CN209686977U - A kind of wisdom communication tower - Google Patents

A kind of wisdom communication tower Download PDF

Info

Publication number
CN209686977U
CN209686977U CN201821924591.1U CN201821924591U CN209686977U CN 209686977 U CN209686977 U CN 209686977U CN 201821924591 U CN201821924591 U CN 201821924591U CN 209686977 U CN209686977 U CN 209686977U
Authority
CN
China
Prior art keywords
tower
base unit
tower bar
pedestal
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821924591.1U
Other languages
Chinese (zh)
Inventor
李震
范志华
许清秀
陈维健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Juyi Steel Co Ltd
Original Assignee
Zhejiang Juyi Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Juyi Steel Co Ltd filed Critical Zhejiang Juyi Steel Co Ltd
Priority to CN201821924591.1U priority Critical patent/CN209686977U/en
Application granted granted Critical
Publication of CN209686977U publication Critical patent/CN209686977U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Support Of Aerials (AREA)

Abstract

The utility model relates to a kind of wisdom communication tower, including tower body and column foot, tower body includes by the first tower bar of casing connection, the second tower bar, third tower bar, the 4th tower bar and the 5th tower bar from bottom to top;First tower bar lower end is equipped with flanged plate, support plate is equipped between the flanged plate and the first tower bar, the first tower bar lower end is connected to pedestal pipeline section upper end;First tower bar top or the second tower bar are equipped with obliquity sensor and several cameras, the obliquity sensor and camera are connect by wireless network with base station communication, all cameras be circumferentially uniformly arranged in the first tower bar or the second tower bar periphery and camera away from ground level between 3.5m-6m;5th tower bar is equipped with antenna system and the solar battery for power supply.The oneself state of the utility model energy feedback communication tower is to base station, convenient for management.

