CN209858707U - Battery pack test equipment - Google Patents

Battery pack test equipment Download PDF

Info

Publication number
CN209858707U
CN209858707U CN201920124927.4U CN201920124927U CN209858707U CN 209858707 U CN209858707 U CN 209858707U CN 201920124927 U CN201920124927 U CN 201920124927U CN 209858707 U CN209858707 U CN 209858707U
Authority
CN
China
Prior art keywords
test box
display screen
gas
pipe
temperature
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920124927.4U
Other languages
Chinese (zh)
Inventor
朱超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Lian Ding Detection Technology Co Ltd
Original Assignee
Guangdong Lian Ding Detection Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Lian Ding Detection Technology Co Ltd filed Critical Guangdong Lian Ding Detection Technology Co Ltd
Priority to CN201920124927.4U priority Critical patent/CN209858707U/en
Application granted granted Critical
Publication of CN209858707U publication Critical patent/CN209858707U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Secondary Cells (AREA)

Abstract

The utility model discloses a battery pack test equipment, including the test box, the universal wheel is installed to the bottom of test box, and the top of test box is provided with the gas-supply pipe that runs through test box top to test box inside, the top of test box is located the place ahead of gas-supply pipe and installs temperature display screen, and the top of test box is close to one side of temperature display screen and installs pressure display screen, the metal mesh is installed to the inner wall of test box, and the top that the inner wall of test box is located the metal mesh is fixed with places the board. The utility model discloses a set up electrothermal tube, temperature sensor and temperature display screen, the battery package is put into the device in to behind the closing means, provide the electric energy for the electrothermal tube, the electrothermal tube can begin to give out the heat, temperature sensor changes real-time temperature for the signal of telecommunication carries to the PLC controller, after the signal of telecommunication was received to the PLC controller, trund it into digital signal and carry to temperature display screen, when the temperature on the temperature display screen reached the predetermined temperature, can test the battery package.

