CN209797238U CN201821906579.8U CN201821906579U CN209797238U CN 209797238 U CN209797238 U CN 209797238U CN 201821906579 U CN201821906579 U CN 201821906579U CN 209797238 U CN209797238 U CN 209797238U
Authority
CN
China
Prior art keywords
jig frame
jig
column
blast furnace
tuyere
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821906579.8U
Other languages
Chinese (zh)
Inventor
杨志刚
李光振
赵建国
张旭亮
王志刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201821906579.8U priority Critical patent/CN209797238U/en
Application granted granted Critical
Publication of CN209797238U publication Critical patent/CN209797238U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Blast Furnaces (AREA)

Abstract

A large and medium sleeve off-line combined hoisting jig frame for a blast furnace tuyere comprises an upper jig frame beam, a lower jig frame beam, a left jig frame column, a right jig frame column, a jig frame base, a lifting lug and four supporting beams, wherein the upper jig frame beam, the lower jig frame beam, the left jig frame column and the right jig frame column form a rectangular frame, the supporting beams are symmetrically welded on two sides of the left jig frame column and the right jig frame column in an inclined mode, and the jig frame base is welded at the bottoms of the left jig frame column and the right jig frame column; a lifting lug is welded on the upper cross beam of the jig frame; and the supporting beam on the upright column on the right side of the jig frame is fixedly connected with the tuyere large sleeve, and the tuyere middle sleeve is connected with the tuyere large sleeve. The utility model discloses be fit for under the less circumstances of operation platform, carry out off-line combination hoist and mount and simple to operate to big well cover of blast furnace tuyere.

