CN209873807U - Suspension structure of deep foundation pit engineering underground socket concrete pipe - Google Patents

Suspension structure of deep foundation pit engineering underground socket concrete pipe Download PDF

Info

Publication number
CN209873807U
CN209873807U CN201920437688.8U CN201920437688U CN209873807U CN 209873807 U CN209873807 U CN 209873807U CN 201920437688 U CN201920437688 U CN 201920437688U CN 209873807 U CN209873807 U CN 209873807U
Authority
CN
China
Prior art keywords
concrete pipe
socket
joint
hoop
foundation pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920437688.8U
Other languages
Chinese (zh)
Inventor
李钟�
净少敏
李闯
刘海涛
周磊
郭海华
宋榘
齐飞
赵越
钟志亮
秦兴武
郭佳柯
何文辉
赵卫星
何茂周
李方利
许彦旭
侯建平
何永健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
China Railway Construction Kunlun Metro Investment Construction Management Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
China Railway Construction Kunlun Metro Investment Construction Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd, China Railway Construction Kunlun Metro Investment Construction Management Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201920437688.8U priority Critical patent/CN209873807U/en
Application granted granted Critical
Publication of CN209873807U publication Critical patent/CN209873807U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A suspension structure of a deep foundation pit engineering underground socket concrete pipe is characterized in that a socket concrete pipe joint is wrapped through a reinforced concrete hoop, the socket concrete pipe is suspended on a steel box girder above the socket concrete pipe through a steel wire rope pre-embedded in the reinforced concrete hoop, the steel wire rope is tightened through a wire tightening buckle and a clamping head, suspension stress conversion is completed, when the suspension structure is implemented, foundation pit earthwork is excavated to the bottom of the underground socket concrete pipe, a groove is dug at the joint of the underground socket concrete pipe, circumferential main ribs, longitudinal and horizontal distribution ribs and a template are installed, the steel wire rope is pre-embedded, and then the reinforced concrete hoop is poured; installing and erecting a steel box girder on the foundation pit support structure; the steel wire rope is hung to the steel box girder, and the steel wire rope is tightened through the wire tightening buckle and the chuck, so that the stress conversion of the socket concrete pipe hanging is completed; after the stress conversion is completed, digging out all soil below the socket concrete pipe; and a plurality of suspension structures between the foundation pit enclosing structures form a suspension system.