Description

Battery pack test equipment
Technical Field
The utility model relates to a battery package test field specifically is battery package test equipment.
Background
The battery pack comprises a lithium battery pack and a lithium battery protection circuit, and after the battery pack is assembled, a tester uses the ammeter to integrally test the battery pack.
At present, the performance of simple test circuit protection is only used during testing, the temperature of the space where the battery pack is located during actual operation cannot be tested, the data tested out are not accurate enough, the pressure of the space where the battery pack is located during operation cannot be tested, the test result is not accurate enough, the existing testing device is not convenient to move, and the efficiency is slow when the device is required to be carried.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a: in order to solve the problem that the tested data is not accurate enough and the efficiency is slow when the device needs to be carried, the battery pack testing equipment is provided.
In order to achieve the above object, the utility model provides a following technical scheme: battery pack testing equipment comprises a testing box, universal wheels are installed at the bottom end of the testing box, a gas pipe penetrating through the top end of the testing box to the inside of the testing box is arranged at the top end of the testing box, a temperature display screen is installed at the position, located in front of the gas pipe, of the top end of the testing box, a pressure display screen is installed at one side, close to the temperature display screen, of the top end of the testing box, a metal net is installed on the inner wall of the testing box, a placing plate is fixed at the position, located above the metal net, of the inner wall of the testing box, a pressure sensor is installed at one side, close to the metal net, of the inner wall of the testing box, a temperature sensor is installed at the rear portion, located behind the pressure sensor, of the inner wall of the testing box, a rotating door is rotatably connected to the front surface of the testing box, an electric heating pipe is, the welding of the top of gas pitcher has the intake pipe, the solenoid valve is all installed with the surface of gas-supply pipe to the intake pipe, the input of intake pipe is connected with the gas storehouse.
Preferably, the electrothermal tube passes through the wire with external power supply and is connected, temperature sensor and temperature display screen pass through PLC controller electric connection, pressure sensor and pressure display screen pass through PLC controller electric connection, solenoid valve and PLC controller electric connection.
Preferably, the test box and the rotating door are rotatably connected through a hinge, and a sealing ring is arranged at a position where the test box contacts with the rotating door.
Preferably, the inner wall of the connecting hole is provided with a sealing ring, and the number of the connecting holes is two.
Preferably, the number of universal wheels is four, and four universal wheels are installed respectively in the four corners position department of test box bottom.
Preferably, the air inlet pipe is connected with the air bin through a connecting pipe, and a sealing ring is arranged at the position where the air inlet pipe is contacted with the connecting pipe.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses a set up the electrothermal tube, temperature sensor and temperature display screen, the battery package is put into the device, and after closing the device, provide the electric energy for the electrothermal tube, the electrothermal tube can begin to give out heat, temperature sensor changes real-time temperature into the signal of telecommunication and carries to the PLC controller, after the PLC controller receives the signal of telecommunication, change it into digital signal and carry to the temperature display screen, when the temperature on the temperature display screen reaches predetermined temperature, can test the battery package, improve the accuracy of battery package test, through setting up the gas pitcher, pressure sensor and pressure display screen, after the solenoid valve is opened, the inert gas in the gas pitcher enters the inside of test box along the gas-supply pipe, along with getting more and more inert gas in the test box, the atmospheric pressure in the test box rises gradually, pressure sensor changes pressure signal into the signal of telecommunication and carries to the PLC controller at this moment, after the PLC controller received the signal of telecommunication, change it into digital signal, and carry to on the pressure display screen, the tester can know the inside real-time pressure of test box through the pressure display screen, after the pressure value on the pressure display screen reached the predetermined pressure, the solenoid valve through PLC controller control gas-supply pipe surface is closed, can test the operational aspect of battery package under different pressure, through setting up the universal wheel, the pulling device can make the universal wheel slide on ground, the inconvenient problem that removes of testing arrangement has effectively been solved.
Drawings
Fig. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the installation of the electric heating tube of the present invention;
fig. 3 is a schematic view of the connection between the gas tank and the gas cabin of the present invention.
In the figure: 1. a test box; 2. a universal wheel; 3. a metal mesh; 4. placing the plate; 5. a temperature sensor; 6. a pressure sensor; 7. a rotating door; 8. connecting holes; 9. a temperature display screen; 10. a gas delivery pipe; 11. an electromagnetic valve; 12. an air inlet pipe; 13. a gas tank; 14. a pressure display screen; 15. an electric heating tube; 16. and (4) air storage.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The pressure sensor (PT124G-210), the temperature sensor (PT100), the pressure display screen, the temperature display screen, the electric heating tube and the electromagnetic valve (3V1-06) of the utility model can be obtained by market or private ordering.
Referring to fig. 1-3, a battery pack testing apparatus includes a testing box 1, a universal wheel 2 is installed at the bottom end of the testing box 1, a gas pipe 10 penetrating the top end of the testing box 1 to the inside of the testing box 1 is installed at the top end of the testing box 1, a temperature display screen 9 is installed at the top end of the testing box 1 in front of the gas pipe 10, a pressure display screen 14 is installed at one side of the top end of the testing box 1 close to the temperature display screen 9, a metal net 3 is installed at the inner wall of the testing box 1, a placing plate 4 is fixed at the inner wall of the testing box 1 above the metal net 3, a pressure sensor 6 is installed at one side of the inner wall of the testing box 1 close to the metal net 3, a temperature sensor 5 is installed at the rear of the pressure sensor 6 at the inner wall of the testing box 1, a rotating door 7 is rotatably connected to the front surface of the testing box 1, and an electric heating, the inside of revolving door 7 is provided with connecting hole 8, and the top welding of gas-supply pipe 10 has gas pitcher 13, and the top welding of gas pitcher 13 has intake pipe 12, and solenoid valve 11 is all installed with the surface of gas-supply pipe 10 to intake pipe 12, and the input of intake pipe 12 is connected with the gas storehouse 16.
Please refer to fig. 1, the testing box 1 is rotatably connected to the rotating door 7 through a hinge, so as to open or close the rotating door 7, and a sealing ring is disposed at a position where the testing box 1 contacts the rotating door 7, so as to improve the sealing performance of the testing box 1; the inner wall of the connecting hole 8 is provided with the sealing ring, so that after the inner wall of the connecting hole 8 is contacted with the connecting line of the ammeter, the gap between the connecting hole 8 and the connecting line can be reduced, the sealing performance of the device is further improved, and the number of the connecting holes 8 is two; the quantity of universal wheel 2 is four, and four universal wheels 2 are installed respectively in the four corners position department of 1 bottom of test box, and the universal wheel 2 of being convenient for provides stable holding power for the device.
Please refer to fig. 3, the gas inlet pipe 12 is connected to the gas chamber 16 through a connecting pipe, so that the gas chamber 16 can conveniently deliver the inert gas to the gas tank 13 through the gas inlet pipe 12, and a sealing ring is disposed at a position where the gas inlet pipe 12 contacts the connecting pipe, so as to prevent the inert gas from leaking from a position where the gas inlet pipe 12 contacts the connecting pipe after the gas inlet pipe 12 is connected to the connecting pipe.
Please refer to fig. 1 and fig. 2, the electric heating tube 15 is connected to an external power source through a wire, so that an external power source can provide electric energy for the electric heating tube 15, the temperature sensor 5 is electrically connected to the temperature display screen 9 through a PLC controller, the temperature sensor 5 can transmit a temperature value to the temperature display screen 9 through the PLC controller, the pressure sensor 6 is electrically connected to the pressure display screen 14 through the PLC controller, the pressure sensor 6 can transmit a pressure value to the pressure display screen 14 through the PLC controller, and the electromagnetic valve 11 is electrically connected to the PLC controller, so as to control the electromagnetic valve 11 to be opened or closed.
The working principle is as follows: firstly, when the device is used, the device is powered on, when the running condition of the battery pack at high temperature is tested, the battery pack is prevented from being placed on the placing plate 4, then a connecting wire on an ammeter passes through the connecting hole 8 to be connected with the battery pack, then the rotating door 7 is closed, the electric heating tube 15 is connected with an external power supply, the electric heating tube 15 starts to generate heat after acquiring electric energy, heat enters the inside of the testing box 1 through the metal net 3, the temperature sensor 5 converts a sensed temperature signal into an electric signal and transmits the electric signal to the PLC, the PLC converts the electric signal into a digital signal and transmits the digital signal to the temperature display screen 9, a tester can know the real-time temperature, when the temperature displayed on the temperature display screen 9 reaches the testing temperature, the electric heating tube 15 is disconnected from the external power supply, and the running condition of the battery pack at the preset temperature; then, when the test electric detector operates under different pressures, the PLC controller controls the electromagnetic valve 11 on the outer surface of the gas pipe 10 to open, after the electromagnetic valve 11 is opened, the inert gas in the gas tank 13 enters the test box 1 along the gas pipe 10, the gas pressure in the test box 1 gradually rises along with the increasing amount of the inert gas entering the test box 1, at the moment, the pressure sensor 6 converts the pressure signal into an electric signal and transmits the electric signal to the PLC controller, the PLC controller converts the electric signal into a digital signal after receiving the electric signal, and then the pressure is transmitted to the pressure display screen 14, so that the tester can know the real-time pressure in the test box 1 through the pressure display screen 14, after the pressure value on the pressure display screen 14 reaches the preset pressure, the PLC controller controls the electromagnetic valve 11 on the outer surface of the gas pipe 10 to be closed, and the running conditions of the battery pack under different pressures can be tested; finally, when the gas in the gas tank 13 is not enough, the gas inlet pipe 12 is connected with the gas bin 16 through the connecting pipe, the PLC controls the electromagnetic valve 11 on the outer surface of the gas inlet pipe 12 to be opened, the inert gas in the gas bin 16 can enter the gas tank 13 along the connecting pipe and the gas inlet pipe 12, and after the gas filling is finished, the PLC controls the electromagnetic valve 11 on the outer surface of the gas inlet pipe 12 to be closed.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (6)

