CN209726169U - Anti-blocking Wind cap for boiler used in a kind of power plant - Google Patents

Anti-blocking Wind cap for boiler used in a kind of power plant Download PDF

Info

Publication number
CN209726169U
CN209726169U CN201920420072.XU CN201920420072U CN209726169U CN 209726169 U CN209726169 U CN 209726169U CN 201920420072 U CN201920420072 U CN 201920420072U CN 209726169 U CN209726169 U CN 209726169U
Authority
CN
China
Prior art keywords
blast cap
rotary shaft
ring disk
cap
power plant
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920420072.XU
Other languages
Chinese (zh)
Inventor
李立东
孙景福
周亦平
杨伟宏
张明朝
张智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Datang Dongying Power Generation Co Ltd
Original Assignee
Datang Dongying Power Generation Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Datang Dongying Power Generation Co Ltd filed Critical Datang Dongying Power Generation Co Ltd
Priority to CN201920420072.XU priority Critical patent/CN209726169U/en
Application granted granted Critical
Publication of CN209726169U publication Critical patent/CN209726169U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Air Supply (AREA)

Abstract

The utility model discloses anti-blocking Wind cap for boiler used in a kind of power plant, including blast cap set and blast cap cone lid, the blast cap cone lid is located at blast cap and covers lower end, and it is fixedly connected, the blast cap set sidewall upper offers exhaust vent, and exhaust vent is equipped with several groups, the blast cap set is internally provided with ventilative partition, the ventilative partition includes isolation the ring disk, and isolation the ring disk is equipped with multiple groups, reinforcement connecting rod is fixedly connected between the isolation the ring disk, air-permeating hole is equipped between the isolation the ring disk and reinforcement connecting rod, the ventilative partition middle-end is provided with rotary shaft hole, the blast cap cone lid inner upper end is equipped with motor, the motor lower end is equipped with rotary shaft, the rotary shaft bottom side of the wall is equipped with exhausting blade, the utility model structure is simple, it is novel in design, the failure for avoiding boiler internal coking occurs, and avoid blast cap because The pernicious phenomenon that can not be reused to be completely plugged, extends the service life of blast cap.