Description

Suspension structure of deep foundation pit engineering underground socket concrete pipe
Technical Field
The utility model relates to a deep basal pit engineering pipeline suspends protection construction technical field in midair, concretely relates to suspension structure of deep basal pit engineering underground socket joint concrete pipe.
Background
In the municipal deep foundation pit engineering construction, the underground pipelines are complex, and the pipelines crossing the foundation pit are generally treated by an in-situ suspension protection method.
Because the socket joint concrete pipe is flexible joint, take place to warp easily and destroy and lead to the water logging foundation ditch, arouse the foundation ditch incident. At present, a common method is to convert a concrete pipe into a steel pipe by adopting a pipe jacking method and then suspend the steel pipe, and the method has high construction cost and great influence on the construction period.
Disclosure of Invention
In order to overcome the not enough of above-mentioned prior art, the utility model aims at providing a suspension structure of deep basal pit engineering underground socket joint concrete pipe does not need to replace the concrete pipe for the steel pipe. By adopting the cast-in-place reinforced concrete pipe hoop, the flexible joint of the socket concrete pipe is converted into the rigid joint and then suspended, and the concrete pipe has the characteristics of simple operation, safe use and cost saving. The utility model discloses the protection construction suspends in midair of all kinds of underground socket joint concrete pipe can be applicable to.
In order to realize the purpose, the utility model discloses a technical scheme is:
the utility model provides a suspension structure of deep basal pit engineering underground socket joint concrete pipe, includes the tight line knot, wraps up socket joint concrete coupling through reinforced concrete hoop, through the wire rope of pre-burying in reinforced concrete hoop, suspends socket joint concrete pipe in midair on the steel box girder of its top to tighten up wire rope through tight line knot, dop, accomplish and suspend the atress conversion in midair.
The suspension system for the underground socket concrete pipe of the deep foundation pit engineering is characterized in that the socket concrete pipe joint is wrapped by the reinforced concrete hoop, so that the flexible joint of the socket concrete pipe is converted into a rigid joint.
The reinforced concrete hoop is formed by pouring concrete into a steel reinforcement framework inside the reinforced concrete hoop, and the steel reinforcement framework comprises main reinforcements and longitudinal and horizontal distribution reinforcements which are arranged in the circumferential direction.
The utility model has the advantages that:
the utility model has the characteristics of easy operation, safe in utilization, saving cost compare with conventional system, only need handle the joint of socket joint concrete pipe, need not the process of push pipe conversion again, practiced thrift construction cost to easy operation is easy-to-use, and construction speed is fast. The method is suitable for suspension protection construction of various underground socket concrete pipes.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic diagram of the system of the present invention;
FIG. 3 is a schematic view of the reinforced concrete hoop structure of the present invention
Wherein, 1 is a wire fastening buckle; 2 is a clamping head; 3 is a steel wire rope; 4 is a reinforced concrete hoop; 5 is a steel box girder; 6 is a socket concrete pipe; and 7, a foundation pit support structure.
Detailed Description
The invention is further described below with reference to the accompanying drawings:
as shown in fig. 1, 2 and 3, the suspension structure of the underground socket concrete pipe of the deep foundation pit engineering comprises a wire fastening buckle 1 and is characterized in that a socket concrete pipe 6 joint is wrapped through a reinforced concrete hoop 4, the socket concrete pipe 6 is suspended on a steel box girder 5 above the socket concrete pipe through a steel wire rope 3 pre-embedded in the reinforced concrete hoop 4, and the steel wire rope 3 is tightened through the wire fastening buckle 1 and a clamping head 2 to complete suspension stress conversion.
The reinforced concrete hoop 4 wraps the socket concrete pipe 6 joint, so that the flexible joint of the socket concrete pipe 6 is converted into a rigid joint.
The reinforced concrete hoop 4 is formed by pouring concrete into a steel reinforcement framework inside the reinforced concrete hoop, and the steel reinforcement framework comprises a circumferential main reinforcement 7 and a longitudinal horizontal distribution reinforcement 8.
The wrapping length of the joint of the reinforced concrete hoop 4 opposite to the socket concrete pipe 6 is not less than 50cm, and the minimum thickness is not less than 30 cm.
A construction method of a suspension structure of an underground socket concrete pipe of deep foundation pit engineering comprises the following steps:
the method comprises the following steps: excavating the earthwork of the foundation pit to the bottom of the underground socket pipe, excavating a groove at the joint of the underground socket concrete pipe 6, installing a circumferential main rib 7, a longitudinal horizontal distribution rib 8 and a template, pre-embedding a steel wire rope 3, and then pouring a reinforced concrete hoop 4;
step two: installing and erecting a steel box girder 5 on the foundation pit support structure 7;
step three: the steel wire rope 3 is hung to the steel box girder 5, and the steel wire rope 3 is tightened through the wire tightening buckle 1 and the chuck 2 to complete the stress conversion of the suspension of the socket concrete pipe 6;
step four: after the stress conversion is completed, digging out all soil below the socket concrete pipe 6;
step five: and a plurality of suspension structures between the foundation pit enclosing structures 7 form a suspension system.

Claims (4)

1. The utility model provides a suspension structure of deep basal pit engineering underground socket joint concrete pipe, includes that the tight line detains (1), its characterized in that, wraps up socket joint concrete pipe (6) joint through reinforced concrete hoop (4), through pre-buried wire rope (3) in reinforced concrete hoop (4), suspends socket joint concrete pipe (6) in midair on steel box girder (5) of its top to detain (1), dop (2) tighten up wire rope (3) through the tight line, accomplish and suspend the atress conversion in midair.
2. The suspension structure of the underground socket concrete pipe of the deep foundation pit engineering according to the claim 1, characterized in that the reinforced concrete hoop (4) wraps the joint of the socket concrete pipe (6) to convert the flexible joint of the socket concrete pipe (6) into a rigid joint.
3. The suspension structure of the underground socket concrete pipe of the deep foundation pit engineering according to the claim 1, characterized in that the reinforced concrete hoop (4) is formed by pouring concrete into the reinforced skeleton inside the reinforced concrete hoop, and the reinforced skeleton comprises a circumferential main rib (7) and a longitudinal horizontal distribution rib (8).
4. The suspension structure of the underground socket concrete pipe of the deep foundation pit engineering according to the claim 1, characterized in that the wrapping length of the joint of the opposite socket concrete pipe (6) of the reinforced concrete hoop (4) is not less than 50cm, and the minimum thickness is not less than 30 cm.
CN201920437688.8U 2019-04-02 2019-04-02 Suspension structure of deep foundation pit engineering underground socket concrete pipe Active CN209873807U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920437688.8U CN209873807U (en) 2019-04-02 2019-04-02 Suspension structure of deep foundation pit engineering underground socket concrete pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920437688.8U CN209873807U (en) 2019-04-02 2019-04-02 Suspension structure of deep foundation pit engineering underground socket concrete pipe

Publications (1)

Publication Number Publication Date
CN209873807U true CN209873807U (en) 2019-12-31

Family

ID=68957969

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920437688.8U Active CN209873807U (en) 2019-04-02 2019-04-02 Suspension structure of deep foundation pit engineering underground socket concrete pipe

Country Status (1)

Country Link
CN (1) CN209873807U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109881679A (en) * 2019-04-02 2019-06-14 中铁十二局集团有限公司 A kind of overhung construction and construction method of deep-foundation pit engineering underground socket joint pipe of concrete

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109881679A (en) * 2019-04-02 2019-06-14 中铁十二局集团有限公司 A kind of overhung construction and construction method of deep-foundation pit engineering underground socket joint pipe of concrete

Similar Documents

Publication Publication Date Title
CN104499504B (en) A kind of road inspection well and construction method thereof
CN106351670B (en) A kind of closed pre support tunnel structure
CN209686444U (en) A kind of structure for protecting electric power pipe culvert using top suspention plus lower support dual in situ
CN205636838U (en) Deviational survey pipe mouth of pipe reinforcing apparatus
CN105544603A (en) Construction method for underground pipeline reinforcement
CN209873807U (en) Suspension structure of deep foundation pit engineering underground socket concrete pipe
CN210766754U (en) Recoverable prestressed anchorage cable stock supporting construction
CN109881679A (en) A kind of overhung construction and construction method of deep-foundation pit engineering underground socket joint pipe of concrete
CN103233432B (en) Bailey beam reverse lifting support system and construction method thereof
CN206408611U (en) A kind of adaptive Recyclable anchor rope system
CN107542086B (en) Anchor cable construction method for filling slope
CN103422499B (en) Casing construction method inside and outside a kind of permafrost region pile foundation
CN211037053U (en) Suspension protection structure for pipe well
CN110685234B (en) Construction method of corrugated steel pipe culvert
CN110629792B (en) Splicing construction method for corrugated steel pipe gallery
CN104018499A (en) Grouting method capable of saving grouting amount on pre-stressed anchor cable tension section
CN106838463A (en) The fastener inserts and usage of longitudinal integral rigidity after raising rectangular top plumber
CN208219638U (en) A kind of deep foundation pit precast stake
CN203821381U (en) Rectangular pre-stressed filling pile
CN203741842U (en) SMW construction method profile steel pullout auxiliary device
CN207092104U (en) A kind of steel-pipe pile attachment structure
CN204756295U (en) PCCP (prestressed concrete cylinder pipe) way accident processing apparatus
CN106193279A (en) Agent structure wall prestressed structure and time building method of agent structure wall
CN108644471B (en) Pipeline sliding transportation structure system on large-area water area and construction method thereof
CN103470275A (en) Method for excavating and supporting large-span level-crossing fork of underground chamber

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant