CN209817441U - Aluminum alloy template pull rod fixing device - Google Patents

Aluminum alloy template pull rod fixing device Download PDF

Info

Publication number
CN209817441U
CN209817441U CN201822276115.XU CN201822276115U CN209817441U CN 209817441 U CN209817441 U CN 209817441U CN 201822276115 U CN201822276115 U CN 201822276115U CN 209817441 U CN209817441 U CN 209817441U
Authority
CN
China
Prior art keywords
aluminum alloy
pull rod
construction
flat iron
fixing device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822276115.XU
Other languages
Chinese (zh)
Inventor
赵志飞
岳齐贤
马光大
娄树松
张宗攀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang 20 Smelter Construction Co Ltd
China MCC20 Group Corp Ltd
Original Assignee
Zhejiang 20 Smelter Construction Co Ltd
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang 20 Smelter Construction Co Ltd, China MCC20 Group Corp Ltd filed Critical Zhejiang 20 Smelter Construction Co Ltd
Priority to CN201822276115.XU priority Critical patent/CN209817441U/en
Application granted granted Critical
Publication of CN209817441U publication Critical patent/CN209817441U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model provides an aluminum alloy template pull rod fixing device, belonging to the technical field of construction engineering; the technical problems of high construction difficulty, high loss and high cost of the existing aluminum alloy template are solved; a pull rod fixing device for an aluminum alloy template comprises a flat iron, wherein the flat iron is in a flat long strip shape and is axially arranged, first connecting holes are formed in two ends of the flat iron, and the flat iron is used for connecting two opposite templates and is pre-embedded into concrete; one end of the L-shaped connecting piece is provided with a hook part, the other end of the L-shaped connecting piece is provided with a second connecting hole, the second connecting hole is fixedly connected with the first connecting hole through a bolt, and a fin is arranged on the outer side wall of the L-shaped connecting piece; this pull rod fixing device, its simple structure, maneuverability is strong, only loses this item of band iron after pouring the completion, has practiced thrift construction cost greatly, simultaneously, compares in traditional screw thread pull rod, and this device greatly reduced construction cycle, reduced the construction degree of difficulty simultaneously.

Description

Aluminum alloy template pull rod fixing device
Technical Field
The utility model belongs to the technical field of the building engineering construction, a aluminum alloy template pull rod fixing device is related to.
Background
With the development of aluminum alloy templates and the large application of the aluminum alloy templates in construction projects. The aluminum alloy template has the advantages of light weight, convenient disassembly and smooth and flat surface of the poured concrete. The aluminum alloy template is used, the disassembly is convenient, the transportation cost can be effectively reduced, and the construction period is saved. In the concrete formwork pouring construction. When concrete is poured into the formwork, the concrete is diffused outwards due to gravity, the formwork is easily pushed outwards, and meanwhile, when the concrete is condensed, a certain amount of expansion of the concrete can be generated, so that the formwork expansion phenomenon can be caused. When the concrete formwork is poured, a threaded pull rod device is mostly adopted for fixing the aluminum alloy formwork. The threaded connecting rod is convenient to connect and can tightly fix the aluminum alloy template.
But threaded connecting rods are costly. The connecting rod is required to traverse the whole aluminum alloy formwork pouring area. The amount of fixing screws used is large. After pouring is finished, the screw rod is greatly injected into concrete, and protruding parts at two ends of the screw rod need to be cut off. Two ends of the threaded connecting rod are fixed in a nut screwing mode. When concrete pouring construction is carried out, a large number of aluminum alloy templates are often needed to be used as supports, and threaded connecting rods are used for connection, so that the construction workload is greatly increased.
In view of the defects of the threaded connecting rod in the pouring construction of the aluminum alloy formwork, the threaded connecting rod comprises the following components: 1. when the aluminum alloy templates are spliced, a connection and fixation mode of the threaded pull rod is adopted, a large amount of labor is consumed, the construction operation difficulty is increased, and the engineering period is easily influenced; 2. the threaded pull rod is high in manufacturing cost, the threaded pull rod is disposable, and a large number of threaded pull rods are used to increase the construction cost. The search of relevant documents shows that at present there is no good solution to the above problems.
SUMMERY OF THE UTILITY MODEL
The utility model aims at the above-mentioned problem that prior art exists, provide an aluminum alloy template pull rod fixing device that simple structure, the construction degree of difficulty are little, with low costs, the loss is little.
The purpose of the utility model can be realized by the following technical proposal: an aluminum alloy template pull rod fixing device comprises
The flat iron is in a flat long strip shape and is axially arranged, first connecting holes are formed in two ends of the flat iron, and the flat iron is used for connecting the two opposite templates and is pre-embedded into concrete;
and one end of the L-shaped connecting piece is provided with a hook part, the other end of the L-shaped connecting piece is provided with a second connecting hole, the second connecting hole is fixedly connected with the first connecting hole through a bolt, and the outer side wall of the L-shaped connecting piece is provided with fins.
Compared with the prior art, the utility model discloses following beneficial effect has:
1. this pull rod fixing device, its simple structure, maneuverability is strong, only loses this item of band iron after pouring the completion, has practiced thrift construction cost greatly, simultaneously, compares in traditional screw thread pull rod, and this device greatly reduced construction cycle, reduced the construction degree of difficulty simultaneously.
2. The utility model discloses a through the combination of L type connecting piece and band iron, realized the construction of buildding of aluminum alloy template, whole construction method is simple, convenient, easy operation. Compared with the existing construction method, the construction method has the advantages of high construction efficiency and small potential safety hazard.
Drawings
Fig. 1 is a plan view of the flat iron of the present invention.
Fig. 2 is a plan view of the L-shaped connector of the present invention.
Fig. 3 is a cross-sectional view of the L-shaped connector of the present invention.
In the figure, 10, flat iron; 11. a first connection hole; 20. an L-shaped connector; 21. a hook portion; 22. a second connection hole; 23. and a fin.
Detailed Description
The following are specific embodiments of the present invention and the accompanying drawings are used to further describe the technical solution of the present invention, but the present invention is not limited to these embodiments.
As shown in fig. 1-3, the utility model relates to an aluminum alloy formwork pull rod fixing device, which comprises a flat iron 10 and an L-shaped connecting piece 20.
The flat iron 10 is a flat long strip which is axially arranged, two ends of the flat iron 10 are provided with first connecting holes 11, the diameter of each first connecting hole 11 is 10mm, the flat iron 10 is used for connecting and fixing two opposite templates and is pre-embedded into concrete, the flat iron 10 is used for 1 time, after the pouring is finished, most of the flat iron 10 is poured in the wall body, the L-shaped connecting piece 20 can be recycled, the service life is long, the manufacturing process is simple, the price is low, one end of the L-shaped connecting piece 20 is provided with a hook part 21, the other end is provided with a second connecting hole 22, the second connecting hole 22 is fixedly connected with the first connecting hole 11 through a bolt, the outer side wall of the L-shaped connecting piece 20 is provided with a fin 23, the fins 23 are used for abutting against the lower portion of the template, so that the whole device can be stressed on average and can firmly lift the cross rod, the template building is simply and quickly completed, and meanwhile, the phenomenon of mold expansion in concrete pouring is effectively prevented.
The utility model discloses can adopt following step to be under construction:
s1: arranging an aluminum alloy template for pouring;
s2: the flat iron penetrates through the template, so that the first connecting holes at two ends of the flat iron are completely exposed out of the template;
s3: aligning a second connecting hole of the L-shaped connecting piece with a first connecting hole of the flat iron, and penetrating the two connecting holes by using bolts after the two connecting holes are aligned;
s4: other limiting devices are sequentially installed, and the limiting devices are installed in a horizontal line so as to be convenient for installing the cross rod;
s5: installing a horizontal cross rod at a concave position between the L-shaped connecting piece and the hook part, enabling the cross rod to be tightly attached to the L-shaped connecting piece and the aluminum alloy template, completing the installation work of the whole set of template, and pouring concrete;
s6: when the concrete is solidified to reach a certain strength, the cross bar is removed;
s7: taking down the fixing bolt and then taking down the L-shaped connecting piece;
s8: and after all the L-shaped connecting pieces are taken down, the aluminum alloy template is taken down, and the two end parts of the flat iron protruding from the concrete wall body are cut off to keep the wall surface smooth.
The specific embodiments described herein are merely illustrative of the spirit of the invention. Various modifications, additions and substitutions for the specific embodiments described herein may be made by those skilled in the art without departing from the spirit of the invention or exceeding the scope of the invention as defined in the accompanying claims.

Claims (1)

1. An aluminum alloy template pull rod fixing device is characterized by comprising
The flat iron is in a flat long strip shape and is axially arranged, first connecting holes are formed in two ends of the flat iron, and the flat iron is used for connecting the two opposite templates and is pre-embedded into concrete;
and one end of the L-shaped connecting piece is provided with a hook part, the other end of the L-shaped connecting piece is provided with a second connecting hole, the second connecting hole is fixedly connected with the first connecting hole through a bolt, and the outer side wall of the L-shaped connecting piece is provided with fins.
CN201822276115.XU 2018-12-31 2018-12-31 Aluminum alloy template pull rod fixing device Active CN209817441U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822276115.XU CN209817441U (en) 2018-12-31 2018-12-31 Aluminum alloy template pull rod fixing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822276115.XU CN209817441U (en) 2018-12-31 2018-12-31 Aluminum alloy template pull rod fixing device

Publications (1)

Publication Number Publication Date
CN209817441U true CN209817441U (en) 2019-12-20

Family

ID=68870523

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822276115.XU Active CN209817441U (en) 2018-12-31 2018-12-31 Aluminum alloy template pull rod fixing device

Country Status (1)

Country Link
CN (1) CN209817441U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109667424A (en) * 2018-12-31 2019-04-23 宁波二十冶建设有限公司 A kind of aluminum alloy mould plate draws lever fixing apparatus and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109667424A (en) * 2018-12-31 2019-04-23 宁波二十冶建设有限公司 A kind of aluminum alloy mould plate draws lever fixing apparatus and construction method

Similar Documents

Publication Publication Date Title
CN103758291A (en) Shearing reinforcing type semi-grouting sleeve
CN209817441U (en) Aluminum alloy template pull rod fixing device
CN204715763U (en) A kind of aluminum alloy mould plate diagonal brace supporting member pre-embedded bolt structure
CN108547383B (en) Hoisting and inclined strut integrated embedded part and using method
CN220725750U (en) Beam-column node template reinforcing device
CN203583859U (en) Embedded bolt anchoring device for fixing cantilever I-shaped steel in building construction
CN203230178U (en) Column formwork and column hoop
CN214942328U (en) Reinforced energy-saving building concrete formwork device
CN203097290U (en) Assembled type split bolt
CN205976532U (en) Sleeve grout connection structure and wall body
CN205134546U (en) But quick detachable I -steel built -in fitting of encorbelmenting of cyclic utilization
CN202359816U (en) Layering reinforcing and supporting device for on-situ concrete casting template
CN103590498A (en) Thin-wall steel structure house corner connecting structure and connection method
CN210622270U (en) Scaffold suitable for shear force wall
CN209585295U (en) Tower crane attaches wall built-in fitting
CN208763436U (en) A kind of PC component supporting apparatus
CN2711307Y (en) Active wall-thorugh crew-bolt device
CN206971718U (en) Novel road bridge anticollision wall form
KR20090091683A (en) Fixing device for mold concrete column of construction
CN204940844U (en) A kind of quick supporting mechanism based on standard combination template
CN219909315U (en) Assembled concrete member node connecting device
CN215978480U (en) Expanding hook bolt
CN216340983U (en) Construction hangs template installation limiter
CN219753297U (en) Supporting and reinforcing device for wall template
CN220245386U (en) Detachable platform of tower crane

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant