CN209702039U CN201920258225.5U CN201920258225U CN209702039U CN 209702039 U CN209702039 U CN 209702039U CN 201920258225 U CN201920258225 U CN 201920258225U CN 209702039 U CN209702039 U CN 209702039U
Authority
CN
China
Prior art keywords
fixedly installed
diameter
ring
stacker
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920258225.5U
Other languages
Chinese (zh)
Inventor
马学飞
赵巍
刘琛
郭鹏
王超
陈旭光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Construction Group Corp Ltd
Original Assignee
Hebei Construction Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Construction Group Corp Ltd filed Critical Hebei Construction Group Corp Ltd
Priority to CN201920258225.5U priority Critical patent/CN209702039U/en
Application granted granted Critical
Publication of CN209702039U publication Critical patent/CN209702039U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to technical field of building construction, and disclose a kind of construction elevator guardrail, including bearing bar, support leg, stacker, locating rod, connector, bolt, connecting plate, mounting rack, hinge, web plate, fixture block, shank, fixed ring, support spring, shift(ing) ring, pull ring, fixed block, clamping block and mobile bar, the bottom end of two bearing bars is fixedly installed with support leg.The construction elevator guardrail, it is docked by the locating rod of setting with stacker, to complete to fix to the position of connecting plate, fixed ring is pushed by the support spring of setting, so that fixed ring drives shank and fixture block stuck, mounting rack is locked to realize, guarantee the stability of its connection procedure, by pulling pull ring that the disassembly to entire guardrail can be completed, working efficiency is improved, the hinge of setting is passed through, facilitate two mounting racks of doubling, reduce space accounting, convenient transportation promotes its reliability.

Description

A kind of construction elevator guardrail
Technical field
The utility model relates to technical field of building construction, specially a kind of construction elevator guardrail.
Background technique
Construction refers to the production activity of engineering construction implementation phase, is the building course of all kinds of buildings, can also be with It says it is various lines on design drawing, in specified place, becomes process in kind, it includes basic engineering construction, master Body structure construction, roof construction and decorative engineering construction etc., the place of construction operation is known as construction site or cries to apply Building site is also named at work scene, and elevator is the hoistway for installing elevator, and the size of hoistway is determined according to elevator selection, the borehole wall Upper installation elevator rail and counterweight track, reserved door opening install elevator door, and well headroom has elevator(lift) machine room.
During construction of lift well, to guarantee that the safety of construction carries out, it is normal to guarantee guardrail to be set in lift port Construction, presently used guardrail generally use fixedly mounted, and installation process is relatively cumbersome, not easy to disassemble, volume itself compared with Greatly, not readily transportable, so a kind of construction elevator guardrail is proposed to solve the above problems.
Utility model content
(1) the technical issues of solving
In view of the deficiencies of the prior art, the utility model provides a kind of construction elevator guardrail, has and facilitates peace The advantages that dress is with transport, solves during construction of lift well, to guarantee that the safety of construction carries out, can be arranged in lift port and protect Column guarantees normal construction, and presently used guardrail generally uses fixedly mounted, and installation process is relatively cumbersome, not readily removable It unloads, volume itself is larger, not readily transportable problem.
(2) technical solution
It is above-mentioned during construction of lift well to realize, to guarantee that the safety of construction carries out, guardrail can be set in lift port Guaranteeing normal construction, presently used guardrail generally uses fixedly mounted, and installation process is relatively cumbersome, and it is not easy to disassemble, Volume itself is larger, and not readily transportable purpose, the utility model provides the following technical solutions: a kind of construction elevator shield Column, including bearing bar, support leg, stacker, locating rod, connector, bolt, connecting plate, mounting rack, hinge, web plate, fixture block, Shank, fixed ring, support spring, shift(ing) ring, pull ring, fixed block, clamping block and mobile bar, the bottom end of two bearing bars It is fixedly installed with support leg, the opposite side of two bearing bars is fixedly installed with the stacker that quantity is two, institute It states and is plugged with locating rod at the top of stacker, connector is fixedly installed at the top of the locating rod, the connector passes through spiral shell Bolt is fixedly connected with connecting plate, and mounting rack, two installations are fixedly connected between two ipsilateral connecting plates The hinge that quantity is two is fixedly connected between frame, the inside of two mounting racks is fixedly installed with web plate, two institutes State the opposite side of mounting rack and be fixedly installed with fixture block, the opposite side of two bearing bars be plugged with respectively with two The shank that fixture block is mutually clamped is fixedly installed with fixed ring on two shanks, and the outside of two shanks is equal It is socketed with the support spring of a side contacts opposite with two fixed rings respectively, the outside of two shanks is fixedly mounted There is the shift(ing) ring of a side contacts opposite with two support springs respectively, two opposite one end of the shank are fixedly mounted There is pull ring, the front of the mounting rack on the left side is fixedly installed with fixed block, and the front of the mounting rack on the right is fixedly mounted There is clamping block, is connected with mobile bar between the fixed block and clamping block.
Preferably, the stacker is in bending, and the bending angle of bending place is 90 degree.
Preferably, locating slot is offered at the top of the stacker, the diameter of locating slot is adapted with the diameter of locating rod.
Preferably, two opposite sides of the bearing bar offer shifting chute, the diameter of shifting chute and shank Diameter is adapted.
Preferably, the diameter of the support spring is adapted with the diameter of shank, and the diameter of the fixed ring is greater than branch The diameter of spring is supportted, the diameter of the shift(ing) ring is greater than the diameter of support spring.
Preferably, the opposite side of two fixture blocks opens up fluted, and two shanks are respectively engaged with two In a groove.
(3) beneficial effect
Compared with prior art, the utility model provides a kind of construction elevator guardrail, has following beneficial to effect Fruit:
The construction elevator guardrail, is docked by the locating rod of setting with stacker, to complete to connecting plate Position is fixed, and fixed ring is pushed by the support spring of setting, so that fixed ring drives shank and fixture block stuck, to realize Mounting rack is locked, guarantees the stability of its connection procedure, by pulling pull ring that the disassembly to entire guardrail can be completed, is mentioned Working efficiency has been risen, by the hinge of setting, has facilitated two mounting racks of doubling, reduces space accounting, convenient transportation promotes it Reliability.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is the enlarged drawing in the utility model Fig. 1 at A;
Fig. 3 is the enlarged drawing in the utility model Fig. 1 at B;
Fig. 4 is the enlarged drawing in the utility model Fig. 1 at C.
In figure: 1 bearing bar, 2 support legs, 3 stackers, 4 locating rods, 5 connectors, 6 bolts, 7 connecting plates, 8 mounting racks, 9 Hinge, 10 web plates, 11 fixture blocks, 12 shanks, 13 fixed rings, 14 support springs, 15 shift(ing) rings, 16 pull rings, 17 fixed blocks, 18 cards Connect block, 19 mobile bars.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Please refer to Fig. 1-4, a kind of construction elevator guardrail, including bearing bar 1, support leg 2, stacker 3, locating rod 4, connector 5, bolt 6, connecting plate 7, mounting rack 8, hinge 9, web plate 10, fixture block 11, shank 12, fixed ring 13, support bullet Spring 14, shift(ing) ring 15, pull ring 16, fixed block 17, clamping block 18 and mobile bar 19, the bottom end of two bearing bars 1 are fixedly mounted There is support leg 2, the opposite side of two bearing bars 1 is fixedly installed with the stacker 3 that quantity is two, and stacker 3 is in bending Shape, the bending angle of bending place are 90 degree, and the top of stacker 3 is plugged with locating rod 4, and the top of stacker 3 offers fixed Position slot, the diameter of locating slot are adapted with the diameter of locating rod 4, and the top of locating rod 4 is fixedly installed with connector 5, connector 5 It is fixedly connected with connecting plate 7 by bolt 6, mounting rack 8, two peaces are fixedly connected between two ipsilateral connecting plates 7 Shelving and being fixedly connected with quantity between 8 is two hinges 9, and the inside of two mounting racks 8 is fixedly installed with web plate 10, two The opposite side of mounting rack 8 is fixedly installed with fixture block 11, and the opposite side of two bearing bars 1 is plugged with blocks with two respectively The shank 12 of 11 phase of block clamping, two opposite sides of bearing bar 1 offer shifting chute, the diameter and shank of shifting chute 12 diameter is adapted, the opposite side of two fixture blocks 11 open up it is fluted, two shanks 12 be respectively engaged with two it is recessed In slot, be fixedly installed with fixed ring 13 on two shanks 12, the outside of two shanks 12 be socketed with respectively with two The support spring 14 of the opposite side contacts of fixed ring 13, the outside of two shanks 12 be fixedly installed with respectively with two branch The shift(ing) ring 15 of the opposite side contacts of spring 14 is supportted, the diameter of support spring 14 is adapted with the diameter of shank 12, fixed The diameter of ring 13 is greater than the diameter of support spring 14, and the diameter of shift(ing) ring 15 is greater than the diameter of support spring 14, two shanks 12 opposite one end are fixedly installed with pull ring 16, and the front of the mounting rack 8 on the left side is fixedly installed with fixed block 17, the peace on the right The front for shelving 8 is fixedly installed with clamping block 18, mobile bar 19 is connected between fixed block 17 and clamping block 18, by setting The locating rod 4 set is docked with stacker 3, to complete to fix the position of connecting plate 7, is pushed by the support spring 14 of setting Fixed ring 13, to realize to the locked of mounting rack 8, guarantees it so that fixed ring 13 drives shank 12 and fixture block 11 stuck The stability of connection procedure improves working efficiency, by setting by pulling pull ring 16 that the disassembly to entire guardrail can be completed The hinge 9 set facilitates two mounting racks 8 of doubling, reduces space accounting, and convenient transportation promotes its reliability.
In conclusion the construction elevator guardrail, is docked by the locating rod 4 of setting with stacker 3, to complete The position of connecting plate 7 is fixed, fixed ring 13 is pushed by the support spring 14 of setting, so that fixed ring 13 drives shank 12 It is stuck with fixture block 11, to realize to the locked of mounting rack 8, guarantee the stability of its connection procedure, by pulling pull ring 16 to be The achievable disassembly to entire guardrail, improves working efficiency, by the hinge 9 of setting, facilitates two mounting racks 8 of doubling, subtracts Space accounting is lacked, convenient transportation promotes its reliability.
It should be noted that the terms "include", "comprise" or its any other variant are intended to the packet of nonexcludability Contain, so that the process, method, article or equipment for including a series of elements not only includes those elements, but also including Other elements that are not explicitly listed, or further include for elements inherent to such a process, method, article, or device. In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including the element Process, method, article or equipment in there is also other identical elements.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (6)

1. a kind of construction elevator guardrail, including bearing bar (1), support leg (2), stacker (3), locating rod (4), connection Part (5), bolt (6), connecting plate (7), mounting rack (8), hinge (9), web plate (10), fixture block (11), shank (12), fixed ring (13), support spring (14), shift(ing) ring (15), pull ring (16), fixed block (17), clamping block (18) and mobile bar (19), it is special Sign is: the bottom end of two bearing bars (1) is fixedly installed with support leg (2), two bearing bars (1) it is opposite one Side is fixedly installed with the stacker (3) that quantity is two, is plugged with locating rod (4) at the top of the stacker (3), described fixed It being fixedly installed with connector (5) at the top of position bar (4), the connector (5) is fixedly connected with connecting plate (7) by bolt (6), It is fixedly connected with mounting rack (8) between two ipsilateral connecting plates (7), it is fixed between two mounting racks (8) It is connected with the hinge (9) that quantity is two, the inside of two mounting racks (8) is fixedly installed with web plate (10), two institutes It states the opposite side of mounting rack (8) to be fixedly installed with fixture block (11), two opposite sides of the bearing bar (1) are plugged with The shank (12) being mutually clamped with two fixture blocks (11) respectively is fixedly installed with fixed ring on two shanks (12) (13), the outside of two shanks (12) is socketed with the support of a side contacts opposite with two fixed ring (13) respectively The outside of spring (14), two shanks (12) is fixedly installed with side opposite with two support spring (14) respectively The shift(ing) ring (15) of contact, two opposite one end of the shank (12) are fixedly installed with pull ring (16), the left side it is described The front of mounting rack (8) is fixedly installed with fixed block (17), and the front of the mounting rack (8) on the right is fixedly installed with clamping block (18), mobile bar (19) are connected between the fixed block (17) and clamping block (18).
2. a kind of construction elevator guardrail according to claim 1, it is characterised in that: the stacker (3) is in curved Shape is rolled over, the bending angle of bending place is 90 degree.
3. a kind of construction elevator guardrail according to claim 1, it is characterised in that: the top of the stacker (3) Portion offers locating slot, and the diameter of locating slot is adapted with the diameter of locating rod (4).
4. a kind of construction elevator guardrail according to claim 1, it is characterised in that: two bearing bars (1) Opposite side offers shifting chute, and the diameter of shifting chute is adapted with the diameter of shank (12).
5. a kind of construction elevator guardrail according to claim 1, it is characterised in that: the support spring (14) Diameter is adapted with the diameter of shank (12), and the diameter of the fixed ring (13) is greater than the diameter of support spring (14), described The diameter of shift(ing) ring (15) is greater than the diameter of support spring (14).
6. a kind of construction elevator guardrail according to claim 1, it is characterised in that: two fixture block (11) phases The side of back opens up fluted, and two shanks (12) are respectively engaged in two grooves.
CN201920258225.5U 2019-03-01 2019-03-01 A kind of construction elevator guardrail Expired - Fee Related CN209702039U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920258225.5U CN209702039U (en) 2019-03-01 2019-03-01 A kind of construction elevator guardrail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920258225.5U CN209702039U (en) 2019-03-01 2019-03-01 A kind of construction elevator guardrail

Publications (1)

Publication Number Publication Date
CN209702039U true CN209702039U (en) 2019-11-29

Family

ID=68642795

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920258225.5U Expired - Fee Related CN209702039U (en) 2019-03-01 2019-03-01 A kind of construction elevator guardrail

Country Status (1)

Country Link
CN (1) CN209702039U (en)

Similar Documents

Publication Publication Date Title
CN201864516U (en) Lifting appliance special for overhauling isolating switch
CN208763263U (en) A kind of connection structure of glass curtain wall crossbeam and column
CN209702039U (en) A kind of construction elevator guardrail
CN211690963U (en) Green energy-saving building curtain wall suitable for multiple places
CN209538656U (en) A kind of detachable large-scale steel structure Construction Supporting System bracket
CN216076389U (en) Combined mechanical auxiliary device for quickly installing complex metal curtain wall
CN216865633U (en) Super large glass curtain wall mounting structure
CN201412940Y (en) Split type air conditioner outdoor machine installing frame
CN210395771U (en) Mounting structure convenient to dismantle building curtain
CN210656136U (en) Device for conveniently sleeving quilt core into quilt cover
CN208844913U (en) A kind of integrated form climbing frame
CN207296356U (en) A kind of easy-to-mount building hanging basket
CN201485204U (en) Gas tank hanging device
CN206359154U (en) A kind of steel construction secondary member hoisting device
CN218562988U (en) Hanging point truss of attached lifting scaffold
CN215483575U (en) Combined steel structural member for building curtain wall engineering
CN210236874U (en) Lifting appliance for mounting elevator track
CN220300184U (en) Portable combination formula curtain unit plate portal frame
CN219986061U (en) Steel bar bending device for engineering building
CN213449400U (en) Support for civil engineering building convenient to adjust
CN216403649U (en) Electromechanical engineering equipment fixing and positioning device
CN209344185U (en) A kind of easy-to-mount battery cupboard battery bracket
CN216405893U (en) Indoor ceiling connection structure
CN217229863U (en) Elevator steel construction well convenient to installation
CN208168429U (en) A kind of construction safety temporary support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191129

Termination date: 20210301

CF01 Termination of patent right due to non-payment of annual fee