CN209873807U - A Suspension Structure for Underground Socket Concrete Pipes in Deep Foundation Pit Engineering - Google Patents

A Suspension Structure for Underground Socket Concrete Pipes in Deep Foundation Pit Engineering Download PDF

Info

Publication number
CN209873807U
CN209873807U CN201920437688.8U CN201920437688U CN209873807U CN 209873807 U CN209873807 U CN 209873807U CN 201920437688 U CN201920437688 U CN 201920437688U CN 209873807 U CN209873807 U CN 209873807U
Authority
CN
China
Prior art keywords
socket
foundation pit
socket concrete
underground
concrete pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920437688.8U
Other languages
Chinese (zh)
Inventor
李钟�
净少敏
李闯
刘海涛
周磊
郭海华
宋榘
齐飞
赵越
钟志亮
秦兴武
郭佳柯
何文辉
赵卫星
何茂周
李方利
许彦旭
侯建平
何永健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
China Railway Construction Kunlun Metro Investment Construction Management Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
China Railway Construction Kunlun Metro Investment Construction Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Fourth Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd, China Railway Construction Kunlun Metro Investment Construction Management Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN201920437688.8U priority Critical patent/CN209873807U/en
Application granted granted Critical
Publication of CN209873807U publication Critical patent/CN209873807U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

A suspension structure of a deep foundation pit engineering underground socket concrete pipe is characterized in that a socket concrete pipe joint is wrapped through a reinforced concrete hoop, the socket concrete pipe is suspended on a steel box girder above the socket concrete pipe through a steel wire rope pre-embedded in the reinforced concrete hoop, the steel wire rope is tightened through a wire tightening buckle and a clamping head, suspension stress conversion is completed, when the suspension structure is implemented, foundation pit earthwork is excavated to the bottom of the underground socket concrete pipe, a groove is dug at the joint of the underground socket concrete pipe, circumferential main ribs, longitudinal and horizontal distribution ribs and a template are installed, the steel wire rope is pre-embedded, and then the reinforced concrete hoop is poured; installing and erecting a steel box girder on the foundation pit support structure; the steel wire rope is hung to the steel box girder, and the steel wire rope is tightened through the wire tightening buckle and the chuck, so that the stress conversion of the socket concrete pipe hanging is completed; after the stress conversion is completed, digging out all soil below the socket concrete pipe; and a plurality of suspension structures between the foundation pit enclosing structures form a suspension system.

Description

一种深基坑工程地下承插混凝土管的悬吊结构A Suspension Structure for Underground Socket Concrete Pipes in Deep Foundation Pit Engineering

技术领域technical field

本实用新型涉及深基坑工程管线悬吊保护施工技术领域,具体涉及一种深基坑工程地下承插混凝土管的悬吊结构。The utility model relates to the technical field of pipeline suspension protection construction in deep foundation pit engineering, in particular to a suspension structure for underground concrete pipes in deep foundation pit engineering.

背景技术Background technique

市政深基坑工程施工中,地下管线情况复杂,对横穿基坑的管线一般采用原位悬吊保护的方法处理。In the construction of municipal deep foundation pit engineering, the situation of underground pipelines is complicated, and the method of in-situ suspension protection is generally adopted for the pipelines crossing the foundation pit.

由于承插混凝土管为软性接头,容易发生变形破坏导致水淹基坑,引起基坑安全事故。目前通常的作法是采用顶管法将混凝土管转换成钢管再进行悬吊,此方法不仅施工成本高,而且对工期影响大。Since the socket concrete pipe is a soft joint, it is prone to deformation and damage, resulting in flooding of the foundation pit and causing safety accidents in the foundation pit. The current common practice is to use the pipe jacking method to convert concrete pipes into steel pipes and then suspend them. This method not only has high construction costs, but also has a great impact on the construction period.

发明内容Contents of the invention

为了克服上述现有技术的不足,本实用新型的目的是提供一种深基坑工程地下承插混凝土管的悬吊结构,不需要将混凝土管置换为钢管。通过采用现浇钢筋混凝土管箍,将承插混凝土管的软性接头转换为刚性接头,再进行悬吊,具有操作简单、使用安全、节约成本的特点。本实用新型可适用于各类地下承插混凝土管的悬吊保护施工。In order to overcome the deficiencies of the above-mentioned prior art, the purpose of the utility model is to provide a suspension structure for socketing concrete pipes underground in deep foundation pit engineering, without replacing the concrete pipes with steel pipes. Through the use of cast-in-place reinforced concrete pipe hoops, the soft joints of socketed concrete pipes are converted into rigid joints, and then suspended, which has the characteristics of simple operation, safe use and cost saving. The utility model can be applied to the suspension protection construction of various underground socket concrete pipes.