Description

Anti-blocking Wind cap for boiler used in a kind of power plant
Technical field
The utility model relates to blast cap technical field, anti-blocking Wind cap for boiler used in specially a kind of power plant.
Background technique
There is a kind of boiler of recirculating fluidized bed in generation current factory, the bottom of burner hearth needs to arrange many blast caps, with Guarantee that coal dust can be burnt in burner hearth with boiling-like.The shape of blast cap is relatively more, to be wherein similar to for the blast cap of mushroom, blast cap The cap head of upper end be it is closed, plug is processed into lower end, to be vertically mounted on the bottom of burner hearth, and blast cap center be it is empty, On the circumference under cap head edge, row's ventilation hole is opened.After boiler shutdown, blast cap no longer air draft, the small-particle coal of high temperature exists The bottom of burner hearth is deposited under gravity.When there is the accident of boiler coke, boiler needs urgent blowing out, and blast cap can be quickly Stop ventilation, then a large amount of high temperature small-particle coals at a deadlock can be easily advanced into the blast cap hole of blast cap, in height The small-particle coal of temperature just forms a bigger cinder group after through supercooling and mutually sticking together, and then causes to block up to blast cap hole Plug causes many troubles to the investigation blocking of later period blast cap.In addition, all blast cap holes when blast cap are after cooling by bulky grain After coke button is completely plugged, blast cap will be unable to continue to use.
Utility model content
The purpose of this utility model is to provide anti-blocking Wind cap for boiler used in a kind of power plant, to solve above-mentioned background The problem of being proposed in technology.
To achieve the above object, the utility model provides the following technical solutions: including blast cap set and blast cap cone lid, the wind Cap cone lid is located at blast cap and covers lower end, and is fixedly connected, and the blast cap set sidewall upper offers exhaust vent, and if exhaust vent be equipped with Dry group, the blast cap set are internally provided with ventilative partition, and the ventilative partition includes isolation the ring disk, and the ring disk is isolated equipped with more Group, is fixedly connected with reinforcement connecting rod between the isolation the ring disk, the isolation the ring disk and reinforces being equipped between connecting rod ventilative Hole, the ventilative partition middle-end are provided with rotary shaft hole, and the blast cap cone lid inner upper end is equipped with motor, and the motor lower end is set There is rotary shaft, the rotary shaft bottom side of the wall is equipped with exhausting blade, and the blast cap cone lid interior lower end is provided with water storage box, described Blast cap cone lid lower end is internally provided with water-supply-pipe, and the water-supply-pipe lower end is equipped with isocon, and the isocon lower end is equipped with spray head, And spray head is equipped with several groups.
Further, isolation the ring disk described in multiple groups is set as structure not of uniform size, and is attached by reinforcing connecting rod It is fixed.
Further, the exhaust vent is provided with 45 ° of inclination angles in blast cap set side wall.
Further, the rotary shaft passes through the rotary shaft hole of ventilative partition middle-end, and the distance between with rotary shaft hole For mm.
Further, the water storage box is circumscribed with water inlet pipe, and carries out control inflow by outside.
Further, the water-supply-pipe passes through blast cap cone lid lower end and communicates with water storage box, and the isocon is bored in blast cap to be covered Lower end has been arranged radially multiple groups.
Compared with prior art, the utility model has the beneficial effects that
1, the utility model drives rotary shaft to drive exhausting blade by motor, allows to increase outlet air rate, so that can Exhaust gas progress to be discharged quickly through exhaust vent, and exhaust vent is provided with 45 ° of inclination angles in blast cap set side wall, allows to It can be more quickly discharged according to oblique after pumping;
2, the utility model carries out water delivery into isocon by water-supply-pipe by water storage box, and is discharged by spray head, So that the high temperature small-particle coal in flue gas is carried out cooling aggregation, allow to be attached to ventilative baffle surface, convenient for after a shutdown into Row is uniformly processed, and boiler internal coking is avoided, so that boiler is able to use longer life expectancy;
3, the utility model structure is simple, novel in design, and the failure for avoiding boiler internal coking occurs, and avoids The pernicious phenomenon that blast cap can not be reused because of completely plugged extends the service life of blast cap.
Detailed description of the invention
Fig. 1 is the utility model overall structure diagram;
Fig. 2 is the utility model schematic diagram of internal structure;
Fig. 3 is the ventilative diaphragm structure schematic diagram of the utility model;
Fig. 4 is the utility model spray structure schematic diagram.
In Fig. 1-4: 1- blast cap set;2- blast cap cone lid;3- exhaust vent;4- motor;5- water storage box;6- rotary shaft;7- exhausting Blade;8- isocon;The ventilative partition of 9-;10- air-permeating hole;11- rotary shaft hole;The ring disk is isolated in 12-;13- reinforces connecting rod;14- Water-supply-pipe;15- spray head.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-4 is please referred to, the utility model provides a kind of technical solution: including blast cap set 1 and blast cap cone lid 2.
The blast cap cone lid 2 is located at blast cap and covers 1 lower end, and is fixedly connected.
Wherein, blast cap set 1 bores being fixedly connected for lid 2 with blast cap, its connection can be made more stable, and in internal element It will not fall off when being worked.
The blast cap covers 1 sidewall upper and offers exhaust vent 3, and exhaust vent 3 is equipped with several groups.
Wherein, exhaust vent 3 exhaust gas can be quickly discharged, and dust is avoided to assemble in inside.
Blast cap set 1 is internally provided with ventilative partition 9, and the ventilative partition 9 includes isolation the ring disk 12, and isolation ring Disk 12 is equipped with multiple groups, is fixedly connected between the isolation the ring disk 12 and reinforces connecting rod 13, and the isolation the ring disk 12 and reinforcement connect Air-permeating hole 10 is equipped between extension bar 13, ventilative 9 middle-end of partition is provided with rotary shaft hole 11.
Wherein, exhaust gas can be carried out isolation rising conveying by ventilative partition 9, can more efficiently pass through 3 row of exhaust vent Out, and after carrying out depositing dust the high temperature small-particle coal in flue gas can be assembled, avoids falling into a pot slagging.
Blast cap cone 2 inner upper end of lid is equipped with motor 4, and 4 lower end of motor is equipped with rotary shaft 6, under the rotary shaft 6 End side wall is equipped with exhausting blade 7.
Wherein, motor 4 drives rotary shaft 6 to drive exhausting blade 7, allows to increase outlet air rate, allows to exhaust gas Progress is discharged quickly through exhaust vent.
Blast cap cone 2 interior lower end of lid is provided with water storage box 5, and the blast cap cone 2 lower end of lid is internally provided with water-supply-pipe 14,14 lower end of water-supply-pipe is equipped with isocon 8, and 8 lower end of isocon is equipped with spray head 15, and spray head 15 is equipped with several groups.
Wherein, water storage box 5 carries out water delivery into isocon 8 by water-supply-pipe 14, and is discharged by spray head 15, and flue gas is made In high temperature small-particle coal carry out cooling aggregation, allow to be attached to ventilative 9 surface of partition, convenient for carry out after a shutdown unification Processing, avoids boiler internal coking, so that boiler is able to use longer life expectancy.
Further, isolation the ring disk 12 described in multiple groups is set as structure not of uniform size, and is carried out by reinforcing connecting rod 13 It is connected and fixed.
Wherein, isolation the ring disk 12 can form multi-level structure, can adhere to the high temperature little particle in more flue gases Coal.
Further, the exhaust vent 3 covers in 1 side wall in blast cap is provided with 45 ° of inclination angles.
Wherein, the exhaust vent 3 at 45 ° of inclination angles preferably can help exhaust gas to be discharged.
Further, the rotary shaft 6 passes through the rotary shaft hole 11 of ventilative 9 middle-end of partition, and between rotary shaft hole 11 Distance be 5mm.
Wherein, rotary shaft 6 can be avoided when being rotated scratches ventilative partition 9, can more quickly Exhausting is carried out, help is quickly exhausted.
Further, the water storage box 5 is circumscribed with water inlet pipe, and carries out control inflow by outside.
Wherein, external water inlet pipe can be supplemented always after the water of water storage box 5 is sprayed, and avoid water shortage.
Further, the water-supply-pipe 14 passes through blast cap cone 2 lower end of lid and communicates with water storage box 5, and the isocon 8 is in blast cap Cone 2 lower end of lid has been arranged radially multiple groups.
Wherein, it is arranged radially the isocon 8 of multiple groups, preferably the high temperature small-particle coal in flue gas can be dropped Temperature, depositing dust processing avoid water is not caused enough from cannot assembling the high temperature small-particle coal in flue gas.
Working principle: in use, in boiler operatiopn, internal exhaust gas is discharged, and then opens motor 4,4 band of motor Dynamic rotary shaft 6 drives exhausting blade 7, allows to increase outlet air rate, allows to carry out exhaust gas quickly through 3 row of exhaust vent Out, and exhaust vent 3 covers in 1 side wall in blast cap and is provided with 45 ° of inclination angles, allow to after pumping can more quickly according to Oblique to be discharged, while exhaust, water storage box 5 carries out water delivery into isocon 8 by water-supply-pipe 14, and by spray head 15 into Row discharge, makes the high temperature small-particle coal in flue gas carry out cooling aggregation, allows to be attached to ventilative 9 surface of partition, is convenient for It is uniformly processed after shutdown, avoids boiler internal coking, so that boiler is able to use longer life expectancy, can effectively prevent pot The failure of furnace interior coking occurs.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment Intrinsic element.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (6)

1. anti-blocking Wind cap for boiler used in a kind of power plant, including blast cap set (1) and blast cap cone lid (2), the blast cap cone lid (2) it is located at blast cap set (1) lower end, and is fixedly connected, it is characterised in that: blast cap set (1) sidewall upper offers exhaust vent (3), and exhaust vent (3) is equipped with several groups, and the blast cap set (1) is internally provided with ventilative partition (9), the ventilative partition (9) Include isolation the ring disk (12), and the ring disk (12) are isolated and are equipped with multiple groups, is fixedly connected with reinforcement between the isolation the ring disk (12) Connecting rod (13) is equipped with air-permeating hole (10) between the isolation the ring disk (12) and reinforcement connecting rod (13), the ventilative partition (9) Middle-end is provided with rotary shaft hole (11), and blast cap cone lid (2) inner upper end is equipped with motor (4), and motor (4) lower end is equipped with Rotary shaft (6), rotary shaft (6) bottom side of the wall are equipped with exhausting blade (7), and described blast cap cone lid (2) interior lower end is provided with Water storage box (5), described blast cap cone lid (2) lower end are internally provided with water-supply-pipe (14), and water-supply-pipe (14) lower end, which is equipped with, to be shunted It manages (8), isocon (8) lower end is equipped with spray head (15), and spray head (15) is equipped with several groups.
2. anti-blocking Wind cap for boiler used in a kind of power plant according to claim 1, it is characterised in that: described in multiple groups every It is set as structure not of uniform size from the ring disk (12), and is attached fixation by reinforcing connecting rod (13).
3. anti-blocking Wind cap for boiler used in a kind of power plant according to claim 1, it is characterised in that: the exhaust vent (3) 45 ° of inclination angles are provided in blast cap set (1) side wall.
4. anti-blocking Wind cap for boiler used in a kind of power plant according to claim 1, it is characterised in that: the rotary shaft (6) rotary shaft hole (11) of ventilative partition (9) middle-end is passed through, and is 5mm with the distance between rotary shaft hole (11).
5. anti-blocking Wind cap for boiler used in a kind of power plant according to claim 1, it is characterised in that: the water storage box (5) it is circumscribed with water inlet pipe, and control inflow is carried out by outside.
6. anti-blocking Wind cap for boiler used in a kind of power plant according to claim 1, it is characterised in that: the water-supply-pipe (14) it passes through blast cap cone lid (2) lower end to communicate with water storage box (5), the isocon (8) is bored lid (2) lower end in blast cap and is arranged radially There are multiple groups.
CN201920420072.XU 2019-03-29 2019-03-29 Anti-blocking Wind cap for boiler used in a kind of power plant Active CN209726169U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920420072.XU CN209726169U (en) 2019-03-29 2019-03-29 Anti-blocking Wind cap for boiler used in a kind of power plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920420072.XU CN209726169U (en) 2019-03-29 2019-03-29 Anti-blocking Wind cap for boiler used in a kind of power plant