Description

A kind of wisdom communication tower
Technical field
The utility model relates to communication tower field more particularly to a kind of wisdom communication towers.
Background technique
Notification number is that the utility model patent of CN204402130U discloses a kind of direct burial single-pipe tower pedestal, including two A pedestal pipeline section in attachment beam upper center, Yi Jilian is bolted in bottom beam that is horizontally disposed and being parallel to each other Connect totally four support rods between two bottom beam upper ends and pedestal pipeline section upper portion side wall.Disclosed in the utility model patent Direct burial single-pipe tower pedestal, using four support rods being connected between two bottom beam upper ends and pedestal pipeline section upper portion side wall Enhance the intensity of pedestal pipeline section, makes it can there is stronger stability after single-pipe tower is installed.But pedestal is by passing through spiral shell It tethers the bottom beam, attachment beam and support rod connect to constitute, bottom beam and attachment beam are channel steel structure, are only applicable to mounting height in 10m Within single-pipe tower, if the height of single-pipe tower is larger, during the pedestal of above structure installation single-pipe tower, in casting concrete Just there is the possibility toppled over before.
On the other hand, communication tower in the prior art, in the use process after communication tower is installed, however it remains incline Possibility, but to not monitored in real time in the use of communication tower, once the communication in a certain area is broken down, can only pass through The scene of carrying out at the communication tower in this area for forming communication network is manually gone to check one by one, it can not be quickly by positioning problems Onto specific communication tower.
Utility model content
To solve the above-mentioned problems, it the purpose of this utility model is to provide a kind of wisdom communication tower, is easily installed and removes Fortune is convenient, and the oneself state of mounting structure stabilization and energy feedback communication tower is to base station, convenient for management.
In order to achieve the above purpose, the utility model uses technical solution below:
A kind of wisdom communication tower, including tower body and column foot, the column foot include multiple first base units, two the second bases Seat unit, a third base unit, a pedestal pipeline section and four support rods, first base unit, the second pedestal list Member and third base unit are reinforced concrete structure;Multiple first base units are combined into the pedestal of pedestal;Second pedestal The both ends of unit are equipped with connector, and the connector includes the connection otic placode perpendicular to the setting of the second base unit upper surface;The Two base units and third base unit are each attached on pedestal, and two the second base units are parallel to each other, two base units On all connectors be distributed in the four corners of pedestal;Third base unit is located at base center, fixes on third base unit There is anchor bolt that is multiple longitudinally disposed and being distributed in the horizontal plane with circumference array, the upper and lower end parts of pedestal pipeline section are respectively equipped with flange Plate, pedestal pipeline section lower end are fixed on third base unit, and the upper outside wall of pedestal pipeline section is fixedly welded there are four engaging lug; The both ends of support rod are connected on connection otic placode and engaging lug, from surrounding support base pipeline section;
The tower body includes by the first tower bar of casing connection, the second tower bar, third tower bar, the 4th tower bar from bottom to top With the 5th tower bar;First tower bar lower end is equipped with flanged plate, support plate is equipped between the flanged plate and the first tower bar, under the first tower bar End is connected to pedestal pipeline section upper end;First tower bar top or the second tower bar are equipped with obliquity sensor and several cameras, described Obliquity sensor and camera are connect by wireless network with base station communication, and all cameras are circumferentially uniformly arranged in the first tower Bar or the second tower bar periphery and camera are away from ground level between 3.5m-6m;5th tower bar is equipped with antenna system and use In the solar battery of power supply.
Preferably, the tower body be no more than 35m, first tower bar, the second tower bar, third tower bar, the 4th tower bar and The length ratio of 5th tower bar is 7:8:8:8:7.
Preferably, being equipped with ground connection band iron in the first tower body;The top of 5th tower bar is equipped with lightning rod.
Preferably, composition pedestal is arranged side by side in multiple first base units, the long edge of the second base unit forms bottom Multiple first base unit short sides setting of seat, two the second base units are separately positioned on the both ends of the first base unit, the It is cooperatively connected respectively by pre-embedded bolt and connecting hole between two base units and each first base unit.
Preferably, be located at the middle of the base wherein several first base units be equipped at least four it is longitudinally disposed and It is evenly distributed on the third pre-embedded bolt of same circumference, passes through the pre-buried spiral shell of third between third base unit and the first base unit It tethers and connects.
Preferably, being equipped with hanging ring on the first base unit, the second base unit and third base unit.
The pedestal of above-mentioned single-pipe tower pedestal, setting reinforced concrete structure soil structure carries out counterweight, increases the stabilization of pedestal Property, it can be used in single-pipe tower of the mounting height in 35m.Two the second base units of reinforced concrete structure are set, it can be into One step increases the weight of pedestal, and one end for four support rods provides connection structure.Communication tower pedestal uses detachable knot Structure, easy to carry and installation.Tower body equally uses Demountable, easy for removal and installation, and by setting on tower body To camera and obliquity sensor, it is capable of the use state of feedback communication tower to base station, convenient for the management to communication tower.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of communication tower pedestal in the utility model.
Fig. 2 is the top view of Fig. 1.
Fig. 3 is the structural schematic diagram of communication tower in the utility model.
Wherein: 1, pedestal, the 11, first base unit, the 12, second base unit, 121, connector, 13, third pedestal list Member, 14, pedestal pipeline section, 15, support rod.
Specific embodiment
The preferred embodiment of this patent is described in further detail with reference to the accompanying drawing.
Present embodiment discloses a kind of wisdom communication towers, including tower body 2 and column foot 1, as depicted in figs. 1 and 2, the column foot 1 The base of third base unit 13, one of the second base unit 12, one being parallel to each other including multiple first base units 11, two Seat pipe section 14 and four support rods 15, first base unit 11, the second base unit 12 and third base unit 13 are Reinforced concrete structure.
First base unit 11 is cuboid, and multiple first base units 11 connect composition one big two-by-two in the horizontal plane Cuboid, the length and width for the cuboid being spliced by multiple first base units 11 are at least 5m, and length and width Difference is within 1m.The pedestal of the big cuboid as pedestal 1, when installation, are placed in bottom of foundation ditch, for pedestal 1 provide big self weight with Guarantee the stability of pedestal 1.A biggish base is spliced into using the first base unit 11 of multiple small volumes in the application Seat pedestal, facilitates carrying.The pedestal can be the single layer structure or multilayered structure spliced by multiple first base units 11, this Pedestal in embodiment is the single layer structure that multiple first base units 11 are spliced into, and the upper surface of the first base unit 11 is in length Rectangular, multiple first base units 11, which are arranged side by side, is spliced into that upper surface is square or the difference of length and width is within 1m Rectangle.In other embodiments, can be two or more first base units 11 is one group, multiple first bases in group Seat unit is set side by side, and the first base unit of multiple groups is arranged side by side and is assembled into pedestal.In other embodiments, the first base unit Upper surface can be square, in such a situation it is preferred to each layer of pedestal be all made of the combining forms such as 3*3 or 4*4 spelling It is connected into the square structure in upper surface.It will be appreciated by persons skilled in the art that being combined into pedestal pedestal in embodiment Multiple first base units and it is indefinite be single size, can also by a variety of various sizes of concrete precast blocks it is combined and spliced at Pedestal.
Second base unit 12 is cuboid, and the both ends of the second base unit 12 are equipped with the second pre-embedded bolt and pass through second Pre-embedded bolt and nut are fitted with connector 121, and connector 121 is made of connecting bottom board and connection otic placode, connecting bottom board Parallel with the upper surface of the second base unit 12, connecting bottom board is equipped with the connection cooperated with the second pre-embedded bolt on second unit Hole;Connection otic placode is vertically fixed on connecting bottom board, and connecting hole is equally offered in connection otic placode.In specific embodiment, even Connect bottom plate and between connection otic placode can be integrally formed, or both by being welded and fixed.Two the second pedestals being parallel to each other Unit 12 is arranged on the pedestal being spliced to form by the first base unit 11, and all connections on two the second base units 12 Part is respectively distributed to the four corners of pedestal.Second base unit 12 is equipped with several longitudinal holes, and the first base unit 111 is corresponding Longitudinal hole on second 2 yuan of pedestal list is embedded with several first pre-embedded bolts, in order to simplify installation, multiple first base units 11 are arranged side by side composition pedestal, and multiple first base unit, 11 short sides of the long edge composition pedestal of the second base unit 12 are set Set, two the second base units 12 are separately positioned on the both ends of 11 length direction of the first base unit, the second base unit 12 with It is cooperatively connected respectively by the first pre-embedded bolt and nut between each first base unit 11.It is multiple by this setup It can not have to that other connection structure is arranged between first base unit 11 to be to pass through the realization of the second base unit to be reliably connected.This Pedestal in embodiment, even if forming can generally stay between the first base unit of adjacent two of pedestal after the completion of connection After having splicing gap, pedestal to be completed in foundation pit and connect single-pipe tower, the concrete or sandy soil filled into foundation pit can be filled out Splicing gap is filled to guarantee the stability of pedestal.
The setting of third base unit 13 in the base the heart, be located between two the second base units 12, be located at the middle of the base Wherein several first base units 11 be equipped at least four thirds that are longitudinally disposed and being evenly distributed on same circumference it is pre- Bolt is buried, is connected between third base unit 13 and first base unit 11 by third pre-embedded bolt.Third base unit 13 are equipped with multiple the 4th pre-embedded bolts for being used to connect pedestal tube section 14.
14 upper and lower end parts of pedestal pipeline section are equipped with flanged plate, and flanged plate is equipped with connecting hole, flanged plate and pedestal pipeline section side Multiple reinforcers are equipped between wall to reinforce the intensity of junction.Connecting hole on the flanged plate of 14 bottom of pedestal pipeline section corresponding the The setting of four pre-embedded bolts, is cooperatively connected between pedestal pipeline section and third base unit by the 4th pre-embedded bolt and nut.Pedestal The upper outside wall of pipeline section 14 is fixedly welded there are four engaging lug.
Support rod 13 is by support tube and is welded on two connection sheets at support tube both ends and constitutes, and two connection sheets are led to respectively Bolt is crossed to be fixedly connected with connection otic placode and engaging lug.By four support rods from surrounding support base pipeline section, base can be enhanced The stability of seat pipe section.
Preferably, being respectively equipped on the first base unit, the second base unit and third base unit in the present embodiment Hanging ring is to carry.
As shown in figure 3, the tower body 2 includes by the first tower bar 21 of casing connection, the second tower bar 22, from bottom to top Three tower bars 23, the 4th tower bar 24 and the 5th tower bar 25;First tower bar, 21 lower end is equipped with flanged plate 3, the flanged plate 3 and the first tower bar Support plate is equipped between 21,21 lower end of the first tower bar is connected to 14 upper end of pedestal pipeline section;First tower bar, 21 top or the second tower bar 22 are equipped with obliquity sensor and several cameras 5, and the obliquity sensor and camera 5 pass through wireless network and base station communication Connection, all cameras 5 are circumferential to be uniformly arranged in 22 periphery of the first tower bar 21 or the second tower bar, and camera 5 is away from ground height Degree is between 3.5m-6m;5th tower bar 25 is equipped with antenna system 251 and the solar battery for power supply.Above-mentioned communication Tower, equipped with camera 5 to monitor tower body ambient conditions, tower body periphery is circumferentially arranged in several cameras, and away from ground height Degree the case where can be realized around 360 ° omni-directional monitoring tower body, and video information is fed back to base station between 3.5m-6m, Once there is the problems such as tower body is toppled over, administrative staff can analyze the environmental factor that tower body is toppled over by video information.Inclination angle is set Sensor monitors the angle of tower body, once the inclination angle for detecting tower body can issue alarm signal to pedestal beyond safe range Management console is locked and is solved the problems, such as in time convenient for administrative staff.
The tower body is no more than 35m, and all tower bars for constituting tower body are round tube of the caliber in 40-80cm, and described first Tower bar 21, the second tower bar 22, third tower bar 23, the 4th tower bar 24 and the 5th tower bar 25 length ratio be 7:8:8:8:7.As It is preferred that billboard can also be equipped in the first tower bar 21 or the second tower bar 22, billboard away from ground level 3.5m-6m it Between;Billboard is liquid crystal display, and billboard is connect by wireless network with base station, is thrown by the advertisement that base station controls billboard It puts.Realize the multifunction of communication tower.
It is equipped with ground connection band iron in first tower bar 21, is equipped with lightning rod at the top of the 5th tower bar 25.Lightning rod and ground connection band iron are logical Conducting wire connection is crossed, and is connected to low aerial drainage earth mat.
It is emphasized that: the above is only the preferred embodiment of the present utility model, not appoints to the utility model What formal limitation, any simple modification made by the above technical examples according to the technical essence of the present invention, etc. With variation and modification, it is still within the scope of the technical solutions of the present invention.For example, passing through between all first base units Laterally or longitudinally perforative long bolt connection is equally able to achieve the scheme of the application.

Claims (6)

1. a kind of wisdom communication tower, including tower body and column foot, which is characterized in that the column foot include multiple first base units, Two the second base units, a third base unit, a pedestal pipeline section and four support rods, first base unit, Second base unit and third base unit are reinforced concrete structure;Multiple first base units are combined into the bottom of pedestal Seat;The both ends of second base unit are equipped with connector, and the connector includes being arranged perpendicular to the second base unit upper surface Connection otic placode;Second base unit and third base unit are each attached on pedestal, and two the second base units are parallel to each other, and two All connectors on a base unit are distributed in the four corners of pedestal;Third base unit is located at base center, third pedestal Anchor bolt that is multiple longitudinally disposed and being distributed in the horizontal plane with circumference array, the upper and lower side part of pedestal pipeline section are fixed on unit Not She You flanged plate, pedestal pipeline section lower end is fixed on third base unit, and the upper outside wall of pedestal pipeline section is fixedly welded with Four engaging lugs;The both ends of support rod are connected on connection otic placode and engaging lug, from surrounding support base pipeline section;
The tower body includes by the first tower bar of casing connection, the second tower bar, third tower bar, the 4th tower bar and from bottom to top Five tower bars;First tower bar lower end is equipped with flanged plate, and support plate is equipped between the flanged plate and the first tower bar, and the first tower bar lower end connects It is connected to pedestal pipeline section upper end;First tower bar top or the second tower bar are equipped with obliquity sensor and several cameras, the inclination angle Sensor and camera are connect by wireless network with base station communication, and all cameras are circumferentially uniformly arranged on the first tower bar or the Two tower bar peripheries and camera are away from ground level between 3.5m-6m;5th tower bar is equipped with antenna system and for powering Solar battery.
2. a kind of wisdom communication tower according to claim 1, which is characterized in that the tower body be no more than 35m, described first Tower bar, the second tower bar, third tower bar, the 4th tower bar and the 5th tower bar length ratio be 7:8:8:8:7.
3. a kind of wisdom communication tower according to claim 1, which is characterized in that be equipped with ground connection band iron in the first tower body;The The top of five tower bars is equipped with lightning rod.
4. a kind of wisdom communication tower according to claim 1, which is characterized in that group is arranged side by side in multiple first base units At pedestal, multiple first base unit short sides setting of the long edge composition pedestal of the second base unit, two the second pedestal lists Member is separately positioned on the both ends of the first base unit, respectively by pre-buried between the second base unit and each first base unit Bolt and connecting hole are cooperatively connected.
5. a kind of wisdom communication tower according to claim 1, which is characterized in that positioned at the middle of the base wherein several One base unit is equipped at least four third pre-embedded bolts that are longitudinally disposed and being evenly distributed on same circumference, third pedestal list It is connected between member and the first base unit by third pre-embedded bolt.
6. a kind of wisdom communication tower according to claim 1, which is characterized in that the first base unit, the second base unit Hanging ring is equipped with on third base unit.
CN201821924591.1U 2018-11-20 2018-11-20 A kind of wisdom communication tower Expired - Fee Related CN209686977U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821924591.1U CN209686977U (en) 2018-11-20 2018-11-20 A kind of wisdom communication tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821924591.1U CN209686977U (en) 2018-11-20 2018-11-20 A kind of wisdom communication tower

Publications (1)

Publication Number Publication Date
CN209686977U true CN209686977U (en) 2019-11-26

Family

ID=68595111

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821924591.1U Expired - Fee Related CN209686977U (en) 2018-11-20 2018-11-20 A kind of wisdom communication tower

Country Status (1)

Country Link
CN (1) CN209686977U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112127696A (en) * 2020-10-26 2020-12-25 东来智慧交通科技(深圳)有限公司 Manufacturing method of multifunctional smart bar base and multifunctional smart bar base

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112127696A (en) * 2020-10-26 2020-12-25 东来智慧交通科技(深圳)有限公司 Manufacturing method of multifunctional smart bar base and multifunctional smart bar base

Similar Documents

Publication Publication Date Title
US7059095B1 (en) Anchored monopole upgrade system
US20110027100A1 (en) Mobile wind power station
US20040233120A1 (en) Temporary cellular antenna site
CN207847228U (en) A kind of overturning-preventing concrete wire pole
CN107839849A (en) Environmentally friendly one uses plug-in water surface photovoltaic generating system
CN209686977U (en) A kind of wisdom communication tower
CN207377264U (en) A kind of spliced foundation pit protective fence
CN111754733A (en) Mountain torrent disaster monitoring and early warning platform
CN108063592A (en) A kind of environmental friend type multifunction pedal plug-in water surface photovoltaic generating system
JP2016220510A (en) Frame unit of photovoltaic power generation panel for snowy district
BR112021014703A2 (en) MULTI-COLUMN WIND TURBINE TOWER AND RAISING METHOD
CN205647344U (en) New energy monitoring camera power supply unit
KR100662883B1 (en) Reinforce structure of steel tower
CN116517016A (en) Traffic facility foundation fixing device with embedded bolts
CN207296567U (en) A kind of intelligence communication bar
CN212162764U (en) Building electrical construction safety device
CN109057497B (en) A kind of anti-freeze expansion shaft tower
CN106437274A (en) Portable reusable communication tower base
CN208347421U (en) A kind of installing type communication tower
CN207974608U (en) A kind of power tower damping base
CN107939613B (en) Stacked tower system for wind gathering power generation
CN113175196A (en) Cable net construction platform
CN214530682U (en) Building strutting arrangement for civil engineering for real estate
CN221194567U (en) Airport escape canal surrounding all-in-one structure
CN210420936U (en) Height-limiting top frame and height-limiting warning device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191126

CF01 Termination of patent right due to non-payment of annual fee