为了实现上述目的,本实用新型采用的技术方案是:In order to achieve the above object, the technical solution adopted by the utility model is:

一种深基坑工程地下承插混凝土管的悬吊结构,包括紧线扣,通过钢筋混凝土箍对承插混凝土管接头进行包裹,通过预埋在钢筋混凝土箍中的钢丝绳,将承插混凝土管悬吊在其上方的钢箱梁上,并通过紧线扣、卡头收紧钢丝绳,完成悬吊受力转换。A suspension structure for underground socket concrete pipes in deep foundation pit engineering, including tight wire buckles, wrapping the socket concrete pipe joints through reinforced concrete hoops, and inserting concrete pipes through steel wire ropes pre-buried in the reinforced concrete hoops It is suspended on the steel box girder above it, and the steel wire rope is tightened by tightening the wire buckle and the chuck to complete the suspension force conversion.

所述的一种用于深基坑工程地下承插混凝土管的悬吊体系,其特征在于,通过所述的钢筋混凝土箍对承插混凝土管接头进行包裹,使承插混凝土管的柔性接头转换为刚性接头。The above-mentioned suspension system for socketing concrete pipes in deep foundation pit engineering is characterized in that the joints of socketed concrete pipes are wrapped by the reinforced concrete hoop, so that the flexible joints of socketed concrete pipes can be converted For rigid joints.

所述的钢筋混凝土箍由其内部的钢筋骨架通过灌注混凝土形成,钢筋骨架包括环向布置的主筋和纵向水平分布筋。The reinforced concrete hoop is formed by pouring concrete into the steel skeleton inside it, and the steel skeleton includes the main reinforcement arranged in the circumferential direction and the longitudinal and horizontal distribution reinforcement.

本实用新型的有益效果是:The beneficial effects of the utility model are:

本实用新型具有操作简单、使用安全、节约成本的特点,与常规的体系相比,仅需要对承插混凝土管的接头进行处理,无需再顶管转换的工序,节约了施工成本,并且操作简单易用,施工速度快。可适用于各类地下承插混凝土管的悬吊保护施工。The utility model has the characteristics of simple operation, safe use, and cost saving. Compared with the conventional system, it only needs to process the joint of the socket concrete pipe, and does not need the process of pipe jacking conversion, which saves the construction cost and is easy to operate. Easy to use and fast construction. It is suitable for the suspension protection construction of various underground socket concrete pipes.

附图说明Description of drawings

图1为本实用新型的结构示意图;Fig. 1 is the structural representation of the utility model;

图2为本实用新型的体系示意图;Fig. 2 is the system schematic diagram of the utility model;

图3为本实用新型的钢筋混凝土箍结构大样图Fig. 3 is a large sample diagram of the reinforced concrete hoop structure of the present utility model

其中,1为紧线扣;2为卡头;3为钢丝绳;4为钢筋混凝土箍;5为钢箱梁;6为承插混凝土管;7为基坑围护结构。Among them, 1 is a tight wire buckle; 2 is a clip; 3 is a steel wire rope; 4 is a reinforced concrete hoop; 5 is a steel box girder; 6 is a socket concrete pipe; 7 is a foundation pit enclosure structure.

具体实施方式Detailed ways

下面结合附图对本实用新型进一步叙述:Below in conjunction with accompanying drawing, the utility model is further described:

如图1、图2、图3所示,一种深基坑工程地下承插混凝土管的悬吊结构,包括紧线扣1,其特征在于,通过钢筋混凝土箍4对承插混凝土管6接头进行包裹,通过预埋在钢筋混凝土箍4中的钢丝绳3,将承插混凝土管6悬吊在其上方的钢箱梁5上,并通过紧线扣1、卡头2收紧钢丝绳3,完成悬吊受力转换。As shown in Fig. 1, Fig. 2 and Fig. 3, a suspension structure for underground socket concrete pipes in deep foundation pit engineering, including a tight wire buckle 1, is characterized in that 6 joints of socket concrete pipes are inserted through reinforced concrete hoops 4 Wrapping, suspending the socket concrete pipe 6 on the steel box girder 5 above it through the steel wire rope 3 pre-embedded in the reinforced concrete hoop 4, and tightening the steel wire rope 3 through the tightening wire buckle 1 and the chuck 2 to complete Suspension force conversion.

