CN209837864U - Rail guard of convenient transportation and installation for building - Google Patents

Rail guard of convenient transportation and installation for building Download PDF

Info

Publication number
CN209837864U
CN209837864U CN201920361504.4U CN201920361504U CN209837864U CN 209837864 U CN209837864 U CN 209837864U CN 201920361504 U CN201920361504 U CN 201920361504U CN 209837864 U CN209837864 U CN 209837864U
Authority
CN
China
Prior art keywords
connecting rod
installation
installation seat
rod
mount pad
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920361504.4U
Other languages
Chinese (zh)
Inventor
孙涌
于亿卓
左艳彬
李玉波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ronghua Construction Group Co Ltd
Original Assignee
Ronghua Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ronghua Construction Group Co Ltd filed Critical Ronghua Construction Group Co Ltd
Priority to CN201920361504.4U priority Critical patent/CN209837864U/en
Application granted granted Critical
Publication of CN209837864U publication Critical patent/CN209837864U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a rail guard of convenient transportation and installation for building, including mount pad one and the mount pad two that is located mount pad one side, the bottom intermediate position of mount pad one and mount pad two all is equipped with recess one, the equal symmetry in inside of recess one is equipped with two sets of removal subassemblies, mount pad one and the equal symmetry in the outside of mount pad two are equipped with the fixed block, the top intermediate position of mount pad one and mount pad two all is equipped with recess two that is located recess one top, the top of mount pad one is equipped with the dead lever one with recess two-phase adaptation, the top of mount pad two is equipped with the dead lever two with recess two-phase adaptation. Has the advantages that: and the drawing mechanism that the cooperation set up has not only increased the stability of device, has increased draught area simultaneously, and then has effectively reduced because the great condition of blowing down the device of wind-force, and then has improved the security of device, has realized that the installation and the dismantlement of device are convenient, provide convenience for the transportation simultaneously.

Description

Rail guard of convenient transportation and installation for building
Technical Field
The utility model relates to a building technical field particularly, relates to a rail guard of convenient transportation and installation for building.
Background
In order to ensure the safety of pedestrians and prevent the pedestrians from entering a construction site in a building construction site, an isolation guard rail needs to be erected outside the construction site, but most of the guard rails in the prior art are vertical structures, the pedestrians are only separated from the isolation guard rail in the construction site, if a construction instrument is very close to the guard rail, if the pedestrians pass through the guard rail, only one guard rail is separated, and since the guard rail is close to the construction site, dangerous accidents are easily caused. The guard rail is generally composed of a plurality of guard rail units, but modern guard rail units cannot be disassembled and contracted, the transportation process to the site is very troublesome, and the guard rail is blown down due to high wind force during use, so that the guard rail is damaged and resources are wasted.
An effective solution to the problems in the related art has not been proposed yet.
SUMMERY OF THE UTILITY MODEL
To the problem among the correlation technique, the utility model provides a rail guard of convenient transportation and installation for building to overcome the above-mentioned technical problem that current correlation technique exists.
Therefore, the utility model discloses a specific technical scheme as follows:
a guardrail for construction convenient transportation and installation comprises a first installation seat and a second installation seat positioned on one side of the first installation seat, wherein grooves I are respectively arranged at the middle positions of the bottoms of the first installation seat and the second installation seat, two groups of moving assemblies are respectively and symmetrically arranged in the grooves I, fixed blocks are respectively and symmetrically arranged on the outer sides of the first installation seat and the second installation seat, grooves II which are positioned above the grooves I are respectively arranged at the middle positions of the top ends of the first installation seat and the second installation seat, fixed rods I which are matched with the grooves II are arranged at the top ends of the first installation seat, fixed rods II which are matched with the grooves II are arranged at the top ends of the second installation seat, a first installation block and a second installation block which is positioned below the first installation block are respectively connected to the first fixed rods and the second fixed rods, shielding plates which are positioned between the first installation block and the second installation block are respectively sleeved on the first fixed rods and the second fixed rods, adjacent connect through linking pole one between the installation piece one, it is adjacent through set up in linking pole two below linking pole are connected between the installation piece two, link pole one with link pole two is connected through parallel arrangement's connecting rod one and connecting rod two between the linking pole two, the bottom symmetry that links up pole one is equipped with the base, and is adjacent connect through linking axle between the base, link up epaxial cover be equipped with link up the propaganda curtain that pole two are connected, link up pole one with link up through being located between the pole two the straining device that propaganda curtain symmetry set up connects.
Furthermore, the propaganda curtain is connected with the second connecting rod through a clamping rod.
Furthermore, the stretching mechanism comprises a first fixing plate connected with the first connecting rod, the bottom end of the first fixing plate is movably connected with a telescopic connecting rod, and one end, far away from the first fixing plate, of the telescopic connecting rod is connected with the second connecting rod through a second fixing plate.
Furthermore, the first joint rod and the second joint rod are respectively provided with two mounting grooves matched with the first fixing plate and the second fixing plate.
Further, the movable assembly comprises a main pipe arranged at the top end in the first groove and a sub pipe connected with the main pipe in a penetrating mode, the main pipe is connected with the sub pipe through a fastening rod, and movable wheels are arranged at the bottom ends of the sub pipes.
Further, the inner top of the main pipe is connected with the top end of the sub pipe through a spring.
The utility model has the advantages that: through the removal subassembly that sets up, the device of being convenient for removes, and then makes and reach the effect of province in handling, the effectual labour that has practiced thrift, this device simple to operate simultaneously, and easy operation, and the drawing mechanism that the cooperation set up, not only increased the stability of device, increased draught area simultaneously, and then effectively reduced because the great condition of blowing down the device of wind-force, and then improved the security of device, the installation and the dismantlement of device have been realized conveniently, simultaneously for the transportation provide convenience.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required to be used in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
Fig. 1 is a schematic structural view of a protective guard for construction convenient transportation and installation according to an embodiment of the present invention;
fig. 2 is a schematic structural diagram of a protective guard stretching mechanism for convenient transportation and installation in a building according to an embodiment of the present invention;
fig. 3 is a schematic structural diagram of a protective guard moving assembly for construction, which is convenient for transportation and installation according to an embodiment of the present invention.
In the figure:
1. a first mounting seat; 2. a second mounting seat; 3. a first groove; 4. a moving assembly; 5. a fixed block; 6. a second groove; 7. fixing a rod I; 8. a second fixing rod; 9. a first mounting block; 10. a second mounting block; 11. a shielding plate; 12. a first connecting rod; 13. a second connecting rod; 14. a first connecting rod; 15. a second connecting rod; 16. a telescopic connecting rod; 17. a base; 18. a connecting shaft; 19. a propaganda curtain; 20. a stretching mechanism; 21. a main pipe; 22. a sub-tube; 23. a moving wheel; 24. a fastening rod; 25. a spring; 26. a clamping rod; 27. a first fixing plate; 28. and a second fixing plate.
Detailed Description
For further explanation of the embodiments, the drawings are provided as part of the disclosure and serve primarily to illustrate the embodiments and, together with the description, to explain the principles of operation of the embodiments, and to provide further explanation of the invention and advantages thereof, it will be understood by those skilled in the art that various other embodiments and advantages of the invention are possible, and that elements in the drawings are not to scale and that like reference numerals are generally used to designate like elements.
According to the utility model discloses an embodiment provides a rail guard of convenient transportation and installation for building.
The first embodiment is as follows:
as shown in fig. 1-3, the protective guard for transportation and installation convenience in construction according to the embodiment of the present invention comprises a first mounting seat 1 and a second mounting seat 2 located at one side of the first mounting seat 1, wherein a first groove 3 is respectively disposed at the middle position of the bottom end of the first mounting seat 1 and the second mounting seat 2, two sets of moving components 4 are symmetrically disposed inside the first groove 3, fixing blocks 5 are symmetrically disposed at the outer sides of the first mounting seat 1 and the second mounting seat 2, a second groove 6 located above the first groove 3 is disposed at the middle position of the top end of the first mounting seat 1 and the second mounting seat 2, a first fixing rod 7 adapted to the second groove 6 is disposed at the top end of the first mounting seat 1, a second fixing rod 8 adapted to the second groove 6 is disposed at the top end of the second mounting seat 2, a first mounting block 9 and a second mounting block 10 located below the first mounting block 9 are connected to the first fixing rod 7 and the second fixing rod 8, the utility model discloses a safe and convenient fixing device, including dead lever one 7 with all overlap on the dead lever two 8 and be located installation piece one 9 with shutter 11 between the installation piece two 10, it is adjacent connect through linking pole one 12 between the installation piece one 9, it is adjacent through setting up in link two 13 of linking pole one 12 below between the installation piece two 10, link pole one 12 with link pole two 13 between link pole two 13 through parallel arrangement's connecting rod one 14 and connecting rod two 15 are connected, the bottom symmetry of link pole one 12 is equipped with base 17, and is adjacent connect through linking axle 18 between the base 17, link axle 18 go up the cover be equipped with link pole two 13 connect the propaganda curtain 19, link pole one 12 with link pole two 13 between through being located propaganda curtain 19 symmetry sets up's straining device 20 connects.
With the aid of the above technical scheme, through the removal subassembly 4 that sets up, the device of being convenient for removes, and then make and reach the effect of province in handling, the effectual labour that has practiced thrift, this device simple to operate simultaneously, and easy operation, and the drawing mechanism 20 that the cooperation set up, the stability of device has not only been increased, the draught area has been increased simultaneously, and then effectively reduced because the great condition of blowing down the device of wind-force, and then the security of device has been improved, the installation and the dismantlement convenience of device have been realized, it is convenient to provide for the transportation simultaneously.
Example two:
as shown in fig. 1, the propaganda curtain 19 is connected with the second connecting rod 13 through a clamping rod 26. Through the clamping rod 26, one end of the propaganda curtain 19 is fixed on the connecting rod two 13, and the propaganda curtain 19 is convenient to install and replace.
As shown in fig. 2, the stretching mechanism 20 includes a first fixing plate 27 connected to the first connecting rod 12, a telescopic link 16 is movably connected to a bottom end of the first fixing plate 27, and an end of the telescopic link 16 away from the first fixing plate 27 is connected to the second connecting rod 13 through a second fixing plate 28. Through the stretching mechanism 20, the stability is effectively improved, meanwhile, the ventilation area is increased, and further the influence of wind power on the device is reduced.
As shown in fig. 1, the first joint rod 12 and the second joint rod 13 are provided with two mounting grooves adapted to the first fixing plate 27 and the second fixing plate 28. The installation groove is arranged to facilitate the fixing of the stretching mechanism 20 between the first joint rod 12 and the second joint rod 13.
As shown in fig. 3, the moving assembly 4 includes a main pipe 21 disposed at the top end in the first groove 3 and a sub-pipe 22 inserted into the main pipe 21, the main pipe 21 and the sub-pipe 22 are connected by a fastening rod 24, and moving wheels 23 are disposed at the bottom ends of the sub-pipes 22. Through the removal subassembly 4 that sets up for the device is convenient for remove, reduces to carry through the manpower.
As shown in fig. 3, the inner top of the main tube 21 is connected to the top end of the sub tube 22 by a spring 25. The spring 25 is arranged, so that the sub-pipe 22 is effectively prevented from being in direct contact with the inner wall of the main pipe 21.
Installation process: the installation of the device is completed by compressing the sub-pipe 22 inside the first installation seat 1 and the second installation seat 2 into the main pipe 21, enabling the moving wheel 23 to be located in the first groove 3, further enabling the fixing block 5 to be in contact with the ground, further fixing the first installation seat 1, enabling the first installation seat 1 to be fastened with the ground through bolts, further enabling the first connecting rod 14 and the second connecting rod 15 to be respectively connected with the first connecting rod 12 and the second connecting rod 13, further enabling the first fixing plate 27 to be connected with the first connecting rod 12, the second fixing plate 28 to be connected with the second connecting rod 13, further enabling two ends of the first connecting rod 12 to be connected with the first installation block 9, further enabling two ends of the second connecting rod 13 to be connected with the second installation block 10, further enabling the second installation seat 2 to be fixed with the ground through bolts, meanwhile, enabling the propaganda curtain 19 to be sleeved on the connecting shaft 18, and further enabling one end of the propaganda curtain 19 to be fixed with the.
To sum up, with the help of the above technical scheme of the utility model, through the removal subassembly 4 that sets up, the device of being convenient for removes, and then make and reach the effect of province in handling, the effectual labour of having practiced thrift, this device simple to operate simultaneously, and easy operation, and the drawing mechanism 20 that the cooperation set up, the stability of device has not only been increased, the area of ventilating has been increased simultaneously, and then effectively reduced because the great condition of blowing down the device of wind-force, and then the security of device has been improved, the installation and the dismantlement convenience of device have been realized, simultaneously for the transportation provide convenience.
The above description is only a preferred embodiment of the present invention, and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The protective guard convenient to transport and install for buildings is characterized by comprising a first installation seat (1) and a second installation seat (2) located on one side of the first installation seat (1), wherein first grooves (3) are formed in the middle positions of the bottoms of the first installation seat (1) and the second installation seat (2), two groups of moving assemblies (4) are symmetrically arranged inside the first grooves (3), fixing blocks (5) are symmetrically arranged on the outer sides of the first installation seat (1) and the second installation seat (2), second grooves (6) located above the first grooves (3) are formed in the middle positions of the top ends of the first installation seat (1) and the second installation seat (2), first fixing rods (7) matched with the second grooves (6) are arranged at the top end of the first installation seat (1), second fixing rods (8) matched with the second grooves (6) are arranged at the top end of the second installation seat (2), the fixing rod I (7) and the fixing rod II (8) are connected with a first mounting block (9) and located a second mounting block (10) below the first mounting block (9), the first fixing rod (7) and the second fixing rod (8) are sleeved with a shielding plate (11) located between the first mounting block (9) and the second mounting block (10), the first mounting block (9) is connected through a first connecting rod (12), the second mounting block (10) is connected through a second connecting rod (13) arranged below the first connecting rod (12), the first connecting rod (12) is connected with the second connecting rod (13) through a first connecting rod (14) and a second connecting rod (15) which are arranged in parallel, a base (17) is symmetrically arranged at the bottom end of the first connecting rod (12), and the bases (17) are connected through a connecting shaft (18), the connecting shaft (18) is sleeved with a propaganda curtain (19) connected with the connecting rod II (13), and the connecting rod I (12) is connected with the connecting rod II (13) through a stretching mechanism (20) symmetrically arranged on the propaganda curtain (19).
2. A transportation and installation convenient guard rail for building according to claim 1 wherein, the propaganda curtain (19) is connected with the second connecting rod (13) through a clamping rod (26).
3. A transportation and installation convenient guard rail for building according to claim 1 wherein, the stretching mechanism (20) comprises a first fixing plate (27) connected with the first connecting rod (12), the bottom end of the first fixing plate (27) is movably connected with a telescopic connecting rod (16), and the end of the telescopic connecting rod (16) far away from the first fixing plate (27) is connected with the second connecting rod (13) through a second fixing plate (28).
4. A transportation and installation convenient guard rail for building according to claim 3 wherein, the first connecting rod (12) and the second connecting rod (13) are provided with two mounting grooves matched with the first fixing plate (27) and the second fixing plate (28).
5. The protective guard for the building convenient to transport and install according to claim 1, wherein the moving assembly (4) comprises a main pipe (21) arranged at the top end in the first groove (3) and a sub pipe (22) inserted into the main pipe (21), the main pipe (21) is connected with the sub pipe (22) through a fastening rod (24), and moving wheels (23) are arranged at the bottom ends of the sub pipes (22).
6. A transportation and installation convenient guard rail for building according to claim 5 wherein the inner top of the main pipe (21) is connected with the top end of the sub pipe (22) through a spring (25).
CN201920361504.4U 2019-03-21 2019-03-21 Rail guard of convenient transportation and installation for building Expired - Fee Related CN209837864U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920361504.4U CN209837864U (en) 2019-03-21 2019-03-21 Rail guard of convenient transportation and installation for building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920361504.4U CN209837864U (en) 2019-03-21 2019-03-21 Rail guard of convenient transportation and installation for building

Publications (1)

Publication Number Publication Date
CN209837864U true CN209837864U (en) 2019-12-24

Family

ID=68907268

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920361504.4U Expired - Fee Related CN209837864U (en) 2019-03-21 2019-03-21 Rail guard of convenient transportation and installation for building

Country Status (1)

Country Link
CN (1) CN209837864U (en)

Similar Documents

Publication Publication Date Title
CN212656515U (en) Adjustable movable scaffold
KR101664990B1 (en) Tunnel type composite bridge constructed by modules
CN114458001A (en) Portable hanging flower basket suspension that construction was used is decorated to outdoor vestibule in high altitude
CN209837864U (en) Rail guard of convenient transportation and installation for building
WO2014073931A1 (en) Vinyl greenhouse
CN213626858U (en) Double-layer dustproof shed for GIS equipment installation
CN217205000U (en) Guardrail bar is prevented temporarily in construction
CN220685902U (en) Guardrail convenient to dismouting
CN209397995U (en) It is a kind of to be easily installed transport sightseeing tower
CN211549073U (en) Protector for construction
CN215056072U (en) Combined guardrail for building safety
CN213330359U (en) Assembled building protective fence
CN220849101U (en) Safety guard rail for engineering management
CN212201595U (en) Security protection device for construction
CN205000890U (en) No hindrance formula portal type tower wagon
CN114293562B (en) Enclosed construction enclosure
CN211396899U (en) Quick detach protection rail for building
CN214576194U (en) Rail guard for building engineering
CN219509394U (en) Protective fence convenient for butt joint installation
CN211369653U (en) Mobilizable large-scale canopy steel construction
CN208456195U (en) A kind of Anti-Typhoon mixing plant placing of material awning
CN216921259U (en) Movable track construction platform convenient to erect
CN215595176U (en) Municipal pipe network auxiliary device for maintenance engineering
CN217896727U (en) Sidewalk wind and rain pipe gallery
CN209873607U (en) Public road bridge is noise insulation for roof beam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191224

Termination date: 20210321

CF01 Termination of patent right due to non-payment of annual fee