CN209798792U - open cut foundation pit deep silt layer vacuum dewatering system - Google Patents

open cut foundation pit deep silt layer vacuum dewatering system Download PDF

Info

Publication number
CN209798792U
CN209798792U CN201821844294.6U CN201821844294U CN209798792U CN 209798792 U CN209798792 U CN 209798792U CN 201821844294 U CN201821844294 U CN 201821844294U CN 209798792 U CN209798792 U CN 209798792U
Authority
CN
China
Prior art keywords
well
precipitation
dewatering
pipe
silt layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821844294.6U
Other languages
Chinese (zh)
Inventor
邹思鹏
刘继鹏
庞前凤
何小送
李朋辉
徐小燕
高延伟
牛永江
高绍鹏
蔡咸银
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 22nd Bureau Group Co Ltd
China Railway 22nd Bureau Group Urban Rail Engineering Co., Ltd.
China Railway Group Ltd CREC
Original Assignee
China Railway 22nd Bureau Group Urban Rail Engineering Co., Ltd.
China Railway Group Ltd CREC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 22nd Bureau Group Urban Rail Engineering Co., Ltd., China Railway Group Ltd CREC filed Critical China Railway 22nd Bureau Group Urban Rail Engineering Co., Ltd.
Priority to CN201821844294.6U priority Critical patent/CN209798792U/en
Application granted granted Critical
Publication of CN209798792U publication Critical patent/CN209798792U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

the utility model discloses an open cut basement deep silt layer vacuum dewatering system and construction method, including the precipitation well, the precipitation well degree of depth is 26 ~ 34m, and the well in-process meets cubic efflorescence or during the unable footage of apoplexy, can make the well in advance the final hole, and the mud aperture is 550mm, adopts diameter 273mm, wall thickness 3mm steel pipe, and the chimney filter is the bridge type strainer, outsourcing 80 mesh polyamide fibre filter screen, has set 1m sedimentation tube, and the filter material is above backfilling the chimney filter, adopts to bore sediment or original place soil to backfill the well cementation on it. The utility model relates to an open cut foundation ditch deep silt layer vacuum dewatering system and construction method, under the thick geological conditions in sea-filling mud flat silt layer, adopt the effectual safety and the efficiency that have guaranteed foundation ditch excavation of having improved dewatering effect of vacuum dewatering. Compared with the conventional precipitation, the precipitation period is shortened by adopting vacuum precipitation, the influence of transition precipitation on the peripheral earth surface and buildings can be prevented, the risk caused by foundation pit excavation precipitation is reduced, and meanwhile, the construction cost is also saved.