Description

Off-line combined hoisting jig frame for large and medium sleeves of blast furnace tuyere
Technical Field
the utility model belongs to the technical field of the construction, especially, relate to a big well cover off-line combination hoist and mount bed-jig of blast furnace tuyere.
Background
With the requirement of the existing blast furnace transformation, the off-line construction of some blast furnaces is further moved to a design position, and the blast furnace building is also completed off line, so that the large and medium sleeves of the blast furnace tuyere also need to be installed off line.
When the existing blast furnace tuyere large and medium sleeves are installed on line, the tuyere platform is installed, so that the operating space of personnel is large, and the installation can be carried out manually according to the lever principle. If the off-line installation is carried out, the method is adopted, and the operation platform is small, so that the manual installation according to the lever principle is difficult to realize.
Disclosure of Invention
The utility model aims at providing a cover off-line combination hoist and mount bed-jig in big or middle of blast-furnace tuyere, this bed-jig are fit for under the less condition of operation platform, carry out off-line combination hoist and mount and simple to operate to the cover in big or middle of blast-furnace tuyere.
As the conception, the technical proposal of the utility model is that: a large and medium sleeve off-line combined hoisting jig frame for a blast furnace tuyere comprises an upper jig frame beam, a lower jig frame beam, a left jig frame column, a right jig frame column, a jig frame base, a lifting lug and four supporting beams, wherein the upper jig frame beam, the lower jig frame beam, the left jig frame column and the right jig frame column form a rectangular frame, the supporting beams are symmetrically welded on two sides of the left jig frame column and the right jig frame column in an inclined mode, and the jig frame base is welded at the bottoms of the left jig frame column and the right jig frame column; a lifting lug is welded on the upper cross beam of the jig frame; and the supporting beam on the upright column on the right side of the jig frame is fixedly connected with the tuyere large sleeve, and the tuyere middle sleeve is connected with the tuyere large sleeve.
The lifting lug is made of a 20MM thick steel plate.
The upper and lower beams of the jig frame, the left and right upright posts of the jig frame, the base of the jig frame and the supporting beams are made of H250-250 section steel.
The included angle between the supporting beam and the left and right upright posts of the mould is 70 degrees.
And positioning pins are fixedly arranged on the left stand column and the right stand column of the jig frame.
The utility model discloses a bed-jig right side supporting beam is fixed as balanced through the bolt with the big cover in wind gap, fix with a bed-jig left side supporting beam after the big well cover in wind gap equipment is integrative, carry out the crane hoist and mount with lug on crane wire rope and 3 tons of chain blocks and the bed-jig entablature and the lug connection of connecting on the big cover in left side wind gap, utilize 3 tons of chain blocks to carry out angular adjustment, then carry out bolt fastening with the big cover in wind gap and the big cover flange in wind gap, utilize 3 tons of chain blocks to carry out angular adjustment, on hoist and mount the big well cover combination in wind gap and the wind gap flange after targetting in place, down, a left side, the right side respectively with two sets of formal bolt fastening screw up, unpack the big well cover in wind gap combination in wind gap and the bed-jig left side fixing bolt down the.
Therefore, because the utility model discloses set up balancing unit, be fit for carrying out off-line combination hoist and mount and simple to operate to big well cover of blast furnace tuyere under the less condition of operation platform.
Drawings
fig. 1 is a schematic elevation view of the utility model;
FIG. 2 is a schematic sectional view taken along line A-A of FIG. 1;
FIG. 3 is a schematic view of a vertical surface of a blast furnace tuyere after a large and a middle sleeve are assembled and installed off line.
In the figure: 1. the device comprises a jig frame, an upper beam, a lower beam, 2 jig frame left and right stand columns, 3 jig frame bases, 4 lifting lugs, 5 lifting lug fixing bolts, 6 supporting beams, 7 fixing bolts, 8 positioning pins, 9 fixing pieces, 10 fixing inclined irons, 11 tuyere large sleeves, 12 tuyere middle sleeves, 13 hoisting steel wire ropes, 14.3 ton chain blocks, 15 furnace shells and 16 tuyere flanges.
Detailed Description
As shown in the figure: a large and medium sleeve off-line combined hoisting jig frame for a blast furnace tuyere comprises an upper jig frame beam, a lower jig frame beam, a left jig frame column, a right jig frame column, a jig frame base, a lifting lug and four supporting beams, wherein the upper jig frame beam, the lower jig frame beam, the left jig frame column and the right jig frame column form a rectangular frame, the supporting beams are welded at two sides of the left jig frame column and the right jig frame column in a symmetrical inclined mode at an included angle of 70 degrees, and the bottom of the left jig frame column and the bottom of the right jig frame column are welded with the jig frame; lifting lugs are welded on the upper cross beam of the jig frame and deviate from the center by 250MM, and the lifting lugs are made of thick steel plates of 20 MM; the supporting beam on the upright column on the right side of the jig frame is fixedly connected with the tuyere large sleeve through five sets of fixing bolts, and the tuyere middle sleeve and the tuyere large sleeve are connected with a fixed wedge arranged on a fixed sheet through the fixed sheet.
The upper and lower beams of the jig frame, the left and right upright posts of the jig frame, the base of the jig frame and the supporting beams are made of H250-250 section steel.
The utility model discloses a work progress is:
1. A supporting beam on the left side of the jig frame and a tuyere large middle sleeve share five sets of fixing bolts with the tail part cut to leave the thickness of 7MM for fixing nuts to the center of the jig frame in the lateral direction, and the tuyere large sleeve is connected with a lifting lug through a lifting lug fixing bolt;
2. A crane steel wire rope and a 3-ton chain block are connected with a lifting lug on the upper beam of the jig frame and a lifting lug connected to the left air port large sleeve to carry out crane lifting, and the 3-ton chain block is used for carrying out angle adjustment;
3. After the tuyere large-middle sleeve combination is hoisted in place, the tuyere large-middle sleeve combination and the upper part, the lower part, the left part and the right part of a tuyere flange are respectively fixed and screwed by two sets of formal bolts, and the gaps between the contact surface of the tuyere large sleeve and the tuyere flange and the surface of the tuyere flange are uniform;
4. And (4) disassembling the air port large and medium sleeve combination and hanging the jig frame down by a fixing bolt on the left side of the jig frame, and completing and screwing the large sleeve and the air port flange bolt.
The above description is only exemplary of the present invention and should not be taken as limiting the scope of the present invention, as any modifications, equivalents, improvements and the like made within the spirit and principles of the present invention are intended to be included within the scope of the present invention.

Claims (5)

1. The utility model provides a big well cover off-line combination hoist and mount bed-jig of blast furnace tuyere which characterized in that: the jig comprises an upper jig frame cross beam, a lower jig frame cross beam, a left jig frame upright column, a right jig frame upright column, a jig frame base, a lifting lug and four supporting beams, wherein the upper jig frame cross beam, the lower jig frame cross beam, the left jig frame upright column and the right jig frame upright column form a rectangular frame, the supporting beams are symmetrically welded on two sides of the left jig frame upright column and the right jig frame upright column in an inclined mode, and the bottom of the left jig frame upright column and the bottom of the right jig; a lifting lug is welded on the upper cross beam of the jig frame; and the supporting beam on the upright column on the right side of the jig frame is fixedly connected with the tuyere large sleeve, and the tuyere middle sleeve is connected with the tuyere large sleeve.
2. the blast furnace tuyere large and medium bushing off-line combined hoisting jig frame as claimed in claim 1, wherein: the lifting lug is made of a 20MM thick steel plate.
3. The blast furnace tuyere large and medium bushing off-line combined hoisting jig frame as claimed in claim 1, wherein: the upper and lower beams of the jig frame, the left and right upright posts of the jig frame, the base of the jig frame and the supporting beams are made of H250-250 section steel.
4. The blast furnace tuyere large and medium bushing off-line combined hoisting jig frame as claimed in claim 1, wherein: the included angle between the supporting beam and the left and right upright posts of the mould is 70 degrees.
5. The blast furnace tuyere large and medium bushing off-line combined hoisting jig frame as claimed in claim 1, wherein: and positioning pins are fixedly arranged on the left stand column and the right stand column of the jig frame.
CN201821906579.8U 2018-11-19 2018-11-19 Off-line combined hoisting jig frame for large and medium sleeves of blast furnace tuyere Active CN209797238U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821906579.8U CN209797238U (en) 2018-11-19 2018-11-19 Off-line combined hoisting jig frame for large and medium sleeves of blast furnace tuyere

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821906579.8U CN209797238U (en) 2018-11-19 2018-11-19 Off-line combined hoisting jig frame for large and medium sleeves of blast furnace tuyere

Publications (1)

Publication Number Publication Date
CN209797238U true CN209797238U (en) 2019-12-17

Family

ID=68816632

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821906579.8U Active CN209797238U (en) 2018-11-19 2018-11-19 Off-line combined hoisting jig frame for large and medium sleeves of blast furnace tuyere

Country Status (1)

Country Link
CN (1) CN209797238U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112139695A (en) * 2020-09-24 2020-12-29 中国二十二冶集团有限公司 Method for replacing middle section of blast furnace shell
CN112575133A (en) * 2020-11-30 2021-03-30 上海宝冶冶金工程有限公司 Method for mounting jig frame of furnace body

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112139695A (en) * 2020-09-24 2020-12-29 中国二十二冶集团有限公司 Method for replacing middle section of blast furnace shell
CN112575133A (en) * 2020-11-30 2021-03-30 上海宝冶冶金工程有限公司 Method for mounting jig frame of furnace body

Similar Documents

Publication Publication Date Title
US6260270B1 (en) Method and apparatus for short-term relining or construction of blast furnace
CN209797238U (en) Off-line combined hoisting jig frame for large and medium sleeves of blast furnace tuyere
CN100412234C (en) Large-scale aluminium electrolysis pre-baking tank
CN112518659A (en) Construction method for replacing joint bearing and pin shaft on inner side of crank on ladle turret
CN109055637B (en) Hydraulic lifting process for mounting furnace shell in blast furnace overhaul
CN201303279Y (en) Motor assembly and disassembly tools of narrow and small terminal surface location in space
CN207738316U (en) Large scale single wall bottom board steel lifting box integral hoisting suspender
CN211769817U (en) Lifting appliance for chemical tower sections
CN101831916B (en) Method for mounting large-size sleeve bolt framework in combined type
CN115367616A (en) Furnace shell hoisting device for blast furnace overhaul and installation and use method thereof
CN214527826U (en) Special hoisting structure of prefabricated bent cap
CN215854574U (en) Quick mounting and dismounting fixture for box girder template
CN105382784B (en) Change the frock of mixed iron blast base and roller-way
CN210702528U (en) Temporary fixing device for ladle turret revolving arm of large slab caster
CN113044732A (en) Special hoisting structure of prefabricated bent cap
CN108975171B (en) Segmented accurate dismounting device for water beam and upright column of heating furnace and use method
CN105033600B (en) Mill liner disassembly and assembly auxiliary tool and working method thereof
CN110724783B (en) Dismantling and installing method of waste heat boiler in converter environment-friendly reconstruction
CN111750667A (en) Prefabricated hanging assembly and prefabricated part at top of kiln head cover of rotary kiln
CN201296785Y (en) Rail hoisting machine group arranged at the maintenance channel of electrolytic aluminium plant
CN102311042A (en) Lifting appliance of transport system for intensive overhaul of electrolytic bath and lifting method
CN218025016U (en) Furnace shell hoisting device for blast furnace overhaul
CN204831512U (en) Single section truck scale of online adjustment of ability and weighing platform screw thread board interchangeable
CN204788607U (en) Take single section truck scale of mould assembling of cambered surface block group and weighing platform screw thread board interchangeable
CN102030271B (en) Lifting device with fixed pulley set dismantling and landing automatically and self-dismantling method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant