with through holes; the arc-shaped bolt comprises an arc-shaped plate and is characterized by further comprising a U-shaped bolt piece, wherein the U-shaped bolt piece comprises two bolt arms, one ends of the two bolt arms are fixedly connected, the other ends of the two bolt arms are open, and the two bolt arms are respectively embedded into through holes of a connecting plate arranged on the arc-shaped plate.
4. The stable steel pipe pile installing structure for the steel bridge girder according to claim 1, wherein the cross brace is provided with an ear plate, and the ear plate is provided with a through hole.
5. The stable installation structure of steel-pipe pile for steel bridge as claimed in claim 1, wherein the transverse supporting rod is provided at its both ends with first installation plates, the outer wall of the arc-shaped plate is provided with second installation plates, a gap for the first installation plate to be inserted is provided between the two second installation plates, the first installation plate and the second installation plate are provided with through holes, and the pin shaft is inserted through the through holes.
CN201920340203.3U 2019-03-18 2019-03-18 Steel pipe pile stable installation structure for steel bridge beam Active CN209907370U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920340203.3U CN209907370U (en) 2019-03-18 2019-03-18 Steel pipe pile stable installation structure for steel bridge beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920340203.3U CN209907370U (en) 2019-03-18 2019-03-18 Steel pipe pile stable installation structure for steel bridge beam

Publications (1)

Publication Number Publication Date
CN209907370U true CN209907370U (en) 2020-01-07

Family

ID=69031655

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920340203.3U Active CN209907370U (en) 2019-03-18 2019-03-18 Steel pipe pile stable installation structure for steel bridge beam

Country Status (1)

Country Link
CN (1) CN209907370U (en)

Similar Documents

Publication Publication Date Title
CN112554337A (en) Self-reset type rigidity self-adaptive control assembly type beam-column node
CN111218941A (en) Combined type section steel supporting rod piece
CN111022072A (en) Combined joint for reinforcing secondary lining of tunnel constructed by mining method and mounting method
KR100954967B1 (en) Prefab apparatus for reinforcing head of pile
CN209907570U (en) Assembled frame beam column node that steel sheet and reinforcement are connected
CN209907370U (en) Steel pipe pile stable installation structure for steel bridge beam
CN210002443U (en) prefabricated combined reinforced concrete shaft
CN112523348A (en) Quick erection column connecting piece
KR101575789B1 (en) Reinforcing bar assembly for concrete pile reinforcement and concrete pile assembly including the same
CN213417843U (en) Foundation pit support structure convenient to disassemble and assemble
CN209816887U (en) Highway bridge construction cofferdam device
CN107761712B (en) A kind of connecting elements of bracing members and steel purlin
CN111119026B (en) Assembled steel-concrete combined structure for reinforcing long-span box type arch bridge
CN209704139U (en) A kind of vertical storehouse of the prefabricated assembling type reinforced concrete with tenon structure
KR20120021977A (en) Wave type steel plate tunnel
CN216739594U (en) Tubular pile subassembly
CN210736042U (en) Novel tower crane foundation structure
CN219886907U (en) Can turnover assembled steel connection tower crane foundation of use
CN212561535U (en) Combined type section steel supporting rod piece
CN215630622U (en) Quick erection column connecting piece
CN217998075U (en) Assembled underground structure
CN220301326U (en) Pile body structure of concrete pipe pile
CN216640596U (en) Assembled combination concrete porous sheet pile supports reinforced structure
CN215926046U (en) Combined assembled plate type foundation
CN215561876U (en) Bracket device for mounting pier steel bars

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 314000 Room 301, 251 Chengxiu Road, Xincheng street, Xiuzhou District, Jiaxing City, Zhejiang Province

Patentee after: Xingtu Co.,Ltd.