1. Battery package test equipment, including test box (1), its characterized in that: the universal wheel (2) is installed at the bottom end of the test box (1), the gas pipe (10) penetrating through the top end of the test box (1) to the inside of the test box (1) is arranged at the top end of the test box (1), the temperature display screen (9) is installed at the top end of the test box (1) in front of the gas pipe (10), the pressure display screen (14) is installed at one side, close to the temperature display screen (9), of the top end of the test box (1), the metal net (3) is installed on the inner wall of the test box (1), the placing plate (4) is fixed above the metal net (3) on the inner wall of the test box (1), the pressure sensor (6) is installed at one side, close to the metal net (3), of the inner wall of the test box (1), the temperature sensor (5) is installed at the rear side, close to the pressure sensor (6), the rotating door (7) is rotatably connected to the front surface of the test box (1, and the inside below that is located metal mesh (3) of test box (1) is provided with electrothermal tube (15), the inside of revolving door (7) is provided with connecting hole (8), the top welding of gas-supply pipe (10) has gas pitcher (13), the top welding of gas pitcher (13) has intake pipe (12), solenoid valve (11) are all installed with the surface of gas-supply pipe (10) in intake pipe (12), the input of intake pipe (12) is connected with gas storehouse (16).
2. The battery pack testing apparatus according to claim 1, wherein: the electric heating pipe (15) is connected with an external power supply through a lead, the temperature sensor (5) is electrically connected with the temperature display screen (9) through a PLC (programmable logic controller), the pressure sensor (6) is electrically connected with the pressure display screen (14) through the PLC, and the electromagnetic valve (11) is electrically connected with the PLC.
3. The battery pack testing apparatus according to claim 1, wherein: the testing box (1) is rotatably connected with the rotating door (7) through a hinge, and a sealing ring is arranged at the position where the testing box (1) is contacted with the rotating door (7).
4. The battery pack testing apparatus according to claim 1, wherein: the inner wall of the connecting hole (8) is provided with a sealing ring, and the number of the connecting holes (8) is two.
5. The battery pack testing apparatus according to claim 1, wherein: the number of universal wheels (2) is four, and four universal wheels (2) are respectively installed at the four corners of the bottom end of the test box (1).
6. The battery pack testing apparatus according to claim 1, wherein: the air inlet pipe (12) is connected with the air bin (16) through a connecting pipe, and a sealing ring is arranged at the position where the air inlet pipe (12) is contacted with the connecting pipe.
CN201920124927.4U 2019-01-25 2019-01-25 Battery pack test equipment Expired - Fee Related CN209858707U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920124927.4U CN209858707U (en) 2019-01-25 2019-01-25 Battery pack test equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920124927.4U CN209858707U (en) 2019-01-25 2019-01-25 Battery pack test equipment

Publications (1)

Publication Number Publication Date
CN209858707U true CN209858707U (en) 2019-12-27

Family

ID=68930879

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920124927.4U Expired - Fee Related CN209858707U (en) 2019-01-25 2019-01-25 Battery pack test equipment

Country Status (1)

Country Link
CN (1) CN209858707U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113759262A (en) * 2021-08-18 2021-12-07 山东理工大学 Thermal runaway safety test device and method for battery energy storage electric cabinet

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113759262A (en) * 2021-08-18 2021-12-07 山东理工大学 Thermal runaway safety test device and method for battery energy storage electric cabinet

Similar Documents

Publication Publication Date Title
CN109164393B (en) Battery thermal runaway experimental device, system and method
CN211443169U (en) Sample storage device for food quality inspection
CN108828457B (en) Battery thermal runaway experimental device and system thereof
CN203909107U (en) Ammeter box
CN209542171U (en) A kind of Portable water sample sampling equipment
CN105606480B (en) A kind of automation coal seam can the direct measurement device of desorbing mash gas content
CN209858707U (en) Battery pack test equipment
CN103000925B (en) Mobile all-vanadium redox flow battery system for vanadium battery material and electric pile structure evaluation
CN205175943U (en) Lithium ion battery fuel factor test system
CN108872877B (en) Battery thermal runaway experimental device and system thereof
CN210893548U (en) Electronic product detector
CN201876093U (en) Vacuum drying oven allowing online measurement of moisture content of gas in oven body
CN207851267U (en) A kind of density monitor on-line testing device
CN208172213U (en) A kind of charging cabinet for testing battery
CN212458501U (en) NB-IOT wireless remote gas meter
CN202420779U (en) Lithium battery leakage detection device
CN212712724U (en) Filling station nozzle leakproofness detection device
CN208961288U (en) A kind of bionical welding manipulator of use for electronic products
CN113719747A (en) Automatic meteorological balloon inflation releasing device based on fixed volumetric hydrogen storage tank
CN207147733U (en) A kind of automatic leak-checking apparatus of lithium ion battery
CN109781202B (en) Intelligent household gas meter with alarm function
CN220133955U (en) Device for measuring liquid level height in shaft
CN208333785U (en) A kind of calibrating installation of airtight leak detector
CN217687425U (en) Test car is suppressed to large-scale water gauge
CN207181044U (en) A kind of removable self circulation cooling device applied on high-speed slip rings electrical feedthrough

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191227

Termination date: 20220125