Description

Open cut foundation pit deep silt layer vacuum dewatering system
Technical Field
the utility model relates to a construction technical field, concretely relates to open cut basement is silt layer vacuum dewatering system deeply.
Background
In the excavation construction of the underground deep foundation pit with higher underground water level and confined water, in order to ensure the safety of the excavation of the foundation pit, particularly in the areas with large water content and large pressure bearing, the deep foundation pit needs to be subjected to precipitation design and construction. According to the scheme, the construction design and construction of deep foundation pit dewatering are carried out under the condition that most of geology of the sea-filling area of the open excavation section between the Shenzhen international convention and exhibition center is a silt layer, and related experiences are summarized so as to guide the dewatering construction under the similar conditions and improve the technical level of the dewatering construction of companies.
SUMMERY OF THE UTILITY MODEL
the utility model aims at providing a deep silt layer vacuum precipitation system of open cut foundation pit that displacement is big, the precipitation degree of depth is big, the precipitation scope is big.
In order to achieve the above object, the present invention provides the following technical solutions:
the utility model discloses an open cut basement dark silt layer vacuum precipitation system, include:
dewatering wells;
the number of dewatering wells is calculated according to the following formula:
In the formula: q is total water inflow (m3/d), Q is single well water output capacity (m3/d), and 20% of standby observation wells;
the depth of the dewatering well is 26-34 m, when the well is subjected to massive strong weathering or stroke weathering in the well forming process and cannot be drilled, the well can be formed in a final hole in advance, the aperture of mud is 550mm, a steel pipe with the diameter of 273mm and the wall thickness of 3mm is adopted, a bridge type water filtering pipe is adopted as a filtering pipe, an 80-mesh nylon filter screen is wrapped outside the filtering pipe, a 1m settling pipe is arranged below the filtering pipe, the filtering material is filled above a backfill filtering pipe, and drilling slag or original stratum soil is adopted for backfill well cementation.
Further, the water yield of a single well of the dewatering well is calculated according to the following formula:
in the formula: q-single well water output capacity (m 3/d); r-radius of filter tube (0.1365 m); l-effective filter tube length, 6 m; k-permeability coefficient of the aquifer (0.2 m/d).
in the technical scheme, the utility model relates to an open cut foundation ditch deep silt layer vacuum precipitation system and construction method under the thick geological conditions in sea-filling mud flat silt layer, adopts the effectual safety and the efficiency that have guaranteed the foundation ditch excavation of having improved precipitation effect of vacuum precipitation. Compared with the conventional precipitation, the precipitation period is shortened by adopting vacuum precipitation, the influence of transition precipitation on the peripheral earth surface and buildings can be prevented, the risk caused by foundation pit excavation precipitation is reduced, and meanwhile, the construction cost is also saved.
drawings
In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings needed to be used in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments described in the present invention, and other drawings can be obtained by those skilled in the art according to these drawings.
fig. 1 is a schematic structural diagram of a first vacuum dewatering system for a deep silt layer of an open trench foundation pit according to an embodiment of the present invention;
fig. 2 is a schematic structural diagram of a vacuum dewatering system for a deep silt layer of an open trench provided in an embodiment of the present invention;
fig. 3 is a third schematic structural view of a vacuum dewatering system for a deep silt layer of an open trench provided in an embodiment of the present invention;
Fig. 4 is a process flow chart of the vacuum dewatering system for the deep silt layer of the open excavation foundation pit provided by the embodiment of the utility model.
Detailed Description
in order to make the technical solution of the present invention better understood by those skilled in the art, the present invention will be further described in detail with reference to the accompanying drawings.
the first embodiment is as follows:
referring to fig. 1 to 3, an embodiment of the present invention provides a deep silt layer vacuum precipitation system for an open trench foundation pit, including:
Dewatering wells;
the number of dewatering wells is calculated according to the following formula:
in the formula: q is total water inflow (m3/d), Q is single well water output capacity (m3/d), and 20% of standby observation wells;
The depth of the dewatering well is 26-34 m, when the well is subjected to massive strong weathering or stroke weathering in the well forming process and cannot be drilled, the well can be formed in a final hole in advance, the aperture of mud is 550mm, a steel pipe with the diameter of 273mm and the wall thickness of 3mm is adopted, a filter pipe is a bridge type water filter pipe, an 80-mesh nylon filter screen is wrapped outside, a 1m settling pipe is arranged below the filter pipe, the filter material is filled to a position above a backfill filter pipe, and drilling slag or original stratum soil is used for backfilling and well cementation.
Preferably, the single-well water yield of the dewatering well is calculated according to the following formula:
In the formula: q-single well water output capacity (m 3/d); r-radius of filter tube (0.1365 m); l-effective filter tube length, 6 m; k-permeability coefficient of the aquifer (0.2 m/d).
example two:
the utility model discloses a construction method of open cut foundation pit deep silt layer vacuum dewatering system, including following step:
s1, preparing;
s2, entering a drilling rig;
s3, positioning and mounting;
S4, opening holes;
s5, a lower mouth guard pipe;
S6, drilling to form a hole;