所述的钢筋混凝土箍4对承插混凝土管6接头进行包裹,使承插混凝土管6的柔性接头转换为刚性接头。The reinforced concrete hoop 4 wraps the joint of the socketed concrete pipe 6, so that the flexible joint of the socketed concrete pipe 6 is converted into a rigid joint.

所述的钢筋混凝土箍4由其内部的钢筋骨架通过灌注混凝土形成,钢筋骨架包括环向主筋7和纵向水平分布筋8。The reinforced concrete hoop 4 is formed by pouring concrete into the steel skeleton inside it, and the steel skeleton includes a hoop main reinforcement 7 and a longitudinal horizontal distribution reinforcement 8 .

所述的钢筋混凝土箍4的对承插混凝土管6接头的包裹长度不应小于50cm,最小厚度不小于30cm。The wrapping length of the reinforced concrete hoop 4 to the joint of the socket concrete pipe 6 should not be less than 50 cm, and the minimum thickness should not be less than 30 cm.

一种深基坑工程地下承插混凝土管的悬吊结构的施工方法,包括以下步骤:A construction method for a suspension structure of underground socket concrete pipes in deep foundation pit engineering, comprising the following steps:

步骤一:基坑土方开挖至地下承插管底部,在地下承插混凝土管6的接头处开挖沟槽,安装环向主筋7、纵向水平分布筋8、模板,并预埋钢丝绳3,然后浇筑钢筋混凝土箍4;Step 1: Excavate the earthwork of the foundation pit to the bottom of the underground socket pipe, excavate a trench at the joint of the underground socket concrete pipe 6, install the circumferential main reinforcement 7, the longitudinal horizontal distribution reinforcement 8, the formwork, and pre-embed the steel wire rope 3, Then pouring reinforced concrete hoop 4;

步骤二:在基坑围护结构7上安装架设钢箱梁5;Step 2: installing and erecting the steel box girder 5 on the foundation pit enclosure structure 7;

步骤三:将钢丝绳3悬挂至钢箱梁5,通过紧线扣1和卡头2收紧钢丝绳3,完成承插混凝土管6悬吊的受力转换;Step 3: Suspend the steel wire rope 3 to the steel box girder 5, tighten the steel wire rope 3 through the tightening buckle 1 and the clip 2, and complete the force conversion of the suspension of the socket concrete pipe 6;

步骤四:受力转换完成后,挖除承插混凝土管6下方全部土体;Step 4: After the force conversion is completed, all the soil below the socket concrete pipe 6 is excavated;

步骤五:基坑围护结构7之间多个悬吊结构构成悬吊系统。Step 5: Multiple suspension structures between foundation pit enclosure structures 7 constitute a suspension system.

Claims (4)

1.一种深基坑工程地下承插混凝土管的悬吊结构,包括紧线扣(1),其特征在于,通过钢筋混凝土箍(4)对承插混凝土管(6)接头进行包裹,通过预埋在钢筋混凝土箍(4)中的钢丝绳(3),将承插混凝土管(6)悬吊在其上方的钢箱梁(5)上,并通过紧线扣(1)、卡头(2)收紧钢丝绳(3),完成悬吊受力转换。1. A suspension structure for underground socket concrete pipes in deep foundation pit engineering, including tight wire buckles (1), characterized in that the joints of socket concrete pipes (6) are wrapped by reinforced concrete hoops (4), and the joints of socket concrete pipes (6) are wrapped by The steel wire rope (3) pre-buried in the reinforced concrete hoop (4) suspends the socket concrete pipe (6) on the steel box girder (5) above it, and passes the tight wire buckle (1), the clamp ( 2) Tighten the wire rope (3) to complete the suspension force conversion. 2.根据权利要求1所述的一种深基坑工程地下承插混凝土管的悬吊结构,其特征在于,所述的钢筋混凝土箍(4)对承插混凝土管(6)接头进行包裹,使承插混凝土管(6)的柔性接头转换为刚性接头。2. The suspension structure for underground socket concrete pipes in deep foundation pit engineering according to claim 1, characterized in that the reinforced concrete hoop (4) wraps the joints of socket concrete pipes (6), Convert the flexible joint of the socket concrete pipe (6) into a rigid joint. 3.根据权利要求1所述的一种深基坑工程地下承插混凝土管的悬吊结构,其特征在于,所述的钢筋混凝土箍(4)由其内部的钢筋骨架通过灌注混凝土形成,钢筋骨架包括环向主筋(7)和纵向水平分布筋(8)。3. The suspension structure for underground socket concrete pipes in deep foundation pit engineering according to claim 1, characterized in that the reinforced concrete hoop (4) is formed by pouring concrete into the steel skeleton inside it, and the steel bars The skeleton includes circumferential main ribs (7) and longitudinal horizontal distribution ribs (8). 4.根据权利要求1所述的一种深基坑工程地下承插混凝土管的悬吊结构,其特征在于,所述的钢筋混凝土箍(4)的对承插混凝土管(6)接头的包裹长度不应小于50cm,最小厚度不小于30cm。4. The suspension structure for underground socket concrete pipes in deep foundation pit engineering according to claim 1, characterized in that the said reinforced concrete hoop (4) wraps the joints of socket concrete pipes (6) The length should not be less than 50cm, and the minimum thickness should not be less than 30cm.
CN201920437688.8U 2019-04-02 2019-04-02 A Suspension Structure for Underground Socket Concrete Pipes in Deep Foundation Pit Engineering Expired - Fee Related CN209873807U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920437688.8U CN209873807U (en) 2019-04-02 2019-04-02 A Suspension Structure for Underground Socket Concrete Pipes in Deep Foundation Pit Engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920437688.8U CN209873807U (en) 2019-04-02 2019-04-02 A Suspension Structure for Underground Socket Concrete Pipes in Deep Foundation Pit Engineering

Publications (1)

Publication Number Publication Date
CN209873807U true CN209873807U (en) 2019-12-31

Family

ID=68957969

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920437688.8U Expired - Fee Related CN209873807U (en) 2019-04-02 2019-04-02 A Suspension Structure for Underground Socket Concrete Pipes in Deep Foundation Pit Engineering

Country Status (1)

Country Link
CN (1) CN209873807U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109881679A (en) * 2019-04-02 2019-06-14 中铁十二局集团有限公司 Suspension structure and construction method of underground socket-inserted concrete pipe for deep foundation pit engineering

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109881679A (en) * 2019-04-02 2019-06-14 中铁十二局集团有限公司 Suspension structure and construction method of underground socket-inserted concrete pipe for deep foundation pit engineering

Similar Documents

Publication Publication Date Title
CN210151752U (en) A kind of foundation pit steel roof support
CN106759347A (en) Steel pipe Larsen steel plate combination fender post constructing structure and its construction method
CN109881679A (en) Suspension structure and construction method of underground socket-inserted concrete pipe for deep foundation pit engineering
CN209873807U (en) A Suspension Structure for Underground Socket Concrete Pipes in Deep Foundation Pit Engineering
CN104763161A (en) Beam-adding reinforced structure of a reinforced concrete floor with an opening and construction method
CN107542086B (en) Anchor cable construction method for filling slope
CN113914891B (en) Pre-empty soft rock roadway supporting structure and construction method thereof
CN214883827U (en) A construction hoist cantilevered foundation support system device
CN213461075U (en) Protection device for underground original pipeline
CN205954636U (en) Prestressing force steel sheet pile supporting construction
CN106193279A (en) Agent structure wall prestressed structure and time building method of agent structure wall
CN206554483U (en) A kind of full fabricated scaffold is encorbelmented component
CN108797396B (en) Reinforcing mesh reinforced bridge underwater pier column structure and construction method
CN206721891U (en) Ground-connecting-wall goes along with sb. to guard him foundation ditch steel pipe support structure
CN206070725U (en) Agent structure wall prestressed structure
CN212114728U (en) Temporary fixing device for submarine cable
CN205000334U (en) Recoverable prestressed anchorage cable
CN204590011U (en) A kind of prestressing force props up hole fender pile
CN116397877A (en) Formwork system and construction method of ultra-deep segmental subsidence large-diameter working well
CN103362315A (en) A kind of hanger used for overall hoisting of pipelines and its construction method
CN103758143B (en) Formwork structure of bridge foundation underwater concrete continuous wall cofferdam
CN211285692U (en) Corrugated steel pipe gallery based on prestressed tendons
CN108644471B (en) A pipeline sliding transportation structure system and its construction method on a large area of water
CN203230183U (en) Shear wall expansion joint formwork erecting and reinforcing device
CN111585236B (en) A temporary fixing device for submarine cable and operation method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191231