Publications (1)

Publication Number Publication Date
CN209726169U true CN209726169U (en) 2019-12-03

Family

ID=68689480

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920420072.XU Active CN209726169U (en) 2019-03-29 2019-03-29 Anti-blocking Wind cap for boiler used in a kind of power plant

Country Status (1)

Country Link
CN (1) CN209726169U (en)

Similar Documents

Publication Publication Date Title
CN102424867B (en) Slag granulating and waste heat recovery device
CN204313270U (en) A kind of biomass shaped fuel boiler
CN209726169U (en) Anti-blocking Wind cap for boiler used in a kind of power plant
CN207694473U (en) Powder silo top dust-extraction unit
CN110056895A (en) A kind of drum-type break slag-draining device for biological combustor
CN206980349U (en) A kind of grey storehouse ash-discharging device
CN204388087U (en) Antibiotic bacterium slag energy treatment facility system
CN210385296U (en) Cyclone spark catcher
CN107416373A (en) A kind of incineration of refuse flyash automatic storage unloads grey storehouse
CN202105544U (en) High-temperature resistant dust remover
CN208326685U (en) Spider-web type anti-blocking fluidization ash conveying system
CN207471566U (en) Biomass combustion boiler nozzle and ashes cooling system
CN206310497U (en) A kind of pneumatic rain cap
CN207073816U (en) A kind of structure beneficial to industrial furnace fuel combustion heat conduction
CN2192807Y (en) Energy-saving outer circulation fluidizing bed boiler
CN108998051A (en) A kind of control dirt control sulphur system of coke oven list gas collecting tube
CN212319684U (en) Built-in biomass particle combustion heat supply equipment
CN214598171U (en) High-efficient tar flue gas desulphurization unit
CN208313090U (en) Anti-clogging is blown row pipe flue gas evaporator
CN205351300U (en) Automatic disintegrating slag combustor of carousel formula
CN213631592U (en) Immersed cooling roasting slag discharging system
CN107726349A (en) Biomass combustion boiler nozzle and ashes cooling system
CN206642491U (en) A kind of glass furnace exhaust processor
CN209584125U (en) A kind of bottom construction for uniform biomass gasifying furnace of slagging tap