S7, punching and replacing the slurry;
S8, a well descending pipe;
S9, diluting the slurry;
S10, filling sand;
S11, sealing water and holes;
s12, washing the well;
and S13, taking down the pump for trial pumping.
preferably, in step S1 above:
(1) preparing materials and implementing personnel, providing 'tee joint and level' for the final package, and entering a drilling machine;
(2) Measuring the well placement: and marking the general packet according to a dewatering well plane arrangement diagram and the field condition well logging position. If there is a surface obstruction at the deployed well site, it should be attempted to clear the obstruction to facilitate drilling. If the ground obstacles are not easy to clear or are influenced by other construction conditions, and the construction cannot be carried out at the original distributed well position, the ground obstacles should be communicated with a technician in time and take other measures, and the well position can be properly adjusted if necessary;
(3) Digging a well hole and burying a mouth protecting pipe: when the mouth protecting pipe is buried, the bottom mouth of the mouth protecting pipe is inserted into an undisturbed soil layer, cohesive soil or a straw braid is applied outside the pipe for sealing, the slurry return outside the pipe during construction is prevented, and the upper part of the mouth protecting pipe is 0.10-0.30 m higher than the ground;
(4) Installing a drilling machine: when a drilling machine is installed, in order to ensure the verticality of a hole, a machine table is installed stably and horizontally, a large hook is aligned with the center of the hole, the large hook, a rotary table and the center of the hole form a line, an opening is tightly closed, two drill collars are arranged at the joint of a drill bit and a drill rod, and the bent drill rod cannot be put into the hole;
(5) and (3) dredging a slurry pool: the size of the mud pit is comprehensively determined according to the well-digging quantity and the slag discharge quantity which are planned to be shared by the mud pit. Generally, 2-3 wells share one mud pit, and a mud tank can be adopted when necessary.
preferably, the construction mechanical equipment adopts a GF200 type engineering drilling machine and matched equipment thereof, and a reverse circulation rotary drilling hole forming process is adopted during hole forming;
(1) drilling to form a hole: in the drilling process, the specific gravity of the slurry is preferably controlled to be 1.10-1.15, and the formation is adopted to make slurry naturally as much as possible;
(2) cleaning holes and replacing slurry: after drilling to the designed depth, cleaning the hole and changing slurry, and adjusting the slurry to about 1.05;
(3) a well pipe is lowered: for the steel pipe well, a suspension pipe descending method is preferably adopted, the bottom of the well pipe is firmly blocked by welding a steel plate, the well pipe and the well pipe are firmly welded, the welding seam is ensured to be uniform and free of sand holes, and the pipe is immediately descended after the pore-forming is finished;
(4) feeding filter materials and cementing wells: after the well pipe is well lowered, the filter material is immediately backfilled according to the design requirement, the filter material is uniformly filled along the periphery of the well wall, and the height of the top surface of the filter material layer is measured along with the filling;
(5) Well washing and trying pumping: after the filter material is backfilled, the well should be washed by a submersible pump within 8 hours until the well water washing reaches the specification requirement. If the well water contains filter materials during well washing, the well washing is stopped, reasons are checked, the well washing is processed, the well washing is discarded if necessary, and the well is sealed according to the well sealing requirement.
according to the technical scheme, the blank of the construction technology of the company in the aspect is filled by summarizing the vacuum dewatering technology of the deep silt layer of the open excavation foundation pit of the sea-filling area, and a technical guidance direction is provided for similar projects of the company later, so that corresponding manpower and material resources are reduced.
the design of the precipitation construction scheme is comprehensively beneficial to reducing potential risks, improving construction efficiency, showing the technical level of technicians of the company to other persons and units in the industry and reducing the remediation cost of possible problems in the follow-up process, thereby reducing production cost.
due to the fact that a refined management mode is adopted in the dewatering well construction project, the method is beneficial to enhancing the utilization of resources, reducing the waste of the resources, further improving the management level and responsibility consciousness of managers, and establishing specialized teams which belong to the managers, so that the enterprise competitiveness of the managers is further improved.
The sea-filling area has rich water content, natural water content is generally greater than liquid limit, geology is mostly soft foundation, once stratum water level changes greatly, ground settlement is easily caused, and therefore the use performance of the building is affected, and therefore the research on the vacuum precipitation technology of the sea-filling area is necessary. Through the research on the vacuum precipitation technology of the deep silt layer of the open-cut foundation pit of the sea-filling area, the influence of earthwork construction on the surrounding environment, particularly the ground settlement of the surrounding area, can be reduced, so that the compensation cost of surrounding buildings is reduced, and the project benefit is maximized.
while certain exemplary embodiments of the present invention have been described above by way of illustration only, it will be apparent to those of ordinary skill in the art that the described embodiments may be modified in various different ways without departing from the spirit and scope of the present invention. Accordingly, the drawings and description are illustrative in nature and should not be construed as limiting the scope of the invention.

Claims (2)

1. The utility model provides an open cut foundation ditch deep silt layer vacuum precipitation system which characterized in that includes:
dewatering wells;
the number of dewatering wells is calculated according to the following formula:
in the formula: q is total water inflow (m3/d), Q is single well water output capacity (m3/d), and 20% of standby observation wells;
the depth of the dewatering well is 26-34 m, when the well is subjected to massive strong weathering or stroke weathering in the well forming process and cannot be drilled, the well can be formed in a final hole in advance, the aperture of mud is 550mm, a steel pipe with the diameter of 273mm and the wall thickness of 3mm is adopted, a bridge type water filtering pipe is adopted as a filtering pipe, an 80-mesh nylon filter screen is wrapped outside the filtering pipe, a 1m settling pipe is arranged below the filtering pipe, the filtering material is filled above a backfill filtering pipe, and drilling slag or original stratum soil is adopted for backfill well cementation.
2. The open cut foundation pit deep sludge layer vacuum dewatering system of claim 1, wherein the water yield of the dewatering well is calculated according to the following formula:
In the formula: q-single well water output capacity (m 3/d); r-radius of filter tube (0.1365 m); l-effective filter tube length, 6 m; k-permeability coefficient of the aquifer (0.2 m/d).
CN201821844294.6U 2018-11-09 2018-11-09 open cut foundation pit deep silt layer vacuum dewatering system Active CN209798792U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821844294.6U CN209798792U (en) 2018-11-09 2018-11-09 open cut foundation pit deep silt layer vacuum dewatering system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821844294.6U CN209798792U (en) 2018-11-09 2018-11-09 open cut foundation pit deep silt layer vacuum dewatering system

Publications (1)

Publication Number Publication Date
CN209798792U true CN209798792U (en) 2019-12-17

Family

ID=68816555

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821844294.6U Active CN209798792U (en) 2018-11-09 2018-11-09 open cut foundation pit deep silt layer vacuum dewatering system

Country Status (1)

Country Link
CN (1) CN209798792U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339080A (en) * 2018-11-09 2019-02-15 中铁二十二局集团轨道工程有限公司 A kind of open-cut foundation ditch deep slob region vacuum precipitation system and construction method
CN112682044A (en) * 2020-12-08 2021-04-20 上海市基础工程集团有限公司 Construction method of small-caliber dewatering well between narrow cracks

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339080A (en) * 2018-11-09 2019-02-15 中铁二十二局集团轨道工程有限公司 A kind of open-cut foundation ditch deep slob region vacuum precipitation system and construction method
CN112682044A (en) * 2020-12-08 2021-04-20 上海市基础工程集团有限公司 Construction method of small-caliber dewatering well between narrow cracks

Similar Documents

Publication Publication Date Title
CN109339080A (en) A kind of open-cut foundation ditch deep slob region vacuum precipitation system and construction method
CN104563098B (en) A kind of super-large diameter all steel casing does operation pore-creating filling pile construction method
CN104032760A (en) Foundation pit construction tube well dewatering method
CN109736338A (en) A kind of hydraulic engineering foundation pit pipe well combination light well point Yield rainfall relation method
CN110029680B (en) Deep foundation pit dewatering construction method
CN101294393A (en) Construction method with dewatering water well equipped outside of foundation pit
CN110735600B (en) Mechanical pore-forming pile construction process for karst geology
CN108457285A (en) A kind of ultra-deep cheats open type precipitation engineering method in hole
CN111139852A (en) Water-rich sandy gravel stratum high-permeability ultra-deep foundation pit dewatering construction method
CN111827328A (en) Subway deep foundation pit well point dewatering system and construction method thereof
CN209798792U (en) open cut foundation pit deep silt layer vacuum dewatering system
CN107816051A (en) Pressure-bearing property phreatic aquifer deep basal pit combination well dewatering construction method
CN111691425B (en) Water conservancy project foundation pit and pipe well combined light well point dewatering and drainage method
CN105926682A (en) Basement baseplate post-cast strip construction method with pressure bearing water and higher water pressure
CN108867673A (en) A kind of underwater prevention method in the foundation pit based on the curtain that draws water
CN214194602U (en) Precipitation structure suitable for deep foundation pit of high-pressure-bearing water-rich karst stratum
CN104652427A (en) Construction method of drilling pile
CN210341957U (en) Precipitation structure suitable for caisson
CN111173017A (en) Water stopping device and water stopping method for concrete pouring at bottom of reverse operation well of cyclone well
CN102979105A (en) Underground water control method of wellhole grouting and seepage insulation
CN114250801A (en) Pipe well and light well point combined dewatering construction method
CN111549807B (en) Water lowering and draining method combining water conservancy project foundation pit and pipe well with light well point
CN211037023U (en) Pipe well dewatering well arranged at bottom of underground diaphragm wall
CN111851548A (en) Dewatering inclined shaft in deep foundation pit and construction method thereof
CN201158823Y (en) Recoverable impact drill steel pipe downcast well

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant